Hi Richard

As discussed, Wellington Water’s understanding and intent, is that the consent be issued with a generic condition in regards to “an approved discharge” for wastewater water. Once we investigate this further and decide the way forward (within the next 4-5 weeks) we will contact you and agree what this approved discharge will be.

In this way you will be able to proceed prior to the ultimate solution being agreed, so as to avoid delaying you project further.

I apologise that there still appears to be an issue. If this email does not provide the resolution to this please let me know and I will chase it further.

Regards

Ryan Rose Manager - Land Development

Tel 04 912 4400 DDI 04 912 4457 [mobile number]
Private Bag 39804, Wellington Mail Centre 5045