Below is a status update for South Express Parker St.
South Express Parker St Project Update 31 March 2025
Property Related Agreements
Reference
Deed of Grant Section 7 Templeton Signed
G92140
Licence to Occupy Lease Variation
Section 7 Templeton
Signed
L67788
Level Crossing Grant Agreement
Drafted
G92258.1
JN sent asset info to property to include in grant
Waterloo Rd Small Grant Addition
agreement
QS Estimate
50%Estimate
Sent to CCC
100% Estimate
Project Scoping to be reviewed
Signals Design
Programmed Complete April 2025
On Hold subject to scope review
Programme Update
Programme
Indication from CCC manager project to be FY 2028
Scope review now under discussion for this project
Risks
Scope
internally at KiwiRail