This is an HTML version of an attachment to the Official Information request 'Whakapapa make good costs'.

 
 
 
18 October 2024  
 
Stephen Prendergast 
 
 
[FYI request #28257 email] 
   
 
Tēnā koe Stephen 
 
Thank you for your request to the Department of Conservation, received on 31 August 2024, 
in which you asked for: 
 
1.  All correspondence since 1 Jan 2024 between DOC and other Crown agencies 
regarding costs to make good the Whakapapa ski concession area, and 
associated facilities. For instance, lift removal, remediation, ski field buildings, ski 
club lodges and related infrastructure such as reticulated services etc. Please 

include all, identified costs such as DOC internal personnel, contract resources as 
backfil  where staff are assigned, or fixed term employees tasked to manage or 
participate in this work. 
 
Please provide the information in 6 monthly periods where this is available. 
 
2.  The forecast income loss that DOC wil  experience as a result of the cessation of 

ski field operations. Including discussions with other crown agencies. 
 
3.  Al  internal DOC correspondence identifying how these figures were determined, 

and the degree of confidence. 
 
4.  Al  documentation and correspondence from 1 Jan 2024 that addresses scenarios 

to reduce or mitigate the financial impact of such an outcome. 
 
5.  Al  ministerial briefings or updates which address this outcome. 

 
We have considered your request under the Of icial Information Act 1982. 
 
On 18 September 2024 you clarified (or refined) your request by confirming that you were 
seeking information from 1 January 2024 and that in regard to question 4 you seek 
information that covers operating scenarios which reduce the requirement for make good 
activities.  
 
On 26 September 2024 we extended the timeframe to respond to your request to 18 October 
2024 due to the large quantity of information sought and consultation required to facilitate its 
release. 
 
Page 1 of 2 



 
 
 
Under section 15(1)(a) of the Official Information Act, I have decided to grant your request. 
However, more time is required to prepare the response for release. We expect to be able to 
provide you with the final documentation no later than 23 October 2024. We apologise for 
any inconvenience that this may cause. 
 
For your reference, some information wil  be withheld under section 9 of the Official 
Information Act as applicable. 
 
In making my decision, I have considered the public interest considerations in section 9(1) of 
the Official Information Act and determined there are no public interests  that outweigh the 
grounds for withholding. 
 
You are entitled to seek an investigation and review of my decision by writing to an 
Ombudsman as provided by section 28(3) of the Of icial Information Act. 
 
Nāku noa, nā 
 
 
 
Phil ippa Fox 
Director Regulatory Authorisations 
Department of Conservation 
Te Papa Atawhai 
 
 
 
 
Page 2 of 2