Woodend Bypass 
Economic Assessment 
October 2024 
under the Official Information Act 1982
Released 
Ref: 2024-007 
Woodend Bypass Economic Assessment V03a 
© QTP Ltd 2024 


1982
Act 
Information 
Official 
the 
under 
Released 


 
Woodend Bypass – Economic Assessment 
 
 
Contents 
1 
Introduction and Executive Summary ........................................................................... 1 
2 
Economic Evaluation Procedures .................................................................................. 3 
3 
Location and Option Summary ...................................................................................... 5 
4 
Adopted Input Assumptions........................................................................................... 6 
4.1  Timing ............................................................................................................................... 6 
4.2  Value of Time .................................................................................................................... 6 
1982
4.3  Vehicle Operating Costs .................................................................................................... 7 
4.4  Emission Costs ................................................................................................................. 8 
Act 
4.5  Crash Costs ...................................................................................................................... 9 
4.6  Walking and Cycling Benefits .......................................................................................... 10 
4.7  Reliability Benefits ........................................................................................................... 10 
4.8  Daily to Annual Expansion Factor .................................................................................... 10 
4.9  Do Minimum .................................................................................................................... 10 
4.10  Traffic Modelling .............................................................................................................. 11 
4.11  Summary of Network Performance .................................................................................. 12 
5 
Project Costs ................................................................................................................. 14 
Information 
5.1  Cost of Do-Minimum ........................................................................................................ 14 
5.2  Option Additional Capital Expenditure (CAPEX) Costs .................................................... 14 
5.3  Option Additional Operating Expenditure (OPEX) Costs ................................................. 14 
5.4  Total PV Costs ................................................................................................................ 14 
Official 
6 
Project Benefits ............................................................................................................. 15 
7 
Benefit Cost Ratio – Summary ..................................................................................... 17 
the 
 Appendices 
Appendix A: Sensitivity Testing 
Appendix B: Toll Modelling Assessment Summary 
under 
 
 
 
 
Released 
Ref: 2024-007 
Woodend Bypass Economic Assessment V03a 
Page ii 
© QTP Ltd 2024 
 


 
Woodend Bypass – Economic Assessment 
 
 

Introduction and Executive Summary 
1.1 
The New Zealand Transport Agency Waka Kotahi (NZTA) have engaged QTP Ltd to use 
updated traffic models to provide design flows and preliminary economic assessment for 
the Woodend Bypass given that it has been identified for delivery in the draft GPS2024.  
1.2 
This  document  summarises  the  preliminary  economic  assessment.  It  directly  utilises  the 
transport modelling used to develop the design flows, which is summarised in the separate 
1982
QTP report titled "Woodend Bypass Traffic Modelling v02a.PDF".  
1.3 
A single bypass option has been tested against the do-minimum.  This option is based on 
Act 
the 'short eastern bypass alignment' (identified during 2013 work) between Pineacres and 
Pegasus.  The  bypass  is  to  include  grade  separated  interchanges  provided  at  Pineacres 
and  Pegasus1.  In  addition  to  the  bypass  component,  the  section  of  SH1  between  the 
northern  end  of  the  northern  motorway  and  Pineacres  has  been  upgraded  to  4  lane 
motorway standard.  
1.4 
The purpose of this report is to summarise the primary project benefits and the Benefit Cost 
Ratio (BCR) in accordance with the NZTA Monetised Benefits and Costs Manual (MBCM).  
This  includes  recording  key  input  assumption  details  and  noting  any  limitations  or  other 
Information 
matters which can then be referenced as part of other preliminary work. 
1.5 
The  resulting  Present  Value  (PV)  benefits  and  costs  for  the  preferred  full  programme  of 
works, along with the resulting BCR, are summarised below: 
•  TOTAL BENEFITS:   
$ 638.8m 

Official 
  TOTAL COST: 
 
 
$ 670.9m 
•  BCRN 
 
 
 
