This is an HTML version of an attachment to the Official Information request 'Itemise the 36 major projects personally overseen by Mayor Andy Watson'.



 
 
 
 
6 March 2026 
 
Sheila Allen 
 
Email: [FYI request #33661 email]  
 
 
 
Dear Sheila, 
Local Government Official Information Request 
Thank you for your request for information from Council. All requests to the Council for information 
are  required  to  be  considered  in  accordance  with  the  Local  Government  Official  Information  and 
Meetings Act 1987 (LGOIMA).  More information about how the  Council handles LGOIMA requests 
can  be  found  in  the  Council’s  LGOIMA  Request  Policy  which  is  available  on  the  Council’s  website 
LGOIMA Request Policy: Rangitikei District Council  
Your request for information was received on 9 February 2026 and requested information about the 
36 major projects personally overseen by Mayor Andy Watson. Your questions and our response can 
be found below: 
Question 1: 
“On the 25th of January 2026 the Whanganui Chronicle published an article titled "Decision-
making power slipping away from councils, Rangitīkei Mayor Andy Watson tells Rātana" In 
this article Mayor Andy Watson claims mayors were being loaded 
with additional governance responsibilities without adequate support, while already juggling 
dozens of projects.  
  
He said he was personally overseeing 36 major projects." 
  
Please provide a list, itemising each of these 36 major projects which must include a brief 
description/scope, cost and estimated completion date for each project”.  
 
Response: 
Please  find  a  list  outlining  the  36  projects  that  Mayor  Andy  Watson  has  provided  which 
includes work programmes he is involved in, as at 9 February 2026 and as referred to in the 
article identified above.  For each project we have provided a brief description/scope, cost 
(where known) and estimated completion date (where known).  
 
1.  2027-2037 Long Term Plan for Council: 
Ten-year plan for Council. See Mayoral role in S41A(2) of the LGA. 
•  Cost: Budget of $205,000 (includes the cost of audit). 
•  Estimated Completion Date: 30 June 2027. 
  
 


2.  2026/27 Annual Plan  
One year plan for Council. 
•  Cost: Cost is primarily staff time and limited printing costs.  
•  Estimated Completion Date: 30 June 2026.  
  
3.  Central Districts Water - Shareholder Committee  
Formation of Council Controlled Organisation (CCO) for the delivery of water membership 
on  the  Shareholder  Committee. Meetings  -  Joint  Shareholder  Committee  -  Central 
Districts Water - Page 1: Rangitikei District Council 

•  Cost: Yet to be finalised.  
•  Estimated Completion Date: Established February 2026, work ongoing.   
  
4.  Central Districts Water appointment of Directors  
Process for appointing directors of new water entity Central Districts Water.  
•  Cost: Mayoral and staff time.  
•  Estimated Completion Date: Recruitment is still being worked on but expected to 
be finalised by end of March 2026.  
  
  
5.  Employment of Independent Chair Risk/Assurance Committee  
This  involves  interviewing  and  appointment  of  the  Chair  for  the  Risk/Assurance 
Committee.  
•  Cost: Staff and governance time to run the process.   
•  Estimated Completion Date: March 2026.  
  
6.  Marton Swimming Pool  
Reopening of the Marton Swim Centre.  
•  Cost: $6M.   
•  Estimated Completion Date: End of 2026. 
  
7.  Taihape Town Hall  
Rebuild/Strengthening of the Taihape Town Hall. 
•  Cost:  Total  budget  for  this  project  is  $14m,  with  $4m  planned  for  the 
25/26 financial year, noting this is subject to final costing.  
•  Estimated Completion Date: Construction to be completed in 2028.  
 
8.  Marton Civic Building/Library Complex  
New build that replaces and combines the Marton administration building and the Marton 
library. 
•  Cost: Total  budget  for  this  project  is  $19m,  with  $3m  planned  for  the 
25/26 financial year, noting this is subject to final costing.  
•  Estimated Completion Date: Project mid-2028.  
  
9.  Horizons Climate Action Joint Committee  
Rangitīkei District Council member on the Joint Committee.   
•  Cost: Mayoral time.  
•  Estimated Completion Date: Ongoing.  
  
