This is an HTML version of an attachment to the Official Information request 'Depositing of fill material 1044 Coast Road'.
 
 
 
 
 
Non-notified resource consent application 
report and decision 
 
 
Summary of decision 
 
 
Activity: 
To  undertake  works  in the bed of the Wainuiomata River 
to  remedy  and  avoid  future  erosion  and  scouring  caused 
by flood flows. 
 
File Reference: 

WGN080503 
 
Date Granted:
 
21 November 2008 
 
Commencement date: 
21 November 2008 
 
Applicant:  
Shayne Edwards 
Totara Downs 
1044 Coast Road 
RD 1 
Wainuiomata 5373 
 
Decision made under: 
Section  104B  &  108  of  the  Resource  Management  Act 
(the Act) 
 
Consent Granted: 
[26982] : Discretionary Activity 
 
Water  permit  –  to  permanently  divert  the  flow  of 
secondary  channels  within  the  bed  of  the  Wainuiomata 
River.  
 
 
[27332] : Discretionary Activity 
Land  use  consent  -  to  construct  rock  rip-rap  bank 
protection structures, to temporarily place bunds in, and to 
drain and reclaim secondary channels within the bed of the 
Wainuiomata  River,  including  the  associated  disturbance 
of the river.  
 
Location: 
Approximately  a  2  kilometre  (km)  stretch  of  the 
Wainuiomata River located within the boundary of Totara 
Downs, 1044 Coast Road, Wainuiomata 
 
Map Reference: 
Upstream  boundary:  At  or  about  map  reference  NZMS 
260: R27:2670268, 5983090 
 

 
Downstream boundary: At or about map reference NZMS 
260: R27:2669103, 5982135 
 
Legal Description: 
Lot 1 DP 323093 
 
Duration of Consent: 
[26982]: 20 years 
 
Subject to conditions: 
Attachment 1 
 
 
 
Decision 
Luke Faithfull 
Resource Advisor, 
 
recommended by: 
Environmental 
Regulation 
Decision peer 
Sean Lisle 
Resource Advisor, 
 
reviewed by: 
Environmental 
Regulation 
Decision approved 
Alistair Cross 
Manager, 
 
by: 
 
Environmental 
Regulation 

 
Reasons for decision:  
resource consent WGN080503 [26982]  & [27332]
 
1. 
Background  
Shayne  Edwards  (the  applicant)  has  applied  to  Greater  Wellington  Regional 
Council (GW) for resource consents to undertake various works in a section of 
the  Wainuiomata  River  that  passes  through  his  property.    The  section  of  the 
river  is  approximately  2  km  in length and the consent will allow the applicant 
to  implement  different  measures  to  assist  in  avoiding,  remedying  and 
mitigating  flood  and  erosion  damage  to  his  land  adjacent to the river.  While 
the specific methodology can only be determined at the time of the works, the 
applicant  has  stated  in  the  application  that  the  river  works  will  potentially 
involve the creation of bunds in the wetbed of the river, the reclamation of side 
channels,  the  permanent  diversion  of  those  side  channels  back  into  the  main 
flow of the river and the movement of river gravels to create bank protection in 
erosion prone areas. 
In the past, the applicant has had a long history of flooding and erosion issues 
on the property.  In 2004, the applicant purchased the property and it was soon 
evident  that  that  the  lack  of  river  maintenance  in  the  past  had  resulted  in 
substantial  erosion  of  the  banks.    Flooding  that  occurred  in  the  subsequent 
years caused further damage to the applicant’s property resulting in the loss of 
large amounts of land and stock.   
This  year  the  Wellington  region  experienced  a  number  of  significantly  large 
rainfall  events  which  resulted  in  increased  high  flow  events  in  the 
Wainuiomata  River.    During  these  events,  the river has eroded a considerable 
amount of the applicant’s land.  The applicant feels that if it is not remedied the 
river  will  continue  to  erode  his  land  and  eventually,  this  would  cause  similar 
issues  further  downstream,  both  on  the applicant’s property and neighbouring 
properties.    While  this  has  been  an  on-going  issue, the applicant is aware that 
erosion protection must be addressed. 
As  illustrated  in  the  following  photos,  substantial  erosion  can  occur  in  a 
relatively short time frame. 
WGN_DOCS-#546526-V1 
PAGE 1 OF 16 
 



 
 
Figure 1:  The Wainuiomata River as it flows through the applicant's property.  
This photo was taken on 8 July 2008. 
 
