This is an HTML version of an attachment to the Official Information request 'Questions regarding Teitei Drive, Ohakune review'.


Request 1
 
Our Ref: s92 Further Information Request 
File: 1598 / 12763 335 00 
 
21 August 2023 
 
 
Barker & Associates 
 
 
Attention: 
Katherine Hu 
Email:   
[email address] 
 
 
Dear Ms Hu 
 
 
SECTION 92 RMA FURTHER INFORMATION REQUEST – APPLICATION FOR SUBDIVISION 
OFFICIAL 
AND LANDUSE, KAINGA ORA AND RUAPEHU DISTRICT COUNCIL, 6 TEI TEI DRIVE, 
OHAKUNE (RDC Ref: RC 1598) 

1982
 
This letter is in relation to your application for Subdivision and Land use consents on land legally 
THE 
described as Lot 2 DP 54909. 
 
ACT 
Section  92(1)  of  the  Resource  Management  Act  1991  allows  for  a  consent  authority  at  any 
reasonable time before its decision to request further information in relation to the application. 
 
You are required to provide the following additional information in relation to the above application: 
 
Extent of Works 
UNDER 
 
1.  Please  clarify  the  extent  and  nature  of  works  shown  on  the  various  plans  in  the 
Engineering  Drawing  set  with  regards  to  works  in  and  around  proposed  Lot  205  (Local 
Purpose Reserve).  The Wetland Assessment recommends that in order to offset the direct 
effects  of  the  proposed  subdivision  works  on  Wetland  2,  that  the  wetland  should  be 
extended into the area contained within Proposed Lot 205.  The Wetlands and Stormwater 
Memorandum sets out the potential for a small stormwater wetland in the area of Proposed 
Lot 205.  It would thus appear that works will be required in the area of Proposed Lot 205 
which is currently shown as outside the extent of works.      
INFORMATION 
 
Wetlands 
RELEASED 
 
2.  The Stage 1 Earthworks Proposed Contour Plan provided in Appendix 4 to the application 
indicates  that  the  10m  wetland  buffer  zone  extends  onto  Proposed  Lots  1,  2  and  3.  
Assuming  that  the  “buffer  zone”  relates  to  the  National  Environmental  Standard  for 
Freshwater (“NES-F”), please clarify what the implications of the NES-F “buffer zone” is for 
the construction of dwellings on Proposed Lots 1-3 in the future, and confirm whether or not 
the  consents  to  be  sought  for  the  project  from  Horizons  under  the  NES-F  address  that 
matter. 
 
Concept Masterplan 
 
3.  Noting that earlier concepts of the Masterplan for the site indicated retention of the existing 
 

Page 2 
Our Ref: [DocumentNo] 
Date 
 
 
shared  path  from  Snowmass  Drive  to  Tei  Tei  Drive  on  its  existing  alignment,  please 
provide
 an explanation of the rationale for the proposal to realign the shared path to in part 
require path users to use local streets in the subdivision (see also information requests later 
in this letter under the Integrated Transportation Assessment heading).  
 
4.  Please  confirm  whether  the  indicative  size  of  the  water  tank  notation  shown  on  the 
Indicative  Lot  Layouts  is  accurate  to  the  size  that  will  actually  be  provided.    This  is 
particularly  important  on  the  Lots  that  are  proposed  to  be  under  450m2  in  site  area  given 
the outdoor stacked parking arrangement that is proposed on those lots. 
 
5.  Please  clarify  whether  the  Indicative  Lot  Layouts  recognize  and  provide  for  the  building 
foundation restriction within the 45 degree zone of influence from pipe inverts as set out at 
section  8.4.2  of  the  Geotechnical  Interpretative  Report.    Please  provide  alternative 
complying layouts if not. 
 