10. Rural Water Schemes in Rangitīkei  
i. 
Erewhon 
 

as council ‘owned’ they are  
ii. 
Hunterville   

under sign-off process  
 


iii. 
Omatane   

but community run  
•  Cost: The schemes are funded by way of a charge direct to the consumers. There 
will need to be some process around incorporation into and out of the new water 
entity.  
•  Estimated Completion Date: Ongoing. To be re-reviewed in conjunction with the 
position of Taumata Arowai as regulator.  
  
11. Ratana Wastewater Process  
•  Cost: Total budget for this project is currently estimated at $6.4m with $1.1m 
planned  for  2025/26.  To  be  re-reviewed  in  conjunction  with  the  position 
of Taumata Arowai as regulator.  
•  Estimated  Completion  Date:  Still  to  be determined.  To  be  re-reviewed  in 
conjunction  with  the  newly  released  discharge  standards.  Will ultimately 
be passed to the new water entity.  
  
12. Mayors Taskforce for Jobs National Programme  
At the time of Ratana speech I was co-Chair of the National Programme.  
•  Cost: Significant budgets across the country.  
•  Estimated Completion Date: Ongoing  
  
13. Mayors Taskforce for Jobs Local Governance  
Governance of MTFJ programme being run locally within the Rangitīkei District.  
•  Cost:  Membership  costs  approximately  $3,000  per  annum  but as  a 
consequence we 
receive 
Ministry 
of 
Social 
Development 
funding 
for programmes to the value of $280,000.  
•  Estimated  Completion  Date:  Programme continuing  for  years  –  no  completion 
date.  
  
14. Marton/Bulls Wastewater Centralisation  
Upgrade and centralisation of the waste water discharges for Marton and Bulls.  
•  Cost:  $79.7m (including  $69m  to  be  spent  between  2033  and  2035). $1.9m  is 
budgeted for 2025/26.  
•  Estimated  Completion  Date:  To  be  re-reviewed  in  conjunction  with  the  newly 
released wastewater discharge  standards. Will ultimately  be passed to the new 
water entity.  
  
15. Rail/Road Transport   
Driving conversations between Rail/Road transport costings – contract renewal.  
•  Cost: Mayoral time only.  
•  Estimated Completion Date: New contract verified late January 2026.  
  
16. Emergency Operations Centre  
Construction of Emergency Operations Centre  
•  Cost: $2m. 
•  Estimated Completion Date: 2027. 
   
17. Civil Defence Review  
As Mayor of Council review of CDEM capability. 
•  Cost: $38,157.52 to date.  
•  Estimated Completion Date: July 2026.  
  
 


18. Zone 3 – Local Government New Zealand 
Co-Chair  of  Zone  3  as  a  region.  This  covers  councils  spread  between  Gisborne/Wairoa 
to Tararua and those spread between New Plymouth and Horowhenua.  
•  Cost: Mayoral time.   
•  Estimated Completion Date: Ongoing.  
  
19. Ngā Wai Tōtā – the governance group for Te Waiū o Te Ika - Whangaehu Catchment  
Governor along  with  Ruapehu  District  Council  and  Whanganui  District  Council  and 
respective Iwi.  
•  Cost: Mayoral time and staff time.  
•  Estimated Completion Date: Multi-year commitment.  
  
20. Mokai Patea Projects  
Similarly under Mokai Patea settlement project covering awa catchments and landlocked 
lands.  
•  Cost: Unknown at this stage.  
•  Estimated Completion Date: Multi-year commitment.  
  
21. Accelerate 35 (Regional Economic Development Body)  
Governorship role to support this regional work.  
•  Cost: Operational costs met by Horizons. Mayoral time.  
•  Estimated Completion Date: No completion date – this is an ongoing programme 
of work.  
   
22. Mayoral Forums  
Governance representation from RDC in regional matters.  
Meetings concerning –  
i. 
Regional Roading – such as national roading/local roading issues.  
ii. 
For our district – FAR rates funding of 66%, balance rate-funded.  
Focus on applications to Government for funding.  
•  Cost: Mayoral time.  
•  Estimated Completion Date: Multi-year commitment.  
  
