o Enhancements to existing Project Management Tool –
Project Online OR
o Implement a new Project Management Tool – Powa PPM
Vision
Mission
o Implement a PM system and processes that is tailored to the
Statement :
needs of TCDC.
PM
Improvements
Goals / Objectives
at TCDC
o Improve PM delivery - currently only 60-65% capital delivery
programme is delivered against (using an average over last 3
years)
o Deliver reporting for internal / external stakeholders to
improve decision making
o Improve PM capability across council
o Implement standardization of the PM approach across
council that meets the needs of TCDC, where lessons can be
captured and incorporated back into the process (continual
improvement)
End to end project management system for TCDC
Include :
Product/
o Project management system
Service : PM
o Appropriate and scalable project management processes
Improvements
o Initial training for al users
at TCDC
o Clear RACI (Responsibility Accountability Contribute Involve)
Matrix for the wider organization
o Integrate to existing systems (i.e. finance / procurement /
risk etc)
o Reporting for internal / external stakeholders
To note
o There are currently approx. 10 project managers at TCDC
o The capital delivery programme is approximately $50m per annum
Accept 2 : Risk needs to be transparent & clearly communicated
to users / business.
Timeframe for
The vendor has advised that PowaPPM has been rol ed out in 1
Rollout
month for one client and 6 months for another client.
The vendor has recommended a rollout of 2 months, noting
requirement changes need to be managed appropriately.
Appendix A : Assessment of Requirements (Project Online vs PowaPPM)