This is an HTML version of an attachment to the Official Information request 'Molesworth St cycle lane'.
 
 
 
Project Business Case  
 
 
 
Thorndon Connections Transitional Project 
 
 
 
WCC Project ID 
6,698 
WCC Classification Tool 
Moderate 
Outcome   
 
Senior Responsible 
Vida Christeller 
Business Owner 
Brad Singh 
 
Owner 
 
 
Funding sought by 
$3,163,609 
Cost Code (CC) 
2094 
 
this Business Case 
 
Funding Source  
WCC with potential for 
Recorded on Annual Plan   Yes 
 
funding assistance 
from Transport 
Choices (CERF) at up 
t0 90% FAR 
Trove Folder 
WCC Project Business 
Project Cost Code 
CAP00097988 
Location 
Case MODERATE 
Thorndon 
Connections.docx 



 
 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 2 of 40 

Template Properties 
These are the details of the template used to create this document. This section cannot be edited. 
Template Name 
Project Business Case (Moderate) 
Template Owner 
Project Governance, Legal & Risk 
Template Version 
V1.1 2020 
Document Properties 
This table describes the properties of the document. 
Author 
Renee Corlett  
Project Manager 
Renee Corlett  
Location 
 WCC Project Business Case MODERATE Thorndon Connections.docx 
Document History 
This table provides a history of changes made when completing this document. 
Version No. 
Date 
Summary of Changes 

27/09/22 
Initial Draft 
Related Documents 
This table lists the documents that support the Business Case (delete/add as applicable) 
Document 
Name and Link 
Council Paper(s) 
Paneke Pōneke: Bike Network Plan 
Project Brief 
Project Brief- Thorndon Connections.docx 
Statement of Work (if applicable) 
 
Assurance Plan 
 
Authority Signatures 
The SRO approves this document as the baseline for the project and grants approval to move to the Plan stage of the IDF. 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 3 of 40 

link to page 6 link to page 7 link to page 7 link to page 8 link to page 8 link to page 9 link to page 12 link to page 12 link to page 14 link to page 16 link to page 16 link to page 18 Prepared by; Renee Corlett  
 
Signature 
Please print;  Renee Corlett 
Project lead 
 
 
Name 
Title  
Date 
Approved by; 
 
Signature 
Please print;  
 
 
 
Name 
Title  
Date 
Table of Contents 
 
1. 
Purpose of this Document ........................................................................................................................... 6 
2. 
Executive Summary .................................................................................................................................... 7 
2.1. 
Recommendation ............................................................................................................................ 7 
3. 
Strategic Case/The Case for Change ......................................................................................................... 8 
3.1. 
Background/ context ....................................................................................................................... 8 
3.2. 
Strategic Context ............................................................................................................................ 9 
3.3. 
Problem statement ........................................................................................................................ 12 
3.4. 
Identified Benefits ......................................................................................................................... 12 
3.5. 
Measurable benefits from addressing specific problems on these routes: .................................. 14 
4. 
Options Analysis ....................................................................................................................................... 16 
4.1. 
Options Summary ......................................................................................................................... 16 
4.2. 
Options considered and preferred option ..................................................................................... 18 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 4 of 40 

link to page 28 link to page 28 link to page 29 link to page 29 link to page 29 link to page 30 link to page 30 link to page 30 link to page 31 link to page 33 link to page 33 link to page 36 link to page 36 link to page 37 link to page 37 link to page 38 link to page 39 link to page 40 link to page 40 link to page 40 link to page 40 link to page 40 5. 
Procurement Approach ............................................................................................................................. 28 
5.1. 
What is our procurement approach? ............................................................................................ 28 
6. 
Funding Approach ..................................................................................................................................... 29 
6.1. 
Funding Arrangement ................................................................................................................... 29 
6.2. 
Operational/Post Project Funding ................................................................................................. 29 
6.3. 
BCR .............................................................................................................................................. 30 
7. 
Project Management Approach ................................................................................................................ 30 
7.1. 
Project Approach .......................................................................................................................... 30 
7.2. 
Implementation Plan ..................................................................................................................... 31 
7.3. 
Transitional projects governance structure ................................................................................... 33 
7.4. 
Risk and Assurance Planning ....................................................................................................... 33 
7.5. 
Change Management Approach ................................................................................................... 36 
7.6. 
Benefits Management Approach .................................................................................................. 36 
7.7. 
Project Management Planning ...................................................................................................... 37 
7.8. 
Next Steps .................................................................................................................................... 37 
8. 
Recommendations .................................................................................................................................... 38 
Appendix 1. 
Investment Logic Map ............................................................................................................... 39 
Appendix 2. 
Multi Criteria Analysis Criteria and Scoring Scale .................................................................... 40 
Appendix 3. 
Concept Designs ...................................................................................................................... 40 
Appendix 4. 
BCR calculation ........................................................................................................................ 40 
Appendix 5. 
Monitoring and Evaluation Plan ................................................................................................ 40 
Appendix 6. 
Project Control Book ................................................................................................................. 40 
 
 
 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 5 of 40 

1.  Purpose of this Document 
The purpose of the Business Case is to enable a robust process that captures what the project (business problem or business need) is, what investment is required, 
what are the available options and associated costs to deliver the preferred solution.  
The five sections used within this document are based on good practice in both central and local government and cover the following: 
1.  The Case for Change 
Reason for the project– provides supporting information as to why the project is required 
 
2.  Options Analysis 
Compare solutions – provides possible solution options and the preferred option 
 
3.  Procurement Approach 
Procurement strategy – provides options on how the solution will be obtained and from where 
 
4.  Funding Approach 
Funding arrangements – provides funding options, project/programme and ongoing costs 
 
5.  Project Management Approach 
Delivery plan – provides high level information as to how the project/programme is going to be managed and delivered 
 
 
 
 
 
 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 6 of 40 

2.  Executive Summary 
 
This  business  case  seeks  formal  approval  to  proceed  with  the  Thorndon  Connections  transitional  project  beyond  concept  designs  and  on  to  completion  of  design, 
public consultation, and pending Council approval, installation evaluation and adaptation. . 
The Thorndon Connections Transitional project is part of the transitional programme accelerating the installation of Paneke Pōneke – the Bike Network plan, ahead of 
the more permanent projects.  This project will accelerate the delivery of benefits by 3-4 years as the Transformational project is not due for physical works completion 
until 2027. 
The proposed cycle routes will connect into the Botanic Gardens to City transitional bike and bus improvements and Let’s Get Wellington Moving projects: the Golden 
Mile, Thorndon Quay and Featherston Street upgrades.  
The project seeks to address the following key problems: 