6.  With  respect  to  the  Typical  Stream  Interface  plan  at  page  18  of  the  Concept  Masterplan, 
please  clarify  how  the  desired  shared  path  along  the  length  of  the  reserve  can  be 
achieved while taking into account the recommendations set out in the Stream Assessment 
OFFICIAL 
Report,  particularly  with  regards  to  ecological  restoration  planting  for  at  least  10m  either 
side of Waterway B. 
1982
 
Stream Assessment 
 
THE 
7.  Please clarify how the recommendations of the Stream Assessment in terms of ecological 
enhancement and restoration are proposed to be implemented. 
ACT 
 
Arboricultural 
 
8.  Please  clarify  whether  the  trees  and  vegetation that  are recommended to  be  retained  as 
set  out  in  the  Arboricultural  report  are  proposed  to  be  retained  as  part  of  the  proposed 
UNDER 
subdivision.    If  they  are  not,  please  provide  an  assessment  of  the  effect  of  not  retaining 
them along with any required measures to remedy, mitigate or offset their loss. 
 
Construction Noise and Vibration 
9.  The site will require bulk earthworks to form the subdivision.  The Geotechnical report 
submitted with the application sets out that a large area of uncontrolled fill exists on the 
subject site that will need to be dug out and replaced with engineered fill as part of 
subdivision formation works.  The compaction process may require multiple phases and will 
require rolling/compaction of the fill.  The area affected is adjacent to existing residential 
INFORMATION 
development on neighbouring sites.   
RELEASED 
10. Further, the Geotechnical Report (para 8.3.2) sets out that given the high moisture content 
of the silts and clays that will be encountered during earthworks the material will need to be 
carefully managed to ensure it is worked at optimum moisture content in order to achieve 
required compaction, and that if intermittent rainfall occurs during the summer months the 
earthworks period could be lengthened considerably.  A lengthened earthworks period will 
mean lengthened duration of potential effects on adjacent properties.   
11. The application (Section 8.3.3) states that “noise and vibration effects to adjacent 
properties during earthworks can be appropriately managed, and a number of consent 
conditions are anticipated to ensure all works are carried out in accordance with best 
practice
”.  Appendix 2 to the application records that the proposed activity will be able to 
comply with Rule DR 3.3.2 which in turn requires compliance with the noise limits of NZS 
6803:1999 Acoustics – Construction Noise.  No further information or analysis is provided. 
 

Page 3 
Our Ref: [DocumentNo] 
Date 
 
 
12.  Accordingly, please provide a report from a suitably qualified and experienced 
acoustic/vibration expert that sets out in more detail what measures will be employed to 
ensure that construction noise and vibration effects will be avoided, remedied or mitigated 
on the occupants of and buildings on adjoining and adjacent sites, including those sites 
fronting Tei Tei Drive. 
Geotechnical/Services 
 
13. Please provide a copy of the Geotechnical Factual Report dated 17 February 2023. 
 
14. The  Geotechnical  Interpretative  Report  (“GIR”)  assumes  that  the  formation  of  the 
subdivision will require minor cuts and fills in the order of 1m.   The Assessment of Effects 
(“AEE”)  report    at  section  4.1  sets  out  that  “fill  depths  of  up  to  approximately  2.3m  are 
proposed within the low-lying parts of the site and cut depths of up to approximately 1.7m
”.  
Accordingly,  given  the  cut  and  fill  assumptions  in  the  GIR  are  proposed  to  be  exceeded, 
please  provide  either  (i)  confirmation  from  the  authors  of  the  GIR  that  the 
recommendations  it  contains  remain  applicable,  and/or  (ii)  any  additional  geotechnical 
analysis and recommendations to address actual cut and fill depths. 
OFFICIAL 
 
15. In  order  to  accurately  identify  which  of  the  proposed  lots  are  within  the  areas  of  the  site 
currently  containing  uncontrolled  fill,  please  provide  a  plan  showing  the  scheme  plan  of 
1982
subdivision overlaid on CMW Drawing 2 “Geotechnical Hazard Plan”. 
 