 
0.95 (with sensitivity 0.71 to 1.4) 
the 
1.6 
The assessment indicates that the BCR is borderline between having a 'low' rating (greater 
than 1.0 but less than 3.0) and ‘very low’ (less than 1.0) for the 'Efficiency' component of 
Waka  Kotahi's  Proposed  Investment  Prioritisation  Method  (IPM)  priority  ranking  for  the 
National Land Transport Fund (NLTP) 2024-2027. 
under 
1.7 
Note  that  this  Economic  Evaluation  informs  part  of  a  wider  IPM  assessment  which  also 
considers 'GPS alignment' and 'Scheduling' components.  The IPM only relates to funding 
being sought from the National Land Transport Fund (NLTF), and it is possible that some 
(or all) of funding for this project could come from an alternative source (e.g. Public Private 
Partnership (PPP) or some form of tolling).   
1.8 
s 9(2)(ba)(ii)
 
 
Released 
1.9 
In addition to the national benefit-cost ratio, the introduction of tolling requires reporting of 
 
1 The 2013 alignment, and previous version of this economic assessment did not include an interchange at Pegasus. 
Ref: 2024-007 
Woodend Bypass Economic Assessment V03a   
Page 1 of 21 
© QTP Ltd 2024 
 
 


 
Woodend Bypass – Economic Assessment 
 
 
the  government  benefit  to  cost  ratio  (BCRG).    The  BCRG  is  used  to  indicate  the  level  of 
benefits obtained from investment of local and central government funds in situations where 
government  funding  is  supplemented  by  the  availability  of  third-party  funding  or  tolling 
revenue. 
1.10 
s 9(2)(ba)(ii)
1982
1.11 
Act 
1.12 
1.13 
Information 
1.14 
Further information about the process and assumptions are provided in the sections below.  
Official 
the 
under 
Released 
Ref: 2024-007 
Woodend Bypass Economic Assessment V03a   
Page 2 of 21 
© QTP Ltd 2024 
 
 


 
Woodend Bypass – Economic Assessment 
 
 

Economic Evaluation Procedures 
2.1 
The  Economic  Evaluation  follows  procedures  specified  in  the  Waka  Kotahi  Economic 
Monetised Benefits and Costs Manual (MBCM) version 1.7 (May 2024). 
2.2 
Section  4.3  of  the  MBCM  describes  the  procedures  used  to  evaluate  the  economic 
efficiency of road improvement activities.  This assessment is based on those procedures.  
2.3 
Due to the financial scale of the project (being greater than $15m)2, 'Full Procedures' have 
1982
been applied.   
2.4 
The  do-minimum  and  do-something  options  have  been  run  using  elastic  assignments  to 
Act 
extract design flows. 
2.5 
The resulting corridor traffic flows indicate that fixed trip matrix benefits are unlikely to differ 
by more than 10%3 from those from a variable trip matrix approach, therefore a fixed matrix 
approach (using do-minimum demands) has been adopted for this assessment, with link-
by-link assessment of core benefits.  
2.6 
Relevant benefits and costs specified in Section 4.3 of the MBCM that are included in the 
analysis include: 
Information 
 
Benefits: 
The following benefits (or disbenefits) from the NZTA Land Transport Benefit Framework 
(LTBF)  have  been  assessed  (listed  by  LTBF  benefit  cluster  and  the  associated  MBCM 
monetised benefit): 
Official 
Changes in User Safety - Impact on social cost of deaths and serious injuries: 
•  Crash cost savings the 
Changes in Human Health - Impact on air emissions on health: 
•  Vehicle emission reduction benefits (air pollutants) 
•  Walking and cycling health benefits 
Changes in transport Costs - Impact on network productivity and utilisation: 
under 
•  Travel time saving. 
•  Vehicle operating cost savings. 
Changes in transport Costs - Impact on System Reliability: 
•  Journey time reliability benefits. 
Change in climate - Impact on greenhouse gas emissions: 
Released 
•  Vehicle emission reduction benefits (greenhouse gas emissions). 
 