Low cycling uptake due to lack of infrastructure and slow delivery 

Low cycle mode share affecting carbon reduction and health 

Poor infrastructure and road user behaviour contributing to higher-than-average rates of harm to cyclists 
The project will deliver the following key benefits: 
•  Improved safety and perception of safety for people on bikes and walking 
•  Increased numbers of people cycling  
•  Increased mode shift away from single occupancy vehicles resulting in reduced emissions   
A monitoring and evaluation plan is in place to measure baselines and ensure ongoing evaluation of benefits post installation. 
The project has worked through the following concept design process with the Future Group Consortium: 
•  Longlisting of options 
•  Shortlisting of options 
•  Multicriteria analysis of shortlist (including 2 rounds of review by internal programme squad and external working group) 
•  Concept designs  
The preferred concepts and rationale are outlined in this business case. 
The total we seek approval for with this business case is the total cost for design construction and installation: $3,163,609 
The project has a BCR of 1.08 with total benefits of $234,064 over a 5 year period.  
 
2.1. Recommendation 
We recommend that the SRO approves this business case so that the project may proceed to 90% design, public consultation 100% design and construction. 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 7 of 40 

3.  Strategic Case/The Case for Change 
3.1. Background/ context 
There has been strong commitment by the Council to develop a safe and connected bike network for the city. Paneke Pōneke - Bike Network Plan was adopted on 10 
March 2022. It sets the strategic direction for investment in a bike network, alongside multi-modal improvements. The objective is to improve safety and connectivity 
for pedestrians, cyclists, and other active travellers of all ages and abilities to create a city where people can move easily and freely without relying on private vehicle 
transport. This is vital to help reduce transport carbon emissions as part of Te Atakura First to Zero, the city’s climate action plan. 
The transitional programme uses interim installations to provide a ‘first cut’ of the whole route using adaptable materials. Following consultation with the community on 
the designs, the Council will gather further feedback on the changes once they are installed and can make improvements to things such as signs, street markings, 
parking and the position of dividers between the bike lanes and traffic. Using this process, we will develop and deliver key sections of the bike network in collaboration 
with the community over the next few years.  
The first two transitional projects (Newtown to the City and Botanic Garden ki Paekākā) will have construction underway in 2022, with the next tranche of project 
design and development now underway for connections to Aro Valley, Ngaio, and Newtown to Island Bay.  
This project is about linking together existing infrastructure investments in the Thorndon/ CBD area (blue in the picture below) including the Botanic Garden to city 
cycleway, the Golden Mile and the Thorndon Quay/ Featherston Street cycleway.  It includes the yellow routes below: Bowen Street west and Lambton Quay east , 
Hill Street and Tinakori Road and Molesworth, Mulgrave and Murphy Street, also Aitken Street and Pipitea Street. 
Tinakori Road and Hill Street are classified as secondary routes while Molesworth, Mulgrave, Murphy and Lambton are primary connecting Wadestown to the city. 
Aitken Street and Pipitea Street were not classified as part of the primary or secondary network in the Bike Network Plan but included within the scope of this project 
based on feedback from the working party through concept design phase and to ensure better connectivity through the area. This includes better connection to 
Wellington Girls College and a more direct route along Aitken Street to the bi-directional facility on Molesworth to the CBD along Lambton Quay. These streets will 
only receive minor improvements such as traffic calming and cycle sharrows, with reallocation of angled parks on Aitken Street.   
Bunny Street East was originally included in scope at the project brief stage but has subsequently been removed due to the overlap with LGWM. Bunny Street East 
currently has some cycling provisions in place and transitional programme improvements were not deemed appropriate due to the large-scale pedestrian 
improvements and larger network planning work needed to be undertaken in this area.   
Stats 2018 census data indicates 4.4% of people travel from Wadestown to work on bike, with 20.3% walking or jogging which is higher than the average for 
Wellington City and highlights the need for improvements to cycling and walking infrastructure within this area.  
 
A project brief was endorsed by the Portfolio Investment Review Committee (previously TPPP) in May and was retrospectively approved by the SRO on Tuesday 11th 
October.  
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 8 of 40 


 
 
 
3.2. Strategic Context 
The proposed investment in cycle routes in Thorndon aligns with national, regional, and local transport strategy and policy. Its core focus is on improved safety and 
enabling more people to walk and cycle so we can reduce the city’s emissions and support healthy ways of getting around.  
 
The project is part of the rapid roll-out of a bike network which is a Council priority in the Long Term Plan.  It aligns with the following Wellington City Council (WCC) 
policies and plans:  
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 9 of 40 

•  Paneke Pōneke / the Bike Network Plan was approved by Wellington City Councillors in March 2022. The objective of the plan is to improve safety and 
connectivity for pedestrians, cyclists, and users of scooters of all ages and abilities, and to reduce transport carbon emissions as part of Te Atakura, the city’s 
climate action plan.  
•  The Long-term Plan (LTP) has an accelerated delivery focus for cycleways.  
o  WCC has committed to investing $231 million to deliver the Cycling Master Plan over a 10-year period (assuming co-funding from Waka Kotahi of 
approximately half this amount). This included pulling $52 million forward into Years 1-3 to accelerate delivery through transitional cycleways. 
o  Priority Objective 3 in the LTP is that the city’s core transport infrastructure is a safe, resilient, reliable network that supports active and public 
transport choices, and an efficient, productive and an environmentally sustainable economy. 
•  The Spatial plan for Wellington City has a strategic imperative of enabling low-carbon transport options, aiming to provide better accessibility, safer 
environments for active modes of transport, and move more people around with fewer vehicles. 
•  Climate Action Area, that of better ways to move around the city, include the bike network, pedestrian safety, public transport and considering the city's 
growth. 
•  District Plan Objective 4.2.12 – Access; aims to improve access for all people, particularly people travelling by cycle. 
•  Wellington Towards 2040: Smart Capital (Strategic Plan) puts focus on having a connected and people-centred city.  
•  The Parking Policy objectives include supporting a shift in mode of transport used and supporting safe movement.  
•  As part of the Social Wellbeing Framework, Council recognizes its role in promoting cycling networks and active transport for personal safety and 
resilience, allowing people to live better lives and better contribute to the city.  
In addition, these objectives align with the wider regional and national policies below: 
•  The Wellington Regional Land Transport Plan (RLTP) 2021-2031 has headline targets for carbon emissions, safety, and mode share. 
•  Land Transport Management Act (2013): The relevance of considering legislation is that all transport proposals are required to be assessed against the 
objectives and purpose of the LTMA (2003). The purpose of the LTMA is to “contribute to an effective, efficient, and safe land transport system in the public 
interest”.  
•  Government Policy Statement on Land Transport 2021 includes strategic priorities of improved access to a range of transport choices, promoting mode 
shift, and safety. 
•  Emissions Reduction Plan - Path towards meeting long-term climate targets, and a low emissions future. An action is the preparation of a National Cycling 
Plan (see below),  
•  Waka Kotahi National Cycling Plan – a plan to accelerate delivery of urban cycle networks to activate mode-shift and drive down carbon emissions. 
•  Waka Kotahi Toitū Te Taiao – Our Sustainability Action Plan. A vision for a low carbon, safe and healthy land transport system. 
•  There is also consistency between the aim of the project and the target in the national Climate Change Response Act 2002 of net zero greenhouse gas 
emissions by 2050. 
•  Waka Kotahi Road to Zero – NZ's road safety strategy, two of the main focus areas of which are infrastructure improvements and road user choices. 
Let’s Get Wellington Moving (LGWM) 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 10 of 40 

