This is an HTML version of an attachment to the Official Information request 'INZ's evaluation for the impact of 2021 resident visa'.





 
IN CONFIDENCE 
 
 
Contents 
Purpose 
 
 
 
 
 
 
 
 
 

Executive Summary 
 
 
 
 
 
 
 
 

Recommendations 
 
 
 
 
 
 
 
 

Appendix I 
 
Objectives and Milestones 
 
 
 
 
 
 

 
Programme Delivery 
 
 
 
 
 
 
 

 
Application Processing Systems 
 
 
 
 
 
10 
Immigration Risk 
 
 
 
 
 
 
 
12 
Visa Decision Quality   
 
 
 
 
 
 
15 
Customer Experience   
 
 
 
 
 
 
19 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Page 2 of 25 
 



 
IN CONFIDENCE 
 
 
Purpose 
1.  The purpose of this report is to review the implementation and delivery of the 2021 Resident Visa 
programme,  including  factors  that  contributed  to  its  success.  The  report  also  offers  some 
recommendations for future programmes of a similar nature.  
Executive Summary 
2.  INZ  received  106,582  RV21  applications  in  total.  The  RV21  programme’s  key  objective  was  to 
process 80% of applications by June 2023. This was achieved in early February 2023. As of 31 July 
2023, 96.5% of RV21 applications had been decided. 
 
3.  The  deadline  for  the  80%  objective  was  initially  set  to  be  completed  by  30  November.  The 
completion date was later amended to June 2023, along with changes around how applications 
were  to  be  prioritised  for  assessment.  Customers  were  dissatisfied  with  these  changes  and 
resulted in a large number of customer correspondence; which may have been avoided if external 
communication was simpler and more transparent.  
 
4.  The  average  number  of  applications  decided  across  all  platforms  per  Full  Time  Equivalent  per 
week, increased from 6.1 to 23.2 with the introduction of ADEPT.  
 
5.  INZ may not have achieved the key RV21 objective if it relied on other platforms, namely AMS, 
IGMS, and Plone. There were significant limitations of using these legacy platforms including an 
inability to handle peak application volumes and the reliance on manual effort. As such, the ADEPT 
platform was critical in delivering RV21. 
 
6.  To further assist meeting the key objective, INZ developed a streamlined approach for the RV21 
programme. The streamlined approach included: 
a.  Reducing the number of risk triage rules from 41 to 33. 
b.  Accepting certain documents at face value. 
c.  Not requiring offshore police certificates and full medical certificates. 
d.  Reducing the number of questions in the quality control (QC) check question set from 
60 to 22. 
e.  Conducting QCs on RV21 applications that met the ‘Skilled’ and ‘Scarce’ criteria only, 
thus reducing the QC rate below 100%. 
 
7.  The streamlined approach to risk management did not produce any significant gaps or unintended 
consequences,  however  not  enough  time  has  elapsed  to  gather  sufficient  data  on  adverse 
outcomes.  
 
8.  Visa decision quality was sustained, and quality scores were not negatively impacted by the RV21 
specific streamlined approach.  
 
Page 3 of 25 
 



 
IN CONFIDENCE 
 
 
9.  Proportionately,  fewer  RV21  customers  submitted  formal  complaints,  and  no  significant 
differences  between  RV21  customers  and  customers  of  other  visa  products  were  found  using 
Customer Experience Survey data.  
 
10. There were, however, a number of issues that affected the delivery of RV21. Examples include: 
a.  The ADEPT platform was not fully developed and tested in time for RV21 processing. 
b.  Payment failure errors when submitting applications with more than six applicants. 
c.  RV21 customers being recorded as unlawful when they were in fact  lawful, due  to 
interim visas not generating. 
d.  Poor ‘technical support’ processes. 
e.  A lack of transparent communication about the limitations of ADEPT. 
f.  Staff finding it challenging with the amount of change occurring at all levels.  
g.  There  was  a  significant  cost  to  staff  wellbeing  throughout  the  delivery  of  the 
programme. 
 
11. Further information of the above findings is detailed in Appendix I.  
Recommendations 
12. Delivery of the programme felt rushed by multiple individuals involved in the implementation of 
the  programme.  To  ensure  a  more  successful  programme,  more  realistic  timeliness  windows 
should be agreed upon. 
 