2 %15m is the upper threshold where ‘Simplified Procedures’ can be applied (Section 4.3 of MBCM). 
3 The relevance of this threshold is explained on page 268 of the MBCM (version 1.7, May 2024) 
Ref: 2024-007 
Woodend Bypass Economic Assessment V03a   
Page 3 of 21 
© QTP Ltd 2024 
 
 


 
Woodend Bypass – Economic Assessment 
 
 
 
 
Costs:  
Any additional Capital Expenditure (CAPEX) over what is expected to be spent on the Do-
Minimum. This includes: 
•  Property 
•  Pre implementation costs (including investigation and design) 
•  Implementation costs (construction). 
1982
Any additional Operational Expenditure (OPEX) over what is expected to be spent on the 
Do-Minimum.  This includes renewal costs and operation and maintenance costs. 
Act 
Information 
Official 
the 
under 
Released 
Ref: 2024-007 
Woodend Bypass Economic Assessment V03a   
Page 4 of 21 
© QTP Ltd 2024 
 
 



 
Woodend Bypass – Economic Assessment 
 
 

Location and Option Summary 
3.1 
The  Woodend  Bypass  scheme  has  initially  been  modelled  based  on  the  alignment  and 
general  arrangement  indicated  within  the  plans  developed  in  the  Scheme  Assessment 
Reporting  of  February  2013  (the  'Short  Eastern  Alignment  Route').  The  modelled  do-
something network, overlaid on the scheme plan, is illustrated within the following diagram, 
extracted directly from the CAST model. 
 
1982
 
Figure 3 1: Activity Location  
Act 
Information 
Official 
 
 
the 
3.2 
The length of corridor affected by the scheme is approximately 9km, with most of this being 
the  Pineacres  to  Pegasus  bypass  component  (6km).    Key  features  associated  with  the 
scheme include: 
•  The scheme is to be generally 100 kph (posted speed limit), but 80 kph from Gladstone 
under 
Road through to the Pegasus Roundabout and north to the tie-in point on SH1. 
•  South-facing ramps only at Pineacres (Williams Street) interchange (operating under 
priority control). 
•  The Pegasus Interchange is to include a 2-lane flyover for SH1, with signalised ramp 
intersections. 
•  Four-laning will extend southbound through the Lineside Road interchange to provide 
four continuous lanes. 
Released 
Ref: 2024-007 
Woodend Bypass Economic Assessment V03a   
Page 5 of 21 
© QTP Ltd 2024 
 
 


1982
Act 
Information 
Official 
the 
under 
Released 


 
Woodend Bypass – Economic Assessment 
 
 
using MBCM table A12.3 (update factors for benefits). 
4.2.5 
The Max CRV is applied on a link-by-link basis based on V/C (applied as per the MBCM 
formula whenever link V/C exceeds 70%). 
4.2.6 
Travel time data (from Tom Tom, supplied by NZTA) indicates that additional congestion 
occurs  during  public  holidays  where  northbound  traffic  flows  increase  significantly  in  the 
evening peak as travellers head north to popular holiday destinations.  This additional travel 
time  has  been  included  in  the  assessment  as  a  separate  calculation  that  imposes  an 
1982
additional 10 minute delay to northbound evening peak traffic for 11 public holiday days per 
year.  It has been assumed that these delays would increase in the future, with guesstimates 
of 12 minutes and 16 minutes adopted for 2038 and 2048 respectively.   
Act 
4.3 
Vehicle Operating Costs 
4.3.1 
The value of vehicle operating costs have been estimated separately for Light Vehicles (LV) 
and Heavy Commercial Vehicles (HCV) using the following MBCM tables: 
•  Table A47: Standard traffic compositions by period and road type 
•  Table 22: Running cost by speed and gradient regression coefficients (cents/km - July 
2015) by vehicle class and road category 
•  Table  23:  Additional  VOC  due  to  congestion  regression  coefficient  by  vehicle  class 
Information 
(cents/km - July 2015) by vehicle class and road category 
4.3.2 
The  adopted  road  type  (which  determines  the  traffic  composition8  and  regression 
coefficients) is 'Rural Strategic'.   
4.3.3 
The resulting 'base' vehicle operating costs are calculated on a link-by-link basis using the 
MBCM formula based on individual link speed and coefficients from MCBM table 22. The 
Official 
terrain is flat in the project area, so gradients for all links have been assumed to be zero in 
these calculations. 
the 
4.3.4 
The resulting 'congested' vehicle operating costs are calculated on a link-by-link basis using 
the MBCM formula based on link V/C and coefficients from MCBM table 23. 
4.3.5 
These  values  increase  by  a  factor  of  1.35  when  converting  from  July  2015  to  July  2024 
using MBCM table A12.3 (update factors for benefits). 
under 
 
