This is an HTML version of an attachment to the Official Information request 'Modelling, Analysis, and Policy Relating to the Cambridge Southern Interchange'.
Waipa & Waikato District Councils s42A Report 
Appendix 12- 
Waikato Expressway – Cambridge Section 
Option   Assessment Summary Document 
Released under the Official Information Act 1982

239
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 

Options 
1.1  Introduction 
This  Report  briefly  describes the alternatives  considered during  the  investigation  phases of 
the Cambridge Section of the Waikato Expressway. 
1.2  Previous Investigations 
1982
The Project has a long history and an extensive record of alternatives being considered. The 
alternatives  have  investigated  improvements  along  the  existing  SH1  corridor,  alternative 
routes within the Cambridge Township (internal routes), and a range of new route alignments 
Act 
external  to  Cambridge  Township.  All  of  these  investigations  have  confirmed  that  the 
designated external route (as described in the Waipa DC District Plan) as being the preferred 
option. 
As  such,  the  option  selection  process  undertaken  for  this  Project  only  consider  the 
alternatives relating to the current designation, and the suitability of the extent of the existing 
designation. The purpose of these investigations is to identify if any further alteration to the 
existing designation, based on the current needs for the Project. 
1.3  Do Minimum 
Information 
The Do Minimum option (for the purposes of option comparison) provides no improvements 
to the existing designated corridor. 
In  general,  the  existing  designation  width  is  approximately  40m  wide  and  was  intended  to 
provide a single lane in each direction. 
Official 
In  order  for  the  Cambridge  Section  to  meet  its  Projects  Objectives,  the  designated  width 
needs  to  cater  for  a  four-lane  Expressway  corridor  and  to  be  consistent  with  the 
requirements of the RoNS Standards. The desirable RoNS cross-section requires a width no 
the 
less than 52m. The required cross-sectional width increases if the corridor is within areas of 
cut or fill or if additional features are required, such as noise or visual mitigation. 
The  existing  designated  width  is  insufficient  to  provide  the  necessary  requirements  for  the 
Project,  without  a  substantial  compromise  in  the  level  of  service  and  degree  of  safety 
under 
provided by the Project. As such, the option for using the existing designation width without 
alteration is not considered a viable option. 
1.4  Project Options 
In  order  to  meet  the  Project  Objectives,  an  alteration  to  the  existing  designation  width  is 
needed for the Cambridge Section. 
The consideration of options for the Project has therefore been undertaken for the following 
Released 
key items: 
• 
Road geometry requirements (RoNS Standards) 
• 
Location of altered designation 
261647.00 
 
 
July 2010 


240
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
• 
Connection Locations and Form: 
− 
Northern Interchange 
− 
Central Interchange 
− 
Southern Interchange 
1982
• 
Karapiro Stream Gully crossing 
• 
Vertical design 
Act 
• 
Pa site options 
• 
Localised design features 
1.4.1  Evaluation Criteria 
In many cases there is an indistinguishable difference between options in consideration 
of  the  overall  effects.  In  these  cases  the  optimal  option  has  been  determined  by  its 
ability  to  best  meet  the  Project  objectives  and  its  ease  in  being  able  to  minimise  or 
mitigate the effect. 
Information 
In general, each option was assessed in terms of the: 
− 
Best  practice  criteria/standards/guidelines  for  each  specialist  area.  Each 
specialist identified the relevant criteria against which to assess the effects 
− 
Effects of known/highly probably changes to land use 
Official 
− 
Ability for effects  to  be  avoided,  remedied,  or  mitigated  in terms  of  meeting the 
RMA requirements 
the 
− 
The importance of the feature in terms of local, regional, national, or international 
significance 
− 
The severity of the effect that the option has on that feature in terms of: 
under 
▪ 
How the effects vary with time including whether the effects are temporary 
or permanent 
▪ 
Whether the effects are irreversible (i.e. cannot be mitigated) 
▪ 
Any cumulative effects (such as mitigation to address one impact having a 
cumulative effect on another feature) 
1.4.2  Road geometry requirements 
Released 
As described previously in this report, the Project is one section of the overall Waikato 
Expressway and is therefore defined as a RoNS project. 
261647.00 
 
 
July 2010 


241
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
As part of the NZTA’s role in identifying RoNS projects, they have also developed a set 
of specific design standards and guidelines to be applied to each RoNS project (known 
as the RoNS Standards). The purpose of this standardisation is to provide a consistent 
approach to the development of each RoNS project throughout NZ. 
The  RoNS  standards  primarily  relate  to  design  considerations  affecting  highway 
geometry,  safety  consideration,  bridge  design,  and  provision  for  alternative  transport 
modes. However, the RoNS standards also consider aspects such as intersection form 
1982
and  spacing,  pavement  requirements,  environmental  considerations,  public  health, 
urban design, and maintenance requirements. 
The RoNS standards have set the base requirements for the geometric design of each 
Act 
of the options. 
1.4.3  Location of altered designation 
Three options were considered for widening the existing designation to accommodate 
the new design along the main corridor length. These included: 
− 
Widening on the north side only 
− 
Widening on the south side only 
Information 
− 
Combination of widening on the north and south sides 
The  south  boundary  to  the  current  designation  generally  follows  existing  property 
boundaries.  As  such,  any  widening  on  the  southern  side  of  the  current  designation 
would affect additional  landowners  (approximately  15 additional  landowners  over  and 
above those currently affected by the designation). 
Official 
The existing  designation has  been  within  the Waipa  District  Plan for  almost 40  years 
and has been well established within urban development plans. As such, existing land 
the 
use  plans  already  provide  planned  development  up  to  the  south  side  of  the  existing 
designation boundary. In particular, the corridor length south of Victoria Road (SH1B) 
has  been  extensively  planned  within  the  Cambridge  North  Structure  Plan  and 
residential  development  south  of  Watkins  Road  already  borders  the  designation 
boundary (generally separated by a 30m wide buffer zone). 
under 
The  Cambridge Jockey  Club  is a  long  established  major  land holder  that  borders  the 
southern  designation boundary.  Any  widening  of the existing designation  towards the 
south  in the  vicinity of  the  Cambridge  Jockey  Club  would have a  major  impact on  its 
viability in the current location. 
The northern side of the existing designation also includes a defined area of planned 
future urban expansion, primarily in the form of the Hautapu Draft Structure Plan. The 
Hautapu Draft Structure Plan is yet to go through a formal notification process and the 
Released 
specific details of the Plan are yet to be confirmed. 
A relative comparison of the three locations for extending the designation boundary is 
tabulated below: 
261647.00 
 
