This is an HTML version of an attachment to the Official Information request 'Monthly reports for election period missing from previous OIA'.









Status Report – GE2023 Programme Status Report  
Emily Redmond, Programme Director 
From 
Report Period 
17 December 2022 
22 February 2023 
Governance Group 
Programme Board 
 
 
Overall RAG status  
 Current   
  
 
December 
  
 
November 
  
 
October 
 
September 
 
 
 
If any one of Scope, Milestone, Budgetor Quality is reporting Red.  
OR 
 
If any one of Scope, Milestone, Budget, or Quality is reporting Amber and Risks/Issues or Resources/Delivery Partners is reporting Red. 
OR 
If any two of Scope, Milestone, Budgetor Quality are reporting Amber. 
Only one of Scope, Milestone, Budget, or Quality is reporting Amber. 
Overall RAG Status Indicator 
 
OR 
Resources/Delivery Partners and Risk/Issues is reporting Red. 
Scope, Milestone, Budget, and Quality are key status indicators for reporting Green. 
 
 
Resources/Delivery Partners and Risk/Issues may be Amber
 
Not applicable/no information available 
<If overall status is AMBER or RED include what needs to happen for the project to return to GREEN> 
 
Summary 
Decisions required from Programme Board 
There are a number of papers to be considered this month for the Programme Board, including the MEO community engagement plan (for approval), the Trust and Security draft strategy (for feedback), 
Translation approach to Te Reo (for approval), scenario planning (for input and feedback) and processes and assurance (for approval). 
 
Executive Summary  
The overall status of the programme has reduced from AMBER to GREEN. 
There is confidence that cost pressures identified for 22/23 can be solutioned within the current Electoral Commission budget (to be confirmed in April) however the 23/24 budgeting round, taking place now, 
will determine if cost pressures for the coming year can be solutioned. The financial status is GREEN, however this may increase to AMBER following the 23/24 budgeting outcome. 
The milestone status indicator is now reporting GREEN. The ARTS project has done a replan and a date change request was approved at the recent Steering Group meeting, enabling most of the key 
milestones to return to GREEN. 
 
The impact of cyclone Gabrielle has been considered and impacts are included for the programme board as part of the scenario planning agenda item. 
 
Schedules and dates 
With the announcement of the election date there is a focus on updating schedules and the critical path is being reviewed and updated. This work will be completed in February and the final integrated 
schedule can soon be confirmed. 
 
Planning Assumptions 
We have completed another round of GE2023 common assumptions review. There were a number of updates (over and above the obvious ones regarding the date change) including: 
• 
For MEO The public information and education campaign will run from when legislation is implemented on 31 March until the start of the exclusion period on 13 July 2023 (this is five weeks longer 
than previous planning assumptions) 
• 
There will be additional budget in FY2023/24 and FY 2024/25 to deliver ongoing Māori Electoral Option messaging after the 2023 General Election (note that this assumption has not been confirmed 
and will be worked through during the 23/24 budgeting round) 
• 
There is an exclusion period from 13 July to 14 October when Māori cannot change roll types 
• 
57% digital entry (approx. 711k) new and updated enrolments between EUC start and ED Roll Close (increased from 40% but now consistent with GE2020) 
• 
The level of activity in market for the public information and motivation campaign will reduce, relative to 2020, because of inflation, media costs and a single campaign budget 
• 
The public information and education campaign will be delivered with a budget of $7.85 million 
• 
Advertising to support the enrolment update campaign will be delivered from 30 July to Writ Day, Sunday 10 September. Enrolment and voting messages will continue until election day 
• 
The enrolment campaign start date will move from 3 July to 30 July. 
Risk & Security 
Work has begun to: 
• 
 Get the Risk & Security workstream underway: 

inter-agency - nominations for representatives from other agencies have been received and the first meeting is on 23 February (there are also internal representatives on this group); 

internal working group – we have a core group identified and the first meeting is on 24 February; 
 
• 
Ensure that critical relationships are in place, key stakeholders are on board about the direction of this work and that roles and responsibilities are well understood: 

inter-agency – we are regular attendees at the Major Events Security Committee and Karl and Mark will be attending the Security Intelligence Board from March (both part of the National 
Security System framework run out of DPMC) – the focus of these meetings at present is educating external support agencies about the elections context/key risks and ensuring that we 
have support and engagement going forward;  
https://electionsnz.sharepoint.com/:w:/s/GE2023Programme/EQeHfP9ArUtHsQLE5vMsooIBrNANFBhBmXJb-UKs702alg?e=zhpWly 


internal - we are preparing a Trust and Security Strategy for the EC Board for their March meeting. The document (presented to the Programme Board in draft): 
▪ 
provides context for the operating and external risk environments into which the GE2023 event will be delivered; 
▪ 
describes the inter-agency governance arrangements and how the work ‘fits together’;   
▪ 
describes the broad workstreams of a Commission-led approach to support safety of and trust in GE2023; 
▪ 
describes the objectives of these workstreams and set out the main strands of work being undertaken across the Commission within the workstreams. 
 