Figure 2:  The same section of river as figure 1 but after a high flow event caused 
bank erosion and undermined a stock fence.  This photo was taken on 28 July 
2008. 

2. 
Proposal 
Given  the  variation  of  flooding  and  erosion along the stretch of the river, t he 
location  of  the  works  will  be  determined  by  the  applicant  and  be  identified 
PAGE 2 OF 16 
WGN_DOCS-#546526-V1 
 
 

 
through  visual  inspections  of  the  river.    As  the  location  of  works  cannot  be 
specified  at  the  time  of  considering  this  resource  consent  application,  I  am 
recommending the granting of a global resource  consent for the works. 
As  with  the  location,  the  duration  of  the  works  cannot  be  determined  at  the 
time  of  considering  the  resource  consent  application.   However, the applicant 
has indicated that each set of works should take approximately half a day to a 
day to complete. 
The  applicant  intends  to  undertake  numerous  methods  to  avoid,  remedy  and 
mitigate  the  effects of erosion on his property.  These are discussed in section 
2.1.1 of this report. 
2.1.1 
Stream works 
The applicant proposed a suite of  works that may be undertaken and these will 
vary  depending  on  what  is  required  for  each  location  within  the  river.  
However, the works may involve the following: 
•  Minor  river  realignment  of  side  channels  (being  meanders  and  secondary 
flow channels) formed during high flows; 
•  Diversion of the flow of side channels back into the main flow of the river 
and reclamation of the channels.  Any diversion works will be undertaken 
by  bunding  the  channels  to  create  dry  working  areas  to  minimise  the 
potential for sediment discharge; 
•  Removal of vegetation on the gravel beaches within the river; 
•  Excavation and cross blading of the river gravels to recontour beaches and 
islands within the river channel; 
•  Moving  gravel  sourced  from  within  the  river  to  provide  additional  bank 
protection for erosion prone areas; and 
•  Tethering of willows and additional planting along the banks of the river  
The applicant would consult GW to determine the methodology of each set of 
the works to be undertaken prior to works commencing.   
The  following  methodology  is  an  example  of  how  the  formation  of  a  side 
channel  causing  bank  erosion  would  be  addressed.    The  methodology  that 
would be used is as follows: 
•  Machinery will ford the newly formed channel to access the gravel beach; 
•  A  bulldozer  will  create  bunds  by passing beach gravel material across the 
side channel, at the upstream and downstream end to create a dry working 
area; 
•  The  side  channel  will  be  reclaimed  by  pushing  beach  gravel  into  the  dry 
channel;  
WGN_DOCS-#546526-V1 
PAGE 3 OF 16 
 

 
•  The  area  will  be  recontoured  to  form, as much as possible, a level area to 
allow flows to spread over the areas evenly; and 
•  Grade the bunds to the same height as the recontoured beach. 
While the applicant’s start date and duration of the works can not be defined it 
is the applicant’s intention to undertake the works on an as required basis.  The 
majority  of  the  works  are  to  be  done  in  the  drier months when the river is in 
low flow.  Undertaking the works during this period will minimise the potential 
for  sedimentation  and  disturbance  of  the  river.    The  majority  of  works  to  be 
undertaken will be outside the actively flowing channel of the river.   
2.2 
Resource consents required 
•  Under  section  13(1)  of  the  Resource Management Act 1991 (the Act) no 
peron  may,  in  relation  to  the  bed  of  any  river-,  use,  erect…place…any 
structure  or  any  part of any structure in...the bed; excavate…or otherwise 
disturb the bed; deposit any substance in, on…the bed; or reclaim or drain 
the  bed  unless expressly allowed by a rule in a regional plan or a resource 
consent. 
As  outlined  in  Section  2.2.1  of  this  report,  the  proposed  vegetation  removal, 
beach recontouring and the tethering of willows and associated activities within 
the  river  are  expressly  allowed  by  rules  in  a  regional  plan,  and  as  such  no 
resource  consent  is  required  for  these  activities.    However,  the  reclamation, 
cross blading and construction of rock  rip-rap bank protection sturctures is not 
expressly allowed by a rule in the  Regional Freshwater Plan for the Wellington 
Region  (RFP)  or  covered  by  existing  resource  consent;  therefore,  resource 
consent is required for this activity. 
•  Under  section  14(1)(a)  of  the  Act  no person may divert any water unless 
the diversion is allowed by subsection (3) or is expressly allowed by a rule 
in a regional plan or a resource consent. 
As discussed in Section 2.2.1 of this report, the proposed permanent diversions 
are not allowed by subsection (3) of the Act, and are not expressly allowed by a 
rule  in  the  RFP  or  covered  by  existing  resource  consent;  therefore,  resource 
consent is required for these diversions. 
2.2.1 
Rules 
Diversions  -  Rule  9  of  the  RFP  provides  for  the  minor  diversion  of 
intermittently  flowing  streams.    The  rule  states  that  the  diversion  of  less that 
1.5  m³/sec  of  fresh  water  from  any  intermittently  flowing  river  or stream is a 
permitted activity. 
The  proposed  diversions  of  the  Wainuiomata  River  do  not  meet  the 
requirements  of  rule  9  of  the  RFP,  primarily  because  the  river  is  not 
intermittent; therefore, the works default to rule 16 of the RFP.   
PAGE 4 OF 16 
WGN_DOCS-#546526-V1 
 