 
Released 
 
8 Weighted average between standard rural strategic traffic composition for passenger cars (PC), light commercial vehicles 
(LCV), medium (MCV)/heavy commercial vehicles (HCV-I and HCV-II) and buses. 
Ref: 2024-007 
Woodend Bypass Economic Assessment V03a   
Page 7 of 21 
© QTP Ltd 2024 
 
 


1982
Act 
Information 
Official 
the 
under 
Released 


1982
Act 
Information 
Official 
the 
under 
Released 


 
Woodend Bypass – Economic Assessment 
 
 
4.6 
Walking and Cycling Benefits 
4.6.1 
The proposed Pegasus interchange will significantly improve the current impediment to safe 
walking and cycling across SH1.  This is covered by section 3.2 of the MBCM (impact of 
mode on physical and mental health), which ascribes a benefit to walking and cycling users 
that  use  the  facility.    This  benefit  is  irrespective  of  the  length  of  the  improvement  and  is 
ascribed to individual users, rather than trips.  The value for walking trips is $9.90 (2021$, 
from  Table  6  of  the  MBCM)  and  the  value  for  cycling  is  $14.70  (2021$,  from  the  text 
following Table 7 of the MBCM). 
1982
4.6.2 
Because  the current site  is  such  an  impediment to  cyclists  and  pedestrians,  demand for 
crossing  SH1  is  presently  unknown.    For  the  purpose  of  assessment,  in  discussion  with 
Act 
NZTA, 30 pedestrians and 70 cycle users per day have been assumed (i.e. 100 users in 
total, applied to all forecast years).     
4.7 
Reliability Benefits 
4.7.1 
Road  journey  reliability  benefits  have  been  estimated  using  the  procedure  described  in 
Section 3.7 of the MBCM.  This procedure can’t use the model link-by-link method used to 
estimate  other  benefits  because  it  would  double  count  whenever  there  a  multiple  links 
between key sections of road (between intersections or speed environments).  
4.7.2 
Therefore, the process is highly manual and relies upon model flows and V/C at selected 
Information 
locations representing discrete segments.  To keep this process manageable, only the main 
corridor sections have been assessed and only for  bypass traffic.  The resulting benefits 
are very small (<1% of total benefits), and compared to other included benefits and make 
negligible difference to the BCR, therefore they serve no other purpose in the assessment 
other do demonstrate that they have been considered.   
Official 
4.8 
Daily to Annual Expansion Factor 
4.8.1 
Traffic model outputs reflect typical weekday (Mon to Fri) values.  These daily values have 
the 
been annualised using an expansion factor of 351. 
4.8.2 
The expansion factor is based upon 245 weekdays per year plus 120 weekend and public 
holidays that have 91% of  weekday flow (based on 2021 SH1 Leithfield count) and 96% 
benefit value reflecting different values of time on weekends compared to weekdays (based 
under 
on MBCM weekend composite values of time for rural strategic roads).  
4.9 
Do Minimum 
4.9.1 
The adopted Do-Minimum (from the concurrent traffic modelling work) includes assumes 
no changes within existing the corridor.  At all other locations, the default transport model 
future year schemes are maintained. 
 