23. Community Volunteer   
Numerous projects, Marton B&C dams is the most significant.  
•  Cost: Mayoral time.  
•  Estimated Completion Date: Ongoing  
  
24. National TUIA programme for New Zealand  
Long term nationwide mentoring initiative to develop leadership among young Māori run 
by Mayors Taskforce for Jobs. At the time of this request I am co-Chair of the programme.  
•  Cost: Financially supported by Local Government New Zealand. Minimal cost for 
local rangatahi.   
•  Estimated Completion Date: Ongoing yearly programme.  
  
25. Local Policing in Hunterville  
Lead project driving retention of local policing.   
•  Cost: My time spent on relationship building between local and regional police. 
RDC budget not needed.  
•  Estimated Completion Date: Decision date should be by July 2026.  
  
 


26. Gentle Annie Road Case Study  
Regional lead with Hastings District Council to have the Gentle Annie Road passed to NZTA 
as a national road and road of significance.  
•  Cost: If possible, effect on our budgets would be a significant financial gain in the 
future.  
•  Estimated Completion Date: Ongoing.  
  
27. JBS Dudding Trust  
Advisory Trustee. Recently distributed $1.1m to the Rangitīkei district.  
•  Cost: No cost to council other than Mayoral and staff time.  
•  Estimated Completion Date: Ongoing  
  
28. Regional Tripartite Defence Group  
Member along with Mayors of Whanganui and Palmerston North. For our district there 
are several projects including housing.  
•  Cost: Mayoral time.  
•  Estimated  Completion  Date:  Multi-year  discussions to  engage Defence and 
Government and how they support our towns associated with Defence.  
  
29. Taihape Grandstand  
Council owned but community lead. My role project is the fundraising contribution by the 
community. Project involves heritage, museum people, rugby clubs etc.  
•  Cost: As Council we committed $1m towards this project with a current balance 
available of circa $700,000.  
•  Estimated Completion Date: Optimistically 2026.  
  
30. Taihape Playground  
Similar to 29. I spend time on this project trying to raise community funds.  
•  Cost: Council has committed $50,000 to help rebuild.  
•  Estimated Completion Date: Best case scenario 2026/27.  
  
31. Regional Transport Committee 
RDC representative on the Regional Transport Committee. Approve the regional transport 
plan.    
•  Cost: Mayoral time  
•  Estimated Completion Date: Ongoing  
 
32. Community Committees  
At the beginning of each triennium the Mayor sets up the community committees, and 
provides representation on many groups.  
•  Cost: Mayoral and staff time.   
•  Estimated Completion Date: February 2026.  
  
33. Planning Bill and Natural Environment Bill submissions 
Working  with  regional  parties,  Elected Members and  staff  to  provide  submissions  to 
Central Government on key reforms, many of the Acts of Government are up to hundreds 
of pages long.  
•  Cost: Mayoral and staff time.  
•  Estimated Completion Date: Lodged 13 February 2026.  
  
 


34. Simplifying  Local  Government (including  governorship  of  Regional  Councils  being 
passed to Mayors with a view to possible aggregation) Submission Process  
Working  with  regional  parties,  Elected Members and  staff  to  provide  submissions  to 
Central Government on key reforms, many of the Acts of Government are up to hundreds 
of pages long.  
•  Cost: Mayoral and staff time.   
•  Estimated Completion Date: Lodged 20 February 2026.  
  
35. Rates Target Model proposal – multi-council discussions  
Working  with  regional  parties,  Elected Members and  staff  to  provide  submissions  to 
Central Government on key reforms, many of the Acts of Government are up to hundreds 
of pages long.  
•  Cost: Mayoral and staff time.  
•  Estimated Completion Date: Lodged 3 February 2026.  
  
36. Proposed Plan Change 3  
Urban Growth Plan Change, focused on future-proofing residential land supply.  
•  Cost:  Whole  of  project  cost  to  date  of  $290,385.30  (mostly  funded  by  grant 
funding to the value of $216,746.25), plus Mayoral and staff time. 
•  Estimated Completion Date: 2027.  
 
You have the right to seek an investigation and review by the Ombudsman of this decision. Information 
about how to make a complaint is available at www.ombudsman.parliament.nz or freephone 0800 
802 602. 
If you wish to discuss this decision with us, please feel free to email [email address]. 
 
Yours sincerely, 
LGOIMA Officer  
Rangitikei District Council