 

 
Rule 16  provides for the taking, use, damming, or diversion of any fresh water, 
is a Discretionary Activity.  
 
Planting - Rule 24 of the RFP allows for the placement of any cabled willow or 
willow clump for river bank erosion protection that is fixed in, on, or under the 
bed of any river including any associated disturbance, deposition and temporary 
diversion  is  a  permitted  activity  subject  to  certain  conditions,  is  a  Permitted 
Activity

As  the  works  will  be  undertaken,  as  far  as  practicable,  in  the  dry  bed  of the 
river  and  the  works are proposed to mitigate erosion which is the direct result 
of flooding, the works meet the provisions of rule 24 of the RFP, as a permitted 
activity. 
Disturbance  -  Rule  36  allows  for  the  disturbance  of  any  river  or  lake  bed 
associated with clearing flood debris that poses a flood or erosion hazard or for 
the  purposes  of  protecting  structures,  is  a  Permitted  Activity,  provided  it 
complies with certain conditions. 
As  the  works  will  be  undertaken within the stretch of river on the applicant’s 
property  and  the  works  are  proposed  to  mitigate  erosion  which  is  the  direct 
result  of  flooding,  the  works  meet  the  provisions  of  rule  36  of the RFP,  as a 
permitted activity. 
Recontouring  -  Rule  37  of  the  RFP  provides  for  the  disturbance  and 
recontouring of any part of the bed of any river that is not covered by water (i.e., 
beach  recontouring)  to  remedy  or  mitigate  the  adverse  effects  of  flooding  or 
erosion is a Permitted Activity, subject to certain conditions. 
As the works will be undertaken to mitigate erosion and the effects of flooding, 
the works meet the provisions of rule 37 of the RFP, as a permitted activity. 
Removal  of  Vegetation  -  Rule  40  of  the  RFP  allows  for  the  trimming  and 
removal  of  vegetation  including  any  associated  disturbance,  deposition  and 
temporary diversion subject to certain conditions. 
As the works will be undertaken to mitigate erosion and the effects of flooding, 
the works meet the provisions of rule 40 of the RFP, as a permitted activity. 
Planting - Rule 41 of the RFP allows for the deliberate introduction or planting 
of  any  plant  in  the  bed of any river or lake  to remedy or mitigate the adverse 
effects of flooding, erosion, or non-point source discharges of contaminants, or 
to restore habitat, is a Permitted  Activity, subject to certain conditions. 
As the works will be undertaken to mitigate erosion and the effects of flooding, 
the works meet the provisions of rule 41 of the RFP, as a permitted activity. 
The  remaining  works  to  be  undertaken  to  avoid,  remedy  and  mitigate  the 
effects  of  flooding  and  erosion  to  the  applicant’s property will be carried out 
under the provisions of rule 49 of the RFP, as a Discretionary Activity
WGN_DOCS-#546526-V1 
PAGE 5 OF 16 
 

