This is an HTML version of an attachment to the Official Information request 'Completion date for Te Ara Tupua'.

   
44 Bowen Street 
Private Bag 6995 
 
Wellington 6141 
New Zealand 
 
T 64 4 894 5400 
 
F 64 4 894 6100 
 
www.nzta.govt.nz 
 
 
 
 
 
 
 
6 October 2025 
 
 
 
 Ben Steele  
[FYI request #32320 email] 
REF: OIA-19623 
 
Dear Ben 
 
Request made under the Official Information Act 1982 
 
Thank you for your email of 15 September 2025 requesting the following information under the Official 
Information Act 1982 (the Act): 
 
I request documents under the OIA related to the completion date of the Te Ara Tupua 
cycleway/works project. 
 
Documents should be dated after 1 July 2025 until the current date. 
 
If documents are too numerous I request a summary table that includes the date the cycleway 
will be open for public use as well as key milestones (with dates) leading to that opening.
 
 
The Te Ara Tupua cycleway project has been in progress since 2019 and has been undertaken in two 
sections – Pito-One to Melling and Ngā Ūranga ki Pito-One. We’ve interpreted your request as being 
for the Ngā Ūranga ki Pito-One section and have responded on this basis.  
 
There are a large number of documents potentially in the scope of your request. Given this, and as 
you have suggested, we have instead provided a summary in Table 1 (below) that includes an 
indication of the key milestones for the Ngā Ūranga ki Pito-One section of Te Ara Tupua from 
September 2025 to project opening.  
 
Please note that the milestones are indicative and subject to change due to project constraints, for 
example: 
•  Meeting consent conditions 
•  Rail Corridor Access restrictions 
•  Weather and other unforeseen issues. 
 
The actual opening date for Te Ara Tupua will be finalised in early 2026 fol owing achievement of the 
construction milestones listed. We’ve provided a range for the opening date in the interim.  
 
 
 
   


Table 1: Summary of key milestones for Te Ara Tupua (Ngā Ūranga ki Pito-One) 
 

Indicative Dates 
Key Milestones (Installation Completed) 
•  Culvert outfalls 
September 2025 
•  Seawalls 
October 2025 
•  Revetments 
•  Soft landscaping 
December 2025 
•  Utilities 
•  Bridge substructure 
February 2026 
•  Bridge superstructure 
•  Hard landscaping including fencing.  
March 2026 
•  Pavements and surfacing 
By  June 2026 
•  Opening to public 
 
If you would like to discuss this reply with NZ Transport Agency Waka Kotahi (NZTA), please contact 
Ministerial Services by email to [NZTA request email] 
 
 
Yours sincerely 
 
 
 
 
Jackie Smith 
Manager Ministerial Services