 
July 2010 


242
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
 
Criteria 
Comments 
Geometric Design 
No  specific  difference  on  geometric  requirements  for 
widening on either side of the existing designated corridor 
Cost 
Expectation for additional property  costs  related to  acquiring 
land  from  the  southern  side  of  the  designation.  Includes  1982
higher  costs  of  residential  zoned  land,  increased  number  of 
landowners  to  complete  acquisition,  large  number  of 
established  residential  properties  (particularly  south  of 
Watkins  Road)  –  widening on  north  side  of  designation  only 
Act 
preferred 
Efficiency 
No noticeable difference in efficiency 
Safety 
All  three  options  can  provide  a  similar  level  of  safety 
assuming the overall corridor width is equal between options 
Structural 
Only  potential  effect  on  structural  features  is  the  location  of 
the  Karapiro  Stream  Gully  crossing.  Any  alteration  from  the 
existing  designated  route  is  likely  to  increase  the  crossing 
Information 
length  and  complexity  by  moving  it  further  away  from  the 
narrowest point of the gully. Preference for widening on both 
sides at Karapiro Stream Gully crossing opposed to one side 
only. No preference elsewhere on corridor length. 
Geotechnical 
Unlikely  to  be  noticeable  change  in  geotechnical  conditions 
Official 
for either options. Although similarly to Structural requirement 
in terms of Karapiro Stream Gully crossing. 
the 
Noise 
Preference  to  develop  corridor  further  away  from  residential 
establishment. Clear preference for widening on the northern 
side only. 
Landscape 
Additional  separation  from  the  residential  development  is 
preferred.  Northern  widening  should  provide  encouragement 
under  of establishment to the Cambridge North Structure Plan 
development  and  buffer  zone  system.  Important  to  provide 
sufficient room for any landscape features. 
Widening on northern boundary only preferable. 
Ecology 
No quantifiable difference in ecological effects 
Released 
261647.00 
 
 
July 2010 


243
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
Criteria 
Comments 
Archaeology 
Known archaeological features exist on both sides of corridor. 
However,  best  preserved  borrow  pits  (Swayne  Road)  occur 
along southern boundary so preference for widening on north 
side  of  designation  in  this  location.  Careful  consideration  of 
effects at Pa site needed. 
1982
General  preference  for  widening  on  northern  side  but  need 
careful consideration at Pa site. 
Iwi/Cultural 
Safety is paramount; as is protection of any cultural features 
Act 
such  as  borrow  pits  and  pa  site.  No  clear  preference  for 
widening on either side. 
Water Quality 
No quantifiable difference in water quality effects 
Drainage 
No  clear  preference  for  drainage  requirements  provided 
sufficient width on either side of the corridor can be provided 
for swale establishment. 
Social Impacts 
The social effects from widening on the southern side of the 
Information 
designation  are  likely  to  be  significantly  greater  than  those 
from  widening  on  the  northern  side  only.  This  is  primarily 
related  to  the  number  of  affected  landowners,  and  the 
substantial impact of planned and existing residential activity 
south of Victoria Road. 
Official 
A  clear  preference  for  widening  on  the  northern  side  of  the 
designation. 
Property Impacts 
Substantially  greater  number  of  affected  properties  if  any 
the 
widening occurs on the southern side of existing designation. 
Well  established  metropolitan  planning  already  established 
for  Cambridge growth  in place  (and development  underway) 
on southern side. More flexibility in planned urban expansion 
on  northern  side  (Hautapu  still  in  draft  form  and  subject  to 
under  change). 
Clear  preference  for  widening  on  the  northern  side  of 
designation. 
Table 1.1: Criteria Comparison for designation widening location 
There  is  a  clear  preference  for  widening  the  designation  on  the  north  side  of  the 
existing corridor. Widening on the north side of the corridor is expected to minimise the 
Released 
overall  effects  from  any  alteration  to  designation.  The  exception  to  this  relates  to 
specific consideration of effects on the pa site and other particular design features. 
261647.00 
 
 
July 2010 


244
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
Subsequent option development  has  been progressed  with  general  corridor  widening 
occurring only on the northern side of the existing designation.  
1.4.4  Connection Locations and Form Selection 
The  NZTA  has  specifically  required  that  the  designation  width  be  sufficient  to  enable 
the SH1 corridor to be fully grade separated along its entire Project length, with no at-
grade crossings. The exception to this is the consideration of intersections at any ramp 
1982
terminations.  
(a) 
Northern Interchange 
Act 
The  northern  interchange  has  considered  two  options  relating  to  access 
provision: 
▪ 
Provision for north facing ramps only (half interchange) 
▪ 
Provision for north and south facing ramps 
Traffic modelling was undertaken to determine the relative demands for each of 
the  two  ramp  arrangements.  The  assessment  determined  that  there  was  no 
reported  demand  for  the  south  facing  ramps  at  this  location  during  any  of  the 
Information 
modelled periods. This included assessment for projected land use development 
beyond the project horizon. As such, only north facing ramps have been included 
in subsequent Project development. 
Provision  for  north  facing  ramps  only  limits  the  grade  separation  options  to 
provide  either  SH1  elevated  over  the  southbound  ramp  (to  Cambridge),  or  the 
southbound  ramp  (to  Cambridge)  elevated.  Ground  water  and  drainage  issues 
Official 
prevent any of the options from being beneath ground level. 
A comparison between having SH1 above or below the ramps identified a clear 
the 
preference for the southbound ramp being separated over the SH1 corridor. The 
advantages of this arrangement include: 
▪ 
Less traffic being elevated to reduce noise impacts 
▪ 
The  embankment  and  bridge  structure  are  significantly  smaller  for  this 
under 
arrangement and therefore more readily able to be mitigated 
▪ 
Less cost 
▪ 
Maintains priority alignment for SH1 corridor; this is particularly problematic 
at this location where having SH1 over the ramp would create complexities 
in combining vertical and horizontal alignment with a merge condition with 
the northbound traffic from Cambridge 
Released The preferred option for the Northern Interchange was considered to be a half 
interchange  with  north  facing  ramps  only,  with  the  southbound  ramp  (to 
Cambridge)  being  grade  separated  over  SH1.  This  is  consistent  with  the 
Hamilton Bypass designation, which was confirmed in 2002. 
261647.00 
 
 
July 2010 



245
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
(b) 
Central Interchange 
The  NZTA  has  agreed  with Waipa  DC  that  the Project  should  provide for  a full 
directional  interchange  at  Victoria  Road  (SH1B).  As  such,  the  option  selection 
process at this interchange has focused on determining the optimal arrangement 
to provide the full directional access. These options included: 
▪ 
Interchange Form 
1982
▪ 
Vertical alignment 
▪ 
Ramp termination intersections 
Act 
Factors affecting the Central Interchange 
A  designation  rail  corridor  (10m  wide)  runs  parallel  to  the  eastern  boundary  of 
SH1B.  This  designation  is  described  as  the  Cambridge  Industrial  Branch.  The 
railway  corridor  has  been  inactive  for  a  considerable  period  and  the  railway 
infrastructure was removed more than 10 years ago. Currently the Cambridge rail 
line  now  stops  3.5km  from  Cambridge  (1.5km  from  the  Project  alignment)  and 
operates as an industrial branch line to Hautapu Dairy Factory. Refer to Figure 
7.1 
below. 
Information 
RAILWAY CORRIDOR 
Official 
the 
under 
 
Figure 1.1: Railway corridor 
Released Extensive consultation has been undertaken with ONTRACK to establish their 
long  term  aspirations  for  the  railway  designation.  ONTRACK  has  provided  a 
consistent position that: 
261647.00 
 