 
While  the  majority  of  the  remedial  and  mitigation  measures  are  within  the 
permitted  activity  provisions  of  the  RFP,  the  responsibility  lies  with  the 
applicant  to  ensure  that  the  conditions  for each of the permitted activities are 
complied with.  If the conditions of the permitted activity rules cannot be meet 
then resource consent maybe required.   
3. 
Consultation 
In  accordance  with  Greater  Wellington  Regional  Council’s  (GW)  agreement 
with  tangata  whenua  regarding  consultation  on  non-notified  consents 
Wellington  Tenths  Trust  and  Ngati  Toa  were  provided  with  a  copy  of  the 
application.  Neither of these parties chose to comment on the application. 
As  part  of  the  pre-application  process,  the  applicant  consulted  with  the 
Department  of  Conservation  (DOC)  and  the  Fish  and  Game  New  Zealand 
(F&G).   
Officers  of  DOC  inspected  the  applicant’s  site  and  supported  the  proposed 
remediation and mitigation works. Rob Stone, Poneke Area Manager, provided 
the written approval on behalf of DOC on 18 September 2008.   
F&G  officer  Corina  Jordan,  reviewed  the  application.  Ms Jordan raised some 
minor concerns regarding the permitted and consented activities of the RFP.  I 
advised  Ms  Jordan  that these would be clearly defined within the report.   Ms 
Jordan  was  happy  with  this  and  provided  F&G’s  written  approval  on  30 
October 2008. 
Sharyn Westlake of GW’s Flood Protection Department was consulted as part 
of  the  application  process  and  stated that they were happy with the proposed 
activities  although  it  is  hard to make a full assessment when the extent of the 
works  are  unknown;  however,  she  supported  the  proposed  works.    Sharyn 
stated that GW’s Flood Protection is happy to provide the applicant advice on 
river management for the duration of the consent. 
Summer Warr of the Environmental Monitoring and Investigations Department 
of GW was consulted as part of the application process.  Miss Warr was happy 
with the proposal and raised no concerns regarding the proposed works. 
No other parties are considered affected by the proposed works. 
4. 
Reasons for waiver of notification 
I consider that notification under Section 93(1)(b) of the Act is not required, as 
the  effects  of  the  proposed  river  works  on  the  environment  will  be  no  more 
than minor, as outlined in section 5.2 of this report. 
Section  94(2)  of  the  Act  provides  that  a  consent  authority  is  not  required  to 
serve  notice  of  an  application  under  subsection  (1)  if  all  persons  who,  in  the 
opinion of the consent authority, may be adversely affected by the activity have 
given  their  written  approval  to  the  activity.   I consider that all the potentially 
affected parties to this application have provided their approval; therefore, the 
PAGE 6 OF 16 
WGN_DOCS-#546526-V1 
 
 


 
provisions of Section 94(2) of the act have been met and the application will be 
processed non- notified. 
The  processing  time  for  the  application  has  been  extended  under  Section 
37A(2)(b) of the Act.  The reason for the extension was to allow the applicant 
further  time  to  for consultation and negotiation to achieve an environmentally 
acceptable outcome. 
5. 
Environmental effects 
5.1 
Existing environment 
The  Wainuiomata  River  flows  through  the  applicant’s  property  on  its  way  to 
the  where  it  discharges  into  the  coast  between  Baring  Head  and  Turakirae 
Head.  The section of river where the works are to take place is approximately 
2km in length.  The characteristics of the river through the applicant’s property 
is  a  typical  meander  pattern  commonly  found  low  lying  rural  flood  plains.  
There  a  number  of  gravel  islands  and  beaches,  both  vegetated  and  un-
vegetated,  located  through  this  section  of  the  river.    The  surrounding  land  is 
dominated by intensive pastoral farming. 
 
Figure 3:  The Wainuiomata River as it flows through the applicant's property.  
Note the large gravel beaches and islands and the eroded banks, both very 
typical of the river in this section. 

5.2 
Effects on water quality 
Works  in  the  beds  of  stream  can  cause  a  local  and  temporary  increase  in 
turbidity  and  suspended  solids  concentration  as  well  as  reducing  the  water 
WGN_DOCS-#546526-V1 
PAGE 7 OF 16 
 

