URGENT: We request urgent processing to update the total value of the contract as there is 
Minister interest on the payment as quickly as possible. 
 
 
 
 
 
 
 
 
 
 
 
 
Coversheet – V.2. March 2024 
 

DEED OF VARIATION 
Deed number: 25760 
Variation number: 2 
 
THIS DEED OF VARIATION 
is made the 27th day of June 2025 
 
BETWEEN: 
 
THE  SOVEREIGN  in  right  of  New  Zealand,  acting  by  and  through  the  Secretary  for  the 
Environment (the Ministry); and 
 
Rotorua Lakes Council (the Recipient
 
BACKGROUND: 
 
A. 
The  Ministry  and  the  Recipient  entered  into  an  agreement  (Ministry  Deed  number 
25760) for the delivery of the Lake Tarawera Sewerage Reticulation Scheme Freshwater 
Improvement Fund Project from 26 October 2022 (the Deed). 
 
B. 
The Parties wish to vary the terms of the Deed in accordance with clause 3.2 (Changes) 
of the Deed. 
 
THE PARTIES AGREE AS FOLLOWS: 
 
1. 
The Parties agree to vary the Deed as set out in the attached Schedule of Changes 
with effect from the Effective Date stated in the Schedule of Changes. 
 
2. 
Subject to the changes made by this Variation, the terms and conditions of the Deed 
remain in effect. 
 
3. 
Words  used  but  not  defined  in this  Variation  shall  have  the  same  meaning  given to 
them in the Deed. 
 
 
 
 
 

 
 
 



Schedule of Changes 
 
Effective Date
: 30 June 2025 
 
Changes 
 
 
1. 

Part A: Specific and Special Terms  
 
1.1 
Term Expiry Date is deleted and replaced with the following: 
  
 
30 September 2025     
 
1.2 The Grant amount is deleted and replaced with the following: 
 
 
$7,500,000 (GST excl) 
 
2. 
Section B: Project details 
 
2.1 Total project cost is deleted and replaced with the following: 
 
$16,711,350.181 
 
2.2 Total Freshwater Improvement Fund contribution is deleted and replaced with the 
following: 
 
$7,500,0002 
 
3. 
Section C: Project objectives, activities, and budget 
 
3.1 Table 6 Funding Information is deleted and replaced with the following: 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
1 Minimum total project costs based on figures reported as of 30 April 2025 
2 $7,500,000 is the maximum payable Crown contribution, in line with the deed of funding (clause 2.1) 
 



Out of Scope