This is an HTML version of an attachment to the Official Information request 'District Plan Appeals Version 2021'.

 
18 March 2025 
 
 
 
 
 
Wendy Pond 
[FYI request #30147 email] 
 
 
 
Dear Wendy 
 
Official information Request for District Plan Appeals Version 2021 
 
I refer to your official information request dated 19 February 2025 for information on the 
legal status of the District Plan Appeals Version 2021. Please see below responses from 
Council’s Strategy and Policy team. 
 
The Resource Management Act 1991 (RMA) sets out the different versions of district plans 
that local authorities may produce. The table below shows this along with the corresponding 
clause of the Act. 
 
TCDC plan 
 
Version of the plan 
RMA provision 
Purpose of the plan version 
version 
 
Operative District Plan  
Schedule 1 cl 17(3) and cl 20 
April 2010 
Plans  are  made  operative  once  al   of  the 
 
appeals  on  them  are  determined.  Local 
Authorities  make  plans  operative  through 
Council  resolution  and  by  affixing  the 
common seal. 
The operative version is important as some 
of  its  rules  will  still  apply  (wil   be  given 
weight)  right  up  until  a  new  plan  is  made 
fully operative.  
Proposed District Plan 
Section 73(1), Schedule 1 cl 2  December 2013 
This  version  of  the  plan  shows  proposed 
and cl 5 
provisions  (objectives,  policies,  rules  and 
methods).  These  are  the  provisions  that 
people  make  submissions  and  further 
submissions about.  
District Plan – Decisions  Schedule 1 cl 10 and cl 11 
April 2016 
This  version  shows  the  provisions  of  the 
Version  
plan  that  were  amended  by  decisions 
made  on  the  submissions  during  the 
hearings process.  
District  Plan  –  Appeals  Section 86F, Schedule 1 cl 10  July 2016 
This  version  is  annotated  with  the 
Version 
and cl 11 
provisions  that  have  been  appealed.  The 
provisions  in  this  version  of  the  plan  are 
operative  unless  they  are  annotated.  The 
role  of  this  plan  is  to  indicate  the  legal 
effect of rules. 
District Plan – Operative  Schedule 1 cl 17(2) 
March 2024 
At  the  start  of  2024  only  two  appeals 
in Part Version 
remained.  The  Council  decided  to  make 
the  parts  of  the  plan  that  were  being 
“treated  as  operative”,  fully  operative,  that 
is, it approved the plan in part. 
Operative District Plan  
Schedule 1 cl 17(3) and cl 20 

 One  appeal  on  the  plan  relating  to  the 
 
plan  provisions  to  apply  at  New  Chums 
Beach, is extant. The plan cannot be made 
fully  operative  until  this  appeal  is 
determined. 
District Office: 515 Mackay Street, Private Bag, Thames 3540, New Zealand P 
+64 7 868 0200, F +64 7 868 0234 E [Thames-Coromandel District Council request email] 
OFFICES AT: COROM ANDEL  •  WHITIANGA  •  WHANGA M ATA 
WWW.TCDC.GOV T.NZ 
 

During the appeals phase of a district plan process, appeals are resolved through negotiation 
and Environment Court consent orders or Court decisions. The plan is amended as those 
decisions are handed down by the Court. The appeal annotations are removed and the 
provisions in the plan are updated as directed by the Court. When this happens, Councils 
must treat the new resolved provisions as operative provisions.  Previous versions of that 
rule cannot be considered, nor can any weight be accorded to the operative plan when 
making a decision on a resource consent application. We are not required to produce a new 
version of the plan throughout the process of resolving appeals to the plan. 
 
To answer your questions: 
 
Council has cited the Thames Coromandel District Plan Appeals Version 2021 as its 
authority to issue resource consents. 
 
I am unaware of the specific circumstances of this citation but the resource consent in 
question was likely issued under the provisions of the district plan at that point in time in 
2021. The citation was likely used to identify the rules at the point in time when the consent 
was issued (given the provisions would have been in a state of flux as they were in the 
process of being amended by the Court). 
 
1.  Why is the Thames Coromandel District Plan Appeals Version 2021 not listed on 
Council's website when recounting the history of the District Plan? 
 
The version is not listed because the RMA enables the versions of the plan that are in the 
table above. The year of issue of the Appeals version remains 2016. 
 
2.  What is the legal status of the Thames Coromandel District Plan Appeals Version 
2021. 
 
The legal status of the plan in 2021 was “Appeals version”. That means that: 
  the provisions had legal effect (ie regard could be had to them when making 
decisions on a resource consent application) because decisions had been made and 
publicly notified on the provisions (s.86B(1) of the RMA); 
  some provisions were treated as operative (ie not subject to appeal).  For any such 
provisions, any previous corresponding rule in the 2010 operative plan would be 
inoperative (s.86F(1) of the RMA); and 
  some provisions were subject to appeal (which means both the annotated appealed 
provision and the corresponding provision in the 2010 operative plan would need to 
be considered when making a decision on a resource consent application). In these 
situations, the appealed provision had legal effect in accordance with s.86B(1), but 
the corresponding provision of the 2010 operative plan remained operative until the 
appeal was resolved.   
 
 
 
 
 

3.  What is the legal status of Section 37A as published in 2022 - 2024. 
 
In 2022-2024, section 37A was treated as operative under s.86F(1) of the RMA because al  
appeals related to those provisions had been resolved. In March 2024 when the plan 
became “operative in part”, the provisions of Section 37A became ful y operative. 
 
That means that once the final appeal on Section 37A was resolved, the provisions in that 
section would have been “treated as operative”. Even though the plan itself remained an 
“Appeals version”, section 86F of the RMA requires councils to treat rules as operative 
where the appeals have been determined. 
 
4.  Please explain why the Thames Coromandel District Plan Appeals Version 2021 
does not have legal status. 
 
The Appeals version of the plan incorporating al  the changes made to resolve appeals up to 
2021 had legal effect under the RMA. 
 
5.  Please explain what course of action should be fol owed with regard to documents 
that depend on the Appeals Version 2021. 
 
Any resource consent issued under the provisions of the Appeals version of the plan 
(regardless of the date of issue) is a valid, legal y binding resource consent, unless it has 
lapsed. 
 
Yours sincerely 
 
 
 
 
Jen Amner 
Legal Coordinator