This is an HTML version of an attachment to the Official Information request 'Details of the EWL redesign'.








This email is only intended to be read by the named recipient. It may contain information which is confidential, proprietary or 
the subject of legal privilege. If you are not the intended recipient you must delete this email and may not use any information 
contained in it. Legal privilege is not waived because you have read this email. 
 
Please consider the environment before printing this email 
 
 
 
 
 
_________  _____________________________________________     
 
                  
 
                 
 
  
Find the latest transport news, information, and advice on our website:  
www.nzta.govt.nz 
 
This email is only intended to be read by the named recipient.  It may contain information which is confidential, 
proprietary or the subject of legal privilege.  If you are not the intended recipient you must delete this email and may 
not use any information contained in it.  Legal privilege is not waived because you have read this email. 
 
2



















design and construction project and remains within the $1.25Bn (P5%) to $1.85Bn (P95%) range 
forecast in the Detailed Business Case. 
 
The Board of Inquiry are due to advise on the East West Link planning approvals early November 
7.  The Board of Inquiry established to assess the planning approvals (resource consents and 
designation) for the East West Link is due to release their Draft findings to the EPA on 7 
November, which are required to be publically released by 14 November.  The full timeline is 
outlined below:  
 
Property negotiations are well developed 
8.  Landowner negotiations commenced in October 2016.  Currently 38 out of 200 properties have 
been secured on a willing buyer/seller basis, the majority along the SH1 corridor.   
9.  We have in principle agreement for another six properties with Public Works Act agreements yet 
to be concluded.  These properties total $98m (purchase price - excludes resale recoveries), 
detailed in Attachment C.  


10.  Public Works Act Section 18 (s18) notices of desire for the required residential properties were 
served in May 2017 on 22 private owners (and 1 in July) around the Princes Street area.  The s18 
notices are valid for 12 months.  There are currently 11 owners for the Princess St properties for 
which the Transport Agency is preparing the Section 23 (compulsory acquisition) paperwork. 
11.  There are approximately 60 remaining landowners.  The Transport Agency has been preparing 
the paperwork to serve s18 notices of desire on all remaining landowners.  Nine signed s18 
notices have been received from LINZ but are currently on hold. 
Procurement for the East West Link 
12.  An existing professional services contract is in place to complete the detailed design and 
procurement of the East West Link.  The proposed procurement has been broken down into three 
contracts as indicated in Attachment D.  
13.  Contract 1 is proposed as a $50m traditional contract for the Princess Street Interchange area.  
Design is in the final stages and is anticipated to be ready to go to market in early 2018. 
14.  Contract 2 is proposed to be a circa $500m Competitive Alliance contract focused on the 
Onehunga interchange and foreshore works.  This contract is expected to go to a  shortlisting 
process just prior to Christmas.   
15.  Contract 3 is proposed as a second alliance type procurement and includes flyovers and 
interchanges from State Highway 1 through to the foreshore.  This package could be up to a 
$700m Competitive Alliance contract and is programmed for tender mid-2018.   
16.  A geotechnical investigation package of work has been prepared to inform the procurement 
process and is currently on hold. 
 
Attachment A 
Key issues (and future freight trends) in the Onehunga Penrose Area