 
clarity.  High suspended solids concentrations can have adverse effects on the 
in-stream ecology, especially  if these conditions are maintained  over time.    
As the works will generally be of a short duration (approximately half a day to 
day at a time), it is considered that the effects on the water quality of the stream 
will  be  no  more  than  minor.    However,  to  ensure  this,  it  is  a  recommended 
consent  condition  that  the  applicant  implements  measures  to  ensure  that 
sedimentation is to be minimised.    
Where  possible,  the  applicant  intends  undertake  the  works  during  periods  of 
low  flow  and,  where  possible,  will  bund  off  the  work  areas  to  create  a  dry 
working environment.  As outlined in the application, machinery entry into the 
watercourse  will  be  minimal;  however,  some  channels will need to be crossed 
to  access  the  gravel  beach/island  areas.    Any  refuelling  or  maintenance  of 
machinery  will  be  conducted  at  a  safe  distance  from  the  watercourse.  
However,  to  ensure  this,  it  is  a  recommended  consent  condition  that  no 
contaminants  (including  but  not  limited  to  oil,  petrol,  diesel,  paint,  solvent) 
shall  be  released  to  water  from  equipment  being  used  for  operation,  and  no 
refuelling of equipment shall take place on any area river or lake bed .   
5.3 
Effects on fish  
The  principal  adverse  effect on fish will be from the discharge of sediment to 
water  during  the  proposed  works  in  the  active  flowing  water.  However,  this 
will be from natural bed material being disturbed and fish are generally able to 
avoid zones of highly turbid water while suffering little or no adverse effect.   
The  proposed  works  will  not  have  an  impact  on  fish  passage  in  the 
Wainuiomata  River,  as  the  works  will  generally  be  taking  place  outside  the 
main channel of the river; therefore, fish passage will be maintained at all times 
as the main channel of the river will not be blocked.  However, to ensure this, it 
is a recommended consent condition that fish passage must be provided for at 
all  times.    I  have  also  recommended  a  consent  condition  to  ensure  that  fish 
passage  is  provided  and  that  should  fish  become  stranded  by  the  works  that 
they are placed back into clear water upstream of the working area. 
5.4 
Flooding 
The applicant does not anticipate that the proposed works will inhibit the flood 
carrying  capacity  of  the  river.    The  proposed  works  involve  the  removal  of 
vegetation  and  the  recontouring  of  the  gravel  beaches  and  islands.    It  is 
anticipated that when high flow flood events occur, the flows should disperse 
evenly over the beach area; therefore, the flood capacity of the river should not 
be inhibited in any way. 
As mentioned in section 2 of this report, the GW Flood Protection Department 
was consulted and no concerns were raised in regard to the impact of the works 
on  the  flood  carrying capacity of the Wainuiomata River.  In addition, I have 
recommended  a  consent  condition  requiring  consultation  with  GW  Flood 
Protection prior to works being undertaken. 
PAGE 8 OF 16 
WGN_DOCS-#546526-V1 
 
 

 
5.5 
Erosion and scour 
The bed recontouring and placement of rock rip-rap in the bed of a stream has 
the  potential  to  cause  erosion  and/or  scour of the stream bed and banks.  The 
applicant does not anticipate that erosion and scour will occur as a result of the 
proposed works as the purpose of the works is to mitigate the effects of erosion 
and  scour.  However,  to  ensure  that  any  such  issues  are  addressed,  it  is  a 
recommend  consent  condition  that  the  consent  holder  repairs  any  erosion  or 
scour that is attributable to the works. 
5.6 
Summary 
Provided the applicant undertakes the works as outlined in the application and 
complies with the recommended consent conditions, the proposed works in the 
Wainuiomata  River  should  have  a  no  more  than  minor  effect  on  the  local 
environment. 
6. 
Statutory assessment 
6.1 
Resource Management Act 1991 
Part  II  (Section  5)  of  the  Act  defines  its  purpose  as  the  promotion  of  the 
sustainable management of natural and physical resources.  Sections 6, 7 and 8 
of Part II define the matters a consent authority shall consider when achieving 
this purpose.  I consider this proposal is consistent with Part II. 
Section  104  of  the  Act  outlines  the  matters  a  consent  authority  must  have 
regard  to.    These  matters  include  any  actual  and  potential  effects  on  the 
environment  of  allowing  the  activity, relevant objectives, policies and rules of 
a  Regional  Plan,  the  Regional  Policy  Statement,  and  any  other  matter 
considered  relevant  and  reasonably  necessary  to  determine  the  application.  
These matters have been considered in section 4 and 5 of this report. 
6.2 
Regional Policy Statement 
The  Regional  Policy  Statement  for  the  Wellington  Region  (RPS)  contains 
several  objectives  and  policies  aimed  at  maintaining  the  quality  of  the 
freshwater environment.  These objectives and policies are intended to provide 
for  the  current  and  reasonably  foreseeable  needs  of  current  and  future 
generations.    The  relevant  chapters  of  the  RPS  are  Chapter  5  (Freshwater), 9 
(Ecosystems) and 11 (Natural hazards).  I consider that the proposed activities 
outlined  in  the  application  are  consistent  with  the  objectives  and  policies  of 
these chapters. 
6.3 
Regional plans 
The  RFP  has  a  number  of  objectives  and  policies  that  relate  to  the  proposed 
activity.  The most relevant objectives and policies to consider is assessing this 
application are listed below: 
WGN_DOCS-#546526-V1 
PAGE 9 OF 16 
 