13. It was reported by programme leaders that the delivery of the RV21 programme may have been 
better in terms of control, oversight and consistency, if it was restricted to one visa processing 
office  rather  than  spread  over  multiple  sites.  Future  one-off  programmes  may  benefit  from 
concentrating visa processing to one office, if possible.  
 
14. A  large  number  of  RV21 specific  correspondence  may  have  been  avoided  if  communication  to 
customers were more transparent. INZ should take a closer look at its communication methods 
used  when  there  are  changes  made  to  announced  programme  objectives,  including  informing 
customers as to how their specific application would be affected.  
 
15. Technology support for ADEPT related issues were reported as being difficult to manage, as the 
escalation process was not well defined. Suggested improvements for managing issues included 
developing better communication channels between processing staff and product owners. 
 
16. It was reported that sufficient consultation with Technical Advisors regarding the quality control 
check process did not occur, which consequentially led to a decreased capability to manage quality 
at the visa processing office level, especially in ADEPT. It is therefore recommended that any future 
designs of the quality check process are developed in partnership with Technical Advisor teams.  
 
Page 4 of 25 
 



 
IN CONFIDENCE 
 
 
Appendix I 
Objectives and Milestones 
17. The 2021 Resident Visa (RV21) was announced in September 2021 to provide a one-off pathway 
to  residence  for  migrants,  partly  as  a  result  of  the  effects  of  COVID-19  on  normal  migration 
patterns. The objectives of the policy were to: 
a.  Provide certainty for employers that their existing migrant workforce would be able 
to remain in New Zealand permanently. 
b.  Enable migrants who were already in New Zealand for the purpose of work to remain 
permanently. 
c.  Attract health workers and other highly skilled critical workers by providing them a 
pathway to stay in New Zealand permanently. 
 
18. Eligibility was primarily based on applicants meeting at least one of the following three criteria: 
d.  Settled – lived in New Zealand holding an eligible visa for at least three years. 
e.  Skilled – in employment where they have been paid at least $27.00 an hour. 
f.  Scarce – in employment where their role has been deemed by INZ as scarce. 
 
19. The programme’s key objective was to complete at least 80% of applications within 12 months of 
delivery, from December 1, 2021 to November 30, 20221.   
 
20. RV21 was implemented in two phases,  with Phase 1 split into two sub-phases: Phase 1 and Phase 
1.5 (see Figure 1).  
 
 
 
1 This was later amended to 30 June 2023, as discussed in ‘Programme Delivery’ section 
Page 5 of 25 
 



 
 



  
 
Phase 1 
21. Applicants who had the following characteristics on 29 September 2021,  were able to submit an 
RV21 from the opening date, 1 December 2021. 
g.  An open application for residence under the Skilled Migrant Category (SMC). 
h.  An open application under the Residence from Work Category (RfW). 
i.  An open Expression of Interest (EOI) which included a dependent child aged 17 years 
or older. 
 
22. Prioritising these customers aimed to ease the ongoing delays of the backlogged SMC and RfW 
queues, as well as allow working age dependents to enter the New Zealand workforce.  
Phase 1.5 
23. Phase 1.5 opened on 21 February 2022, allowing all other INZ customers who held an EOI on 29 
September 2021.  
Phase 2 
24. Phase 2 opened to all other eligible applicants under the Settled, Skilled, or Scarce criteria.  
 
25. On 31 July 2022, INZ closed the RV21 category and customers could no longer submit an RV21 
application. 28,964 applications were  lodged under Phases  1 and 1.5, and 77,618 were  lodged 
under Phase 2, resulting in 106,582 RV21 applications in total. 
 
26. As of 31 July 2023, 96.5% of applications have been processed. 
Programme Delivery 
27. Before  the  announcement  of  the  programme,  senior  leaders  of  the  Manukau  office  were 
designated as Project Leads, with ownership of the delivery of RV21. The Manukau Project Leads 
reported that they embraced this decision (made in partnership with INZ Operational Policy team). 
They believed it was logical to design a programme that they would be responsible for and are 
subject  matter  experts  on.  Part  of  the  programme  design  included  developing  a  streamlined 
approach in order to meet the key objective. 
 
