This is an HTML version of an attachment to the Official Information request 'Cost of connected communities and plans to implement any findings'.


 
20 Viaduct Harbour Avenue Auckland 1010 
Private Bag 92250, Auckland 1142, New Zealand 
Ph 09 355 3553   Fax 09 355 3550 
26 March 2024 
J Turner 
[FYI request #25993 email] 
 
 
Kia ora J Turner 
 
The information you requested – CAS-871668-H1C7W7 
 
Thank you for your request for information dated 5 March 2024 about our connected 
communities programme.  
 
“’I am writing to request information in two parts about the "connected communities" 
programme: 
  •  Total expenditure on the programme from initiation to closure in 22/23 
•  Plans to implement any of the findings of the programme, particularly on New North 
Road which saw extensive community consultation. 
•  If not covered in the above, any plans to implement T2/Bus lanes along the stretches 
of New North Road where they do not currently exist.” 
 
Connected Communities Programme 
The Connected Communities programme was established in 2019 with the intention of 
optimising 12 key transport corridors across the region with a focus on get ing the most out 
of the existing infrastructure and developing solutions with local boards and the community.  
 
The programme commenced in the financial year (FY) 2020 to investigate upgrading 
corridors for bus priority, safety and cycling and to connect to supporting cycling networks. 
 
Covid 19 impacts on Programme 
As the programme was about to commence community engagement in March 2020, Covid 
19 and its associated lockdowns bought significant changes to the delivery of the 
programme.  
 
To deliver on contractual arrangements technical emerging options were developed for each 
of the corridor workstreams and then the commercial contracts were put on hold until the 
outcome of Covid 19 could be clarified on the programme.  
 
The Auckland Council emergency budget in July 2020 (FY 2021) significantly altered the 
funding and resources available for the programme. Work was recommenced on two 
corridors Great North Road, New North Road and investigations into dynamic bus lanes and 
cycle lanes. 
 
Progress on the programme continued to be interrupted by Covid 19 lockdowns which 
significantly impacted on community engagement. This resulted in significant delays and 
reductions in appropriate resources for the programme. In the FY 2022 the Council budget 
aucklandtransport.govt.nz 



was further constrained and progress on New North Road, Great North Rd and cycling links 
were the only projects to continue.  
 
The Mayoral Letter of Expectation and Auckland Council financial budgetary 
constraints in 2022 
 
In 2022 the Great North Road upgrade was identified for construction ($28.1m for 1.6km of 
corridor) and the New North Road corridor business case had identified a preferred option 
($140M for 11.8km of corridor). 
 
With the continued significant financial constraints on Auckland Transport’s budget, the new 
Mayoral letter of expectation 2022 and the Statement of Intent in early 2023, it was 
confirmed to the Board in May 2023 that the organisation could not afford a transformational 
corridor programme at this time. 
 
Continued use and development of Connected Communities programme workstreams 
 
Auckland Transport continue to use many of the successful outputs developed within the 
programme including: 
  •  Community Collaboration Panels assisting in developing technical designs and 
incorporating Local Board representation. 
•  Network approach for corridor improvements incorporating safety, bus priority and 
cycle outcome. 
•  Business cases for major Auckland arterial corridors 
•  Kerb to kerb solution development to reduce costs and community and business 
disruption. 
•  Dynamic bus and cycle lane option research and trials 
•  Organisational wide matrix teams and programme management frameworks  
 
The data and outcomes from the programme are continuing to be utilised across Auckland 
Transport including: 
 
•  Construction of the Great North Road upgrade 
•  Corridor sections incorporated into the Kianga Ora brownfield development street 
upgrades programme. 
•  Northwest busway designs for the Central City area incorporating Vincent St 
•  Connecting development stages for Auckland Council Te Ha Noa Victoria St cycle 
lanes 
•  Development of dynamic bus lanes delivery 
•  Delivery of optimisation programme initiatives 
•  Delivery of priorities for bus priority, walking, safety and cycling programmes 
•  Delivery of priorities for AT 10-year funding plans 
•  Prioritization of corridor upgrades 
 
In terms of the New North Road corridor a number of transport optimisation projects have 
been completed within the timeframe of the programme including: 
  •  Intersection improvements at Woodward Road 
•  Clearway amendments along the corridor 
•  Additional signalised pedestrian crossing at Morningside train station  
•  Pedestrian safety improvements at the Sandringham Road intersection 
 
 




•  Road and vehicle priority changes for buses including traffic signalisation in close 
proximity to Mt Eden Train Station. 
 
Further investigation are being undertaken on: 
 
•  Optimising the New North Road corridor in terms of clearway, special vehicle lanes 
including bus lanes and traffic signal changes. 
•  Following the bus routes commencing in Rosebank, work is currently being 
progressed to confirm priority measures for buses along Rosebank, Avondale and 
Blockhouse Bay Road that feed into New North Road.  
 
The Mayoral Letter of Expectation for Auckland Transport and Auckland Council 

financial budgetary constraints in 2024 
 
Auckland Transport are working to determine the best way forward that wil  enable us to 
deliver solutions quickly within our funding parameters and prioritise improvements across 
Auckland key arterial road corridors including New North Road corridor. This is being 
incorporated into the Joint Transport Plan for Auckland and forms part of the 2024 Draft 
Regional Land Transport Plan. 
 
Timing of the delivery of these initiatives wil  be funding dependant in line with the Council’s 
allocation identified in the draft Long Term Council Plan which is currently undergoing public 
consultation. Currently the corridor upgrade of New North Road is sitting below the line in 
terms of priority for the draft Long Term Council Plan and budget. 
 
There remains a significant need to develop viable solutions that optimise Auckland 
Transport corridors, ensure they most effectively meet the needs of our current and future 
customers across all modes and that align with Auckland Transport’s Mayoral Letter of 
Expectations and Statement of Intent for the next three years.  
 
As requested, please also find below a cost breakdown of the spend each year for the on 
Connected Communities/Integrated Corridors. 
  Financial Year  2018 / 2019  2019/2020  2020 /2021  2021/ 2022 
2022 / 2023 
Investment $m  1.8 
16.4 
4.1 
7.5 
2.7 
 
Should you believe that we have not dealt with your request appropriately, you are able to 
make a complaint to the Of ice of the Ombudsman in accordance with section 27(3) of the 
LGOIMA Act and seek an investigation and review in regard to this matter. 
 
Ngā mihi, 
 
 
 
Phil Wrat  
Engagement Manager 
Customer Care