 
Policy  6.2.14  states  that  it  is  appropriate  to  allow  minor  or  temporary 
diversions where they are associated with authorised works and/or the exercise 
of resource consent. 
Objective  7.1.2  seeks  to  ensure  that  the  risk  of  flooding  and  erosion  is  not 
increased  by  carrying  out  activities  in  the  beds  of  rivers.    These  effects  are 
addressed in section 5 of this report. 
Policy  7.2.1  indicates  that  it  is  appropriate  to  allow  activities  for  flood 
mitigation and erosion protection purposes of any waterbody and its margins. 
Policy  7.2.8  allows  the  re-contouring  of  the  beds  of  rivers  provided  the 
activities are necessary  to avoid or mitigate the effects of flood hazard. 
It  is  considered  that  the  proposed  works  are  consistent  with  the  relevant 
policies  and objectives of the RFP. 
7. 
Main findings 
1.  The  proposed  activities  are consistent with the Purposes and Principles of 
the Act. 
2.  The  proposed  activities  are  consistent  with  the  relevant  objectives  and 
policies  of the RPS and the RFP.   
3.  The  actual  or  potential  adverse  effects  of  the  proposed  activities  on  the 
environment will be no more than minor. 
4.  Conditions of the consent will ensure that the potential adverse effects of 
the  activities  on  the  environment  will be appropriately avoided, remedied 
or mitigated. 
5.  The  proposal  incorporates  appropriate  mitigation  measures,  to  ensure  the 
adverse effects are no more than minor. 
7.1 
Duration of consent 
For  water  permit  WGN080503  [26863]  and  land  use  consent  WGN080503 
[27332], it is considered that a duration of 20 years is appropriate, which is the 
maximum  allowable  under  section  123(c)  of  the  Act,  as  the mitigation works 
are of an on-going nature. 
8. 
Monitoring 
Annual inspections of the works will be undertaken, as required, in accordance 
with  the  Resource  Management  Charging  Policy  (2008).  Charges  relating  to 
this inspection are outlined in the cover letter enclosed with this report. 
 
 
PAGE 10 OF 16 
WGN_DOCS-#546526-V1 
 
 

 
Application lodged: 
06/06/08  Application official y received: 
27/06/08 
 
Application stopped:
 
01/08/08  Application started: 
04/11/08 
 
Applicant to be notified of decision by:
  21/11/08  Applicant notified of decision on:   21/11/08 
 
Time taken to process application:
 
40 working days 
 
WGN_DOCS-#546526-V1 
PAGE 11 OF 16 
 

 
9. 
Attachment 1 WGN080503 [26863] 
Water permit – to permanently divert the flow of secondary channels within the 
bed of the Wainuiomata River.  
 
1.  
The  location,  design,  construction,  implementation  and  operation  of 
all  works  shall  be  carried  out  in  accordance  with  the application and 
associated documents and plans, lodged with the Wellington Regional 
Council  on  6 June 2008  and  further  information  received  on 
16 September 2008. 
 
Note: 
Any  change  from  the  location,  design  concepts  and 
parameters,  and  implementation  may  require  a  change  in  consent 
conditions under section 127 of the Resource Management Act 1991. 
 
2. 
The  Manager,  Environmental  Regulation,  Wellington  Regional 
Council,  shall  be  given  least  48  hours  notice  prior  to  works 
commencing, and thereafter shall be notified at least 48 hours prior to 
further works. 
 
3. 
The  permit  holder  shall  provide  a  copy  of  this  permit  and  any 
documents  referred  to  in  this  permit  to  each  operator  or  contractor 
undertaking  works  authorised  by  this  permit,  before  that  operator  or 
contractor starts any works. 
 
4. 
The permit holder shall ensure that a copy of this permit is kept on site 
at all times and presented to any Wellington Regional Council officer 
on request.  
 
5. 
All  reasonable  steps  shall  be  taken  to minimise sediment loading and 
increased  turbidity  during implementation of all diversion works. The 
permit holder shall divert water only for the period necessary to carry 
out the works. 
 
6. 
All  works  shall  be  undertaken  in  a  manner  that  provides  for  fish 
passage  wherever  possible.    Any  fish  entrapped  by  works  shall  be 
relocated upstream into clear water as soon as possible. 
 