• 
Next steps for this programme of work are: 

evaluating our current protections, identifying the main gaps in the work programme and key decisions that need to be taken through the internal workshop (including e.g. implications for 
the budget); 

documenting the strands of work occurring across the orgainsation in support of the trust and safety of GE2023 into a consolidated project plan at a more fine-grained level to track 
progress against a centralised view; 

progressing the inter-agency support work to develop a risk profile and begin to work with the agencies on mitigations and support arrangements; 

recruiting a Senior Advisor Interagency Liaison to support this work. 
IQA 
Caravel have been appointed to undertake the IQA, interviews have begun and key documents have been shared with them. 
 
Field update 
The Electorate Managers (EMs) are started on February 13 and their training is being held on February 20 to 23 in Wellington. All but Southland and Invercargill HQ properties have been secured (although 
there is positive progress) and the technology set up in HQ locations is underway. 
 
 
 
 
 
 

Successes for reporting period:  
(Programme) IQA commenced 
(C&E) The Public Information and Education campaign strategy was approved by the Electoral Commission Board. 
 (C&E) The Advertising Services Order (ASO) for the Public information and Education Campaign has been submitted to the Electoral Commission Board for approval.  
(C&E) Work is underway on the Kids Voting programme with placement of advertising confirmed in school magazines and stakeholder communications to schools to start in March. An online registration form 
for elections.nz is being built. 
(E&CE) Endorsement of the Strategic Engagement and Partnership Strategy by the Electoral Commission Board. 
(RPR) Successful creation of an EMS employee via the SnapHire to EMS integration enterprise service bus component. 
(RPR) The Enterprise Service Bus (ESB) integration to MoJ has successfully sent a test file to the MoJ SFTP server. 
(RPR) Successful replanning session. 
(VS) Leased 63 electorate Headquarters, with termination dates of 31 December 2023.  Our only outstanding Electorate are Invercargill and Southland.  
(VS/ES) Employed all 65 Electorate Managers 
(VS) Employed a new Auckland South Regional Manager  
(VS) Sent Volume 1 of the Operations Manual to the printers on 16 December, on schedule 
(VS) Delivered the “Appointment Supplies” to the EMs (including Volume one of the Operations Manual  
(VS) New AoG agreement for Stationery was signed in January, allowing us to order GE2023 Stationery 
(VS) Successful dress rehearsal for Electorate Managers’ training. 
(GETP) All procurement complete 
(GETP) Prepared Electorate Manager laptops and mobile phones for IT induction events 
(GETP) Created Electorate Manager user accounts 
(ES) Post announcement of the date of the 2023 General Election, update variation letters issued to RM’s RAs and EMs with new fixed term end dates. 
Details on specific areas of work/workstreams. 
 
OPERATIONS GROUP 
Communications and Education
 
The monthly status report for Communications and Education can be found here. The overall status is GREEN. There has been a huge focus on MEO. 
 
Enrolment and Community Engagement  
The monthly status report for Enrolment & Community Engagement can be found here. The overall status is GREEN.  There has been ELT agreement to push the start of the enrolment campaign out from 3 
July to 30 July due to the confirmation of the election date. 
The GE2023 Strategic Engagement and Partnership Strategy is complete and was presented to the Board for endorsement which was granted. 
 
Centralised Enquiries Project 
The monthly status report for the Centralise Enquiries Project can be found here. The overall status is GREEN. In the last month the focus has been on analysis and engagement with Zendesk.  
 
Voting Services 
The monthly status report for Voting Services can be found here. The overall status is GREEN. The main focus has been preparing for the Electorate Manager training event from 20-23 February. 
 
Recruitment Process Redesign (ARTS) 
The monthly status report for the Recruitment Process Redesign project can be found here. The overall status is RED, however following the approval of the date change request, it has now returned to 
GREEN. A replan activity took place with the business, and the launch date is still set for the end of April. 
 
ENTERPRISE SERVICES  
 
GETP 
 
The monthly status report for GETP is GREEN and can be found here. The focus for the last month has been finalising all procurement activities, which are now all complete. 
Work now shifts to the implementation phase of the project, starting with the fitting out of technology at 65 Electorate Headquarters and preparing for the onboarding of Electorate Managers. 
 
Enterprise Services  
The monthly status report can be found here. The overall status is GREEN.  
 
The focus for the IT workstream over the past month has been the focus for the IT workstream since December Steering Group has been;  
•  Replanning and realigning the IT work plan to the confirmed GE2023 Election date.  
•  Working with ARTS project on confirming schedule of IT related tasks 
•  C&A for the Enterprise Service Bus 
 
The ES workstream has been busy with:  
• 
Supporting managers with Snaphire and working on Phase 2, including the Ops Manual for VS. 
• 
Finalising Induction for electorate Managers to be presented this month. 
• 
Finalised master forms for RRM and LSM recruitment e.g., interview templates, phone screening.   
• 
All job descriptions for GE with Voting Services are being finalised. 
 
https://electionsnz.sharepoint.com/:w:/s/GE2023Programme/EQeHfP9ArUtHsQLE5vMsooIBrNANFBhBmXJb-UKs702alg?e=zhpWly 

























Focus for next month:  

Baselining of all GE project schedules with the confirmed election date 

Project Dependencies & Critical Path updated 

Workstreams continuing to meet their milestones 

Complete the procurement plan and ASO for recruitment advertising 

Kick off Zendesk Phase 2 enhancement work. 