 
Released 
Ref: 2024-007 
Woodend Bypass Economic Assessment V03a   
Page 10 of 21 
© QTP Ltd 2024 
 
 


 
Woodend Bypass – Economic Assessment 
 
 
4.10 
Traffic Modelling 
4.10.1  Traffic  modelling  of  the do-minimum  and option was  undertaken  using the  CAST  model. 
Changes made to the CAST model for this application are described in the report "Woodend 
Bypass Traffic Modelling v02a.PDF
".   
4.10.2  The model demands used in this assessment are based on a 'fixed' matrix approach, where 
both  the  do-min  and  option  use  the  do-min  demands.    This  enables  the  work  to  be 
progressed more quickly and is appropriate for a preliminary assessment where there is still 
1982
a lot of uncertainty around the project, especially in relation to cost. 
4.10.3  A link-by-link assessment method has been adopted for many of the benefit streams (travel 
time costs, vehicle operating costs and emissions).  This enables link speed to be used to 
Act 
directly for calculate emissions and vehicle operating costs, and V/C to directly calculate 
any additional congestion costs (for both travel time and vehicle operating costs).  This was 
done for all seven time slices in the CAST model. These were then summed to Average 
Weekday  Traffic (AWT) using  local  expansion factors.  Resulting  values were  annualised 
using the factors described in Section 0 above.  
4.10.4  Centroid connectors were included in the assessment to ensure internal consistency. While 
these don't represent actual roads, they do represent part of the journey (typically on local 
access streets not included in the modelled network).  Some zones in the CAST model have 
Information 
multiple  centroid  connectors,  where  different  network  options  could  alter  the  choice  of 
connector  used  when  calculating  least-cost  paths.  Omitting  the  centroid  travel  would 
exclude a small part of the trip that is necessary for consistently comparing total trip time 
and distance. 
4.10.5  To make the process more efficient, and reduce potential noise, the model runs were done 
using a cordoned area that included all model links north the Waimakariri River, as shown 
Official 
in the figure below. 
 
the 
 
 
under 
Released 
Ref: 2024-007 
Woodend Bypass Economic Assessment V03a   
Page 11 of 21 
© QTP Ltd 2024 
 
 


1982
Act 
Information 
Official 
the 
under 
Released 


1982
Act 
Information 
Official 
the 
under 
Released 


1982
Act 
Information 
Official 
the 
under 
Released 


1982
Act 
Information 
Official 
the 
under 
Released 


 
Woodend Bypass – Economic Assessment 
 
 
6.6 
There are disbenefits associated with vehicle operating costs, associated with faster vehicle 
speeds and additional distance travelled on the bypass. There are also slight disbenefits 
related  to  greenhouse  gas  emissions  for  the  same  reasons.    These  are  indicated  to 
decrease  over  time  despite  ongoing  traffic  growth  due  to  the  assumed  changes  in  the 
vehicle fleet over time (with increased electrification). 
6.7 
The other included benefits are all much lower, but collectively add value. 
1982
Act 
Information 
Official 
the 
under 
Released 
Ref: 2024-007 
Woodend Bypass Economic Assessment V03a   
Page 16 of 21 
© QTP Ltd 2024 
 
 


 
Woodend Bypass – Economic Assessment 
 
 

Benefit Cost Ratio – Summary 
7.1 
The resulting present value (PV) of net benefits using the standard MBCM 40-year analysis 
period and 4% discount rate are summarised below: 
•  Travel time saving (107%)  
 
 
 
 
 
 
 
$       684.0m 
•  Vehicle operating cost savings (-15%)   
 
 
 
 
$        -93.4m 
•  Vehicle emission reduction benefits (GHG) (<1%) 
 
 
$          -1.2m 
1982
•  Vehicle emission reduction benefits (air pollutants) (<1%) 
$           0.5m 
•  Crash cost savings (5%)   
 
 
 
 
 
 
 
$          32.5m 
•  Active modes (1%) 
 
 
 
 
 
 
 
 
 

 
6.9m 
Act 
•  Holiday Travel Time (1%)   
 
 
 
 
 
 
 
$            7.6m 
•  Journey time reliability benefits (<1%)   
 
 
 
 
$            2.1m 
•  TOTAL BENEFITS   
 
 
 
 
 
 
 
 
$        638.9m 
7.2 
The PV of costs are summarised below: 
•  Additional CAPEX (95%):   
 
 
 
 
 
 
 
$        640.3m 
•  Additional OPEX (5%):   
 
 
 
 
 
 
 
 
$           30.6m 
Information 
•  TOTAL COST 
 
 
 
 
 
 
 
 
 
