This is an HTML version of an attachment to the Official Information request 'Project management system'.
DocuSign Envelope ID: 410E44B8-54C7-4981-84F6-C6775C22815A
DocuSign Envelope ID: 4C651DDA-01D1-458A-8526-812749B73C10
Project Management System 
 
 
Procurement Plan 
 
Purpose  The primary uses of the document are to: 
•  Define the procurement activity, to form the basis of its management and 
assessment of overall success; 
•  Bring together the strategy for the procurement and prior analysis into an 
operational plan to carry out the procurement and select a supplier/s; and 
•  Record approval for the procurement to proceed on the basis set out in this plan. 
•  To ensure consideration has been given to the optimal procurement strategy, 
methodology and outcomes at a local, regional and national level. 
•  To deliver an end to end Procurement solution for the Council. 
 
 
 

Guidance Notes 
DocuSign Envelope ID: 410E44B8-54C7-4981-84F6-C6775C22815A
DocuSign Envelope ID: 4C651DDA-01D1-458A-8526-812749B73C10
 
 
 
When to  This Procurement Plan is intended for use for procurements which are either between 
use 
$50,000 and $250,000 with a low to medium risk rating, for procurement over $250,000 or 
any procure with a high risk rating. 
   
How to  Al  sections within the Core Information Section must be completed for procurement over 
use 
$50,000 regardless of risk rating. For those projects over $250,000 or of any value with a 
high risk rating the Additional Information Section must also be completed.  
NB: If you are using a Business Case or Project Plan the information provided within these 
documents must be equivalent to the sections required for completion in the Procurement 
Plan.  
 
In some cases, a Business Case or Project Plan wil  be required. It is acceptable to use it 
in lieu of a Procurement Plan subject to the fol owing: 
1.  Al  the elements that must be completed in the Procurement Plan (this wil  vary 
dependent on whether or not it over or under $250,000 and the risk level) are 
completed ful y in the Business Case or Project Plan (this is detailed above); 
 
2.  That the appropriate Delegated Authority levels are prepared to  sign off the 
Procurement Plan requirements as part of the Business Case or Project Plan;  
 
3.  Al  aspects of Procurement Policy remain complied with. (For example if a 
Procurement exemption would be required, this stil  gets completed as part of the 
process); 
 
4.  The Business Case or Project Plan Checklist page and the Approval Page of the 
Procurement Plan are to be completed and the Business Case or Project Plan, 
plus  any supporting documentation are  included in the Procurement Plan 
appendices. 
 
For clarity, a checklist has been provided with the requirements. 
 
 
 
 
 
 

Business Case or Project P
DocuSign Envelope ID: 410E44B8-54C7-4981-84F6-C6775C22815A
DocuSign Envelope ID: 4C651DDA-01D1-458A-8526-812749B73C10 lan Checklist 
Documentation Checklist 
CORE INFORMATION 
Check the box 
if complete 
Procurement Information including: 
☒ 
•  Procurement information 
•  General information 
•  Procurement scope 
•  Proposed contract details 
•  Estimate of value 
Procurement Methodology including: 
☒ 
•  General procurement strategy statement 
•  Procurement Method 
Procurement Exemption Information 
N/A 
Risk Information including: 

•  General risk management 
 
Supplier Information including: 
N/A
•  Current supplier / contracts 
 
Stakeholder Information including: 
•  Consultation checklist 
☒ 
Procurement Timeframe including: 

•  Basic timeframe 
 
Evaluation Information including: 
•  Evaluation Methodology 
☒ 
•  Evaluation Panel 
Procurement team including: 
•  Team Members basic 
☒ 
APPENDICIES 
Check the box 
if complete 
Al  appendices included – e.g. Business Case, Project Plan, Procurement 
Exemption, Conflicts of Interest and Confidentiality, HSE approval and Capex. 
☒ 
 
 






link to page 5 link to page 7 link to page 7 link to page 7 link to page 8 link to page 8 link to page 8 link to page 8 link to page 8 link to page 8 link to page 8 link to page 8 link to page 9 link to page 9 link to page 9 link to page 9 link to page 9 link to page 10  Table of Contents 
DocuSign Envelope ID: 410E44B8-54C7-4981-84F6-C6775C22815A
DocuSign Envelope ID: 4C651DDA-01D1-458A-8526-812749B73C10
CORE INFORMATION SECTION .......................................................................................................... 5 
1.  PROCUREMENT INFORMATION .................................................................................................. 6 
1.1. 

Procurement Information ......................................................................................................... 6 
1.2. 
General Information................................................................................................................. 6 
1.3. 
Procurement scope ................................................................................................................. 7 
1.4. 
Proposed contract details ........................................................................................................ 7 
1.5. 
Estimate of value ..................................................................................................................... 7 
2.  PROCUREMENT METHODOLOGY .............................................................................................. 8 
2.1. 