THE 
16. Section  6.3  of  the  GIR  notes  that  during  geotechnical  testing  in  the  late  spring/early 
summer period groundwater was encountered at relatively shallow levels.  Section 8.4.4 of 
ACT 
the GIR notes that due to the high groundwater table, disposal of concentrated stormwater 
flows to ground is not considered suitable.  Please clarify how this finding has been taken 
into account in the design of the proposed drainage swales and what the implications of the 
high groundwater table are for the functioning of the swales. 
 
17. Section 8.2 of the GIR sets out that a building restriction line set back at least 5m from the 
UNDER 
crest of the open drains on the site is required to define a Slope Instability Hazard Zone for 
structures,  unless  alternative  slope  instability  mitigation  measures  are  implemented.  
Please confirm which of the methods set out in Section 8.2 are to be employed, and in the 
event  that  the  Slope  Instability  Hazard  Zone  is  preferred,  provide  a  plan  showing  the  5m 
building restriction line overlaid on the scheme plan of subdivision. 
 
18. Given  that  the  prevailing  wind  in  the  Ohakune  area  is  from  the  west/nor’west  towards 
adjoining  residential  development,  control  of  dust  during  the  earthworks  phase  will  be 
important.    While  the  AEE  (Section  7.5.2)  notes  that  water  will  be  applied  to  the  site  to 
INFORMATION 
control  dust  during  construction,  please  provide  information  on  any  other  specific  dust 
control measures to be utilised (eg will soil stockpiles be covered?) to ensure that Ruapehu 
RELEASED 
District Plan Standard RE3.3.11 is able to complied with. 
 
19. Please  provide  information  that  demonstrates  that  the  proposed  depth  of  reticulated 
services  and  associated  invert  levels  to  be  installed  in  the  proposed  subdivision  is 
appropriate taking into account adjacent reticulation depths. 
 
20. Please provide any other information that has been prepared to respond to the last bullet 
point in Section 10 (Further Work) of the Geotechnical Interpretative Report.  
 
 
 
 
 

Page 4 
Our Ref: [DocumentNo] 
Date 
 
 
Hydrology 
 
21. Section  3.1.3  of  the  Hydrology  Assessment  sets  out  parameters  for  channel  design  to 
accommodate a 1:400 ARI storm event.  One of the parameters is to have 1:1 side slopes.  
Please  provide  information  to  demonstrate  that  this  recommendation,  along  with  the 
expected channel section set out in Enclosure 3 to the Hydrology report, can be reconciled 
with the recommendations in Section 8.2 of the GIR as to channel slope stability. 
 
22. Please  clarify,  in  light  of  the  earthworks  that  are  proposed  to  be  undertaken  at  the  site, 
what  the  recommended  minimum  building  floor  level  to  apply  to  the  proposed  residential 
lots is. 
 
23. Allied to above, please provide information that reconciles the statement in the Engineering 
Services  report  (page  11)  that  “Care  will  need  to  be  given  when  elevating  the  building 
platforms  to  mitigate  the  flood  waters  as  this  potentially  could  exacerbate  flooding  on 
neighbouring properties
” with . 
 
Integrated Transport Assessment (“ITA”) 
OFFICIAL 
 
24. The  cross-sections  for  the  18m  wide  Primary  Road  and  the  14m  wide  Secondary  Road 
1982
indicate  allowance  for  recessed  parking  within  the  sidewalk,  with  swales  next  to  the 
sidewalk.  Please clarify and assess the safety and efficiency of how this arrangement will 
work for pedestrians where recessed parking occurs (ie will they be required to walk on the 
THE 
carriageway or in the swale to get around parked cars?). 
 