 
$         670.9m 
7.3 
The resulting BCR is 0.95 with a sensitivity range 0.71 - 1.4
7.4 
The First Year Rate of Return (FYRR) is 3.08%
Official 
7.5 
Results of the sensitivity tests are included in Appendix A. 
7.6 
The assessment indicates that the BCR is borderline between having a 'low' rating (greater 
than 1.0 but less than 3.0) and ‘very low’ (less than 1.0) for the 
the 
'Efficiency' component of 
Waka  Kotahi's  Proposed  Investment  Prioritisation  Method  (IPM)  priority  ranking  for  the 
National Land Transport Fund (NLTP) 2024-2027. 
7.7 
Note  that  this  Economic  Evaluation  informs  part  of  a  wider  IPM  assessment  which  also 
under 
considers 'GPS alignment' and 'Scheduling' components.  The IPM only relates to funding 
being sought from the National Land Transport Fund (NLTF), and it is possible that some 
(or all) of funding for this project could come from an alternative source (e.g. Public Private 
Partnership (PPP) or some form of tolling).   
7.8 
s 9(2)(ba)(ii)
 
Released 
Ref: 2024-007 
Woodend Bypass Economic Assessment V03a   
Page 17 of 21 
© QTP Ltd 2024 
 
 


 
Woodend Bypass – Economic Assessment 
 
 
s 9(2)(ba)(ii)
1982
Act 
Information 
Official 
the 
under 
Released 
Ref: 2024-007 
Woodend Bypass Economic Assessment V03a   
Page 18 of 21 
© QTP Ltd 2024 
 
 


1982
Act 
Information 
Official 
the 
under 
Released 


1982
Act 
Information 
Official 
the 
under 
Released 


 
Woodend Bypass – Economic Assessment 
 
 
Summary of Woodend Bypass Economic Assessment
1982
Prepared 17/10/2024 
COSTS
BENEFITS
BCR
Option Description
Model Reference
COMPONENT
Undiscounted (40 year)
Present value (@4% 40 Year)
COMPONENT
Undiscounted (40 year)
Present value (@4% 40 Year)
Toll Revenue
BCR(N)
BCR(G)
FYRR
Act 
CAPEX
Property
$                          34,900,000
$                             33,187,870
TTC
$               1
  ,727,039,732
$                             6
  84,039,893
Pre-Implementation
$                          56,500,000
$                             54,341,864
VOC
-$                   2
  21,109,486 -$                                9
  3,554,448
With Bypass, no Tolls
Option 2a_T00
Implementation
$                        648,600,000 $                          552,768,421 Crash
$                     6
  9,362,677
$                                3
  2,512,361
$                  -
  
0.95
0.95
3.08%
OPEX
Maintenance & Renewal
$                          87,034,576
$                             87,034,576
Other
$                     3
  8,407,124
$                                1
  5,855,969
TOTAL
$                       827,034,576
$                          827,034,576
TOTAL
$               1
  ,613,700,047
$                             6
  38,853,774
 
-$                                     
11,800,000
 
COSTS
BENEFITS
BCR
Option Description
Model Reference
COMPONENT
Undiscounted (40 year)
Present value (@4% 40 Year)
COMPONENT
Undiscounted (40 year)
Present value (@4% 40 Year)
Toll Revenue
BCR(N)
BCR(G)
FYRR
 
CAPEX
Property
$                          34,900,000
$                             33,187,870
TTC
$               1
  ,324,141,267
$                             5
  08,610,129
Pre-Implementation
$                          56,500,000
$                             54,341,864
VOC
-$                   1
  77,764,928 -$                                7
  4,742,304
With Bypass, Woodend 30kph,  Option 2b_Ta125
Implementation
$                       660,400,000
$                          562,094,132
Crash
$                     4
  9,650,936
$                                2
  2,780,642
$    3
   8,931,623
0.69
0.67
1.83%
Toll N   of Pineacres $1.25/$2.50
OPEX
Maintenance & Renewal
$                          87,034,576
$                             30,598,542
Other
$                     3
  6,407,169
$                                1
  5,004,483
TOTAL
$                       838,834,576
$                          680,222,407
TOTAL
$               1
  ,232,434,443
$                             4
  71,652,950
 