 
July 2010 


246
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
▪ 
They  wish  to  maintain  all  their  rights  over  the  rail  corridor  and  have  no 
plans to dispose of the corridor at this time 
▪ 
They would be most unlikely to agree to any “at-grade” crossing of the rail 
corridor by any part of the Project, including on/off ramps 
▪ 
They would be unlikely to agree to an interim at-grade crossing of the rail 
corridor, whereby full grade separation would be provided if the rail was re-
1982
activated. ONTRACK advised they would not like any option that potentially 
compromises the future to this rail line 
However, in March 2010, ONTRACK advised that they had agreed to allow an at-
Act 
grade crossing of their railway designation. This was subject to NZTA agreeing to 
meet all future costs for any subsequent infrastructure needed to enable the rail 
traffic to travel unimpeded through the interchange if the rail line were reinstated. 
This  agreement  is  being  established  within  a  Memorandum  of  Understanding 
(MOU) between ONTRACK and NZTA. 
The central interchange is also located in an area of extensive planned land use 
development,  including  Cambridge  North  Structure  Plan  and  the  Hautapu  Draft 
Structure  Plan.  Waipa  DC  has  indicated  a  strong  preference  for  options  that 
minimise  the  amount  of  land  lost  to  provide  the  interchange  and  associated 
Information 
ramps. 
There is a growing emphasis on the urban design philosophy of “live, work, play”, 
meaning  there  is  a  need  to  closely  integrate  living  and  employment  zones  to 
minimise  the  reliance  on  motor  vehicles  and  encourage  the  use  of  active 
transport modes. The Waipa DC land use development plans look to promote this 
Official 
by  identifying  land  use  proposes  for  large  residential  areas  (Cambridge  North) 
adjacent to large employment centres (Hautapu Industrial). SH1B (Victoria Road) 
will  therefore  always  be an  important  transport  connection  within  the Waipa  DC 
the 
network, by serving as the key link between Hautapu Draft Structure Plan and the 
residential area of Cambridge. Waipa DC also supports this connectivity through 
the  establishment  of  “buffer  zones”  adjacent  to  the  Project  designation.  These 
buffer  zones  incorporate  walking  and  cycling  paths  and  cross  the  Project 
alignment (from the south side to the north side of the designation) at the Central 
Interchange. Refer to Figure 7.2 below. 
under 
 
Released 
261647.00 
 
 
July 2010 



247
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
1982
Act 
 
Figure 1.2: Pedestrian Cyclist Linkages Information 
Geotechnical investigations have determined that the ground water levels around 
the Central Interchange are variable and range between 7m below the surface to 
approximately  2m  below  surface  on  the  eastern  approach  to  the  interchange. 
Excavation  in  these  sandy  soils  would  be  challenging  where  they  encounter 
groundwater and it is recommended this is avoided if possible. Dewatering of any 
Official 
excavation  would  be  needed  during  construction  to  prevent  collapse  of  sand 
under  seepage  pressures.  In  addition,  the  proximity  to  the  groundwater  levels 
would  necessitate  the  need for  permanent  dewatering  within  open  cuts.  Due  to 
the 
the very flat topography and the substantial distance to any gully system (4km to 
Karapiro  Stream  Gully)  dewatering  would  likely  require  permanent  pumping 
stations. 
Only  minor  settlement  of  embankment  fills  is  expected  and  this  should  occur 
relatively quickly and without specific treatment being required. Embankments do 
under 
not have any constructability or stability issues (in comparison to open cuts) and 
are preferable from a geotechnical perspective. Excavation of cuts could impose 
significant  geotechnical  risks  with  regard  to  pavement  performance,  cut  slope 
stability,  environmental  effects  from  lowering  water  tables  and  the  long  term 
drainage needs of the cut. 
(i) 
Interchange Form: 
Early  traffic  analysis  determined  that  the  need  for  continual  movement 
Released  ramps was not warranted at this location. As such, all interchange options 
included ramp terminations at SH1B. 
Two interchange options were considered: 
261647.00 
 
 
July 2010 




248
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
– 
Conventional “diamond” layout 
– 
Half clover leaf (or “Parclo”) arrangement 
North 
RAB 
OR 
OTHER 
INTERSECTION 
1982
TREATMENT 
Hamilton 
Tirau Act 
RAB 
OR 
OTHER 
INTERSECTION 
TREATMENT 
RAIL CORRIDOR 
Information 
 
Figure 1.3: Conventional “diamond” layout 
Official 
RAB 
OR 
OTHER 
North 
INTERSECTION 
TREATMENT 
the 
RAIL CORRIDOR 
Hamilton 
Tirau 
under 
RAB 
OR 
OTHER 
INTERSECTION 
TREATMENT 
Released 
 
Figure 1.4: Parclo arrangement 
 
261647.00 
 
 
July 2010 
10 

249
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
The  conventional  diamond  layout  requires  the  east  facing  ramps  to  cross 
the railway corridor either at-grade (if SH1B remained at ground level) or on 
bridges (if SH1B were elevated). The parclo arrangement avoids the need 
for the ramps to cross the railway corridor as it has a loop arrangement that 
locates  both  west  and  east  facing  ramps  on  the  western  side  of  the 
interchange. 
Table  1.2  below  provides  a  summary  of  the  option  comparison  for  the 
1982
preferred interchange form.  
Criteria 
Comments 
Act 
Geometric Design 
The  Parclo  arrangement  is  less  desirable,  with  the 
northbound  off-ramp  visibility  being  affected  by  any  bridge 
structure  (SH1  or  SH1B).  From  a  design  perspective  the 
diamond  layout  is  preferable.  It  is  also  consistent  with  other 
interchanges on the Waikato Expressway. 
Cost 
The Parclo arrangement was estimated to cost approximately 
$1.1M more than the diamond layout (ignoring land costs). 
Efficiency 
The  Parclo  arrangement  is  marginally  less  efficient  than  the 
Information 
diamond  layout  due  to  the  relative  difference  in  conflicting 
movements and the increased travel distance for travel on the 
south  facing  ramps.  From  an  efficiency  perspective  the 
diamond arrangement is preferred. 
Safety 
The Parclo arrangement is less traditional and has associated 
Official 
safety  features  that  make  the  arrangement  less  safe  than  a 
traditional diamond layout. The diamond layout is preferred. 
the 
Structural 
Bridging  arrangement  will  be  similar  between  the  options, 
although some additional bridge widening may be needed for 
the  Parclo  arrangement  to  counter  the  visibility  problem  for 
the northbound off-ramp. No clear preference. 
Geotechnical 
No quantifiable difference between interchange forms. 
under 
Noise 
No quantifiable difference between interchange forms. 
Landscape 
No quantifiable difference between interchange forms. 
Ecology 
No quantifiable difference between interchange forms. 
Archaeology 
No quantifiable difference between interchange forms. 
Released 
Iwi/Cultural 
Safety  is  considered  paramount  by  iwi;  therefore  diamond 
layout  likely  to  be  preferred  from  this  perspective.  However, 
no clear difference in effects between options. 
261647.00 
 
 
July 2010 
11 

250
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
Criteria 
Comments 
Water Quality 
No quantifiable difference in water quality effects 
Drainage 
No quantifiable difference between interchange forms. 
Social Impacts 
No quantifiable difference between interchange forms. 
1982
Property Impacts 
The  Parclo  arrangement  has  a  significantly  greater  property 
requirement than the diamond layout and affects a large area 
of  proposed  industrial  land.  On  this  basis  the  diamond 
arrangement is preferable from a property perspective. 
Act 
Rail effects 
The  Parclo  arrangement  requires  no  crossing  of  the  railway 
corridor.  The  diamond  arrangement  will  require  additional 
features to re-establish priority to the railway corridor if the rail 
line were re-established. 
Table 1.2: Criteria Comparison for Form of Central Interchange 
On the basis that ONTRACK has confirmed acceptance for interim at-grade 
crossing of the railway corridor, the overall preference for interchange form 
Information 
is  the  diamond  arrangement.  However,  this  preference  is  subject  to  the 
necessary  interchange  alterations  being  readily  achievable  to  allow  rail 
traffic  operation.  Subsequent  discussions  with  ONTRACK  have  confirmed 
that  they  would  be  agreeable  to  the  rail-crossings  being  controlled  by 
signalised at-grade crossings with appropriate bells and barrier arms. 
Official 
(ii) 
Vertical alignment: 
Geotechnical  recommendations  are  that  any  grade  separation  should  be 
provided by embankments. As such, the option for developing interchanges 
the 
with one of the corridors within cut has not been considered further. 
Traditionally  (from  a  traffic  perspective)  it  is  considered  beneficial  for  the 
“main”  through  road  to  remain  at-grade  and  the  secondary  road  to  be 
separated  above  or  below.  This  arrangement  generally  provides  a  better 
under 
“alignment  profile”  to  the  dominant  movement.  However,  this  requirement 
needs to be considered in relation to all other parameters, such as effects 
on  other  transport  modes  (walking/cycling/rail),  urban  design,  cost, 
landform etc. 
Two options have been considered 
– 
SH1B over SH1 (SH1B overbridge) 
Released 
– 
Requires  SH1B  to  be  graded  onto  an  8-9m  high  embankment 
with an approximate length of 350m from either approach (this 
provides  the  ramp  terminations  to  be  located  at  the  top  of  the 
261647.00 
 