•  The project is working closely with LGWM who are working on Golden Mile and Thorndon Quay cycleways providing useful connections into these proposed 
solutions. 
Wider Programme of work 
Transitional projects such as the Thorndon Connections are part of a strategic programme of work to fast track the realisation of benefits identified in the Bike Network 
Plan. The other projects are listed in the table below. The table lists the Transitional- and Transformational Projects indicating the timing for each project. 
 
Transitional Timing – 
Transformational (or 
 
 
Project 
Physical works completed 
LGWM) 
Botanic gardens – Waterfront (underway) 
Feb 2023 
Mar 2026 (LGWM) 
Newtown - Waterfront (underway) 
Feb 2023 
2026 (LGWM) 
Ngaio (underway) 
Q1 23/24 
Feb 2028 
Aro Valley (underway) 
 Q1 23/24 
Mar 2027 
Kilbirnie Connections (underway) 
Q2 23/24 
May 2030 
Thorndon Connections (underway) 
Q4 23/24 
Dec 2027 
Newtown – Island Bay (underway) 
Q2 23/24 
Dec 2027 (LGWM) 
Khandallah connection 
Q4 23/24 
Nov 2029 
Ngaio – Johnsonville  
Q1 24/25 
Nov 2029 
Salamanca Rd – Northland  
Q1 24/25 
Apr 2028 
Eastern Package  
Q1 24/25 
Jan 2032 
Newtown centre to zoo/SWIS  
Q1 24/25 
Mar 2029 
Botanic – Karori  
Q2 24/25 
Jan 2031 
Ngaio – Karori  
Q2 24/25 
Aug 2033 
Thorndon – Wadestown  
Q2 24/25 
Aug 2033 
Newlands connection  
Q4 24/25 
Jun 2034 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 11 of 40 

3.3. Problem statement 
The problems are aligned with the Investment Logic Mapping included in the Wellington Bike Network Plan (Paneke Pōneke) PBC (Appendix 1). 
Problem: The lack of appropriate infrastructure and slow delivery to create a cohesive/ complete cycling network is reducing the uptake of cycling 
There are currently significant gaps in the bike network in Thorndon. Connecting these will make it easier and safer to cycle to, from and around these suburbs 
including from Wadestown into the CBD.    
 
Without the proposed Thorndon Connections cycle network there is no safe connection to key destinations in the area like the many schools, businesses, and 
workplaces as well as no safe connection from Wadestown to the CBD.  
 
Permanent street changes in the area as part of the transformational cycleway programme are not scheduled to happen until 2027. This transitional project will aim to 
provide these connections 3-4 years ahead of transformational changes. 
 
Problem: Low cycling mode share is negatively affecting carbon reduction and public health 
Opportunities for a mode shift to more active modes of travel on these routes are currently limited, therefore delaying the goal of reducing transport emissions. A lack 
of connectivity can lead to suppressed uptake of cycling. 70% of people in Wellington said they would cycle more often if safe infrastructure was provided (Source: 
Cycling Demand Analysis, 2014).   
 
Transformational projects in the area are not scheduled for implementation until 2027.  This transitional project will deliver carbon reduction and public health benefits 
for an extra 3-4 years before the transformational project can make them permanent.     
 
Problem: Poor road user behavior and poor quality infrastructure is resulting in harm to people on bikes and walking.  
There have been 1 minor crash and 1 non-injury crash involving cyclists and 2 serious, 11 moderate and 1 non-injury involving pedestrians on the proposed routes in 
the last 5 years (CAS data).  
There were also near miss incidents recorded through dangerspace.nz since 2019 shown in the map below. (Dangerspace.nz only has incidents on this corridor 
dating back to 2019)  
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 12 of 40 


 
3.4. Identified Benefits  
The transitional programme aims to accelerate the delivery of the following benefits ahead of the permanent Paneke Pōneke - Bike Network Plan cycleway rollout. 
The transformational project for Thorndon is not scheduled to be complete until 2027 meaning that this project will accelerate the delivery of benefits by 3-4 years. 
Key Bike Network Programme benefits, identified through the Bike Network PBC are:  
•  Improved safety for people on bikes  
•  Increased role of cycling in the transport network  
•  Increased mode shift from single occupancy vehicles resulting in reduced emissions   
•  Improved environmental and health outcomes  
 
In addition, the transitional projects provide the following benefits to the bike network programme as a whole:  
•  An opportunity to take the public on a challenging journey using more adaptable materials and faster processes which can reduce resistance to 
change and lowers fears around making permanent changes. Interim changes are likely to build confidence in the deliverability of the permanent scheme 
and reduce delivery risks, by tackling the complicated road space re-allocation issues up front and providing evidence of the benefits and impacts.   
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 13 of 40 

Delivering interim improvements via the transitional approach offers an opportunity to refine designs in real-time and improve the quality of the final permanent 
solutions by testing bike, micro-mobility, pedestrian, and bus improvements.  
 
