Bus Services Review 
UPDDATE
11 SEPTEMBER 2025 - COUNCIL WORKSHOP
Tamsin Evans, Kaiwhakahaere Matua, Network & Customer

Purpose
To update Councillors on our service design approach to reduce 
service costs by $5 million during the 2025/26 financial period
1. Background and recap
2. Work to date
3. Emerging implementation challenges
4. Step back
5. Service reduction principles
6. Opportunities for savings
7. Proposed services review programme



Background
The 2024 Long Term Plan noted: 
‘Constrained funding availability may affect the size and 
timing of our proposed service design …’ and ‘We will 
regularly review the network and the quality and 
capacity of our services to ensure that we are delivering 
services where they are needed the most.’
In late 2024, Metlink started to review expenditures to determine where efficiencies 
and cost savings could be found to reduce the rating increases forecast in the LTP for 
the 25/26 Annual plan, including avenues such as bus service level reductions.
During Council workshops on 12 Nov 24 we discussed with Councillors cost savings 
options (see recap slide). Based on this, we have developed a services review 
programme proposal.



 RECAP: Bus Network Cost Reduction Opportunities
Slide from 
12/11/24
The current bus network contains opportunities to reduce cost on services with 
poor cost recovery and/or services that exceed RPTP requirements.
Low Impact
Medium Impact
Higher Impact
SAVINGS
$1m
$2.5m
$5.0m
Off-peak - some 
Low Impact changes + 
Medium Impact changes + 
KEY CHANGES
reduction or removal of  Further off-peak reduction to  some reduction of interpeak 
very low use services
days and span of low use and  frequency on lower use and 
highly duplicated services
duplicated services
Concentrated impact for  Impacts for a small number 
Impacts more customers 
CUSTOMER 
a very small number of 
of customers affecting 
with less frequent service or 
IMPACT
customers with no 
available days and times of 
more need to transfer.
service.
travel.
Limited effect, relatively  More driver hour reductions 
Greater impact on split 
OPERATOR 
minor effect on overall 
& some effect on split shifts shifts and reduction in driver 
driver hours
hours








Work to date
TARGET: save $5M in the 25/26 year from network optimisation 
MAY 25
• Context shared with operators, high level approach 
socialised
JUNE 25
• Assessment methodology developed, all services 
assessed against strict application of RPTP policies
JULY / AUGUST 25
• Worked through application of methodology with one 
operator
• Other operators updated on progress

Emerging implementation challenges
Who will be affected?
• Customers and communities
• Operators
What does implementation need?
• Metlink
• Operators
How much change can we deliver?
• Lots of small changes vs fewer big changes
• Perceptions of fairness
How do we do this?
Removing services is not our usual practice – we need a robust process
Have we got enough time?
We started late – is it realistic to find $5M savings this financial year?

Taking a step back
Saving costs by reducing bus services is more complicated than it seemed, but 
reducing our rates increases is essential.
We need to:  • make changes easy for our customers and ratepayers to understand
• be seen to be even handed with our operators
• do this well
Instead of a one-off $5m cut, we recommend following a deliberate, cost-capping 
approach to service design, with a focus on ongoing cost efficiency and cost reduction:
• Using a set of principles to enhance the policies in the RPTP
• Using a standard methodology to identify and quantify potential changes
• Continue the current review to optimise services and make short term savings
• Inform a structured programme of ongoing, area-based service reviews
• Make manageable changes focused on cost efficient services and community priorities
• Identify more significant opportunities to reduce longer term costs through service changes in 
future procurement tranches (bus and rail)

Service reduction principles
• Avoid reductions that affect critical peak capacity and mode shift.
• Avoid reductions that leave whole communities without basic coverage and 
access.
• Focus on lower usehigher subsidy and overlapping services.
• Align with rail services
• Apply RPTP service delivery thresholds:
• Minimum usage (<4 per trip)
• Cost recovery (<20%)
• Catchment thresholds  (<2700 population, minimum density and private 
vehicle ownership)
• Align to RPTP Service level guidance for Core and Local services.

What are our opportunities for savings?
Our Bus Operations budget is $125.82 million - $5mill reduction = ~4%
We have started from an approach of what we must provide (i.e. core network expenditure 
required to meet key policy obligations under the RPTP) vs. what we’d like to reduce?
MUST PROVIDE
Impact of inaction
TO REDUCE
Impact of inaction
Core network capacity - 
Passenger left behind – longer 
Standing on buses – at 
Poorer customer 
passengers are able to board  term reputation impact on PT 
peak and off-peak
experience, but 
the bus or train.
network
customers still get to 
destinations
Basic network coverage – 
Loss of access - Users with no 
RPTP aim to bring PT to 
transport alternatives lose access 
Network duplication to 
Slower journeys with 
within 5-10 mins walk of 
to work, education, shopping etc.
reduce transfers (RPTP 
transfer, but customers 
passengers.
beyond nearest town and 
still get to destinations
city centres)
Seven day a week services  Loss of access - Users with no 
– RPTP guidance for Core and  transport alternatives lose access 
Late night services (RPTP  Reduced travel options
Local routes
to work, education, shopping etc
Core after 11pm, Local 
less support for night 
after 9pm) 
economy and shift workers 
School bus services to 
Loss of access – vulnerable users 
(Poneke Promise)
nearest and zoned schools 
required to transfer, make longer 
where no public alternative
journeys and/or significant walk to 
Express services (if not 
Slower journeys that may 
nearest and/or zoned schools.
required for M1 or M2)
affect mode share

Proposed services review programme
SEPTEMBER 2025 – JUNE 2026
Current network wide review activity to 
optimise services.
Short term, cost reductions <$5M pa
JANUARY 2026 – JUNE 2027
Programme of detailed reviews to maximise service optimisation 
aligned with Transport Services Procurement Tranches. 
Long term, greater opportunity for cost reductions
JULY 2026 – ONGOING
Programmed reviews by community area, rail line, and implementation of 
Bus Priority Action Plan as per RPTP.
Any cost increases must be offset by reductions unless new funding is 
provided.
SEPTEMBER 2025 – ONGOING
Continual operational changes, ie community or operator requests for minor timetable changes, disruption 
management etc. 
Any cost increases must be offset with cost reductions.