This is an HTML version of an attachment to the Official Information request 'Procedures / Instruction copies'.










 
 
P2 Operations reviews (OM E1) 
P2 Operations Reviews (OM E1) 
Purpose   
This document provides for: 
  safe and effective Operations Reviews being carried out following significant NZFS 
1982
operations. 
Requirements for Operations Reviews 
Act 
Introduction 
An Operations Review is the process by which the National Commander, Fire Region Mangers, 
and Chief Fire Of icers can analyse a particular incident to identify ways of improving safety, 
effectiveness and efficiency.   
It is expected that Regions and Districts wil  take an active approach to learning and look for 
opportunities for Operations Review rather than wait for an event trigger to occur. 
Legislative requirements 
Operations Reviews contribute to New Zealand Fire Service (NZFS) meeting the following 
legislative requirements: 
Information 
  section 17O (b) of the Fire Service Act 1975, which requires the National Commander to 
ensure that the NZFS is maintained in a state of operational efficiency 
  The Health and safety in Employment Act 1992, which requires all places of work  to 
-  identify hazards  
-  investigate serious harm and near miss accidents. 
Official 
Objectives 
Operations Reviews provide an objective, documented analysis of an incident/event or an 
aspect of an incident/event in order to: 
the 
  improve operational effectiveness and efficiency in an end-to-end service delivery  
  improve operational procedures, particularly in regard to safety and best practice  
  achieve compliance with the Fire Service Act 1975 
  provide a measure of operational performance  
under 
  identify training needs  
  provide evidence of hazard management as part of the NZFS Health and Safety policies 
as described in the NZFS Health and Safety Manual
 
Criteria 
Operations Reviews are to be carried out when directed by the sponsor, which may be the 
Released 
National Commander, Fire Region Manager, or Chief Fire Officer. This wil  include: 
  al  responses to regional civil defence emergencies  
NZFS Department of Operations and Training 
Page 1 of 2 
P2 Operations reviews December 2008 









P2 Operations reviews (OM E1) 
al  significant or major incidents resulting in: 
-  4th alarm or greater  
-  substantial community disruption or loss  
-  substantial business impact  
-  substantial cultural, heritage or environmental impact 
-  long term loss to communities and or businesses. 
anytime it is considered that the outcome wil  benefit the whole NZFS, including when 
there wil  be significant benefit from the sharing of information obtained from incidents 
that have been handled successfully  
when recommended by the Regional or National Health & Safety Advisor in preference 
to an accident investigation following a serious harm accident or near miss  
when equipment or procedures have not operated in the manner intended 
NZFS operational assets, including equipment and appliances suffer significant damage, 
(significant damage is where any potential insurance claim exceeds $2000)  
civil disturbances where NZFS resources are used. 
Notes: 
When firefighters receive serious harm at an operations incident, then the accident investigation 
process wil  form part of the Operations Review. 
Incidents that meet the criteria for an Operations Review, may also meet the criteria for 
requiring a Serious and Unusual Incident Report, as listed in P3 Fire investigation
Reporting  
An Operations Review will have its limits defined by Terms of Reference provided by the 
sponsor. These are to be as specific as possible in order to focus on key issues. 
Review reports wil  be forwarded to the sponsor who wil  be responsible for developing a 
Corrective Action Plan and ensuring its completion.  Where a corrective action plan identifies 
national issues and/or actions, these are to be referred to the Director of Operations & Training. 
An electronic copy of the report can be attached to the incident report in SMS, similar to a Fire 
Investigation Report. 
The report wil  be considered finished when all actions in the corrective action plan have been 
under the Official Information Act 1982
signed off as complete and a copy filed at Region and with the Information Centre, NHQ. 
Limits of Operations Reviews 
Operations Reviews are not to be used to investigate: 
Fire safety issues. If an area of concern is identified, a separate Fire Investigation Report 
wil  be required  
The actions of individuals. If areas of concern are identified, a separate inquiry may be 
Released 
implemented. 
NZFS Department of Operations and Training 
Page 2 of 2
P2 Operations reviews December 2008