
Memorandum
To
Tony Innes / Megan Wheeler
From
s 9(2)(a)
Copy
Scott Elwarth; Daryl Lim
Document Code
10722-PTA-230-TR-MEM-0004
Date
October 2025
Pages
3
(including this page)
Subject
Reported Travel Time Savings in the Investment Case
Purpose
ACT 1982
This technical note summarises how travel time savings reported in the Northland Corridor
Investment Case were calculated.
Background
Two complementary approaches were applied to estimate potential savings across the
corridor:
•
Observed data assessment – based on 2025 weekday travel times, providing an
INFORMATION
indicative estimate of potential savings under existing conditions; and
•
Model-based assessment – using the updated Northland Corridor full corridor
traffic model for the 2054 forecast year, supported by SIDRA network modelling for
Section 3B, to provide an assessment of long-term performance.
While both approaches were consistent in demonstrating travel time savings across the
corridor, the model-based assessment formed the basis of the economic evaluation as it
provided average conditions and should be seen as a conservative estimate of the long-
term corridor performance. The observed data was used primarily to illustrate the potential
scale of benefits under a range of travel time conditions.
Observed Data
Observed weekday travel times in May 2025 along the existing SH1 route from 52 minutes
to 82 minutes across the 73-kilometre length of SH1 (Sections 2A to 3B).
The corresponding potential travel time savings on the proposed Highway ranges from 7.8
minutes under uncongested conditions to 37.8 minutes (assuming the upper range
congestion levels are resolved). This was based on an assumed operational speed of
105km/hr on the new highway (Section 2A to 3A). Section 3B is split between 75km/hr
RELEASED UNDER THE OFFICIAL
(peri-urban) and 45km/hr for the urban section.
Document Code: 10722-PTA-230-TR-MEM-0004
Revision: A
Page
1 of
3

Memorandum
Table 1: Typical Weekday Travel Time Savings (May 2025)
Observed Range of Weekday Travel
Range of Typical Weekday Travel
Times along existing SH1
Time Savings (mins) using new
(mins, May 2025)
Highway
ACT 1982
General traffic
Lower
Upper
Lower
Upper
Section 2A
14
20
2.9
8.9
Section 2B
10
16
1.5
7.5
Section 2C
8
10
2.0
4.0
Section 3A
14
22
0.9
8.9
INFORMATION
Section 3B
6
14
0.5
8.5
Total
52
82
7.8
37.8
Typical weekday travel times along the full corridor currently vary considerably between
uncongested and heavily congested conditions, as demonstrated above and illustrated by
Labour Day travel patterns.
On Labour Day morning, travel between Loop Road and Te Hana was relatively smooth,
averaging 84 km/h and taking approximately 47 minutes to cover the 66-kilometre stretch
(noting this is slightly shorter than the full project corridor between Te Hana and
Whangārei).
By contrast, southbound traffic volumes increased sharply in the afternoon, with the most
severe delays occurring between 3:00–4:00 pm, when average speeds fell to 46.9 km/h and
journey times extended to 84 minutes.
These Labour Day travel times closely align with the upper end of the observed weekday
travel time range in Table 1.
RELEASED UNDER THE OFFICIAL
Document Code: 10722-PTA-230-TR-MEM-0004
Revision: A
Page
2 of
3

Memorandum
Model-Based Output
Model outputs were available for Sections 2A–3A (Te Hana to Loop Road) from the full
corridor model, while Section 3B was assessed separately using SIDRA intersection
modelling.
Weekday travel time savings on the highway, relative to the existing SH1 route, were
modelled for the 2054 model year, refer to Table 2 below.
ACT 1982
Table 2: Typical Weekday Travel Time Savings 2054 forecast period
AM Peak
PM Peak
Year
Source
Section
Savings
Savings
(minutes)
(minutes)
2054
Corridor Model
2A–3A
12.0
19.2
INFORMATION
2054
SIDRA
3B
16.0
15.8
Corridor Model /
Total
2A-3B
28.0
35.0
SIDRA
The travel time savings derived from the model are comparable with the observed results
presented in Table 1. Travel times are forecast to reduce from approximately 74 minutes to
46 minutes during the AM peak, with similar reductions observed during the PM peak (refer
to Table 3 below).
Table 3: Typical Weekday Travel Times 2054 forecast period
Corridor
Travel Times (AM)
Travel Time (PM)
(Old) SH1 Route Travel time
74.5
81.6
(Section 2A-3B)
New Highway Travel Time
46.5
45.6
(Section 2A-3B)
Conclusion
RELEASED UNDER THE OFFICIAL
Both observed and model-based assessments demonstrated consistent patterns of travel
time savings.
Document Code: 10722-PTA-230-TR-MEM-0004
Revision: A
Page
3 of
3