Start work on Centralised Enquiries Service Model. 

Finalising and undertaking the EM Training event to be held in Wellington between 20-23 February 

Complete the SnapHire configuration for Voting Services General Election recruitment  

Full SnapHire to MoJ integration complete 

Full SnapHire to EMS integration complete 

Recruitment Process Redesign - C&A Phase 2 complete 

Onboarding 65 Electorate Managers at 5 IT induction events in Auckland, Palmerston North, Taupo, and Christchurch 

Start fitout of technology at Gibson Sheat Centre for the Centralised Processing Team 

Continue implementing network circuits at Electorate Headquarters 

Continue setting up all technology at Electorate Headquarters 

Update GE2023 Recruitment Plan to include all roles. 

Complete Induction for Field training presentation 

E&CE -Kick off meeting with Blue Star – Roll Print 

E&CE - Secure EUC suppliers with SOW 
 
For the table below please refer to the RAG Status guide to understand the ratings  
 
Status 
Key Status Indicators 
Comments and expected actions. If AMBER or RED include what needs to be done to return to GREEN 
Last 
This 
Next 
Report 
Report 
Report 
There are currently four medium programme risks and five low risks. This report contains only medium and critical risks and the low risks have 
1.    Risks 
 
 
 
been omitted. Since the last reporting period three medium risks have been closed. 
2.   Issues 
 
 
 
There are no issues reported this period. No change from the last reporting period. 
This green status relates to the 22/23 financial year. It is likely there will be cost pressures identified for 23/24 and this will be reported on 
3.  Budget 
 
 
 
following the 23/24 budgeting exercise which is taking place currently. 
Work is underway to reset milestones following the announcement of the election date. A decision was agreed at Steering Group that dates that 
change due to the election date announcement won’t need to go through a formal change request. The milestones included in this report will be 
overhauled one the individual workstream schedules have been update. 
4.   Milestones 
 
 
 
The ARTS project replan has taken place and a change request has been approved at the last Steering Group meeting, meaning many key 
milestones that we previously reporting red have returned to green.  
There are a few milestones that are not reporting green, however the overall project associated with these milestones will meet the approved 
delivery date, hence the overall milestone status reporting green. 
5.   Scope 
 
 
 
There are no changes to programme scope. 
6.   People Resources 
 
 
 
Additional resources continue to be recruited for, but there are no concerns 
There are no delivery partner concerns, however it is not yet known if cyclone Gabrielle will impact on delivery partners. This is still being 
7.   Delivery Partners 1 
 
 
 
determined. 
8.   Quality 
 
 
 
There are no quality concerns. 
9.   Dependencies  
Known dependencies are being actively managed.  
 
1 Note: A delivery partner is defined as an external vendor, service provider or other agency contracted to deliver components of the project.  
 
 
 
 
 

1. Risks 
The risks below have been identified as Programme risks. They do not include risks raised for each workstream. The full risk register can be found here. 
Treatment Action (Mitigations) 
Assessment of CURRENT Risk 
Risk 
Last date 
Risk Owner 
Risk title 
Risk description 
Treatment action log 
category 
What can be done to reduce the 
Risk 
reviewed 
Likelihood 
Consequence 
likelihood? 
Rating 
All ELT 
Reliance on key staff 
Capability 
IF, we continue to be reliant on a 
1.Identify and document key staff and key roles 
Items 1-4 have been 
Likely 
Significant 
Medium 
Nov 22 
Managers 
on a small number of key SME’s and 
2. BCP work has required that back-up plans are 
implemented 
workloads remain high THEN if any 
identified and documented including cover for 
Sept 22: A workshop will be 
of those people get sick, burnt out 
critical tasks. Revisit this document to ensure it 
run with ELT on 12 October, 
or leave the organisation, this will 
is still valid 
focussing on implementing 
compromise our ability to deliver 
3. Review the TOM work which has identified 
mitigations 
and creates critical points of failure 
critical staff risk and has incorporated this into 
14 October: A first workshop 
the organisational changes being implemented 
was run with ELT which did a 
to determine if it is still valid and if it has 
deep dive into this risk. New 
mitigated any risk 
mitigations were identified. 
4. Identifying back-ups for all key staff during 
Not everything was 
the GE 
completed, so another will be 
5. Document all critical GE delivery processes 
run and this risk will be 
showing clear ownership and back ups 
updated as a result of the two 
6. Staff retention and attraction policies and 
workshops next month. 
practices being implemented 
11 Nov – this risk needs to be 
7.Recruitment, H&S, BCP, reprioritisation 
updated based on the ELT 
8.Review of GE 2023 critical path to identify 
workshop. This will be done 
critical points of failure and where we may need 
post Hamilton West by 
to have more documentation around process.  
election 
9. Identify ways to support critical staff if a crisis 
 