ACT 
25. Allied to the above the Masterplan for the site proposes to realign the existing straight line 
shared  path  from  Snowmass  Drive  to  Tei  Tei  Drive  to  require  path  users  to  in  part  use 
Road  E  (Rural  Lane)  and  Road  A  (Primary  Road).    Both  of  these  proposed  carriageway 
cross-sections  require  cyclists  to  share  the  carriageway  with  vehicles  with  no  specific 
provision for cyclists.  Please provide additional assessment of the safety and efficiency of 
UNDER 
this  arrangement  compared  to  the  existing  and  any  alternative  cross-sections  to  address 
the issue. 
 
26. Please provide details of the proposed traffic calming measures to be implemented on the 
various  proposed  carriageways.    It  is  noted  that  given  the  climate  in  Ohakune  with  snow 
and  ice  occurring  during  the  colder  months,  traditional  measures  such  as  speed  humps 
may  in  themselves  become  a  hazard  and  not  be  appropriate.    Allied  to  this,  one  of  the 
traffic  calming  measures  set  out  in  the  ITA  (Section  3.5)  is  to  avoid  the  establishment  of 
long, straight roads.  On the face of it, Roads A and C would appear to be long and straight 
meaning  the  implementation  of  other  traffic  calming  measures  takes  on  additional 
INFORMATION 
importance. 
 
RELEASED 
27. In  light  of  the  increased traffic  movements  that  would  be  generated  on  Tei  Tei  Drive from 
the residential subdivision, please provide details of what design measures are proposed 
to allow pedestrians and cyclists to safely cross the existing/extended Tei Tei Drive to and 
from  the  destinations  on  the  northern  side  of  the  street  (eg  Carrot  Park,  Ohakune  town 
centre).  These measures should also take into account the proposed provision of the local 
purpose reserve (Lot 205) along the northern frontage of the site, which it appears is to be 
extended if future stages of subdivision at the site occur, and which is noted in the Concept 
Masterplan  as  “Additional  Amenity  Space  for  the  community  -  linking  in  with  the 
playground”. 
 
28. Please provide comment from NZ Transport Agency/Waka Kotahi on the adequacy of the 
existing  Tei  Tei  Drive/SH  49  intersection  to  safely  and  efficiently  cater  for  vehicle 
movements from the proposed residential subdivision. 
 


Page 5 
Our Ref: [DocumentNo] 
Date 
 
 
 
Service Confirmation 
 
29. Please  provide  correspondence  from  the  relevant  utility  service  provider  confirming  that 
the proposed subdivision can be supplied with electricity connections. 
 
Proposed Consent Conditions 
 
30. Please  provide  a  consolidated  set  of  proposed  consent  conditions  that  address  the 
recommendations in the various technical reports and the AEE. 
 
The  consent  authority  is  requesting  this  information  to  enable  it  to  determine  the  potential  for 
adverse effects to be created by your proposal.  Your application will remain on hold awaiting this 
information.   
 
The  time  period  starting  at  the  date  the  further  information  was  requested  and  ending  when  you 
provide the information will be excluded from the processing time in accordance with Section 88C 
of the Resource Management Act 1991. 
OFFICIAL 
 
Section 92A of the Resource Management Act 1991 applies to further information requests.  This 
1982
section states: 
 
“92A  Responses to request 
THE 
 
(1)  An applicant who receives a request under section 92(1) must, within 15 working days 
ACT 
of the date of the request, take one of the following options: 
 
(a)  provide the information; or 
(b)  tell the consent authority in a written notice that the applicant agrees to provide the 

information; or 
UNDER 
(c)  tell the consent authority in a written notice that the applicant refuses to provide the 
information. 
 
(2)  A consent authority that receives a written notice under subsection (1)(b) must –  
 
(a)  set a reasonable time within which the applicant must provide the information; and 
(b)  tell the applicant in a written notice the date by which the applicant must provide the 
information.” 
 
Please  provide  the  Council  with  the  requested  information  by  11  September  2023,  or  advise  the 
INFORMATION 
consent authority whether you agree or refuse to provide the requested information. 
 