3.5. Measurable benefits from addressing specific problems on these routes: 
 
Problem 
Proposed change  Benefits 
Benefits measures 
How we will measure this 
•  Reduction in serious injury crashes   •  CAS data 
Lack of perceived and actual 
Provide a higher 
Improved safety for 
•  Improvement in perception of 
•  Baseline Survey and post installation 
safety on the routes (10 
level of service 
people on bikes 
safety and ease of cycling.  
•  Speed data 
reported cycle crashes in last 
that aligns with 
10 years) 
design standards 
for people on 
bikes and micro-
mobility devices 
•  Increase in number of people on 
•  Cycle counter data (new one to be installed prior 
The lack of appropriate 
Improve uptake 
Increased role of 
bikes 
to cycle network installation) 
infrastructure and slow 
through  improving  cycling in the transport 
•  Increase in cycling mode share 
•  On-street counts 
delivery to create a cohesive/ 
connectivity 
network 
•  Number of people living within 
•  Tube counts before and after install  
complete cycling network is 
between existing 
Increased mode shift 
500m of a high-quality cycling 
•  Schools - survey trips to school before 
reducing the uptake of cycling –  cycle routes and to  resulting in reduced 
facility 
installation and after 
in particular lack of connectivity  key destinations in  emissions 
•  Desktop analysis of distance from cycling 
between existing cycle routes 
the area 
infrastructure  
and key destinations( 
 
Wadestown, schools, shops, 
CBD)  
 Low cycling mode share is 
•  Physical health benefits from 
•  Longer term changes 
Improved 
negatively affecting carbon 
cycling 
•  Desktop analysis using Waka Kotahi 
environmental and 
reduction and public health 
•  Reduction of CO
methodology  
health outcomes 
2 emissions. 
•  Shift in the number of users 
•  ADT figures and cycle counters 
Oversubscribed parking and 
Provide safe 
Mode shift from single 
counted 
•  Bus patronage  
traffic congestion around key 
connected routes 
occupancy private 
•  Decrease for private vehicles. 
•  Survey 
facilities in the area 
in the suburb so 
vehicles 
Increase for sustainable modes.  
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 14 of 40 

that people 
consider 
alternative modes 
of transport to the 
car 
Improve the time it  Spatial coverage 
•  Percentage completion of the 
•  Point in time assessment at end of construction 
The lack of appropriate 
takes to install the 
strategic cycle network 
(for both measures) 
infrastructure and slow 
cycleway 
delivery to create a cohesive/ 

infrastructure 
  Speed of completion of transitional 
complete cycling network is 
through 
project from project brief to 
reducing the uptake of cycling 
completion of construction 
 
transitional 
approach and 
accelerate 
realisation of 
benefits 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 15 of 40 

4.  Options Analysis 
4.1. Options Summary 
The sections 
The seven routes in the table below are proposed for Thorndon Connections to connect the existing 
infrastructure and encourage mode shift from private motor vehicles to bicycles and micro-mobility devices 
such as scooters. These are moderately flat routes that would connect to the city-wide bike network. 
Route 
Distance 
1.  Tinakori Road  
280 metres 

Bowen Street to Hill Street  
2.  Hill street  
500 metres 
3.  Aitken Street  
160 metres 
4.  Pipitea Street 
150 metres 
5.  Molesworth Street/ Mulgrave Street and Murphy Street 
1530 metres 
6.  Bunny Street West 
90 metres  
7.  Lambton Quay  
125 metres 

Whitmore Street to Bunny Street  
 
Total = 2.8km 
 
The scope of this transitional project includes: 
•  The flexibility to adjust the interim solution and make further improvements throughout the lifespan. 
•  Installation of low-cost, adaptable bike network improvements such as non-permanent materials for 
hit sticks, placemaking and kerb build outs.  
•  Raised pedestrian crossings to support traffic calming, ensure pedestrian benefits are realised and 
the programme builds back better. 
•  Intersection changes to allow the transitional cycleway to operate safely until more permanent 
changes can occur. 
•  Minor speed limit changes  
•  The ability to prepare the way for permanent transformational works in 2027. 
Long list options were identified following a site visit and discussions along the routes. These were then 
refined to a short list in an MCA workshop discussion. The long list included: 
•  One way separated cycleways on each side of the road;  
•  Two way separated cycleways on one side of the road 
•  Painted cycle lanes; 
•  Painted buffered cycle lanes 
•  Shared bus/cycle lanes;  
•  Shared paths; and  
•  Shared neighbourhood zones.  
The following solutions are considered out of scope for the transitional cycleways programme due to cost 
and time to implementation: 
•  A permanent cycleway solution 
•  Land / property acquisition 
•  Relocation of utilities 
•  Lighting upgrades 

link to page 33 •  Road resurfacing 
•  Extensive kerb and channel relocation: The transitional cycleways are intended to require minimum 
physical works and ability to amend or reinstate if required 
Other alternatives not considered appropriate for this route and not assessed as short list options include: 
•  Alternate routes: These routes are identified in the Wellington Cycle Network Plan which has been 
consulted and approved in a separate process which considered alternate route options. Our 
assessment is not intended to repeat this (except in this case adding Pipitea Street and Atkin Street 
as strong option presented itself to ensure connectivity.) 
•  Shared path where the existing footpath is not wide enough: The route is intended to form a key part 
of the cycle network with high cyclist volumes. A narrow shared path would not be compliant with 
Austroads and Waka Kotahi guidance due to the lack of adequate space for both pedestrians and 
cyclists. 
•  Sealed shoulders: These do not provide an adequate level of service or safety, and therefore do not 
generate significant uptake in cycling. 
 
The short list was then taken to a full draft Multi Criteria Analysis by the Future Group consortium team.  This 
was reviewed by the external Transitional programme working group and the WCC programme squad.  (See 
section 7.3 for members of each group).  Reviews from these groups were incorporated and final concept 
designs agreed upon and approved by the Transitional Programme Manager. 
The MCA provides the evidence for recommending the preferred option. The criteria for the MCA can be 
found in Appendix One. The full MCA document can be found at Appendix 2.   
The table in the next section summarises the shortlisted and preferred options for each route section.  These 
preferred options will be further considered during 90% design. This includes the 5 proposed raised 
pedestrian crossings/ platforms along this corridor including Tinakori Road , Hill Street,  Pipitea Street , 
Molesworth and Murphy Street. The raised pedestrian crossings were originally not in scope but have been 
included due to the significant safety benefits they provide to pedestrians and people on bikes by ensuring 
slower vehicle speeds and greater pedestrian visibility and accessibility. While temporary materials were 
considered to deliver these raised platforms, the associated costs and reduced quality and aesthetic of the 
result meant this option was discounted. Raised pedestrian crossings do not need to be tested, and tweaked 
– they are a standardised primary safety system interventions and have an assumed Death and Serious 
Injury reduction factor of 20% as outlined in the Waka Kotahi Standard safety intervention toolkit 
(nzta.govt.nz). 
Raised crossings are approximately $20,000 and take two weeks to install, therefore adding 
an additional $100,000 to construction cost already accounted for and 10 weeks (2.5 months) of construction 
time.  
Minor speed limit changes are also identified within scope of this project as we have confirmed an approach 
with Waka Kotahi to make site specific speed limit changes as part of the consultation process. These speed 
limit changes will be inline with the proposed city wide plans that are currently being developed due for roll 
out in 2025, ensuring safety benefits can be reached in this area for a few years prior to that programme of 
work.  
 