 
July 2010 
12 

251
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
embankment. This embankment height is needed to maintain a 
6m clearance along the SH1 corridor 
– 
Requires  the  rail  corridor  to be built on  a  large embankment  if 
rail  reinstated.  The  rail  embankment  would  be  approximately 
1km  long  on  either  approach  to  meet  the  necessary  vertical 
requirements for rail design 
1982
– 
The SH1B bridge over the Expressway would be approximately 
78m  long  and  approximately  16m  wide.  A  total  bridge  surface 
area  of  approximately  1,250m2.  However,  a  separate  bridge 
structure  would  be  required  for  the  rail  corridor  if  it  were  re-
Act 
established. 
– 
Expressway  ramps  will  need  to  be  constructed  on  8-9m  high 
embankments 
to 
intersect 
with  SH1B.  These 
ramp 
embankments  would  be  approximately  350m  long  in  either 
direction 
– 
Special  provision  is  needed  to  connect  the  pedestrian  and 
cyclist routes up to the SH1B corridor 
Information 
– 
The SH1B  overbridge  would  create  a 700m  long  severance  to 
frontage access and is likely to discourage walking and cycling.  
– 
SH1 over SH1B (SH1B underpass) 
– 
Requires SH1 to be graded onto an 8m high embankment with 
an  approximate  length  of  900m  from  either  approach  This 
Official 
embankment  height  is  marginally  lower  than  the  alternative 
SH1B  embankment  because  SH1B  can  be  constructed  closer 
to the existing ground level 
the 
– 
The  SH1  bridge over  SH1B  would be approximately  84m  long 
and  comprise  of  two  structures  (for  each  direction)  of 
approximately  11.5m  each.  A  total  bridge  surface  area  of 
approximately  1,900m2.  This  bridge  would  not  require  any 
under  adjustment if the rail were reinstated. 
– 
Expressway ramps would be constructed at ground level  
– 
There  are  known  localised  flooding  issues  commencing 
approximately  500m  east  of  the  Central  Interchange.  The 
placement of the SH1 on an embankment in this location will be 
needed  to  ensure  the  Expressway  (and  its  infrastructure) 
remain above these flood levels. This option is compatible with 
Released 
this arrangement. 
– 
Maintaining  SH1B  at  ground  level  will  provide  a  better  linkage 
across  the Expressway  by  maintaining  access  at  ground  level. 
261647.00 
 
 
July 2010 
13 


252
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
This avoids a length of “broken active edge” (refer to Figure 7.5 
below). This is particularly important for encouraging linkage by 
active 
modes. 
In 
addition, 
this 
arrangement 
allows 
intensification  of  landuse  adjacent  to  Victoria  Road,  which 
supports  active  transport  modes.  It  is  also  likely  to  be  more 
amenable  to  creating  a  welcoming  corridor  (or  entrance)  into 
Cambridge  Township  along  Victoria  Road.  This  is  illustrated 
further in Figure 7.5 and Figure 7.6 below. 
1982
Act 
Information 
Official 
the 
 
under 
Figure 1.5: Accessibility at Central Interchange 
Released 
261647.00 
 
 
July 2010 
14 
























253
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
1982
Act 
Information 
 
Official 
Figure  1.6:  Ability  of  SH1  embankment  option  providing  better  visual 
connection  to  Victoria  Road  (source:  Brewer  Davidson  Preliminary 
Urban Design Report) 

the 
Table  1.3  below  provides  a  summary  of  the  option  comparison  for  the 
vertical arrangement between SH1 and SH1B.  
Criteria 
Comments 
under 
Geometric Design 
No particular preference from a design perspective 
Cost 
The two options are likely to be similar in overall costs if the 
needs  for  the  rail  corridor  are  included  in  both  options.  No 
particular  preference  from  an  upfront  cost  perspective. 
However, this does not take account of the need for NZTA to 
maintain funds to establish the rail corridor embankment and 
bridge structure at some point in the future. 
Released 
261647.00 
 
 
July 2010 
15 

254
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
Criteria 
Comments 
Efficiency 
There are some marginal efficiency gains for SH1 vehicles if 
SH1B  is  graded  over  the  Expressway.  These  gains  are 
provided  by  reduced  vehicle  operating  costs  with  flatter 
expressway  grades.  However,  accessibility  for  pedestrians 
and  cyclists  will  be  significantly  impacted  if  SH1B  is  located 
on an embankment.  
1982
Safety 
The arrangement  with  the  ramp terminations at ground  level 
is  considered  to  be  marginally  preferable  to  having  them 
Act 
constructed  on  embankments.  The  option  with  SH1  over 
SH1b is therefore preferred. 
Structural 
Overall there is little difference between the two options from 
a structural perspective if the needs for the rail corridor bridge 
are included in the assessment. No clear preference. 
Geotechnical 
No quantifiable difference between arrangements. 
Noise 
There is likely to marginally greater noise effects with the SH1 
corridor  on  an  embankment.  This  is  due  to  the  elevation  of 
Information 
the  higher  volume of traffic.  However,  the effects from noise 
are  likely  to  be  easier  to  mitigate  along  the  SH1  corridor. 
Mitigation  along  a  SH1B  embankment  would  be  difficult 
without a significant effect on accessibility. On this basis, the 
preference for noise effects is considered to be neutral. 
Official 
Landscape 
The  SH1  embankment  is  likely  to  have  a  greater  impact  on 
the  background  landscape  by  forming  a  clearly  obvious 
landform  change.  However,  it  is  acknowledge  that  even  the 
the 
SH1B  overbridge  arrangement  will  also  include  some 
significant  embankment  structures  from  the  Expressway 
ramps connecting with the elevated SH1B alignment.  
Overall, there is a preference for the SH1B overbridge option. 
under 
Ecology 
No quantifiable difference between arrangements. 
Released 
261647.00 
 