28. Although  the  RV21  programme  was  led  by  Manukau,  it  was  delivered  over  three  processing 
offices: Manukau, Hamilton, and Christchurch. A large majority was processed by the Manukau 
processing office. In hindsight, it may have been better to restrict delivery to one processing office. 
Having  one  office  responsible  for  the  delivery  of  the  programme  would  have  ensured 
consistencies, with control and oversight of delivery being easier to maintain. 
 
29. In  June  2022,  a  decision  was  made  to  amend  the  key  objective.  As  a  result,  INZ  was  to  now 
complete 80% of RV21 applications by 30 June 2023. Changes were also implemented around how 
applications were to be prioritised for assessment.  
 
30. The Manukau processing office reported that a large number of customers were dissatisfied with 
both the above changes, as customers were unsure  how the changes would affect processing of 
their application. Manukau reported a large influx of complaints, and thus additional work. It was 
Page 7 of 25 
 



 
 



 
 



 
IN CONFIDENCE 
 
 
37. Taking into account only the quantitative evidence summarised above, the delivery of the RV21 
programme was a success. However, if INZ is to  present itself as a people-centric organisation, 
then any future programmes should consider the wellbeing of its staff during periods of transition, 
especially processing office staff.  
Application Processing Systems 
38. Historically, most Residence visa applications have been paper based. As a result of the COVID-19 
related lockdowns, staff were not able to enter physical processing offices, This was a significant 
disruption to the processing of Residence applications. To mitigate this issue INZ decided to house 
RV21  processing  on  online  platforms  only,  especially  so  to  further  guarantee  meeting  the  key 
objective.  
 
39. At the time of the announcement of RV21, INZ was already using AMS, and the Immigration Global 
Management  System  (IGMS)  for  online  submissions,  however  it  was  mainly  being  used  for 
submitting temporary visa applications. It was decided that RV21 Phase 1 applications would be 
received via IGMS. The Enhanced Immigration Online Platform, otherwise known as ADEPT, was 
still being built.  
 
40. When the programme entered Phase 1 on 1 December 2021, INZ received a large initial influx of 
applications,  which  affected  the  performance  of  the  IGMS  platform.  Subsequent  performance 
testing indicated that IGMS would struggle with peak loads as observed in the opening phase of 
the programme. It was reported that processing during Phase 1 was straightforward as AMS was 
familiar, but  also that the platform connected with 3rd  party stakeholders such as the s 6(a)
 
 and the Immigration Health System (IHS). To cope with peak loads, 
INZ made the decision to use the Plone platform. Plone was historically deployed at times of high 
demand and outages. It was also used to manage border exceptions during the COVID-19 border 
closure.  Although  Plone  was  largely  able  to  handle  the  influx  of  applications,  it  did  require 
significant manual processing, affecting all parts of the visa assessment process. Given the amount 
of effort required to lodge applications using Plone and the expected number of applications to 
be received in Phase 2, Plone was not marked as the platform to be used as a permanent solution 
if INZ was committed to achieving the Key objective.   
 
41. Due to the issues identified during Phase 1, some changes were made for Phase 1.5. To alleviate 
the  difficulties  with  peak  loads,  submitted  applications  were  staggered.  INZ  accepted  1,500 
applications per day, with a maximum of 200 per hour. This process was supported by regular 
monitoring. As a result, there were no additional disruptions reported during Phase 1.5. Given the 
expected  application  volumes  for  RV21  Phase  2  customers,  AMS,  IGMS,  and  Plone  were  not 
marked as the technology solution.  
 
42. INZ decided that Phase 2 would be processed using the ADEPT platform. As ADEPT is a cloud-based 
software service, it’s capacity was scalable to accommodate much larger volumes of applications. 
However, the service was not built with RV21 in mind.  ADEPT was developed to accommodate 
processing of approximately 1,000,000 applications across all categories per year, which equates 
to 4,000 per day. During Phase 2, it was estimated that INZ would receive around 120,000 RV21 
applications  within  the  first  few  days,  well  beyond  ‘normal’  visa volumes.  With  the  support  of 
Microsoft,  the  INZ  ADEPT  Operations  Team  (AOT)  implemented  a  solution,  using  an  iteration 
Page 10 of 25 
 



 
IN CONFIDENCE 
 
 
process with a front- and back-end throttling capability. This capability enabled applications to be 
submitted,  but  then  held  in  a  “virtual  lobby”,  until  the  back-end  processing  development  was 
ready to begin visa assessments.  
 