 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 17 of 40 



4.2. Options considered and preferred option 
 
1.Tinakori Road (Bowen Street to Hill Street) 
 
 
Nature of the road 
Shortlist 
Preferred Option 
Reasons 
1.  Uni-directional protected cycle lane 
Town Centre  
on each side (All parks removed) 
Minor Safety improvements only, with 
Uni-directional protected cycle lanes which ranked highest 
transformation team looking to make more 
will provide a better outcome for people on bikes, however 
ADT: 12,841 vehicles 
2.  Uphill protected cycleway (50% parks 
significant changes in the future.  Reducing 
it will have a significant impact on local businesses in an 
removed) 
Narrow corridor, 9.4m 
vehicle speeds through traffic calming 
area which has a high place function and an existing speed 
3.  Minor Safety improvements 
measures such as kerb build outs and 
limit of 30kph. The proposed treatment for other transitional 
 
only, including parklets, kerb 
extending 30km/hr limit. Pedestrian 
cycleway projects with a similar village / town-centre section 
build outs, raised pedestrian 
improvements with raised pedestrian 
such as Aro Valley is to retain the parking and reduce 
crossing and extending the 
crossing. Parklets opportunities to increase 
speeds (current average operating speed ~30km/h) as 
30km/hr speed limit.  
bike parking and amenities.  
much as possible. This section of the proposed network is 
also identified as a secondary route with the primary route 
running down Bowen Street. For the reasons set out above, 
the preferred option is 3 (minor safety improvements) 
 



2.  Hill Street  
 
 
Nature of the road 
Considered/shortlisted 
Preferred Option 
Reasons 
1.  Uphill protected cycleway (50% 
Mostly residential use 
Minor Safety improvements only, with 
Due to the lower traffic volumes using this section and the 
parks removed) 
and school 
transformation team looking to make more 
opportunity to leverage off existing traffic calming measures 
2.  Minor safety improvements 
significant changes in the future.  Reducing 
the preferred option is 2 (minor safety improvements). 
ADT: 2,677 Vehicles  
only including parklets, kerb 
vehicle speeds through traffic calming 
Minor safety improvements for Hill St also aligns with the 
Narrow corridor, 9.7m 
build outs, raised pedestrian 
measures such as kerb build outs and 
preferred option for Tinakori Road with both Hill St and 
wide road.  
crossing and extending the 
extending 30km/hr limit. Pedestrian 
Tinakori Road being secondary cycling routes and reflects 
30km/hr speed limit. 
improvements with raised pedestrian 
the narrower corridor width being well placed for a traffic 
 
crossing. Parklets opportunities to increase 
calming approach. 
bike parking and amenities 
 
 
 
 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 19 of 40 


3. Aitken Street 
 
 
Nature of the road 
Considered/shortlisted 
Preferred Option 
Reasons 
1.  Buffered cycle lane outside 
Angle parked cars, low 
Buffered cycleway outside parking. 
Due to the lower traffic volumes and speeds (~25km/h 
parking 
volume commercial 
Relocating the angled parking to parallel 
average operating speed) on this section of the route and 
zone.  
2.  Protected cycle lane both sides  
parking removing some parking spaces. 
the need to accommodate bus layover spaces, Option 1 
Ensuring design is consistent and doesn’t 
(buffered cycle lane outside parking) is proposed to be 
ADT: 2,585 Vehicles  
3.  Minor safety improvements only   
impend on the temporary bus layover 
taken forward to concept design. This street was not 
12m wide road.  
spaces.  
originally identified as part of the Wellington Bike Network 
but through more detailed network planning analysis has 
 
shown to be an important connector into the city.  
 
 
 
 
 
 
 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 20 of 40 



4. Pipitea Street  
 
 
Nature of the road 
Considered/shortlisted 
Preferred Option 
Reasons 
Minor Safety improvements only.  Reducing 
Commercial, parallel 
1. Painted uni-directional cycle lanes 
Due to the low traffic volumes and narrow cross-section 
vehicle speeds through traffic calming 
parks  
on this section of the route, Option 3 (minor safety 
2. Protected bi-directional bike lane + 
measures. Pedestrian improvements with 
improvements only) is proposed to be taken forward to 
ADT: 2,891 Vehicles  
convert to one-way road  
new raised pedestrian crossing. Sharrows to 
highlight cyclists to drivers.  
concept design. This will ensure better connectivity and is 
9.43 metres wide 
3.Minor Safety improvements only  
inline with the approach to similar streets eg Hill Street. 
This street was not originally identified as part of the 
 
Wellington Bike Network but through more detailed 
 
network planning analysis has shown to be an important 
connector into the city 
 
 
 
 
 
 
 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 21 of 40 



5.Molesworth, Mulgrave, and Murphy Street  
  
Red indicating bi-directional facility and blue uni directional. Eyes indicate direction of street mixes perspective.  
 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 22 of 40 



 
 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 23 of 40 



 
 Note this section is now proposed to be reduced to one lane to allow loading zone at 61 Molesworth Street  
 
 
 
 
 
 
 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 24 of 40 


Proposed raised crossings 
 
Nature of the road 
Considered/shortlisted 
Preferred Option 
Reasons 
4.  Protected cycle lane in each direction (Molesworth 
•  Protected cycle lanes in both 
High volume 
The preferred option to be taken forward to concept 
uphill and Mulgrave downhill) 
directions on Molesworth and 
connection to SH1 
design is option 3 (Protected cycle lanes both 
Murphy Street.  
5.  Bi-directional cycle facility on Molesworth Street 
directions with bidirectional facility on part of 
ADT:  
full-length 
•  Raised pedestrian crossing at 
Molesworth Street). Option 3 offers the following 
9,079 Molesworth  
the top of Murphy Street in 
6.  Protected cycle lanes both directions with 
advantages over option 1 (Protected cycle lane in 
order to slow vehicles where 
each direction): 
8,582 Murphy Street 
bidirectional facilities on part of Molesworth Street 
there is insufficient space for a 
•  Greater cycling network connectivity with the 
9.5 meters wide 
cycle facility.  