$                                                   
-
Information 
 
COSTS
BENEFITS
BCR
Option Description
Model Reference
COMPONENT
Undiscounted (40 year)
Present value (@4% 40 Year)
COMPONENT
Undiscounted (40 year)
Present value (@4% 40 Year)
Toll Revenue
BCR(N)
BCR(G)
FYRR
CAPEX
Property
$                          34,900,000
$                             33,187,870
TTC
$               1
  ,300,268,059
$                             4
  98,814,853
 
Pre-Implementation
$                          56,500,000
$                             54,341,864
VOC
-$                   2
  00,231,899 -$                                8
  5,577,585
With Bypass, Woodend 30kph,  Option 2b_Tb125
Implementation
$                       665,400,000
$                          566,045,705
Crash
$                     7
  7,808,532
$                                3
  7,397,812
$    5
   4,271,353
0.68
0.65
1.76%
Toll S of Pineacres $1.25/$2.50
 
OPEX
Maintenance & Renewal
$                          87,034,576
$                             30,598,542
Other
$                     3
  6,919,873
$                                1
  5,127,825
TOTAL
$                       843,834,576
$                          684,173,980
TOTAL
$               1
  ,214,764,564
$                             4
  65,762,905
 
$                                       
5,000,000
Official 
COSTS
BENEFITS
BCR
 Option Description
Model Reference
COMPONENT
Undiscounted (40 year)
Present value (@4% 40 Year)
COMPONENT
Undiscounted (40 year)
Present value (@4% 40 Year)
Toll Revenue
BCR(N)
BCR(G)
FYRR
CAPEX
Property
$                          34,900,000
$                             33,187,870
TTC
$                   9
  04,975,350
$                             3
  30,298,704
With   Bypass, Woodend 30kph, 
Pre-Implementation
$                          56,500,000
$                             54,341,864
VOC
-$                   1
  85,248,818 -$                                7
  8,848,811
the 
Toll N & S of Pineacres 
Option 2b_Tc125
Implementation
$                       677,400,000
$                          575,529,479
Crash
$                     5
  5,829,442
$                                2
  7,464,772
$ 1
  25,088,731
0.42
0.29
0.48%
$1.25/$2.50
OPEX
Maintenance & Renewal
$                          87,034,576
$                             30,598,542
Other
$                     3
  3,649,310
$                                1
  3,555,137
 
TOTAL
$                       855,834,576
$                          693,657,754
TOTAL
$                   8
  09,205,284
$                             2
  92,469,802
$                                     
17,000,000
 
COSTS
BENEFITS
BCR
Option Description
Model Reference
 
COMPONENT
Undiscounted (40 year)
Present value (@4% 40 Year)
COMPONENT
Undiscounted (40 year)
Present value (@4% 40 Year)
Toll Revenue
BCR(N)
BCR(G)
FYRR
CAPEX
Property
$                          34,900,000
$                             33,187,870
TTC
$                   7
  57,385,334
$                             2
  68,233,216
under 
Pre-Implementation
$                          56,500,000
$                             54,341,864
VOC
-$                   1
  98,038,469 -$                                8
  4,526,865
With  Bypass, Woodend 30kph,  Option 2b_Tb250
Implementation
$                       670,400,000
$                          569,997,277
Crash
$                     6
  3,255,953
$                                3
  0,934,884
$ 1
  28,958,812
0.33
0.18
0.09%
Toll S of Pineacres $2.50/$4.50
OPEX
Maintenance & Renewal
$                          87,034,576
$                             30,598,542
Other
$                     3
  3,063,945
$                                1
  3,367,443
 
TOTAL
$                       848,834,576
$                          688,125,553
TOTAL
$                   6
  55,666,763
$                             2
  28,008,678
$                                     
10,000,000
Note that numbers above are linked to spreadsheets and are not rounded to assist with checking (but do not imply an accuracy a corresp 
onding level of accuracy)
Ref: 2024-007 
Woodend Bypass Economic Assessment V03a   
Page 22 of 22 
© QTP Ltd 2024 
 