RELEASED 
Should you require further information or assistance regarding this letter, please do not hesitate to 
contact me. 
 
Yours sincerely 
 
 
 
 
Grant Eccles 
CONSULTANT PLANNER 
 
 
 


Request 2 - part 2 
OFFICIAL 
1982
THE 
ACT 
UNDER 
INFORMATION 
RELEASED 


OFFICIAL 
1982
THE 
ACT 
UNDER 
INFORMATION 
RELEASED 

Request 2, part 4
 
 
-----Original Message----- 
From: Min Kim [mail to:[email address]] 
Sent: 20 March 2023 12:20 PM 
To: [email address] [mail to:[email address]],Ree Anderson [mail 
to:[email address]],Giles Tait [mail to:[email address]],Colleen 
McCorkindale [mail to:[email address]],[email address] 
[mail to:[email address]],[email address] [mail to:[email address]] 
CC: Richard Gibbs [mail to:[email address]],Min Kim [mail 
to:[email address]],Vini Dutra [mail 
to:[email address]],Grant Eccles [mail 
to:[email address]],[email address] [mail 
to:[email address]],Stuart Watson [mail 
to:[email address]],Danielle Rogers [mail 
to:[email address]] 
Subject: Meeting Minutes - Pre-application meeting: 6 Teitei Drive development 
OFFICIAL 
   Some people who received this message don't often get email from [email address]. Learn 
why this is important 
 
CAUTION: External email. Do not click or open attachments unless you recognise the 
1982
sender and know the content is safe. If unsure use the Report Phishing button. 
THE 
  
ACT 
Good afternoon, 
Please find the attached meeting minutes. 
Katherine – Please forward this email to any attendees who are not listed on this email. 
Thank you. 
UNDER 
 
Kind regards, 
Min Kim 
 
---------------------------- 
Min Kim        
INFORMATION 
Consents Manager 
Ruapehu District Council 
RELEASED 
 
Ruapehu District Council  |  Private Bag 1001  |  Taumarunui 3946  |  New Zealand 
Phone: 07 895 8188  ext:  237  |  Fax: 07 895 3256  |  Mobile: 
email: [email address]  |  RDC website: www.ruapehudc.govt.nz 
 
 
If you are not the intended recipient of this email please notify the sender and immediately delete the email and any attachments - Thank you. 
---------------------------- 
  
  
 

Request 2, part 4 - attachment
 
 
Pre-application meeting: 6 Teitei Drive development 
15/03/2023 13:00-14:00pm, Microsoft Teams.   

People 
People present 
• 
Min Kim, Vini Dutra, Ewen Skinner, Stuart Watson, Ree Anderson – Ruapehu District Council 
(RDC) 
• 
Sunil Prasad – Cheal Consultants (CC) 
• 
Colleen McCorkinsdale, Fletcher Wilson, Giles Tait – Kainga Ora (KO) 
• 
Katherine Hu, Fraser McNutt – Barker and Associates (B&A) 
• 
Todd Langwel  – TPL (transport) 
• 
James Pattullo – Isthmus (urban design) 
• 
Grant Eccles, Danielle Rogers – Tonkin & Taylor Ltd (T+T) - for RDC 
Apologies 
OFFICIAL 
• 
Richard Gibs – RDC 
1982

Agenda 
THE 
• 
Brief introduction and overview of the project background (Giles) 
• 
Overview of proposed concept plans and design approaches (James) 
ACT 
• 
Resource consent (RC) pathways, activity status and key RC considerations, and information 
requirements (Fraser) 
• 
Approaches on roading layouts and information/matters to be covered in technical report 
(James / Fraser) 
UNDER 
• 
Approach and initial design thinking of stormwater (Sunil) 

Summary of questions & discussion 
• 
Giles (KO) – This is a shovel ready project with hard deadlines with an aim to be on site doing 
works approved under resource consent by December 2023. The tight deadlines on the 
project are from a financial point of view to work with funding provided to KO. The aim is to 
lodge the resource consent application by end of April. 