 
July 2010 
16 

255
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
Criteria 
Comments 
Urban Design 
The need to consider the connectivity between landuse areas 
is important and cannot be replaced if broken.  
There is also a need to consider all transport modes and it is 
acknowledged  that  any  forced  grade  separation  for 
pedestrians and cyclist above ground level will create a lower  1982
amenity.  
It  is  likely  that  Victoria  Road  will  become  the  preferred 
northern entrance into Cambridge and its corridor needs to be 
Act 
protected for future development.  
Finally, it is seen that the SH1 embankment may be seen as 
a  positive  way  to  provide  a  defined  separation  between 
residential  activities  with  Cambridge  North  the  industrial 
activities  within  Hautapu  (creating  a  town  edge).  Buildings 
within industrial areas can be up to 12m in height and these 
blank  rear  walls  are  seen  to  be  unattractive.  Whilst  these 
walls could be screened by dense planting, although this may 
create unsafe (or unsecure) walking and cycling paths along 
Information 
the proposed Industrial and residential buffer zones. 
The SH1 embankment option is preferred. 
Archaeology 
No quantifiable difference between arrangements. 
Official 
Iwi/Cultural 
No quantifiable difference between arrangements. 
Water Quality 
No quantifiable difference between arrangements. 
the 
Drainage 
No quantifiable difference between arrangements. 
Social Impacts 
No quantifiable difference between interchange forms. 
Property Impacts 
There are similar property impacts with both options, although 
under  the SH1B embankment option requires marginally more land 
overall to construct the offline embankment to avoid affect on 
the  rail  corridor.  In  addition,  there  are  increased  problems 
associated with maintaining access to the SH1B corridor. It is 
noted  that  this  assessment  does  not  consider  the  relative 
difference in forecast land values post construction. 
From  a  property  requirement  perspective  there  is  a 
preference for the SH1 embankment option. 
Released 
261647.00 
 
 
July 2010 
17 

256
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
Criteria 
Comments 
Rail effects 
ONTRACK have confirmed that they would not be favourable 
to  any  arrangement  that  made  the  reinstatement  of  the  rail 
difficult or expensive. The SH1 embankment option provides 
the easiest reinstatement of the rail corridor. 
The SH1 embankment option is preferred. 
1982
Table 1.3: Criteria Comparison for SH1 and SH1B vertical arrangement 
Overall,  the  option  that  places  SH1  on  an  embankment  over  SH1B  was 
Act 
determined to be the preferred option. 
(iii)  Ramp termination intersections: 
Although the precise form of the intersections may be re-engineered during 
the detailed design phase of this Project, the following provides a summary 
of the option  selection process undertaken  to  determine the best practical 
option. 
Three intersection forms were investigated, including: 
Information 
– 
Priority controlled 
– 
Roundabouts (RAB’s) 
– 
Traffic Signals 
Official 
The priority controlled “Give Way” intersections were deemed inappropriate 
because they would not provide sufficient capacity during peak periods. As 
such, they were not considered further. 
the 
Only  the  traffic  and  urban  design  specialists  determined  a  particular 
preference for either of the two intersection forms. 
Traffic 
under 
Both the RAB and traffic signal layouts provide a similar level of service for 
the traffic operation (based on delays). However, it is noted that the RAB’s 
have less delay and shorter queues during the early years, whilst the traffic 
signals  layout  provides  better  performance  during  the  latter  years  of  the 
project  horizon.  As  such,  from  an  operational  perspective  the  ultimate 
intersection form is the traffic signalised layout. However, it is also noted that 
the traffic signals layout provide additional benefit (other than efficiency) over 
the RAB option because: 
Released  –  The traffic signals can be optimised to favour any route and ensure 
queuing on the off-ramps can be avoided 
261647.00 
 
 
July 2010 
18 

257
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
– 
The  traffic  signals  are  compatible  with  the  ultimate  arrangement 
necessary  if  the  rail  corridor  were  reinstated  (i.e.  if  the  rail  corridor 
were  re-established  the  intersection  would  need  to  be  signalised  to 
control traffic across the live rail line). Therefore, the early adoption of 
traffic  signals  avoids  potential  retrofitting  costs  and  minimises  the 
overall Project cost. 
– 
The  traffic  signals  layout  provides  an  easier  crossing  point  for 
1982
pedestrians  and  a  safer  alternative  for  on-road  cyclists  when 
compared to the RAB layout. 
Urban Design 
Act 
The urban  design  assessment for  the SH1B  intersection forms  is focussed 
on the need for good accessibility. On this basis the traffic signalised layouts 
were deemed preferable, because: 
– 
The traffic signals layout provided a better level of service and safer 
crossing points for active modes of transport 
– 
This  layout  enhanced  user  choice  and  supports  social  cohesion  by 
providing good connectivity between land use areas and activities 
Information 
– 
The  emphasis  on  supporting  active  modes  is  consistent  with  NZ 
Urban Design Protocols 
In summary, the Traffic Signals layout is preferred at the intersections of the 
Project ramp terminations with SH1B. 
Official 
(c) 
Southern Interchange 
Traffic modelling predictions determined a need for this interchange to be grade 
the 
separated,  which  is  also  consistent  with  the  overall  RoNS  philosophy  for  the 
Waikato Expressway. As such, no at-grade interchanges were considered. 
The southern interchange option evaluation considered the: 
▪ 
Provision for south facing ramps only (half interchange) 
under 
▪ 
Provision for north and south facing ramps 
Traffic modelling was undertaken to determine the relative demands for each of 
the  two  ramp  arrangements.  The  assessment  determined  that  there  was  a 
negligible  demand  for  the  north  facing  ramps  at  this  location  during  any  of  the 
modelled periods. This included assessment for projected land use development 
beyond the project horizon. The modelling recognises that: 
Released ▪  The route for local trips (e.g. from Shakespeare Street to Hamilton) is 
approximately  2km  longer  if  they  were  to  use  the  Southern  Interchange 
ramps to access the Cambridge Section when compared to the route along 
the existing network through the township 
261647.00 
 
 
July 2010 
19 

258
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
▪ 
The Project will remove approximately 50-60% of the through trips from the 
existing  SH1  corridor  through  Cambridge.  As  such,  when  the  Project  is 
complete the  route  through  Cambridge  township becomes  less  congested 
and  therefore  becomes  more  attractive  to  traffic  to/from  Shakespeare 
Street 
As  such,  the  modelling  determined  that provision  for  north facing  access  at  the 
Southern Interchange would not result in a traffic demand that was justifiable for 
1982
including the north facing ramps. 
A  turning  count  (and  destination)  survey  was  undertaken  at  the 
SH1/Shakespeare  Street  intersection  to  determine  the  potential  catchment  of 
Act 
northbound  HCV’s  if  prohibition  required  HCV’s  to  travel  north  through  the 
Southern Interchange. The survey determined that: 
▪ 
74%  of  HCV’s  that  use  the  intersection  are  northbound.  Of  these 
northbound HCV’s: 
– 
16% were local buses 
– 
28% carried local building supply materials 
Information 
– 
22% were local delivery type vehicles 
– 
8% were refuge/recycle vehicles 
▪ 
Overall,  50%  of  the  northbound  HCV’s  were  found  to  have  a  destination 
within the Cambridge CBD (near Victoria Street) or within the Queen Street 
industrial/commercial area. A further 25% had a destination along industrial 
Official 
areas  of  Victoria  Road.  Only  25%  of  the  northbound  HCV’s  had  a 
destination north of Cambridge along SH1 or SH1B. As such, even if travel 
through  the  township  was  prohibited  for  HCV’s  after  the  Project  was 
the 
constructed,  only  25% of the  northbound  HCV’s would  be  attracted  to  the 
north facing ramps  
The turning count confirmed that the inclusion of north facing ramps would have 
very little demand given the efficiency of the alternative route along the existing 
under 
SH1,  even  if  HCV’s  were  prohibited  from  travel ing  through  the  township.  As 
such,  only  south  facing  ramps  have  been  included  in  subsequent  Project 
development. 
(i) 
Interchange Options 
A prime issue with the southern interchange relates to the need to maintain 
access to adjacent properties. 
Released  Overall, five interchange options were considered, including: 
– 
Option 1: as per arrangement identified in original designation 
261647.00 
 