43. Overall,  the  ADEPT  system  coped  well  with  the  incoming  demand,  allowing  for  more  efficient 
processing. ADEPT was able to automatically identify and trigger requests for Medical Certificates, 
and  NZ  Police  checks.  It  also  allowed  for  a  higher  capacity  of  additional  documentation  to  be 
uploaded, and visas could automatically be issued. The success of the implementation of ADEPT 
for the RV21 programme meant that productivity rates more than doubled. It can be concluded 
that the RV21 programme’s key objective may not have been achieved if INZ relied on AMS, IGMS, 
and Plone, and as such ADEPT was critical in the success of the RV21 programme. 
 
44. ADEPT was not without its own issues. Although AOT reported that once issues were raised, they 
were  fixed as quickly as possible either with a permanent fix or a workaround. This was made 
possible by the level of built-in flexibility and the team of technical and subject matter experts 
available  for  support.  This  however  was  in  contrast  to  the  user  experience  at  the  processing 
offices. Processing staff reported that there were major difficulties in resolving issues, especially 
during the  beginning of Phase 2. This view  did ease over time  as workarounds were  deployed. 
There was some consensus at the processing office level that the ADEPT related issues were due 
to a lack of design forethought. It was suggested that the ADEPT product owner be made more 
accessible,  and  more  efficient  project  management  to  enable  smoother  running  of  the 
programme.  
 
45. A number of specific issues are described in Table 1.  This was expected as ADEPT was not fully 
developed,  and  so  the  system  was  not  systematically  tested.  A  lot  of  the  critical  errors  were 
identified and fixed earlier in the year, when the Visitor Visa product transitioned onto ADEPT.  
 
Table 1. Summary of some ADEPT related issues  
Initial ADEPT issues during Submission 
Initial ADEPT issues during Processing 
Payment  failure  error  message  when  trying  to  Training  for  ADEPT  was  insufficient,  and 
submit  seven  or  more  individuals  on  one  commonly  occurring  issues  had  inadequate 
application. This issue is still being monitored. 
responses.  
Some  customers  were  incorrectly  recorded  as  The  ADEPT  User  Guide  didn’t  cater  for  all 
unlawfully in New Zealand and were not able to  scenarios,  including  the  differences  between 
submit an application. Customers were unaware  applications  being  ‘pushed’  to  immigration 
of  this  error  until  they  contacted  INZ.  Clearer  officers  vs  applications  being  ‘pulled’  by 
communication has since been implemented.  
immigration officers.  
The  application  form  had  the  National  ID  As ADEPT was a new technology solution, there 
Number  as  a  mandatory  field,  despite  some  was  a  steep  learning  curve  alongside  a  steep 
nationalities  not  using  national  ID  numbers.  cultural  change  due  to  the  streamlined 
Customers  had  to  enter  ‘Nil’  to  progress  the  approach.  This  amount  of  change  was  difficult 
application.  
for some to deal with.  
Because of the use of the ‘virtual lobby’, interim  The ‘Help’ infrastructure was not designed well 
visas  were  not  being  automatically  issued.  A  enough, especially for those who were not tech 
manual  workaround  was  put  in  place  to  savvy. Those staff who were tech savvy, 
Page 11 of 25 
 



 
IN CONFIDENCE 
 
 
generate  interim  visas  on  a  daily  basis  for  any  unofficially became ‘experts’, as it wasn’t easy 
affected customers.  
to get support. A lot of reliance was placed on 
them to raising tickets with the MBIE Service 
Desk. 
Some  customers  who  were  eligible  to  be  There was a lack of transparent communication 
included in an RV21 application, were unable to  about the limitations of ADEPT and a perceived 
submit an application due to eligibility screening  lack of ownership from ADEPT product owners 
questions.  Given  the  low  number  of  cases,  a  of the staggering amount of issues. A better 
workaround  was  deployed  directing  these  escalation process was suggested for future 
customers to a paper form. 
programmes.  
The form requested for details of the parents of  It was suggested that ‘Super User’ type access 
the  customer,  despite  there  being  no  field  to  could have helped with trouble shooting.  
enter such information. This was later fixed. 
 