General procurement strategy statement................................................................................ 8 
2.2. 
Procurement Method ............................................................................................................... 8 
3.  PROCUREMENT EXEMPTION ...................................................................................................... 8 
4.  RISK ................................................................................................................................................ 8 
4.1. 

General Risk Management ..................................................................................................... 8 
5.  SUPPLIER INFORMATION ............................................................................................................ 8 
5.1. 

Current suppliers/contracts ..................................................................................................... 8 
6.  STAKEHOLDERS ........................................................................................................................... 9 
7.  PROCUREMENT TIMEFRAME ...................................................................................................... 9 
7.1. 

Basic Timeframe ..................................................................................................................... 9 
8.  EVALUATION PLAN ...................................................................................................................... 9 
8.1. 

Evaluation methodology .......................................................................................................... 9 
8.2. 
Evaluation panel .................................................................................................................... 10 
9.  PROCUREMENT TEAM ............................................................................................................... 11 
9.1. 

Team Members Basic ........................................................................................................... 11 
 
CORE INFORMATION SECTION 
 
This must be completed for all procurement over $50,000 with a low or medium risk rating. 
 



The intent of this PM improvement process
DocuSign Envelope ID: 410E44B8-54C7-4981-84F6-C6775C22815A
DocuSign Envelope ID: 4C651DDA-01D1-458A-8526-812749B73C10 is to increase Capex delivery from 60% (Average delivery of 
overall capex programme between 2020 – 2023) to 85% going forward.  This aligns with a new CEO KPI 
that has been approved by council. 
 
1.3. Procurement scope 
The intent of this procurement exercise is to deliver a simple digital Project Management tool that aligns 
with the approved PM Methodology.  See attached detailed requirements for this tool. 
 
1.4. Proposed contract details 
 
Proposed Contract  It is anticipated the costs for the implementation of a PM Tool wil  consist of the 
following : 
Phase 1  
-  Implementation & configuration (Including testing / user acceptance 
testing/training) of tool.  This wil  enable TCDC to : 
o  Load in project baselines including scope, programme milestones 
and budgets (Currently being developed & approved in excel) 
o  Produce project status reporting by project, programme and portfolio 
(Note : Need to include reports for council / community boards) 
o  Enable PM’s to input regular monthly updates on status 
o  Ability to carry out financial forecasting at project level and pul  in 
actuals from CashTrack  
o  [See Tool Requirements – Must Have] 
Phase 2 
-  Further enhancements to the tool –  next 6-12  months, this will include 
additional risk reporting, workflows, idea generation & approval (ready for 
FY25/26 AP) 
o  [See Tool Requirements – Could/Should Have] 
Ongoing costs 
-  Ongoing licence / support costs for tool 
Any additional 
n/a 
contractual terms 
or issues 
Length of the 
The proposed term is be a short term contract for implementation and an annual 
arrangement 
contract for licencing & maintenance. 
 
1.5. Estimate of value 
 
Expected $ value 
$120,000 for implementation 
of the contract / 
purchase 
Budget details 
Has the funding been approved? 
Yes 
Is funding required from other agencies (e.g. NZTA)? 
No 
As noted above, an al ocation of $120,000 has been assigned to this project for 
24/25.  Other large projects are being delivered by the ICT team.  If there are 
additional funds required an OOC request wil  be sought. 
Due to the changes in the Tool decision making additional effort wil  be required from 
Lorenzo Canal / Ian Morton.  This is provided for under professional services 
contracts through Glen McIntosh budget. 
 

2.  Procurement Methodolog
DocuSign Envelope ID: 410E44B8-54C7-4981-84F6-C6775C22815Ay
DocuSign Envelope ID: 4C651DDA-01D1-458A-8526-812749B73C10  
 
2.1. General procurement strategy statement 
This wil  be run as an open tender process for RFP’s through GETS.  
 
2.2. Procurement Method 
The Method for the first or only phase 
RFP 
The Method for the second phase 
N/A 
 
3.  Procurement Exemption 
 

Procurement 
Is this a request for a procurement exemption? 
No 
Exemption 
 
Running an RFP is in line with the procurement process for a contract of $120,000 
n/a 
4.  Risk 
4.1. General Risk Management 
 
Risk Description 
Risk Level  
Proposed Action 
(Low/Medium/High/E
(manage/mitigate/accept) and Risk 
xtreme) 
Owner 
Changes to the agreed contract –  Medium 
Through the RFP process any 
scope change as a result of 
clarifications wil  be shared with al  
undefined requirements  
vendors.  Before contracting all 
relevant queries wil  be addressed. 
Requirement changes occur after  Medium 
Detailed requirements available & wil  
contract award  
work through this in advance of 
contracting where possible.  Need to 
include some contingency for potential 
variations – normal practice (15%) 
Lack of internal resource to support  Medium 
PM’s / Finance / IT teams are busy, 
rollout 
impact the rol out timeline.  Need to 
ensure all relevant internal resources 
are identified and float added into the 
schedule. 
Integration with Cashtrack could be  Medium 
Included in the requirements & we wil  
problematic 
ask for clear proposal through the 
RFP. 
5.  Supplier Information 
 