 
July 2010 
20 



259
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
1982
Act 
 
• 
Provides high speed (80km/h) south facing ramps 
• 
Places southbound ramp on bridge over the Expressway 
Information 
• 
Provides no consideration of local access to adjacent properties 
– 
Option 2: Loop Road to provide combined on ramp and local access 
Official 
the 
under 
 
• 
Southbound ramp is split part way along its length to provide two-
way directional traffic for local access and one way traffic for on-
Released 
ramp function 
• 
Mixture  of  local  traffic  and  Expressway  traffic  is  not  ideal  at  an 
interchange location 
261647.00 
 
 
July 2010 
21 


260
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
• 
Changes  in  directional  provision  on  roads  is  not  ideal  near 
interchange ramps 
• 
Large land requirement to construction southbound ramp 
• 
Southbound ramp has a low speed design of 60km/h 
• 
Approximately $1.5M more expensive than option 1 
1982
– 
Option  3:  Two  roundabout  configuration  to  connect  local  traffic  to 
roundabouts 
Act 
Information 
Official 
 
• 
The  dual  RAB’s  minimise  the  property  footprint  imposed  by 
Option 2, but maintains access to adjacent properties through the 
the 
RAB’s 
• 
The RAB’s provide a good speed threshold to manage the speed 
differentials between the local traffic and the Expressway traffic 
under • The RAB’s would impose a significant delay and additional 
operating cost to the dominant through movement that don’t wish 
to  access  the  adjacent  properties.  Therefore  this  option  is 
significantly less efficient when compared to the other free-flowing 
options 
• 
The RAB’s add a significant cost to the Project. Overall this option 
is approximately $3.8M greater than Option 1 
Released  –  Option 4: Utilising a single roundabout for local connections to the 
north and separate access way for properties to the south 
261647.00 
 
 
July 2010 
22 



261
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
1982
Act 
 
• 
Similar  benefits  as  Option  3,  but  requires  only  one  RAB  to  be 
constructed 
• 
Similar effect on operational efficiency as Option 3 (but lesser) 
Information 
• 
Approximately $1.8M more expensive than Option1 
– 
Option 5: Separation of local traffic from high speed on-off access to 
expressway,  providing a  separate access  road adjoining  Tirau  Road 
further west for the properties to the north. Similar to option 1 except 
Official 
the southbound ramp passes beneath the expressway 
the 
under 
Released 
 
• 
Similar  efficiency  to  Option  1  and  provides  a  free-flowing 
operation 
261647.00 
 
 
July 2010 
23 

262
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
• 
Includes  provision  for  adjacent  property  access  through 
development of parallel local service roads alongside ramps 
• 
Lengthens  the  overpass  to  allow  an  additional  width  for  the 
parallel local road 
• 
Additional construction cost over Option 1 of approximately $1.5M 
1982
Options 2, 3, and 4 were primarily developed to al ow north facing ramps to 
be  constructed  without  significant  construction  effort.  However,  these 
arrangements imposed significant cost and negligible demand for the north 
facing ramps makes the additional costs unjustifiable, particularly because 
Act 
of the reduced efficiencies imposed on the southbound traffic (regardless if 
north facing ramps were ever constructed). 
Overall Option 5 (high speed ramps with separate local road access) was 
deemed to be preferable for the Southern Interchange arrangement as it: 
– 
Provided  good  access  for  both  local  traffic  and  Expressway  traffic, 
without compromising safety 
– 
Provides an efficient option for all traffic movements for the long term 
Information 
– 
Minimises the  land requirement for the interchange footprint 
– 
Has  minimal  additional  cost  to  provide  for  the  long  term  access 
requirements for adjacent properties 
(d) 
Local Road connection  Official 
To  enable  the  Project  to  be  developed  consistently  with  the  Project  Objectives, 
the corridor provides no direct connection with any local roads. This arrangement 
the 
is consistent with the current designation arrangements. As such, all local roads 
that cross the existing designation need to be severed or grade separated from 
the Project. 
Long  term  plans  for  local  road  connectivity  have  been  developed  over  a  long 
period with collaboration between NZTA and Waipa DC. The decision for which 
under 
roads  remain  open  and  which  are to be  closed has been determined by Waipa 
DC.  As  such,  no  option  evaluation  for  the  local  road  connectivity  has  been 
undertaken by the NZTA. 
The options for grade  separation arrangements between  the  local  road  and the 
Project  are  limited  to  above  ground  options  only.  Geotechnical  investigations 
have determined a high risk associated with constructing corridors below ground 
level,  primarily  associated  with  the  risk  of  ground  water  flows  and  a  lack  of 
Released opportunity to drain water from the cut areas. 
261647.00 
 
 
July 2010 
24 

263
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
1.4.5  Karapiro Stream Gully Crossing 
The Karapiro Stream has formed a large and impressive gully and it is by far the most 
substantial natural physical feature encountered by the Project, which for the most part 
passes through a flat, highly altered landscape. 
The two principal options for crossing the gully are: 
1982
− 
Bridge structure, consisting of tall piers with medium to long spans. 
− 
Embankment fill requiring large diameter culverts within the embankment to carry 
the stream flow. This option also has a sub-option of using reinforcement within 
Act 
the  fill,  mechanically  stabilised  earth  (MSE)  to  steepen  the  embankment  side 
slopes and thus decrease the quantity of fill and length of culverts. 
A comprehensive option evaluation was undertaken for the two crossing options. The 
following provides a brief summary of the evaluation comparison. 
 
Bridge 
Embankment 
Cost 
Lowest 
cost, 
even 
with  Highest  cost  (Approximately  $11M 
highest  bridge  construction  greater  than  the  bridge  option).  The 
cost rates. 
MSE  sub-option  is  approximately 
Information 
 
$8M greater than the bridge option 
Technical 
Technical  and  design  issues  Technical  and  design  issues  to  be 
feasibility 
to be resolved with respect to  resolved 
with 
foundation 
gully  side  slope  stability  improvement  and  the  MSE  sub-
works 
option  
 
Official 
Risk 
Risks  associated  with  gully  High 
construction 
risk 
from 
slope stability, pile foundation  unforeseen  settlements,  instability, 
depths 
and 
access 
for  flooding during construction 
the 
construction  
 
Potential 
environmental 
damage 
risks  are  higher  than  the  bridge 
option 
 
Constructability 
Construction  techniques  well  Significant  issues  to  be  resolved  for 
under 
developed  for  bridge  gully  fill  transport  to  base  of  gully  and 
crossings 
management  of  stream flows  during 
construction 
 
Waterway 
No significant affect 
Considerable likely impact 
 
Released 
261647.00 
 
 
July 2010 
25 

264
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
 
Bridge 
Embankment 
Ecological 
Effects can be minimised and  Major effect on gully system 
gully  enhanced  in  the  long  Loss  of  potential  gully  walkway 
term 
system 
Significant 
vegetation 
clearing  of  gully  side  slopes 
in  the  vicinity  of  the  bridge 
required  to  enable  stability 
1982
works 
 
