ID 
Category 
Decision 
Responsible party 
Date 
Comment 
Removal of the crossing opposite the Mirage Apartments. There seems to be 
insufficient demand to justify a signalised crossing. The rail overbride is also due 
for replacement in the next 3 years, therefore sigalisation of the Gladstone 
Ranjan Pant (Outcomes 
5  Design 
intersection is to be considered at a later date.   
Manager) 
26/02/2024 
Shared with the design and project team. 
Removal of the crossing at Saatchi & Saatchi. This crossing appeared to have the  Ranjan Pant (Outcomes 
6  Design 
greatest impact on traffic flow as this is a pintch point in the corridor. 
Manager) 
Unknown 
Shared with the design and project team. 