Immigration Risk 
46. To  enable  timely  delivery  of  the  RV21  programme  it  was  agreed  that  any  proposed  risk 
management  process  would  need  to  support  the  overall  streamlined  approach  and  enable 
efficient  decision  making.  The  Risk  Monitoring  Review  Governance  Group  (RMRGG),  in 
consultation  with  the  Risk  and  Verification  (R&V)  network  and  the  Risk  Control  Group  (RCG), 
agreed to risk appetite thresholds that would support a streamlined approach. As a result, several 
adjustments were made to tolerance settings and risk controls.  
Phases 1 & 1.5 
47. The key risk areas identified in preparation for Phase 1 include: national security risk, non-genuine 
partnership  claims,  identity  fraud,  and  character  concerns.    Of  the  41  triage  rules  that  would 
normally trigger on regular residence visa applications, 33 rules were excluded from triggering on 
RV21  applications,  aligning  with  the  key  risk  areas  identified  by  the  RMRGG.  The  same  risk 
management approach was deployed for Phase 1.5, with the inclusion of an additional risk rule 
(RR1013)
s 6(c)
 
 
  For  all  phases,  the  approach  to  adverse  information 
triggering within the system was maintained.  It was also agreed that applicants would still require 
New Zealand Police Checks (NZPC) and specified applicants would also require National Security 
Checks (NSC). To support streamlined decision making it was agreed that certain documents could 
be accepted at face value and that offshore police and full medical certificates would not normally 
be required for assessment. 
 
48. The RMRGG also recommended post-decision monitoring of outcomes to refine risk management 
at the application stage and to drive compliance with immigration standards. R&V completed risk 
monitoring  activity on 5% of the approved RV21 Phase  1 and 1.5 cohort,  where  a partner was 
included, to better understand the risks and determine whether any changes to risk treatments 
for this category were required.  The results of this monitoring activity concluded that the current 
risk treatment was appropriate and would continue to be used for Phase 2.  
 
Page 12 of 25 
 



 
 



 
IN CONFIDENCE 
 
 
54. Of the risk rules that triggered for Phase 1, RR0604 triggered with the highest frequency. s 6(c)
 
. In Phase 2, RR1013 triggered 
with the highest frequency. s 6(c)
 
 This was likely due to a large amount of RV21 applicants’ employment not having ever been 
assessed by INZ, relevant for the Skilled and Scarce criteria. The risk rule with the second highest 
frequency of triggering during Phase 2 was RR1009, which was designed to surface AMS alerts and 
warnings in the ADEPT platform.  
 
55. Of  the  applications  that  were  triaged  as  ‘High  Risk’,  0.46%  were  declined  and  1.2%  were 
withdrawn. Of the applications that were triaged as ‘Medium Risk’, 0.34% were declined and 0.3% 
were withdrawn. Of the applications where a triage risk was not applicable, 0.35% were declined 
and 0.7% were withdrawn (see Table 5).  
Table 2. Risk Level of RV21 Applicants as of 26 July 2023 
 
 
Decision 
Risk Level 
Approved 
Declined 
Withdrawn 
Total 
14,938 
68 
183 
15,189 
High 
(98.35%) 
(0.45%) 
(1.2%) 
(100%) 
39,595 
136 
118 
39,849 
Medium 
(98.36%) 
(0.34%) 
(0.3%) 
(100%) 
148,330 
523 
1,124 
149,977 
Not Applicable 
(98.90%) 
(0.35%) 
(0.75%) 
(100%) 
633 

603 
1,243 
Other 
(50.93%) 
(0.56%) 
(48.51%) 
(100%) 
203,496 
734 
2,028 
206,258 
Total 
(98.66%) 
(0.36%) 
(0.98%) 
(100%) 
 
56. While  the  applications  that  triaged as  ‘Not  Applicable’  had  a  higher  percentage  of  decline  and 
withdrawal decisions than those that triaged medium risk, it is likely that these applications did 
not  meet  immigration  instructions,  such  as  for  Character  or  Health,  and  thus  have  not  been 
analysed in this report.  
 
57. The intended streamlined approach to the RV21 category is clearly reflected in the interventions 
and outcomes. In summary, 73% of all applications did not automatically trigger any risk flags and 
only 0.36% of all applications processed (by 26 July 2023) have resulted in a decline decision.  
 
58. Risk  monitoring  activity  completed  between  phases  did  not  reveal  any  significant  gaps  and 
supported the continuation of the proposed risk management approach for Phase 2.   
 