Ngāti Rangi have been involved in meetings and development agreements between KO 
and RDC. B&A are waiting on a signed agreement between all parties. 
INFORMATION 

s 9(2)(g)(i)
 
RELEASED 
• 
James (Isthmus) – The project includes sports fields, good connectivity with walkways, roads 
and town centre. No requirement for further facilities as everything is relatively local. 

Amenity considered within the site with the proposed stream and the existing cycle way 
on northern part being brought forward to front of houses rather than the back. 

Stormwater - indicative locations of ponds are shown with the attempt to leverage that 
value with the community. 

Resilience of the site taken into account to allow future development to the south. 

Allowance for SW swale in road width, flexibility with street layout. 
• 
Fraser (B&A) – 38 lots proposed for Stage 1 with the potential for more lots on western side 
to total 44 lots. 

 

 
 

Not applying under Comprehensive Residential Development Rule in the Ruapehu 
Operative District Plan (ODP) and rather for a landuse consent for residential 
development under Rule 3.2.4 as a non-complying activity due to failure of density 
condition (RE 3.3.2). Feeling that with the effects aside, they are still achieving the 
intentions of the ODP.  

Working with Horizons Regional Council to check if consents are required. 

Prelim discussions have already been undertaken with RDC. 
• 
Grant (T+T) – queried whether the application would simply be a subdivision consent.  Action 
is to check the District Plan and see if landuse consent would be necessary to authorise the 
houses on the under 450m2 lots on the assumption they were approved. 

Interested if any wetlands present and how the 3 waters engineering is going to work. 

As the proposal does not comply with density standards, and the development has its 
sole access to the wider roading network via the TeiteiDrive/SH49 intersection, it is 
highly likely that Waka Kotahi will be regarded as an affected party and their written 
approval should be sought by the applicant – gaining their approval should not be an 
issue if Teitei Drive/SH49 intersection adequately designed. A Traffic Impact Assessment 
(TIA) will be required to support the application and address safety and efficiency in the 
OFFICIAL 
normal manner including specific consideration of any measures that may be required 
on Teitei Drive to address pedestrian movements across the road coming and going 
1982
from the development to the Carrot Park. 

Vinny's team to advise on whether there is sufficient 3 waters capacity to handle the 
THE 
demand from the development. 

Departure from roading standards not fatal as long as roading function still works and 
ACT 
integrates appropriately with adjoining landuse. 

The more comprehensive the information, the better when applying.  Expects that the 
application will contain a full and thorough notification assessment and assessment of 
effects.  No opinion one way or the other on notification/non-notification at this point 
but encouraged to see complying lot sizes along the site boundary with Snowmass. 
UNDER 
• 
Ree (RDC) – Col een interested in Roading Hierarchy. Roads are not the only a transport 
medium but also represent open space and can complement reserves.     
• 
Sunil (CC) – From a civil perspective, there are 44 lots for stage 1 and it will be chal enging to 
get gravity feed to the network. 

Proposing gravity main to stage 2 boundary and pump station and rising main further 
north. Wastewater connecting to the 100mm pipe. 

The groundwater table is 300m and shallower in some places.  As this is quite shallow 
and pond needs to be quite deep, more soil will need to be used to build up the pond. 
INFORMATION 

Storage tanks or retention devices are proposed for SW attenuation on each lot to 
capture roof water. This wil  help with SW on the site and keep the pond smaller. 
RELEASED 

Need to confirm rising main route, however, balance lot owned by RDC so no need for 
easement. 
• 
Todd (TPL) – The application is working with design team to integrate the development with 
surrounding environment. 

In context the application for Stage 1 is only 44 lots and may not trigger anything at this 
stage. Approximately 40 vehicle movements is not high volume. 