7. 
The  works  shall  remain  the  responsibility  of  the  permit  holder  and 
shall be maintained to the satisfaction of the Manager, Environmental 
Regulation,  Wellington  Regional  Council.    This  shall  include  the 
repair  of  any  erosion  of  the  bed  and/or  banks  of  the  river  that  is 
attributable  to  the  works  and  completing  any  reshaping  of  the  river 
bed  channel  should  it  be  deemed  necessary  by  the  Manager, 
Environmental Regulation, Wellington Regional Council. 
 
8. 
All  works  affecting  the  river,  including  tidy up on completion of the 
works,  shall  be  to  the  satisfaction  of  the  Manager,  Environmental 
Regulation, Wellington Regional Council. 
PAGE 12 OF 16 
WGN_DOCS-#546526-V1 
 
 

 
10. 
Attachment 2 WGN080503 [27332] 
Land  use  consent  to  construct  rock  rip-rap  bank  protection  structures,  to 
temporarily place bunds in, and to drain and  reclaim secondary channels within 
the bed of the Wainuiomata River, including the associated disturbance of the 
river. 
1. 
The location, design, implementation and operation of the works shall 
be  in  general  accordance  with  the  consent  application  and  its 
associated plans and documents lodged with the Wellington Regional 
Council  on  6 June 2008  and  further  information  received  on 
16 September 2008. 
 
2. 
A  copy  of  this  consent  shall  be  held  on-site  for  the  duration  of  the 
activity/works  and  be  made  available  to  any  Wellington  Regional 
Council officer on request. 
 
3. 
The  consent  holder  shall  ensure  that,  as  far  as  practicable,  all  works 
carried  out  in  the  dry  bed  of  the  stream,  including  shaping  and 
construction of the banks. 
 
4.  
The  Manager,  Environmental  Regulation,  Wellington  Regional 
Council  shall  be  given  least  48  hours  notice  prior  to  any  works 
commencing.    This  notice  must  include  but  not  be  limited  to  the 
following: 
 
a) 
description of the works to be undertaken; and 
 
b) 
methodology of the works to be undertaken. 
 
5.  
The Manager, Flood Protection, Wellington Regional Council shall be 
given  least  48  hours  notice  prior  to  any  works  commencing.    This 
notice must include but not be limited to the following: 
 
a) 
description of the works to be undertaken; and  
 
b) 
methodology of the works to be undertaken. 
 
6.  
The  consent  holder  shall  take  all  practicable  steps  to  minimise 
sedimentation  and  increased  turbidity  of  the  stream  during  the 
construction,  implementation  and  maintenance  of  the  works, 
including: 
 
a) 
completing all works in the minimum time practicable; 
 
b) 
minimising  the area of disturbance at all times;   
 
c) 
avoiding  placement  of  construction  or  excavated  material  in 
the wetted channel;  
 
WGN_DOCS-#546526-V1 
PAGE 13 OF 16 
 

 
d) 
separating  construction  activities  from  the  wetted  channel, 
where practicable;  and 
 
e) 
minimising  time  spent  by  machinery  in  the  wetted  channel, 
and  the  number  and  frequency  of  machine  crossings  of  the 
wetted channel of the stream, to a practicable minimum at all 
times. 
 
7.   
Any  excess  material from the construction and implementation of the 
works  shall  be  immediately  removed  from  the  bed  and  banks  of  the 
stream on completion of the works, and disposed of in an appropriate 
manner. 
 
8. 
The consent holder shall ensure that: 
 
a) 
all  machinery  is  thoroughly  cleaned  of  unwanted  vegetation 
(e.g. weeds), seeds or contaminants prior to entering the site; 
 
b) 
no  contaminants  (including  but  not  limited  to  oil,  petrol, 
diesel,  hydraulic  fluid)  shall  be  released  into  water  from 
equipment being used for the works; 
 
c) 
all  contaminant  storage  or  re-fuelling  areas  are  bunded  or 
contained  in such a manner so as to prevent the discharge of 
contaminants; 
 
d) 
all  machinery  is  regularly  maintained  in  such  a manner so as 
to minimise  the potential for leakage of contaminants; and  
 
e) 
no machinery is cleaned, stored or refuelled within 10 metres 
of any ephemeral or permanent watercourse. 
 
9. 
The  consent  holder  shall  ensure  that  the  works  are  undertaken  in  a 
manner  that  does  not  impede  fish  passage  and  that  fish  passage  is 
maintained  at  all  times  during  and  on completion of the construction 
works  along  the  stretches  of  river  affected  by  the  exercise  of  this 
consent.   
 