Table 7.4: Karapiro Stream Gully Crossing Option Evaluation 
Act 
Ngaiti Koroki Kahukura and Ngaiti Haua (as mana whenua for the Project area) have 
indicated  to  the Project  team  that  they  have a  clear  preference for  the bridge  option. 
This  is  because  they  have  particular  concerns  relating  to  potential  greater  adverse 
effects on the gully system with the culvert option. 
The  bridge  solution  for  crossing  the  Karapiro  Stream  Gully  is  favoured  on  almost  all 
grounds  over  the  embankment  option(s)  and  provides  the  lowest  cost  solution. 
Therefore the bridge option is the preferred option. 
1.4.6  Vertical alignment design 
Information 
The options for considering the vertical alignment of the corridor are very limited. Key 
limitation relate to: 
− 
The requirement to treat and discharge stormwater to appropriate watercourses 
Official 
− 
The  flat  terrain  which  makes  it  difficult  to  grade  stormwater  to  suitable  outlets 
(minimum vertical grades needed to convey stormwater) 
the 
− 
The limited number of suitable stormwater discharge points 
− 
The relatively high ground water level 
− 
The close proximity to established residential areas 
under 
− 
Known ground surface flood levels adjacent to the corridor 
In  general,  it  is  recognised  that  many  of  the  adverse  effects  associated  with  a  road 
corridor can be minimised by placing the alignment below ground level. However, this 
arrangement  is  not  possible  except  on  the  approaches  to  the  Karapiro  Stream Gully, 
whereby the gully provides a potential location for stormwater disposal. 
As  such,  comparable  vertical  alignment  options  were  not  considered  as  part  of  this 
Project.  Instead  the  vertical  alignment  has  been  optimised  by  identifying  key  design 
Released 
constraints that prevent further lowering of the corridor. These constraints include: 
− 
Maintaining  a  0.3%  vertical grade  towards the  Karapiro Stream  Gully  to  ensure 
positive flow to the stormwater outlet 
261647.00 
 
 
July 2010 
26 


265
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
− 
Provision of a minimum acceptable free-board above the 1-in-100 year flood level 
at Watkins Road 
− 
Limiting  practical  cut  heights  to  8m  in  depth  to  limits  effects  on  adjacent 
properties,  minimise  ground  water  intrusion flows,  and  limit  the  need  for  use  of 
retaining wall systems 
1.4.7  Pa site options 
1982
The presence of the Pa site adjacent to the Karapiro Stream Gully was firstly identified 
during  an archaeological  walkover  assessment. Subsequent  investigations of  the  site 
were undertaken:  
Act 
− 
a non-intrusive survey, using Ground Penetrating Radar was carried out around 
in and around the identified pa site and the borrow pits 
− 
a topographical ground survey of the observed archaeological sites to accurately 
map these archaeological features in relation to the designated road corridor 
The extent of the pa site was found to intrude at least 15m into the existing (40m width) 
designation, with most of the apparent extents of the pa being located to the north of 
the  Project  alignment.  Hence  it  was  clearly  apparent  that  the  Project  could  not  be 
Information 
constructed along its current alignment without affecting the Pa site. 
Official 
Extent 
of 
pa 
site 
identified  within  GPR 
investigation 
the 
under 
Existing 
designation 
boundary 
 
Released 
Figure 1.7: Extent of pa site adjacent to Karapiro Gully 
261647.00 
 
 
July 2010 
27 

266
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
In December 2008, mana whenua advised that they considered the pa site to be waahi 
tapu  and  they  would  be  opposed  to  any  disturbance  to  the  pa  site,  either  partial  or 
complete. 
Four  options  were  considered  to  minimise  the  impacts  on  the  Pa  site,  including  two 
horizontal realignments and two vertical realignments. 
(a) 
Horizontal Realignment towards the east 
1982
This option involves shifting the horizontal alignment to pass to the north east of 
the Pa site. This would involve a significant alignment shift (as the majority of the 
pa extends to the north east of the current designation). The following provides a 
Act 
brief description of the option considerations: 
▪ 
The realignment would add approximately 300m to the road corridor length. 
▪ 
The archaeological investigations undertaken to date could not determine if 
there were any additional archaeological sites that may be affected with this 
realignment option. 
▪ 
This realignment would result in the Karapiro Stream Gully crossing being 
located  at  a  much  wider  location.  This  would  add  at  least  100m  to  the 
Information 
length of the bridge structure.  
▪ 
Another local road bridge would be required if St Kilda Road was to remain 
connected to Thornton Road. 
▪ 
Three additional houses would need to be removed 
Official 
▪ 
The  total  additional  cost  would  be  approximately  $10M  with  $6M  in 
additional construction and $4M in additional property costs. 
the 
(b) 
Horizontal Realignment towards the west 
This option only requires a very minor centreline shift, when combined with some 
refinement  to  the  cross-section  (narrowing  of  the  median  and  inclusion  of 
retaining  walls).  The  following  provides  a  brief  description  of  the  option 
considerations: 
under 
▪ 
The construction footprint can be accommodated within the space between 
the  eastern  boundary  of  the  Athlone  Drive  properties  and  the  western 
extent of the pa.  
▪ 
There is some encroachment into an existing Waipa DC buffer strip. 
▪ 
Waipa DC have indicated that the loss of the buffer strip is acceptable if an 
equivalent reserve area can be established from severed land adjacent to 
Released  the Karapiro Stream Gully. 
▪ 
One additional house would need to be removed 
261647.00 
 
 
July 2010 
28 

267
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
▪ 
The cost of this option is approximately $2M (primarily associated with the 
purchase of the additional house and construction of the retaining walls) 
(c) 
Vertical Realignment beneath the Pa site 
The Project’s preferred vertical alignment is approximately 7m below the ground 
level  in  the  vicinity  of  the  pa  site.  It  is  likely  that  the  remains  of  pa  exist  to  a 
maximum depth of 1m. Therefore, only a minor lowering of the vertical alignment 
1982
would enable the corridor to be “tunnelled” underneath the pa and still maintain 
appropriate  vertical  headroom.  The  following  provides  a  brief  description  of  the 
option considerations: 
Act 
▪ 
Conventional tunnelling would not be feasible because of the shallow cover 
above  the  tunnel  (approximately  2m),  the  relatively  short  length  of  tunnel 
being required (less than 50 metres), and the nature of the soils (SANDS). 
▪ 
The  only  feasible  construction  option,  which  avoids  disturbance  to  the  Pa 
remains, would involve thrusting a large “shield type structure beneath the 
pa  site.  The  shield  will  support  the  soil  whilst  the  cavity  is  excavated  and 
supports the roof whilst the walls are constructed. 
▪ 
The cost of this operation would be considerable and there are a number of 
Information 
technical  challenges  to  avoid  disturbance  to  the  overlying  soil  during 
construction. 
▪ 
The overall  appearance  of  a short  tunnel  section  adjacent  to the  Karapiro 
Stream Gully bridge would be unusual. 
▪ 
Iwi have advised that this option is culturally inappropriate and they would 
Official 
be opposed to it.  
▪ 
The cost of this option is approximately $5M. However, there would also be 
the 
large contingency risk items that would need to be included due to design 
uncertainties. 
(d) 
Vertical Realignment over the Pa site 
This option includes the construction of a bridge over the Pa site and leaving the 
under 
ground  underneath  largely  undisturbed.  The  Project  would  be  aligned 
approximately 10m above the existing ground level. The following provides a brief 
description of the option considerations: 
▪ 
This  option  would  cause  significant  adverse  environmental  effects 
(including noise and visual), which would be difficult to mitigate. 
▪ 
The Project’s  preferred  vertical alignment  has  the  corridor  in a  substantial 
cut.  The  cutting  minimises  the  visual  impact  and  provides  excellent  noise 
Released  mitigation for the residents adjacent to the corridor. 
261647.00 
 
 
July 2010 
29 

268
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
▪ 
The  raising  of  the  vertical  alignment  would  affect  the  Thornton  Road 
crossing  and  require  Thornton  Road  to  be  lowered  beneath  the 
Expressway, which will have consequential geometric and visibility issues. 
▪ 
The  Karapiro  Stream  Gully  Bridge  would  be  lengthened  by  approximately 
40m  and  require  the bridge  piers  to be  lengthened by  approximately 17m 
(to 45m+). 
1982
▪ 
The additional cost of this option would be at least $6M.  
 