arises that they need to deal with 
10. Develop and roll out succession planning 
including understanding and planning for career 
pathways 
11.Identify substitutes and ensure they are well 
informed to be able to step in  
12.Capture knowledge to make it readily 
accessible for others 
13.Run an ELT workshop to identify critical 
issues and develop a shared plan going forward. 
DCE 
SMEs leaving 
Capability 
IF people leave without providing a 
1. Managers set expectations with the team that 
Sept 22: This is a new 
Very Likely 
Minor 
Medium 
Feb 23 
Enterprise 
without sharing 
substantive handover (either in 
they are to document key processes  
programme risk and has been 
Services 
information 
person, via documentation or 
2. Managers to ensure that when someone 
assigned to the risk owners 
DCE 
both), THEN we lose a significant 
resigns they prioritise writing a thorough 
only this month. Progress 
Operations 
amount of knowledge that makes 
handover document 
against treatments will be 
the next person's role harder, 
3. Managers prioritise recruitment so there is a 
reported next month. 
potential rework and potential non 
handover period 
14 Oct – progress has been 
delivery of items 
4. P&C prioritise recruitment for critical roles 
made on treatment 3 & 4. 
20 Feb -The process and 
assurance work that is starting 
in March will address much of 
this risk as key processes will 
be documented 
CIO and 
Catalyst resource 
Technology 
IF, the Catalyst team has resource 
1. Have regular meetings with the Catalyst 
12 Nov 21 - Weekly meetings 
Feasible 
Significant 
Medium 
Oct22 
Business 
contention/resource 
contention due to illness and other 
account manager  
Commenced 
System 
availability 
EC projects, THEN this may delay 
2.Hold them to account over delivery dates 
19 Nov 21 - Draft Statement of 
Owner 
delivery of GE projects 
3. Have 2 EC staff on site 
Work received 
4. Ensure the Catalyst statement of work is 
26 Nov 21 - Final Statement of 
realistic 
work expected 
5. Create a dashboard that informs EC of all the 
30/6/22 - A dashboard of work 
work catalyst have on and when it is due 
is prepared and will be 
6. Make trade-off decisions if necessary, based 
presented to the EEV Steering 
off information in the dashboard 
Group for prioritisation 
7. PMs to work with Catalyst to monitor delivery  
Sept 22: Significant work has 
8. Ensure we are providing Catalyst with 
gone into prioritising Catalyst 
business requirements in a timely fashion 
work to ensure there is clear 
9. Ensure we are clear to Catalyst about our 
direction so that their 
priorities 
resources are working on the 
areas of greatest need. An 
additional resource has been 
secured for the next two 
https://electionsnz.sharepoint.com/:w:/s/GE2023Programme/EQeHfP9ArUtHsQLE5vMsooIBrNANFBhBmXJb-UKs702alg?e=zhpWly 

Treatment Action (Mitigations) 
Assessment of CURRENT Risk 
Risk 
Last date 
Risk Owner 
Risk title 
Risk description 
Treatment action log 
category 
What can be done to reduce the 
Risk 
reviewed 
Likelihood 
Consequence 
likelihood? 
Rating 
months to work on the MIKE 
system 
14/10/22 – Catalyst has been 
briefed on the work and work 
continues to be prioritised 
with the business.  
20/02/2023 - Regular 
prioristisation meetings 
between Catalyst and EC 
continue with focus on 
completion of Must have 
functionality for GE2023 
CIO 
Cyber Attack on 
Technology 
IF, A malicious cyber attack were to 
1.Structured improvement of controls 
30/6/2022 - Treatment items 
Feasible 
Major 
Medium 
Sept 22 
Critical Systems 
occur on critical systems, THEN, 
(technology, human, supply chain management) 
1-6 have been implemented 
Security of information would be at 
to enable us to continually improve our ability 
Sept 22: Treatments 1-11 have 
risk and systems may be down. 
to identify, prevent and respond to cyber 
been implemented 
security incidents. 
20/2/2023 - work continues on 
2.Resourcing focused on cyber security issues. 
Treatment 12 in conjunction 
3.Draft enterprise-wide information systems 
with the ARTS project, to 
strategic plan (ISSP) Phishing, training, SMT 
automate parts of the 
focus and leadership to inform staff. 
onboarding process. Enhanced 
4.Cloudflare DDoS protection. 
threat intelligence now 
5.Developing playbooks for incident types 
implemented into device 
6.Funding in FY21/22 budget for control 
endpoints as part of 
improvements including resources, software 
Treatment 13. 
and process improvements. 
7.Certifying and accrediting GE critical systems. 
8.Links to NCSC and acting upon security 
bulletins. 
9.Patching applications, infrastructure regularly 
and quickly. 
10.Pentesting applications and infrastructure 
annually. 
11.Third party supply chain audits. 
12.In the process of improving 
authentication/authorisation at the Commission 
to reduce ability for attackers to harvest 
credentials. 
13.Implementing extra monitoring software to 
improve our ability to detect and prevent 
incidents 
14.Larger Cyber Security awareness campaigns 
 
2. Issues 
The issues below have been identified as Programme issues. They do not include issues raised for each workstream. The full issues register can be found here. 
There are no current medium or high programme issues to report this month. 
 