59. Quality  assurance  was  completed  on  152  or  0.07%  of  the  completed  RV21  applications,  post-
decision. These checks resulted in a Risk specific score of 92.1% and did not identify any concerns 
with the risk mitigation of the completed RV21 visas.  While the overall score for risk mitigation 
was 4% lower compared to that of regular residence visas, it is not a significant difference to be of 
concern (see Visa Decision Quality section below).  
 
Page 14 of 25 
 



 
IN CONFIDENCE 
 
 
60. It is also worthy to note processing office staffs’ views on management of risk. The view was mixed. 
 
61. Some processing office staff agreed that the design of the RV21 category mitigated immigration 
risk  appropriately. It was mentioned that the category was designed to only include  applicants 
who  met  certain  criteria  and  immigration  instructions  were  simple  and  easy  to  assess.  It  was 
agreed that both instructions and processes were clear, and R&V were available to provide advice 
for applications that were identified as High risk.  
 
62. There was however, a small amount of scepticism regarding the propensity for risk, but this eased 
over time as processing staff became accustomed to the streamlined approach. This resulted in a 
change of culture of application processing, as decision makers were “less defensive” and more 
open to approving applications with a lesser degree of checks undertaken. 
 
63. Some processing staff noted that there were differences in the practical handling of risk between 
applications assessed on AMS vs ADEPT. ADEPT enabled automation of some tasks and this meant 
that occasionally, applications with risk would ultimately be approved. A minority continued to 
feel uncomfortable with the fact that more risk-laden cases were being approved.  
 
64. Despite  the  residual  concerns,  there  is  no  evidence  to  suggest  that  risk  was  handled 
inappropriately throughout the implementation and delivery of the RV21 programme.  
 
65. It is not yet possible to fully assess the actual impacts of the applied risk management approach 
for RV21 until sufficient  time has lapsed to gather data on adverse outcomes.  Such outcomes 
would usually first become visible during Permanent Residence Visa processing when assessing 
whether the Residence Visa holder is eligible for Permanent Residence based on the commitment 
demonstrated while holding a Residence Visa. 
Visa Decision Quality 
66. Alongside the organisational RV21 objective of completing all applications within 12 months, INZ 
was also committed to maintaining high visa decision quality for RV21.   
 
67. Visa decision quality is measured by INZ at two points: pre-decision and post-decision. The quality 
model aims to ensure that quality performance is sustained or improved over time.  
Quality Control 
68. The  quality  control  (QC)  check  is  completed  pre-decision  i.e.  before  a  visa  assessment  is 
completed.  The  purpose  of  the  QC  check  is  to  confirm  that  the  necessary  decision-making 
processes were followed, and if not, are completed before a final decision on the application is 
made.  
 
69. Because the RV21 programme was a one-off visa category ultimately aiming to automate some 
decisions,  it  was  decided  that  the  QC  component  of  the  visa  assessment  procedure  would  be 
simplified  as  much  as  possible  (streamlined)  while  still  meeting  INZ’s  quality  standards.  The 
streamlined  approach  included  reducing  the  number  of  questions  in  the  question  set,  and 
decreasing the QC rate below 100%.  
Page 15 of 25 
 



 
 



 
IN CONFIDENCE 
 
 
using the QC Tool, which sits on an online platform independent to AMS, ADEPT, IGMS, and Plone 
altogether. QCs for RV21 Phase 1 were completed on this QC Tool.  
 
76. QCs for RV21 Phase 2 were completed within ADEPT. This was the first time QC checks were being 
conducted on the  ADEPT platform.  As such, there  were  critical  technical issues  that prevented 
conducting QC checks in an efficient manner. One such issue led to a backlog of 2,000 QCs and 
often  taking  longer  to complete  a  QC  check  than  to  complete  the manual assessment  activity. 
Therefore,  in  June  2022,  INZ  decided  that  those  RV21  applications  that  fell  under  the  ‘Settled’ 
criteria would not undergo a QC check. This decision allowed INZ to focus 100% of its QC efforts 
on the RV21 subtypes that presented more risk (Skilled, Scarce).  
 
77. This  does  not  mean  that  Settled  application  had  no  oversight.  The  Risk  and  Assurance  team 
reviewed a sample of ‘Settled’ RV21 applications post-decision each quarter as a discrete exercise. 
To date, no issues have been found. This further indicates that the decision to drop QC checks for 
‘Settled’ RV21 applications did not have an adverse impact on visa decision quality. This decision 
was also well-received by TAs and the instructions were clear for them to quickly change the QC 
process. 
 