10. 
Any fish stranded or trapped by the construction works as authorised 
by  this  consent  shall  be  immediately  relocated  by  the consent holder 
to clear, flowing water. 
 
11. 
No  works  shall  be carried out between 1 May to 31 August inclusive 
(trout  spawning  season),  unless  authorised by the written approval of 
the  Manager  Environmental  Regulation,  Wellington  Regional 
Council.  
 
 
Note:  Manager  Environmental  Regulation,  Wellington  Regional 
Council will consult with Fish and Game New Zealand with regard to 
any works within trout spawning season.  
PAGE 14 OF 16 
WGN_DOCS-#546526-V1 
 
 

 
 
12. 
The  consent  holder  shall  take  all  practicable  steps  to  ensure  that  the 
works are carried out such that: 
 
a) 
a meander pattern is maintained in the wetted channel of the 
river; 
 
b) 
the width of the wetted channel of the stream is not reduced 
by  the  planting  of  willows  or  native  plants  (i.e.  all  planting 
shall be outside the active bed of the river); 
 
c) 
disturbance to the bed of the stream is minimised; and 
 
d) 
areas  of  complex  river  habitat  (i.e. pool-riffle-run sequences) 
are maintained. 
 
13. 
The  consent  holder  shall  ensure  that any area of native vegetation on 
the banks of the stream that is damaged or destroyed due to the works 
is  replanted  with  appropriate  native  species  within  one  month  of 
works being completed.  
 
14.  
The consent holder shall ensure that all exposed areas of stream banks 
are  stabilised  against  erosion  by  re-vegetating  the  area,  as  soon  as 
practicable, upon completion of the works.  
 
Note: For the purposes of this condition “stabilised” means inherently 
resistant  to  erosion  or  rendered  resistant,  such  as  by  using  indurated 
rock  or  by  the  application  of  basecourse,  colluvium,  grassing,  mulch, 
or  another  method  to  the  reasonable  satisfaction  of  the  Manager, 
Environmental  Regulation,  Wellington  Regional  Council  and  as 
specified  in  the  Erosion  and  Sediment  Control  Guidelines  for  the 
Wellington  Region,  September  2002.    Where  seeding  or  grassing  is 
used on a surface that is not otherwise resistant to erosion, the surface 
is  considered  stabilised  once,  on  reasonable  visual  inspection  by  the 
Manager,  Environmental  Regulation,  Wellington  Regional  Council, 
80% vegetative ground cover has been established. 
 
15. 
If  koiwi,  taonga  or  other  artefact  material  is  discovered  in  any  area 
during  the  extraction  works,  the  consent  holder  shall  contact  the 
Manager,  Environmental  Regulation,  Wellington  Regional  Council, 
Wellington  Tenths  Trust  and  Ngati  Toa  immediately,  and  works  in 
that  area  shall  cease  to  allow  a  site  inspection  by  the  Manager  and 
these  groups and their advisors. The consent  holder shall then consult 
with  Wellington  Tenths  Trust  and  Ngati  Toa  on  appropriate  steps  to 
recover  the  artefacts  in  order  that  works  can  resume.  If  skeletal 
remains  are discovered, works shall also cease and the consent holder 
shall contact the New Zealand Police. 
 
16.  
To  minimise  the  potential  for  erosion,  scour  and/or  instability,  the 
consent holder shall: 
WGN_DOCS-#546526-V1 
PAGE 15 OF 16 
 

 
 
a) 
only  use  natural  rock  and  soil  material  to  reclaim the bed of 
the stream; and  
 
b) 
carefully place and sufficiently compact all fill material. 
 
17.  
The  works  shall  remain  the  responsibility  of  the  consent  holder  and 
shall  be  regularly  inspected  and  maintained  by  the  consent holder so 
that  any  erosion  of  the  stream  banks  or  bed  due  to  the  works  is 
remedied by the consent holder 
 
Note:  Maintenance  works  shall  not  include  any  works outside of the 
scope  of  the application.  Any additional works (including structures, 
reshaping  or  disturbance  to  the  stream  bed)  following  completion  of 
the  construction  works  as  proposed  in  the  application  may  require 
further resource consents. 
 
18.  
All works affecting the stream, including tidy up on completion of the 
works,  shall  be  completed  to  the  satisfaction  of  the  Manager, 
Environmental Regulation, Wellington Regional Council. 
PAGE 16 OF 16 
WGN_DOCS-#546526-V1