Impacted area 
Expected 
Date 
Issue Description  
Impact on business 
Management / Progress update 
Reputation/ 
RAG 
Assigned To 
Resolution 
People 
Process 
Systems 
Finance 
Reported 
Other 
Date 
 
 
 
 
 
 
 
 
 
 
 
 
 
3. Financials 
The most recent budget information available is December YTD as follows: 
 
% Full Year 
 
Current 
 
YTD 
 
Full Year 
Spend 
  
Actual 
Budget 
Variance 
 
Actual 
Budget 
Variance 
 
Budget 
  
 
 
 
 
 
 
 
 
   
 
Total Operating Expenses 
667,949  
1,665,637  
997,689    
4,972,755  
8,740,921  
3,768,165     38,705,877  
12.8% 
 
We are reporting a $3.8m underspend YTD, however the majority of this is due to phasing. It is expected that we will spend the full budget for 22/23. Cost pressures that were identified for 22/23 are highly likely to be able to be solutioned within the current budget (this will be confirmed by April).  
The 23/24 budgeting exercise is underway and cost pressures for that financial year have been identified. These will be considered following the budgeting exercise. 
 
 
 

4. Milestones 
Key milestones that have been identified are listed below and these will be updated following the reset based on the election date confirmation. 
Milestone key: Green = Milestone date will be met. Amber = Milestone may not be delivered on time. Red = Milestone will not be delivered by agreed baseline date 
 
Critical path milestones are included below and a visual representation can be found here. The major milestones have been reviewed following the election date announcement, although more review is required and will be worked through over the coming month. 
 
 
 
 
Estimated 
Baseline 
Re-baseline 
Current Finish 
 
 
Finish 
Finish Date 
finish date 
Date 
Workstream 
Type 
Date (early 
or Work 
planning) 
packets 
Milestone 
Status 
IT-GETP 
All requirements completed 
L0-Governance 
 
24/02/22 
 
24/02/22 
Completed 
ES 
Recruitment Strategy approved 
L0-Governance 
 
13/05/22 
 
28/05/22 
Completed 
ES-GETP 
Procurement plan completed 
L0-Governance 
 
30/05/22 
 
06/07/22 
Completed 
Programme 
EC Board approval of EC Board engagement calendar 
L0-Governance 
 
06/7/22 
 
6/70/22 
Completed 
ES 
Electorate Manager Recruitment Go Live 
Critical Path 
 
8/8/22 
 
8/08/22 
Completed 
ES 
Recruitment plan approved 
L1-Primary 
 
10/06/22 
 
17/08/22 
Completed 
Programme 
EC Board approval of Programme Board ToR 
L0-Governance 
 
17/08/22 
 
17/08/22 
Completed 
Programme 
Environmental Scan to EC Board 
L0-Governance 
17/08/2022 
 
 
17/08/22 
Completed 
ES-IT 
All systems ready for HQ Simulation 
Critical Path 
 
11/9/22 
 
11/09/22 
Completed 
Mark L 
Trust in the Election to EC Board 
L0-Governance 
21/09/22 
 
 
14/09/22 
Completed 
Legal & Policy 
Amended policy on party registration and logos to EC Board 
L0-Governance 
 
17/08/22 
 
14/09//22 
Completed 
VS-RPR 
GE Implementation ready for HQ Simulation 
L1-Primary 
 
30/06/22 
 
23/09/22 
Completed 
VS 
HQ Simulation Start 
Critical Path 
 
23/09/22 
 
23/09/22 
Completed 
Legal & Policy 
Registration of political party and logo to EC Board 
L0-Governance 
 
12/10/22 
 
12/10/22 
Completed 
Legal & Policy 
Broadcasting allocation process and timeline to EC Board 
L0-Governance 
 
12/10/22 
 
12/10/22 
Completed 
Ops- MEO 
MEO implementation plan – EC Board approval 
L0-Governance 
 
12/10/22 
 
12/10/22 
Completed 
VS 
HQ Simulation Completed 
Critical Path 
 
14/10/22 
 
14/10/22 
Completed 
Programme 
Programme Management Plan to Programme Board 
L0-Governance 
31/03/22 
12/12/22 
 
19/10/22 
Completed 
VS-RPR 
Career site design and implementation complete 
L1-Primary 
 
April 22 
 
02/11/22 
Completed 
VS-RPR 
Certification and Accreditation completed – Phase 1 
L1-Primary 
 
May 22 
31/10/22 
28/11/22 
Completed 
VS-RPR 
Privacy Impact Assessment completed – Phase 1 
L1-Primary 
 