78. For Phase 2 specifically, some TAs felt that quality control was difficult to manage in ADEPT as they 
were less able to truly control quality effectively, which led to some cases having to be reassessed, 
including after  a decision had been made.  This may have  been an unintended consequence  of 
either  the  truncated  question  set  not  being  able  to  capture  a  critical  error,  or  not  identifying 
potential issues for ‘Settled’ applications.  
 
79. It was suggested that any future designs of the QC process should consult TAs, as they do the large 
majority of the quality control tasks, and understand the subtleties of QC related issues the best.  
 
80. Although the attempts to streamline the QC process were successful, contributing to achieving the 
Key objective, it is important to evaluate whether visa decision quality was sustained or adversely 
impacted. This can be observed from Quality Assurance data.  
Quality Assurance 
81. Quality  Assurance  (QA)  is  performed  post-decision  on  a  sample  of  decided  visa  decisions.  The 
scores  are  aggregated  into  two  scores:  one  for  Residence  applications  and  one  for  Temporary 
decisions.  Analysing quality of RV21 quality over time,  allows to observe whether visa decision 
quality was sustained from the implementation of the programme onwards. 
 
82. Between the Dec 21 – Jun 23 period, 152 RV21 quality assurance assessments were conducted, 
analysed over five quarters. Figure 7 illustrates the overall RV21 quality scores compared to the 
aggregate Residence score excluding RV214. 
 
 
4 Data for the Apr-Jun 2022 quarter is missing as a business decision was made not to quality assess this 
particular quarter. Instead qualitative analysis was conducted on a sample of ‘Settled’ RV21 applications. No 
issues were found for all 30 applications.  
Page 17 of 25 
 



 
 



 
 



 
 



 
 



 
 



 
 



 
IN CONFIDENCE 
 
 
110. 
Process delays are overwhelmingly the issue that most RV21 customers complained about, 
with  half  of  all  complaints  containing  some  dissatisfaction  with  the  time  taken  to  process  an 
application.  This  is  not  an  extraordinary  finding,  as  delays  are  the  most  common  case  ground 
overall.  
 
111. 
Additional  reports  from  processing  offices  indicated  that  the  extension  of  the  timeliness 
objective from December 2022 to June 2023 as well as the decision to prioritise some applicant 
skills over others led to decreases in customer satisfaction.  
 
112. 
Taking into both sources of data from the CXS and CFT, it appears that customer satisfaction 
with the RV21 product was more positive than negative.  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Page 24 of 25 
 



 
IN CONFIDENCE 
 
 
Document Control 
Version 
Date 
Responsible 
Description of change 
1.0  
11 Aug 23 
Divesh Prakash 
Initial Draft 
1.1 
15 Aug 23 
Divesh Prakash 
Second Draft 
2.0 
25 Aug 23 
Divesh Prakash 
Final Draft 
3.0 
29 Aug 23 
Divesh Prakash 
Final 
 
 
Document Handling Instructions 
Security Procedures 
This document must be handled, stored and transferred in accordance with the security procedures 
applicable to its security restriction as detailed in the MBIE Security Hub. 
Dissemination  
Primary Customers (as noted on the front page) are welcome to share this document internally 
within INZ. This document (or attachments) must not be distributed to other work areas outside of 
INZ without prior authorisation from a Manager from the Insights Team. Any requests for further 
distribution of this document should be directed to the Manager Insights and include a reason for 
the request. 
Copying  
This document may not be copied without authorisation from a manager within the Insights Team. 
Information in this document may only be incorporated in other documents or otherwise used, subject 
to the conditions in the Handling Instructions and provided that such use does not lessen the degree 
of protection afforded this information. 
Official Information Act 1982 
This document remains the property of MBIE. The release of information contained in the document 
may prejudice the maintenance of the law, including the prevention, investigation and detection of 
offences. 
Privacy Act 2020 
This document may contain information relating to individuals that is covered by the principles of the 
Privacy  Act  2020.  Accordingly,  this  document  should  be  protected  by  use  of  the  above  security 
measures to safeguard against its loss, or unauthorised access, use, modification or disclosure. 
 
 
Page 25 of 25