bi-directional cycleway on lower Molesworth 
  Bi-directional cycle facility on 
Street allowing cyclists to take a shorter route 
Molesworth Street between 
to Lambton Quay and The Terrace 
Lambton Quay and Aitken 
Street 
•  Insufficient traffic lane width on upper Murphy 
Street (3.8m) to provide a protected cycleway 
section of bi-directional cycleway on 
Molesworth St between Murphy St and May 
was considered in order to provide a 
connection to the Ministry of Health. 
However, this sub-option was discounted due 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 25 of 40 


to the compromised legibility of changing 
from uni-directional to bi-directional and back 
to uni-directional. 
6.  Bunny Street West  
   
Nature of the road 
Considered/shortlisted 
Preferred Option 
Reasons 
Shared space, low 
1.  Retain existing shared street  
Retain existing shared street, 
The preferred option for Bunny Street west is to retain 
volume only access to 
2.  Shared lane westbound, narrow painted cycle lane  improve shared space with 
the existing shared street due to the low traffic volumes 
5 Mobility parking 
eastbound  
roadway art 
and speeds. Bunny Street west currently allows 
spaces and Victoria 
3.  Shared lane westbound, protected cycle lane 
cyclists to travel in the eastbound direction with 
University Loading 
eastbound.  
Victoria University, buses and cyclists allowed to travel 
zone  
in the westbound direction. In discussions with Metlink 
it was agreed that access for buses to Bunny Street in 
ADT: 479 vehicles 
the westbound direction needed to be retained to allow 
Narrow road: 6.4m 
buses to reposition via Bunny Street west. Potential 
wide 
improvements to the existing layout to be investigated 
include road art and relocating the bus layout space. 
 
 
 
 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 26 of 40 


 
 
7.  Lambton Quay (Whitmore Street to Bunny Street) 
 
 
Nature of the road 
Considered/shortlisted 
Preferred Option 
Reasons 
Limited parking, school  1.  Protected cycle lane northbound, shared lane 
Bi-directional cycle facility east 
Option 2 is the preferred option because it seamlessly 
bus stops  
southbound 
side connecting with the Golden 
ties into the proposed bi-directional cycling facility on 
2.  Bi- directional cycle facility east side  
Mile facility.  
Lambton Quay south of Whitmore St. This is because 
ADT: 8,761 vehicles 
3.  Bi-directional cycle facility west side 
it is logical for cyclists to be able to continue along 
Wide road: 23.4m  
 
Lambton Quay on a continuous bi-directional cycleway 
rather than needing to change facility types at 
 
Whitmore St. In discussions with the Golden Mile 
project team, it was confirmed that construction of 
Thorndon Transitional Cycleways programme 
implementation dates could be aligned with the Golden 
Mile avoiding the need for an interim layout. 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 27 of 40 

5.  Procurement Approach 
5.1. What is our procurement approach? 
Implementation will be approved by the Senior Responsible Owner with final design signoff from the asset 
owner. 
All procurement on the programme is coordinated by WCC’s Commercial Partnerships team. Four main 
services that we have procured/are procuring:  
•  Design Services,  
•  Road Safety- and Accessibility- auditing Services,  
•  Engagement Services, and  
•  Construction Contractor Services. 
Design 
The Transitional Programme is using WCC’s Master Services contract for design services with two design 
consortia which has been setup to deliver design to the LGWM and the Transitional Programme. The benefit 
is that these consortia work in the same geographical areas. The consortium working on this project is the 
Future Group consortium including WSP and Stantec.  
Road Safety and Accessibility Auditing services 
We have procured ViaStrada appointed through a closed RFQ with a focus on smaller providers with 
experience in the urban multi-modal realm. 
Engagement services  
The transitional programme is currently running a competitive tender to procure these services with the 
support of the Commercial Partnerships team.  
Construction services 
The Transport and Place Planning Delivery team will implement, and project manage the construction of the 
proposed transitional cycleways. The team is establishing a panel of suitably skilled and qualified providers 
who have the range of skills that will be required. WCC has a strong broader outcomes agenda that will look 
to specifically target this work using local suppliers within the Greater Wellington Region. 
 
 
 
 
 


6.  Funding Approach  
6.1. Funding Arrangement 
Funding for the transitional cycleways has been approved as part of the Bike Network plan. 
Estimated costs based on concept designs are $2,676,900 - $3,163,609 based on a 30% contingency as 
outlined below to allow for risk and uncertainty at this stage of design.  Link in Appendix 10.  
  
6.2. Operational/Post Project Funding 
Post project funding arrangements include 3-4% of the project construction budget to allow for 
maintenance of the proposed cycleways. 
Projected 
Financial year 
costs 
 
22/23 
23/24 
24/25 
25/26 
26/27 
Total 
 
Capital expenditure 
 
$2,000,000 
$1,163,609 
 
 
 
$3,163,609 
Operating 
 
 
 
$42,178 -
$42,178 -
$42,178 -
$126,534 - $168,714 
expenditure 
$56,238 
$56,238 
$56,238 
Total expenditure 
 
$2,000,000 
$1,163,609 
$42,178 -
$42,178 -
$42,178 -
$3,290,143 - $3,332,323 
$56,238 
$56,238 
$56,238 
 
 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 29 of 40 

6.3.  BCR  
We have done a BCR calculation which returned a BCR of 1.08 over the first five years based on the 
estimated cost with 20% contingency. A 20% contingency was used for the calculation as this is what is 
recommended in Waka Kotahi guidance however, we are requesting funding up to 30% contingency due to 
the transitional nature of these projects which increases uncertainty   
 
Sensitivity analysis has been done below on what adding a 10% and 20% increase on top of this would do to 
the BCR.  The duration of benefits that will be accrued from this project will depend on the outcome of the 
Transformational team business case.  
 