May 22 
07/10/22 
28/11/22 
Completed 
ES-GETP 
Procurement complete 
L0-Governance 
 
28/10/22 
 
30/11/22 
Completed 
Programme 
Programme Management Plan to EC Board 
L0-Governance 
31/03/22 
14/12/22 
 
14/12/22 
Completed 
Comms &Ed 
GE Public Information and education campaign strategy and budget to EC Board 
L0-Governance 
 
14/12/22 
 
14/12/22 
Completed 
Programme 
IQA ToR to EC Board 
L0-Governance 
14/12/22 
 
 
14/12/22 
Completed 
VS-RPR 
Reporting tested and completed – Phase 1 
L1-Primary 
 
July 22 
18/11/22 
31/01/23 
Completed 
Comms &Ed 
GE Public Information and education campaign strategy and budget approved 
L0-Governance 
 
Completed 
by EC Board 
 
31/01/23 
31/01/23 
ES-GETP 
Electorate Manager IT setup complete 
Critical Path 
 
13/02/23 
 
13/02/23 
Completed 
VS 
Electorate Managers start 
Critical Path 
 
13/02/23 
 
13/02/23 
Completed 
ES-IT 
Training event preparation complete 
Critical Path 
 
13/02/23 
 
13/02/23 
Completed 
Operations 
Participation & Engagement Strategy to EC Board 
L0-Governance 
 
14/12/22 
 
14/02/22 
Completed 
VS 
Electorate Manager Centralised training start 
Critical Path 
 
20/02/23 
 
20/02/23 
Completed 
ES 
Designation, Delegations and Declarations in place 
Critical Path 
 
14/02/23 
22/02/23 
22/2/23 
In progress 
ES-IT 
EMS Operationally Ready (excl SnapHire Integration)  
Critical Path 
 
31/12/22 
28/02/23 
28/02/23 
In progress 
ES-GETP 
Electorate HQ location design complete  
Critical Path 
 
31/12/22 
 
28/2/23 
In progress 
ES 
Electorate HQ properties secured 
Critical Path 
 
31/12/22 
 
28/2/23 
In progress 
ES-IT 
EMS Operationally Ready (incl SnapHire Integration) 
Critical Path 
 
 
 
28/02/23 
In progress 
ES-IT 
ERSA Development Complete 
Critical Path 
 
28/02/23 
 
28/02/23 
In progress 
VS 
Covid protocols confirmed 
Critical Path 
 
1/03/23 
 
1/03/23 
Not started 
https://electionsnz.sharepoint.com/:w:/s/GE2023Programme/EQeHfP9ArUtHsQLE5vMsooIBrNANFBhBmXJb-UKs702alg?e=zhpWly 

 
 
Estimated 
Baseline 
Re-baseline 
Current Finish 
 
 
Finish 
Finish Date 
finish date 
Date 
Workstream 
Type 
Date (early 
or Work 
planning) 
packets 
Milestone 
Status 
IT-GETP 
Centralised Processing Team setup complete 
Critical Path 
 
01/02/23 
 
1/03/23 
Not started 
VS-RPR 
Recruitment Process Redesign/MoJ integration complete 
Critical Path 
 
June 22 
15/03/23 
15/03/23 
In progress 
VS 
Centralised Processing Team Simulation 
Critical Path 
 
Mid March 
 
Mid March 
Not started 
Programme 
IQA results to EC Board 
L0-Governance 
15/03/23 
 
 
15/03/23 
In progress 
Comms&Ed 
GE Public Information and education plan to EC Board 
L0-Governance 
15/03/23 
 
 
15/03/23 
In progress 
Legal & Policy 
Final Party registrations and logos to EC Board (by Writ Day) 
L0-Governance 
15/03/23 
 
10/09/23 
15/03/23 
Not started 
Legal & Policy 
Progress on broadcasting allocation, submissions and upcoming oral hearings to 
L0-Governance 
 
 
Not started 
EC Board 
15/03/23 
15/03/23 
TBC 
Security Strategy to EC Board 
L0-Governance 
2/11/22 
 
 
15/03/23 
In progress 
VS-RPR 
Final Snaphire testing completed  
L1-Primary 
 
June 22 
18/03/23 
18/03/23 
In progress 
VS-RPR 
Integration – ESB – End to end UAT complete 
L1-Primary 
 
 
24/03/23 
24/03/23 
In progress 
VS 
HQ Supplies delivered 
Critical Path 
 
24/03/23 
 
24/03/23 
Not started 
VS-RPR 
Privacy Impact Assessment completed – Phase 2 (full go live) 
L1-Primary 
 
 
3/04/23 
3/04/23 
Not started 
VS-RPR 
Career site design and implementation complete 
L1-Primary 
 
April 22 
12/04/23 
12/04/23 
Not started 
VS-RPR 
Reporting tested and completed – Phase 2 (full go live) 
L1-Primary 
 
July 22 
13/04/23 
13/04/23 
Not started 
VS-RPR 
Certification and Accreditation completed – Phase 2 (full go live) 
L1-Primary 
 
