Background / Overview
• Manukau identified as major rail / bus interchange location
• Southern New Network to be implemented prior to / at start of 
construction of the Manukau Bus Interchange
• 15 routes to use the proposed Interchange
• 13 of the 15 routes are planned to terminate at Manukau
Interchange
• Interim arrangements needed until bus operations can migrate to 
new facility (~18 months construction period)
DRAFT



3
Interim Proposal

Interim arrangements needed until bus operations can migrate to new facility (~18 
months construction period)
Rationale for not using site in temporary capacity

Manukau Interchange already hard pressed to be delivered to budget. Using site while 
building on it at the same time will mean additional cost and probable delay to the 
project

Southern area of site proposed as parking (to mitigate HR staff issues with parking 
allocation lost)

Temporary facilities at the site (rather than on street) will be harder to manage from a 
build perspective – not desirable outcome to be on site until Interchange built

easier and better operational and customer offering to provide adequate on-
street facilities

PT Operators and AT Metro preference when opening new facility is to be handed the 
facility first before opening (4-6 weeks) to ensure drivers and staff have training without 
interference – this is a best practice approach. 
DRAFT

Above approach endorsed at SMG meeting 15/4 (Mark Lambert agreement)



4
Route Details – New Network
Peak Freq. (bus Peak Freq. (bus 
Sl No Route No Description
Through/ 
per hour)
per hour)
Terminate
2016
2026
1
33
Papakura to Otahuhu
Through
4
6
2
361
Manurewa to Highbrook via Clendon, Manukau and Otara
Through
3
4
3
368
Wiri Industrial ‐ clockwise loop
Terminate
2
4
4
369
Wiri Industrial ‐ anti‐clockwise loop
Terminate
2
4
5
313
Onehunga to Manukau via Mangere, western Papatoetoe and Plunket Ave
Terminate
3
4
6
362
Weymouth to Manukau
Terminate
3
4
7
365
Porchester Rd to Manukau
Terminate
4
4
8
366
The Garden to Manukau
Terminate
4
4
9
35
Botany to Manukau via Chapel Rd
Terminate
3
4
10
355
Botany to Manukau Via Flat Bush
Terminate
3
4
11
356
Flatbush ‐ Manukau
Terminate
3
4
12
325
Mangere, Otahuhu, Otara to Manukau
Terminate
4
4
13
352
Panmure to Manukau via Highbrrok and East Tamaki
Terminate
3
4
14
353
Botany to Manukua via Preston Rd
Terminate
2
4
DRAFT
15
30
Airport
Terminate
4
6
Total Bus per hour
47
64
Source : Network Team



5
Facility Inventory– New Network (2016)
Layover 
Route 
Through/ 
Peak Freq. 
Sl No
Description
(Tentative/ 
Loading Bays
No
Terminate
(bus per hour) Interchangeable)
1
33
Papakura to Otahuhu
Through
4
0
2 (Davies Av. Both dir.)
2
361 Manurewa to Highbrook via Clendon, Manukau and Otara
Through
3
0
2 (Davies Av. Both dir.)
3
Terminate
1 (Davies Av. 
368 Wiri Industrial ‐ clockwise loop
2
1 (Davies Av. One dir.)
Service lane)
4
369 Wiri Industrial ‐ anti‐clockwise loop
Terminate
2
Shared with 368
1 (Davies Av. One dir.)
5
313 Onehunga to Manukau via Mangere, western Papatoetoe and 
Terminate
3
1 (Ronwood Av.)
2 (Davies Av. Both dir.) & 
Plunket Ave
LO
6
362 Weymouth to Manukau
Terminate
3
1 (Putney Way)
1 (Putney Way)
7
365 Porchester Rd to Manukau
Terminate
4
1 (Ronwood Av.)
2 (Davies Av. Both dir.) & 
LO
8
366 The Garden to Manukau
Terminate
4
1 (Putney Way)
1 (Putney Way)
9
35
Botany to Manukau via Chapel Rd
Terminate
3
1 (Putney Way)
1 (Putney Way)
10
355 Botany to Manukau Via Flat Bush
Terminate
3
1 (Putney Way)
1 (Putney Way)
11
356 Flatbush ‐ Manukau
Terminate
3
Shared with 355
Shared with 355
12
325 Mangere, Otahuhu, Otara to Manukau
Terminate
4
1 (Putney Way)
1 (Putney Way)
13
352 Panmure to Manukau via Highbrook and East Tamaki
Terminate
3
1 (Rainbows End)
2 (Davies Av. Both dir.) 
14
353 Botany to Manukua via Preston Rd
Terminate
2
1 (Rainbows End)
2 (Davies Av. Both dir.) 
DRAFT
15
30
Airport
Terminate
4
1 (Rainbows End)
2 (Davies Av. Both dir.) 
Total
47
11
Source : Network Team




33
6
355
361
356
368
325
369
352
313
353
362
30
365
366
35
DRAFT
Through routes = 2
Terminating routes = 13






7
Proposed Bus stops on Davies Ave
Use existing BS, extend to make 
2 spaces
Got Space for 2 buses, 
need restricting of kerb 
elements
40m
DRAFT





8
33
361
325
362
355
366
35
Last Stop + Layover 
on Putney way
DRAFT
Through routes & routes 
coming from Redoubt 
Road





9
352
353
30
Option 1 – Layover at 
Putney Way may be shared
Option 2 – Out of service running 
Option 3 – Layover at 
to layover near Rainbow’s End. 
Davies Av
Can be on-street or off-street
New Bus Stops 
created (required for 
final scheme anyway 
Routes coming from 
DRAFT
North through Davies 
Road - Options






10
Last stop + Layover 
on Ronwood Av, 
taking U-Turn at the 
Bus Stops created 
Roundabout
313
(required in final 
scheme anyway)
365
DRAFT
Routes coming through 
Wiri Station Road






11
368
369
Last stop + Layover on Davies Av. 
DRAFTWiriIndustrial –Clockwise 
& Anti-Clockwise




12
DRAFT
Interim Coach Options



13
Next Steps / Risks
Next Steps:
• Interim layover options to be further analysed and finalised
• Detailed design commences for interim proposal – July / Aug
• Design consultation – Aug / Sept
• TCC approval – Oct / Nov
• Construction Drawings / shelter orders etc – Oct / Nov
• Construction temporary on-street facilities – Jan / Feb 2016
• Go live temporary on-street facilities – May 2016
Risks to N Network ‘Go Live’
• Design/consult/construction process for temporary infrastructure 
DRAFT
delayed
• Budget