 
Total over project life (all 
Project  
numbers discounted)  
Cycle facility benefits  
$203,945  
Cycle health benefits  
$337,842  
Increased cycle safety  
$54,554  
Increased pedestrian safety  
$7,268  
Increased car safety  
$219,198  
Total benefits  
$3,249,244  
Total costs (@20% 
contingency)  
$3,015,180  
Net benefit  
$234,064  
BCR  
1.08  
  
  
Sensitivity Analysis on this BCR is as follows:  
  
Sensitivity  
BCR  
Increased Cost by 10%  
1.04  
Increased cost by 20%   
1.00  
Decreased Cost by 10%  
1.12  
Decreased Discount to 3%  
1.10  
Increased Discount to 6%  
1.03  
The rise in cycling numbers is decreased to 4 %  
1.01  
The rise in cycling numbers is increased to 10 %  
1.14  
Project lasts 10 years (Transformation programme does not go 
ahead) 
2.37  
 
The BCR calculation can be found at Appendix 4. 
7.  Project Management Approach 
7.1. Project Approach 
The transitional street changes are intended to be an interim solution before permanent upgrades seeking 
the same objectives are delivered. The project will adapt based on public consultation and findings where 
necessary, there may be unforeseeable circumstances that lead to removal of the transitional cycleway, but 
these will be managed at the time, in consultation with stakeholders. The project is being delivered using 
temporary and quick install materials so any changes made are low cost and can be arranged relatively 
quickly. The data and other evidence gathered will also help with the adaptation of the bus and bike 
improvements. 
Specific councillor support for the Thorndon Connections Transitional Cycleway will be confirmed again 
during the Traffic Resolution process.  
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 30 of 40 



The adaptive approach of the project is explained in the diagram below. 
 
 
7.2. Implementation Plan 
Following the WCC Investment Delivery Framework process, upon approval of business case, the project 
manager will be accountable for planning, coordinating and overseeing the project implementation as well as 
coordinating and overseeing all pre-implementation activities. 
Pre-implementation activities include ensuring the completion of the detailed design package, stakeholder 
management and engagement including the traffic resolution process, risk management and procurement of 
construction services. 
The engineer contract will follow standard 3910 construction contract administration protocols including, but 
not limited to, issuing and responding to notices to/from contractor, responding to requests for information 
and conducting field inspection for quality control and to ensure conformance with design drawings and 
relevant standards. 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 31 of 40 

There will be monthly reporting to the SRO. 
Implementation will be approved by the SRO with final design signoff from the asset owner. 
The programme squad (internal stakeholders who have a role in reviewing and making recommendations) 
and working group are kept up to date with project progress fortnightly. They are project advisors who 
provide formal feedback into each of the design stages. 
The project falls under the wider Bike Network programme which is managed by Hazel Durkin, Bike Network 
programme manager.
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 32 of 40 


7.3. Transitional projects governance structure 
 
 
The following internal programme squad are consulted at each step of the design process and provide 
review input: 
•  Traffic Engineer - Dennis Davis 
•  Signals Engineer – Haydn Wardley  
•  Principal Transport Engineer – Daniel Cairncross 
•  Delivery specialist – Stephen Harte and Dale Bowman 
•  Urban Designer – Paige Boyd 
•  Traffic Signals Specialist – Tim Kirby 
•  Behaviour Change Specialist – Georgia Halley 
•  Network Manager – Denise Beazley  
•  Evandro Scherer, Peter Hamilton and Kylie Hook 
•  Parking Services Specialist – Renee Reedy and Karan Parkinson 
  
7.4. Risk and Assurance Planning 
Risk information 
Describe the risk  
Risk rating
Risk treatment/ mitigation 
 
(including cause and impact) 
If we do not coordinate projects and 
 
Early communication with other projects 
communications with the other WCC and wider 
including the bus interchange, reworking 
 
transport projects including LGWM and 
designs to ensure limited rework of 
construction sites in this area we could create 
High  
intersection. Early communications with 
disconnected network and upset residents and 
61 Molesworth Street to determine if 
businesses and lose the goodwill of the 
TMP can incorporate cycleway. 
community.   
Business readiness engagement can 
encompass the wider picture.  Ongoing 


communication between projects and 
alignment of timelines to minimise 
disruption for residents and businesses.
  
The visibility of the project to embassy 
High  
Brief local MP and connect with 
parliament staff might mean the project's profile 
parliamentary services to ensure early 
is easily elevated to national levels (both +ve 
engagement and to promote awareness 
and -ve) meaning increased scrutiny and time to 
of project. Understand any concerns that 
manage that. 
arise early to provide response and 
 
communicate clear story with key 
messages.  

 
If the scope of work desired is too great for 
High  
Undertake Road Safety Audits at 30% 
interim solutions, we will need to compromise 
and 90% designs to identify safety 
design which could lead to safety issues and 
issues. Focus on the Moderate and 
cycle uptake.  
Severe risks and look at options to 
alleviate through design. Work closely 
with Transformation team for next step 
improvements  

If the loss of parking leads to more push back 
Medium 
Balancing this in decision making 
by businesses, residents, and other 
informed by comprehensive on and 
stakeholders this could lead to compromised 
offstreet parking assessments at the 
cycleway infrastructure.  
MCA stage and seeking alternative 
solutions or phased approaches. 

Production of a Parking Management 
Plan in accordance with the Parking 
Policy and specific engagement strategy 
with Businesses, Residents Association, 
Schools and Community groups. 

If the Traffic resolution prior to install is not 
Medium 
Regular briefings and updates to 
supported by elected members this will lead to 
councillors, show how the community 
redesign or halt to the project 
has fed into the design process and how 
it continues after the TR and install. Be 
clear what has been considered and 
what hasn't and why. Be clear about 
what we will monitor 

If unable to implement protected cycleways and 
Medium 
Communication plan with the public to 
public expectations too high, it could result in 
provide context of transitional cycleways 
lower uptake and reputational impact 
to manage expectations. 
If there isn't enough behavioural 'how-to' work to 
Medium 
Ensure communication is clear and 
complement delivery, the cycleway on the right 
activations raise awareness of new road 
hand side may confuse people and be opposed 
layouts.  
If contractor resources are constrained, then it 
Medium 
Early contractor procurement to commit 
leads to delay in implementation and 
resources.   
reputational damage 
If material availability is delayed, then it will 
Medium 
Early procurement of materials that 
delay the delivery timelines leading to 
require freighting or manufacturing i.e. 
reputational damage 
hit posts 
If costs of the project are perceived as high 
Medium 
Communication and engagement 
given permanent planned works, then the 
through our comms channels  
project can lose public support / reputational 
damage. 