 
14/04/23 
14/04/23 
In progress 
IT-GETP 
Electorate headquarters operational 
Critical Path 
 
21/04/23 
 
21/04/23 
Not started 
VS-RPR 
Go Live Part 2 (full integrated system) 
L0-Governance 
 
 
26/04/23 
26/04/23 
Not started 
VS 
Operations Manual complete (Vol. 1 complete, Vol 2 and 3 in progress) 
Critical Path 
 
16/12/22 
28/04/23 
28/04/23 
 In progress 
ES-IT 
BCP DR Enhancements complete 
L0-Governance 
 
30/12/22 
 
28/04/23 
 In progress 
ES/Comms 
Logistic & Supply Mgr recruitment goes live  
Critical Path 
 
23/01/23 
1/05/23 
1/05/23 
Not started 
ES/Comms 
Rostering & Recruitment Manager recruitment go live 
Critical Path 
 
20/02/23 
1/05/23 
1/05/23 
Not started 
ES 
Tupu Election Ready 
Critical Path 
 
1/05/23 
 
1/05/23 
Not started 
Legal & Policy 
Progress on broadcasting allocation, submissions and upcoming oral hearings to 
L0-Governance 
 
 
Not started 
EC Board 
17/05/23 
17/05/23 
Comms&Ed 
GE Public Information and education campaign update to EC Board 
L0-Governance 
17/05/23 
 
 
17/05/23 
Not started 
VS 
Readiness Test 1 Completed - EMS focus 
Critical Path 
 
18/05/23 
 
18/05/23 
Not started 
E&CE 
Enrolment Update Mailout – MIKE Data Extract (NZ Post) 
Critical Path 
 
22/05/23 
 
22/05/23 
Not started 
ES-IT 
ERSA Go Live 
Critical Path 
 
1/06/23 
 
1/06/23 
Not started 
VS 
Overseas Temp staff recruited 
Critical Path 
 
1/06/23 
 
1/06/23 
Not started 
IT-GETP 
RRM IT set up complete 
Critical Path 
 
1/06/23 
 
1/06/23 
Not started 
VS 
RRMs start 
Critical Path 
 
6/06/23 
 
6/06/23 
Not started 
ES/Comms 
Trainer Recruitment Goes Live 
Critical Path 
 
12/05/23 
9/06/23 
9/06/23 
Not started 
VS 
RRM Centralised training completed 
Critical Path  
 
14/06/23 
 
14/06/23 
Not started 
ES-GETP 
LSM IT set up complete 
Critical Path 
 
1/05/23 
19/06/23 
19/06/23 
Not started 
VS 
LSMs start (rural electorates) 
Critical Path 
 
26/04/23 
19/06/23 
19/06/23 
Not started 
Legal & Policy 
Final Party registrations and logos to EC Board 
L0-Governance 
21/06/23 
 
 
21/06/23 
Not started 
VS 
LSM Centralised Training (rural/regional electorates) 
Critical Path 
 
3/05/23 
23/06/23 
23/06/23 
Not started 
VS 
LSMs start (urban electorates) 
Critical Path 
 
22/05/23 
27/06/23 
27/06/23 
Not started 
VS 
Readiness Test 2 completed - all electorates 
Critical Path 
 
28/06/23 
 
28/06/23 
Not started 
VS 
Critical Path 
 
23/05/23 
28/06/23 
Not started 
LSM Centralised training (urban electorates) 
 
28/06/23 
VS 
Ballot Papers dress rehearsal 
Critical Path 
 
30/06/23 
 
30/06/23 
Not started 
VS 
List of draft voting places sent to parties for consultation 
Critical Path 
 
2/06/23 
30/06/23 
30/06/23 
Not started 
ES-IT 
EMS Election Ready 
Critical Path 
 
1/07/23 
 
1/07/23 
Not started 
ES-GETP 
Mobile phones for voting places complete 
Critical Path 
 
1/07/23 
 
1/07/23 
Not started 
ES/Comms 
Bulk Recruitment Goes Live 
Critical Path 
 
1/06/23 
03/07/23 
3/07/23 
Not started 
E&CE 
Enrolment update campaign starts, first packs in letterboxes 
Critical Path 
 
3/07/23 
 
3/07/23 
Not started 
 
 
 

 
 
Estimated 
Baseline 
Re-baseline 
Current Finish 
 
 
Finish 
Finish Date 
finish date 
Date 
Workstream 
Type 
Date (early 
or Work 
planning) 
packets 
Milestone 
Status 
E&CE 
Community Engagement Campaign starts 
Critical Path 
 
3/07/23 
 
3/07/23 
Not started 
VS 
EasyVote dress rehearsal complete 
Critical Path 
 
6/07/23 
 
6/07/23 
Not started 
VS 
Bulk supply deliveries complete 
Critical Path 
 
13/07/23 
 
13/07/23 
Not started 
VS 
Electorate trainers begin to start 
Critical Path 
 
18/07/23 
 
18/07/23 
Not started 
Legal & Policy 
Final Party registrations and logos to EC Board 
L0-Governance 
2/08/23 
 