Act 
Table 1.5 below provides a summary of the option comparison for the four options.  
 
Horizontal Realignment 
Vertical realignment 
Criteria 
East 
West 
Lower 
Raise 
 
Geometric Design 
No specific 
No specific 
No specific 
No specific 
issues 
issues 
issues 
issues 
Additional Cost 
$10M 
$2M 
$5M (plus 
$6M 
significant risk) 
Information 
Longer route 
Insignificant 
Some slight 
Substantial 
Efficiency 
resulting in 
change 
increase in 
increase in 
additional 
operating costs 
operating costs 
operating costs 
due to increased 
due to steeper 
grades 
grades 
Safety 
No specific 
No specific 
No specific 
No specific 
Official 
issues 
issues 
issues 
issues 
Structural 
Longer bridge but 
Minor increased 
Particular 
Additional bridge 
the 
technically 
structural 
structural risk 
structure for 
feasible. Also 
requirements 
Expressway. Also 
includes 
complications 
additional local 
with Thornton 
road bridge 
Road crossing 
under 
Geotechnical 
No specific 
No specific 
Some additional 
No specific 
issues 
issues 
risk 
issues 
Noise 
No specific 
No specific 
No specific 
Increased noise 
change 
change 
change 
mitigation 
requirements 
Landscape 
No specific 
No specific 
No specific 
Visual effects 
change 
change 
change 
more difficult to 
Released 
mitigate 
Ecology 
No specific 
No specific 
No specific 
No specific 
change 
change 
change 
change 
261647.00 
 
 
July 2010 
30 

269
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
 
Horizontal Realignment 
Vertical realignment 
Criteria 
East 
West 
Lower 
Raise 
 
Urban Design 
No specific 
No specific 
No specific 
Vertical 
change 
change 
change 
separation of 
Thornton Road 
crossing is not 
ideal 
1982
Archaeology 
Unknown risk 
Likely to affect 
Very risky to 
Unknown risk 
outer lying 
archaeological 
portions of the pa  
site 
Act 
Iwi/Cultural 
Avoids pa site 
Avoids pa site 
Culturally 
Culturally 
inappropriate 
inappropriate 
Water Quality 
No specific 
No specific 
No specific 
No specific 
change 
change 
change 
change 
Drainage 
No specific 
No specific 
No specific 
No specific 
change 
change 
change 
change 
Social impacts 
No specific 
Minor effects 
No specific 
Not favoured 
Information 
change 
from alignment 
change 
closer to Athlone 
Drive residents 
Property impacts 
Significant due to 
Minor effect on 
No change 
No change 
corridor being 
buffer zone and 
Official 
very removed 
one additional 
from existing 
property 
designation. 
Additional land 
the 
required 
Table 1.5: Summary of Pa site realignment option evaluation 
Overall,  the  option  with  a  minor  horizontal  realignment  towards  the  west  was 
determined to be preferred.  
under 
Ngaiti Koroki Kahukura and Ngaiti Haua (as mana whenua for the Project area) have 
indicated to the Project team that the preferred pa site realignment option is acceptable 
to them. 
1.4.8  Localised design features 
The  stormwater  design  identified  a  need  for  a  wetland  to  store  and  treat  stormwater 
collected  by  the Project.  This  is  required  to  be  located at  the  low  point  of  the  vertical 
Released 
alignment within the cut section of the Expressway (identified at Chainage 9100). 
261647.00 
 
 
July 2010 
31 

270
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
Options for placing the wetland on either side of the Expressway in this location have 
been  considered. Both options are technically feasible and  there  is  no  preference for 
locating the pond on either side of the corridor from a design perspective. 
A  landscape  design  and  urban  design  assessment  has  determined  a  particular 
preference for  the  wetland  to  be  located  on  the west  side of the  Expressway.  This  is 
considered to be preferred because: 
1982
− 
It will be more compatible with the 30m wide buffer zones currently identified on 
the western side of the Expressway within the Waipa District Plan.  
Act 
− 
It provides great opportunity to link the buffer zone to Thornton Road and Athlone 
Drive, thereby directing the buffer corridor to the proposed reserve area adjacent 
to Karapiro Stream Gully.  
− 
The proposed landscaping around the wetland wil  provide a more useable asset 
for Waipa DC.  
− 
The  wetland  will  provide  better  separation between the  residential  area and  the 
Expressway. 
− 
The alternative location (wetland on the eastern side of the Expressway) does not 
Information 
provide  any  connectivity between  the  proposed  landscaped  area  and any other 
landscape or community feature 
Placement  of  the  wetland  on  the  western  side  of  the  Expressway  will  affect  one 
landowner  (also  affected  by  the  existing  designation).  Three  landowners  will  be 
affected  with  the  wetland  being  located  on  the  east  side  of  the  Expressway  (two  are 
Official 
already affected  by  the existing  designation  and the  third  is  affected  by  the  proposed 
alteration to designation). 
One  of  the  directly  affected  landowners  has  identified  a  particular  attachment  to  the 
the 
land  bordering  St  Kilda  Road  and  has  a  long  family  association  with  the  land  since 
1880.  They  have  indicated  a  strong  preference  for  the  wetland  to  be  located  on  the 
eastern side of the Expressway. 
Overall, the option for locating the wetland on the western side of the Expressway has 
under 
been determined to be preferred. 
1.5  Conclusion 
In summary the option evaluation process has determined that: 
• 
An alteration to designation is required to accommodate the latest design requirements 
• 
There  is  a  preference  for  the  widening  of  the  designation  to  generally  occur  on  the 
Released 
northern  side  of  the  existing  designation,  except  to  accommodate  specific  design 
features 
261647.00 
 
 
July 2010 
32 

271
Waikato Expressway – Cambridge Section 
Option Assessment Summary Document 
 
• 
The  Northern  Interchange  should  only  provide  north  facing  ramps.  The  southbound 
ramp should be graded vertically over the Expressway 
• 
The  Central  Interchange  should  be  a  traditional  diamond  layout.  The  Expressway 
should be graded vertically over Victoria Road (SH1B). The intersection at the Central 
Interchange ramp terminations should be signalised junctions. 
• 
The Southern Interchange should provide only south facing ramps. The layout should 
1982
provide  high-speed  free  flowing  movements  and  provide  separate  local  roads  for 
adjacent property access 
• 
There should not be any direct connection between the Expressway and local roads 
Act 
• 
The Karapiro Stream Gully crossing should be a bridge 
• 
A minor horizontal realignment of the Expressway towards the west should be included 
to minimise the effects on the Pa site. This shall also include a localised refinement of 
the  Expressway  cross-section  (including  narrowing  the  median  and  incorporation  of 
retaining walls) 
• 
The Thornton Road wetland should be positioned on the west side of the Expressway 
Information 
 
 
Official 
the 
under 
Released 
261647.00 
 
 
July 2010 
33 

272
 
1982
Act 
Information 
 
Official 
the 
under 
Released 
261647.00 
 
 
July 2010 
34