If the shortage of parking enforcement staff 
Medium 
Provide clear comms through our usual 
leads to insufficient enforcement, some of the 
channels, consider visual signs (VMS) at 
cycleways/lanes will be used as parking leading 
sections that have this risk 
to safety & reputational issues 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 34 of 40 


If the project team reaches capacity due to the 
Medium 
Comms and engagement planning. 
number of projects happening concurrently. This 
Identify when extra capacity is needed 
could mean that there is an overwhelming 
early, and bring in resource (from within 
stakeholder or communication load that isn't 
WCC or contactor) when required 
effectively managed, creating reputational risks 
If using in-lane bus stops, this could have 
Low  
Engagement with emergency 
significant impact to emergency responders and 
responders and key stakeholders to 
network operations, the programme reputation 
understand requirements and 
will be damaged 
incorporate into the design. Using 
adaptable materials that can be 
changed. 

If the accessibility is compromised through 
Low 
Accessibility Audits at 30% and 90% 
design, then sections of the community will be 
designs to identify critical issues and 
excluded through the new infrastructure 
resolve through design.   
Position responsible for any escalated risks   Chief Planning Officer  
Chief Infrastructure Officer 
Project assurance processes in place 
1.  Risks are managed and monitored by the assigned project manager 
in the Project Control book 
8.  The project’s weekly WIP meeting is a platform for the project team 
to discuss/update/raise risks 
9.  Significant project risks (as earmarked by the project manager) are 
included in the Project Control Book (Appendix 6) 
10. All risks are assigned to an owner who is responsible for monitoring 
specific risks 
11. Significant project risks are raised during the monthly programme 
board meeting 
Risk allocation 
 
All risks will be managed by Wellington City Council  
 
 
 
 
 
The process and response hierarchy for post implementation changes  
 
 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 35 of 40 

 
7.5. Change Management Approach 
Once the business case is agreed any changes to project scope will be fully documented with reasoning in a 
change register.  If the project starts to deviate from approved project cost, time or scope we will use the 
change request processes provided by the PMO and seek board approval. 
7.6. Benefits Management Approach 
The programme will have a 0.5 FTE dedicated to assisting the project managers with the monitoring and 
evaluation on these projects. 
The programme has a comprehensive monitoring and evaluation plan which starts by baselining before 
implementation and ensuring ongoing measurement.  We have a wider programme of work focussed on 
rolling out more cycle counters on planned routes well ahead of implementation which will allow us to gather 
good baseline data as well as show the impact of the transitional cycleways. 
Our monitoring and evaluation of benefits has a close connection with communications and engagement.  
We are using a baseline survey to help with engagement. Statistics from this survey help to inform our key 
messages and communications during the project and after.  
The monitoring and evaluation framework can be found at Appendix 5. 
 
 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 36 of 40 

 
7.7. Project Management Planning 
Please refer to Appendix 6 for the Project Control book. 
Key Project Milestone 
Description 
Approximate 
Date 

Procurement 
Procurement of professional services.  
Completed 
Project brief  
Approval gained.  
 Completed 
Discovery/Readiness engagement 
Commence discussions with local businesses   Completed 
starts  
and resident groups to understand their 
needs and support levels 
Concept design 
Optioneering from shortlist to concept 
 –  Completed 
design of preferred option completed  
Approval of Business Case by WCC  
Seek approval to proceed with project 
October 2022 
30% Designs  
Preferred option   
October 2022 
RSA on 30% Designs  
Scheduled in  
October 2022 
90% Designs  
Scheduled in  
December 2022  
RSA on 90% Designs  
 
January 2022 
Asset owner approval of 90% 
Seeking approval for construction to 
December 2022 
Designs 
commence.  
Traffic Resolution consultation 
Active business and community engagement   April 2022 
completed 
Approval of Traffic Resolution by 
 
May 2022 
Planning & Environment Committee 
100% designs signed off 
 
May 2022 
Pre-implementation commences 
 
June 2022 
Installation commences 
Installation of the activity aim to commence 
Q1 23/24 
in 2023 and completed by 2024 
Installation completed 
 
Q4 23/24 
Post implementation alterations and  Adaptability to make tweaks based on 
Ongoing as 
tweaks 
feedback post installation.   
sections 
completed July 
2023 – June 2024 
7.8. Next Steps 
The team are working on a baseline survey for circulation on 31 October.  The survey will ask questions 
about how they currently experience the route and the suburb.  A letter drop to the area will support this to 
advise residents and businesses of the changes coming to the suburb and provide them with a link to the 
survey.  Analysis of survey feedback will feed into 90% designs in December.  
Following the approval of the Business Case the project will proceed to 30% design on the preferred 
concepts and we will seek further internal project team and external working group feedback as well as 
safety and accessibility audits on the proposed designs.   Once 30% designs are complete engagement will 
focus on awareness in the area and further discussions with key groups.  
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 37 of 40 

The designs then proceed to 90% and preparation will begin for the traffic resolution 
consultation.  Consultation on a traffic resolution for these sections is expected to take place in March 2023.  
  
 
8.  Recommendations 
It  is  recommended  that  the  SRO  approves  this  Business  Case  and  the  recommended  preferred  option 
presented above. 
Approve:  
Name 
Title 
Date 
 
 
 
 
 
 
 
 
Note any comments made by the governance board, if any. 
 
 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 38 of 40 


Appendix 1. Investment Logic Map 
 
 
Taken from the Updated Bike Network Plan PBC: 
WCC Project Business Case MODERATE template.docx (Moderate) Thorndon Connections Transitional Project 
Page 39 of 40 



 
Appendix 2.  Multi Criteria Analysis Criteria and Scoring 
Scale 
2022-10-10_FINAL_Transitional Cycleways Multi Criteria Analysis - MM_with appendix.pdf 
 
Notes: Consideration should be given to fatal flaws, such as removing bus lanes, or causing significant 
safety issues.  
Appendix 3. 30% Concept Designs 
5-C3880.32_C30-C40(A) (General Layout).pdf 
5-C3880.32_C105-C106 (Molesworth St - Hill St - Aitken signals) C105-C106.pdf 
Appendix 4. BCR calculation 
Thorndon BCR calculations (003).xlsx 
Appendix 5. Monitoring and Evaluation Plan 
M&E for Thorndon Connections .xlsx 
Appendix 6. Project Control Book 
Thorndon Connections Project Control Book.xlsm 
Appendix 7. Communication Plan  
 Thorndon Connections - Communication and Engagement Plan.docx 
Appendix 8. Project Schedule   
Thorndon Connections project schedule .mpp 
Appendix 9. Cost breakdown  
Thorndon Connections Cost Estimates.xlsx 
WCC Project Business Case MODERATE template.docx (Moderate): Thorndon Connections Transitional Project 
Page 40 of 40