 
2/08/23 
Not started 
VS 
Election night dress rehearsal - all electorates 
Critical Path 
 
8/08/23 
 
8/08/23 
Not started 
E&CE 
Writ Day Roll Close 
Critical Path 
 
13/08/23 
 
13/08/23 
Not started 
VS/ES 
Party List generated and printed 
Critical Path 
 
14/08/23 
 
14/08/23 
Not started 
E&CE 
Data Extract: Easy Vote & Roll Print 
Critical Path 
 
17/08/23 
 
17/08/23 
Not started 
E&CE 
Roll Print – MIKE Data Extract (Blue Star) 
Critical Path 
 
18/08/23 
 
18/08/23 
Not started 
E&CE 
EasyVote – MIKE Data Extract (NZ Post) 
Critical Path 
 
18/08/23 
 
18/08/23 
Not started 
VS 
Early count and post election training complete 
Critical Path 
 
25/08/23 
23/08/23 
23/08/23 
Not started 
Comms&Ed 
Upload Voting papers & Download VP Live on website 
Critical Path 
 
30/08/23 
 
30/08/23 
Not started 
VS 
Readiness Test 3 complete - post election processes 
Critical Path 
 
31/08/23 
 
31/08/23 
Not started 
VS 
Voting places approved by CE 
Critical Path 
 
4/08/23 
1/09/23 
1/09/23 
Not started 
VS 
Advanced voting papers provided 
Critical Path 
 
1/09/23 
 
1/09/23 
Not started 
VS 
Delivery of equipment to voting places open in advance completed 
Critical Path 
 
3/09/23 
 
3/09/23 
Not started 
VS 
Main run EasyVote packs delivered 
Critical Path 
 
4/09/23 
 
4/09/23 
Not started 
ES-IT 
UVP Election Ready 
Critical Path 
 
4/09/23 
 
4/09/23 
Not started 
ES-IT 
DVP Election Ready 
Critical Path 
 
4/09/23 
 
4/09/23 
Not started 
ES-IT 
Overseas App Election Ready 
Critical Path 
 
4/09/23 
 
4/09/23 
Not started 
VS 
EasyVote supplementary delivered 
Critical Path 
 
7/09/23 
 
7/09/23 
Not started 
VS 
All ballot papers delivered to electorate HQs  
Critical Path 
 
8/09/23 
 
8/09/23 
Not started 
VS 
Training for voting place staff completed 
Critical Path 
 
15/09/23 
 
15/09/23 
Not started 
IT-GETP 
Results phone solution Election Day ready 
Critical Path 
 
15/09/23 
 
15/09/23 
Not started 
IT-GETP 
NO Processing Team (NOPT) operational 
Critical Path 
 
15/09/23 
 
15/09/23 
Not started 
VS 
NOPT staff start 
Critical Path 
 
17/09/23 
 
17/09/23 
Not started 
E&CE 
Election Day Roll qualified – start SVD Processing 
Critical Path 
 
20/09/23 
 
20/09/23 
Not started 
VS 
Overseas Voting Go Live 
Critical Path 
 
30/08/23 
25/09/23 
25/09/23 
Not started 
VS 
Dictation Service Go Live 
Critical Path 
 
30/08/23 
26/09/23 
26/09/23 
Not started 
E&CE 
SVD Processing deadline for return to Electorate Manager 
Critical Path 
 
26/09/23 
 
26/09/23 
Not started 
VS 
Last day for return of special declaration votes (legal date) 
Critical Path 
 
29/09/23 
 
29/09/23 
Not started 
VS 
Advanced Voting starts 
Critical Path 
 
4/09/23 
2/10/23 
2/10/23 
Not started 
VS 
Last day to receive postal votes from overseas 
Critical Path 
 
29/10/23 
 
29/10/23 
Not started 
VS 
Last day to get special votes to home returning officer 
Critical Path 
 
29/10/23 
 
29/10/23 
Not started 
VS 
Declaration of official results 
Critical Path 
 
6/10/23 
3/11/23 
3/11/23 
Not started 
VS 
Voting Services electorate HQs closed 
Critical Path 
 
30/11/23 
 
30/11/23 
Not started 
IT-GETP 
Decommissioning complete 
L0-Governance 
 
31/12/23 
 
31/12/23 
Not started 
5. Dependencies  
All dependencies are being tracked in the Master dependency register. Following the 5 August planning day, the register has been tidied up, and dependencies relating to the critical path can be clearly identified. Dependencies are being well managed and there are no concerns to report. 
6. Change Requests 
There are no change requests for this reporting period. 
 
https://electionsnz.sharepoint.com/:w:/s/GE2023Programme/EQeHfP9ArUtHsQLE5vMsooIBrNANFBhBmXJb-UKs702alg?e=zhpWly 

7. Key Decisions 
Reference 
Description 
Decision Actions 
Required From 
Raised By 
Agreed By