5.1. Current suppliers/contracts 
N/A – There is no current suppliers in place.   
 

DocuSign Envelope ID: 410E44B8-54C7-4981-84F6-C6775C22815A
DocuSign Envelope ID: 4C651DDA-01D1-458A-8526-812749B73C10
Current supplier 
n/a 
Current contract #  n/a 
Current contract 
n/a 
expiry date  
Current annual 
n/a 
expenditure 
Relevant history 
n/a 
6.  Stakeholders 
Key stakeholders for this are the business owners (PM Team, Activity managers and GM’s), IT and 
finance support teams plus process improvement team.  Al  have bene involved in the PM improvement 
project to date. 
Consultation Checklist 
Impact 
Yes/No 
Is this procurement liable to impact on the reputation of the Council? 
No 
Does this procurement involve any security issues, building alterations, building space  No-  Need to 
requirements, environmental impacts, staff relocation, electrical services, essential power  comply with 
requirements, compressed air, hot or cold water or any other service connection? 
council 
requirements 
for security 
Does this procurement involve any hardware or software that needs to be connected to or to  Yes 
operate on our network or be supported by IS?   Does it involve any telecommunications 
equipment or services?   
If yes, you must inform IT and involve them in the assessment of the options. 
Does this procurement involve a significant hazard (something that can cause serious harm)?  No 
Does the procurement impact the community/external users/industry? 
No 
 
7.  Procurement Timeframe 
 
7.1. Basic Timeframe 
Milestone 
Due date 
Approve Procurement Plan 
26 Jun 24 
Proposed date to go to market 
1 Jul 24 – 29 Jul 24 (4w open tender process) 
Evaluation date 
31 Jul 24 – 2 Aug 24  
Negotiation date 
5 – 9 Aug 24 
Award date 
12 Aug 24 
Contract start date 
19 Aug 24 
 
8.  Evaluation Plan 
See Details below. 
8.1. Evaluation methodology 
 
Evaluation Method  A weighted attribute approach wil  be used in assessing RFP’s. 

DocuSign Envelope ID: 410E44B8-54C7-4981-84F6-C6775C22815A
DocuSign Envelope ID: 4C651DDA-01D1-458A-8526-812749B73C10
Criteria & 
See attached evaluation criteria / scoring. 
Weightings 
Evaluation Process  When evaluation panels are scoring submissions, our top of mind focus must 
always be on ensuring our individual and collective behaviours meet 
appropriate standards of probity. 
  Everyone involved in the evaluation must have completed/signed 
a Conflict of Interest & Confidentiality Agreement. 
  Confidentiality must be respected and maintained throughout the 
process  
  Contact with suppliers - the Project Manager is the only person 
permit ed to comment to outside parties about the evaluation 
process and outcome. The panel should not discuss any element 
of the process with work colleagues or any other party. 
 
Conflict of Interest / bias: The evaluation process must be free of bias and any perception  
of bias. Any conflicts of interest (Actual, potential or perceived) and possible issues of bias 
must be disclosed and discussed with the Project Manager before commencement of this stage  
 
There are a number of principles that should be applied when you are 
evaluating the supplier submissions: 
  Each evaluator must carry out an independent evaluation. 
Individual scores wil  then be reviewed and debated as a panel. 
Either a consensus wil  be arrived at or panel members wil  be 
asked to carry out a ‘second pass’ of their evaluations, taking into 
account the panel discussions. 
  Proposals must be evaluated in accordance with the criteria 
enclosed/attached to these instructions. 
  Only information contained in the tender submission is to be 
evaluated.  You may also take into account information obtained 
from any early stage of the process. No extraneous views, 
supposition or assumptions should influence your evaluation. 
  You must evaluate each submission on its own merit and not in 
comparison to another submission. While moderation wil  involve 
naturally comparing the evaluation of scores across tenders, 
evaluators should keep any such comparison to a minimum. 
  Clear, succinct but comprehensive notes are required in support 
of your scores. Al  evaluation notes and material must be 
retained for audit purposes. 
 
Once the panel members have completed their evaluations a panel review 
meeting wil  be held.  Each panel member wil  table their proposed scoring and 
their rationale.   
Following this discussion if a panel member wishes to update their scoring, this 
needs to be documented with clear rationale. 
Al  details wil  be col ated and a final decision made by consensus on the 
preferred supplier.   
 
Evaluation Matrix 
Has an evaluation matrix been completed and appended to the  Yes 
document? 
 
8.2. Evaluation panel 
The evaluation panel wil  comprise of Council representatives listed as evaluation panel members in the 
Procurement Team – See Section 9.1. 



Document Outline