Re: Waikōwhai Boardwalk Repair 
 
 
Thank you for your email dated 25 February 2024, in which you requested information about 
the Waikōwhai Boardwalk. The specific details of your request and our response are below. 
 
The Waikōwhai Boardwalk (Onehunga Bay to Waikowhai) is currently closed following 
the cyclone last year. I am requesting: 
  1.  1: What assessment work of the boardwalk has been carried out since it was 
shut? 
 
Waikōwhai Boardwalk sustained significant damage following the storms in early 2023 and 

from subsequent slips and trees onto sections of the path. Evidence of this is captured in the 
attached photos (the aerial photo was taken soon after the initial storm at the end of January 
2023). 
 
Due  to  the  amount  of  damage  the  tracks  and  walkways  sustained  along  the  Manukau 

Foreshore  and  continual  bad  weather  throughout  2023,  access  to  these  tracks  has  been 
restricted due to the health and safety risk to staff and contractors’ until the area was more 
stable. 
 
Our external consultants have completed an assessment and schedule of works. The Parks 

and Community Facilities department are now waiting to confirm priorities with the local board 
prior to proceeding. 
 
(A  council  assessment  was  undertaken  (attached),  however  this  was  completed  prior  to 

another slip which dislodged some of the boardwalk (which is shown in one of the photos)). 
 
Slip assessments have been also completed for the private properties above the boardwalk. 

 
Private Bag 92300, Auckland 1142  |  aucklandcouncil.govt.nz  |  Ph 09 301 0101 


  2.  What work has been completed so far in relation to repairing the walkway? 
 
No physical works have been completed in relation to repairing the walkway, however some 

arborist (tree removal) work has been undertaken. 
  3.  What is the expected time to completion of repairs to the walkway? 
 
There is currently no timeframe for any works to be completed as the whole coastal walkway 

wil  be reviewed and prioritised in relation to the scale of damage and repair.  
 
Staff wil  workshop with the local board in 2024 the suggested priorities and timeframes for 

undertaking  the  work,  following  which  we  wil   then  be  able  to  confirm  what  work  wil   be 
undertaken and when.    
 
We anticipate that there wil  be some walkways that require minimal work to reopen while 

others wil  require more substantial work, such as the Waikōwhai Boardwalk. 
 
Decisions relating to the information that is being released to you were made by Taryn Crewe, 
General Manager - Parks and Community Facilities.   
 
You have the right to complain to the Ombudsman if you believe we have not responded 
appropriately to your request. Information about how to make a complaint is available at 
www.ombudsman.parliament.nz or freephone 0800 802 602. 
 
If you have any further queries, please contact me on 09 301 0101 quoting official information 
request number 8140013229. 
 
Ngā mihi  
 
Amanda Pil ay 
Privacy and Official Information Business Partner 
Governance Services 
Private Bag 92300, Auckland 1142  |  aucklandcouncil.govt.nz  |  Ph 09 301 0101