James to provide more feedback on roads and hierarchy and SW requirements. 

Flexibility available to widen carriageways or walkways etc. 

Can't see any Significant issues with Stage 1 development.   

 

 
 

Next steps/actions: 
• 
Ruapehu District Council to confirm whether a landuse consent (for residential activity) and/or 
a subdivision consent is required for the activity – ASAP. 
• 
Applicant to continue with preparation of application and maintain contact with RDC 
regulatory team as required. 
 
OFFICIAL 
1982
THE 
ACT 
UNDER 
INFORMATION 
RELEASED 

 

Request 3, part 5 - email 1
-----Original Message----- 
From: Ree Anderson [mail to:[email address]] 
Sent: 5 March 2021 9:47 AM 
To: Rachael Hurzeler [mail to:[email address]] 
CC: Neil Mayo [mail to:[email address]],Rebecca Van Orden [mail 
to:[email address]] 
Subject: Fwd: LIM 6 Teitei Drive, Ohakune 
Hi Rachael 
 
 
Please find below a link to the LIM for the TeI Tei site in Ohakune. 
 
 
Hopefully this means you have all the information needed. 
 
 
Please can you confirm receipt and let me know if you have any further queries. 
 
OFFICIAL 
 
Most appreciated. 
 
1982
 
Kind regards, Ree 
THE 
 
 
ACT 
 
Ree Anderson | Director |  [email address] 
  
 
 
UNDER 
 
Tel: +64 27 687 9709 | PO Box: 56097 Dominion Road, Auckland, 1446 
 
Begin forwarded message: 
From: Rebecca Van Orden <[email address]> 
 
Subject: FW: LIM 6 Teitei Drive, Ohakune 
 
Date: 5 March 2021 at 9:40:51 AM NZDT 
 
INFORMATION 
To: Clive Manley <[email address]>, Tessa Owen 
<[email address]>, Margaret Hawthorne 
RELEASED 
<[email address]>, Ree Anderson <[email address]> 
 
 
 
Hi everyone, 
Please see below link for completed LIM for 6 Teitei Drive. 
 
Thanks 
Rebecca 
 
 

  
 
  
---------------------------- 
Rebecca Van Orden      BMS (Hons)      
Team Leader Community Property 
Ruapehu District Council  
 
Ruapehu District Council  |  Private Bag 1001  |  Taumarunui 3946  |  New Zealand 
Phone: 07 895 8188  ext:   276   |  Fax: 07 895 3256  |  Mobile:  s 9(2)(a)
 
email: [email address]  |  RDC website: www.ruapehudc.govt.nz 
 
 
---------------------------- 
  
  
From:  Claudia Zimmer <[email address]> 
Sent: Friday, 5 March 2021 9:37 am 
OFFICIAL 
To: Rebecca Van Orden <[email address]> 
Subject: LIM 6 Teitei Drive, Ohakune 
1982
 
Dear Rebecca 
 
THE 
Thank you for the application for LIM for the property 6 Teitei Drive, Ohakune . 
 
ACT 
This is the link to your LIM.  We recommend that you save the document to your computer to be 
able to access it as we will delete it from One Drive on or after 5 April 2021. 
 
Please advise if you have problems accessing the information. I am available in the office from 8am 
to 5pm, Tuesday to Thursday on 07 895 8188 extension 201.  For enquiries outside these days and 
UNDER 
hours, please contact Customer Services. 
 
If you have any further questions in relation to this LIM, please do not hesitate to contact Council. 
 
Yours sincerely 
 
 
Claudia Zimmer 
Land Information Memorandum (LIM) Officer 
INFORMATION 
 
  RELEASED 
---------------------------- 
Claudia Zimmer        
 
ext:   201 
Land Information Memorandum (LIM) Officer 
---------------------------- 
 
CAUTION: External email. Do not click or open attachments unless you recognise the 
sender and know the content is safe. If unsure use the Report Phishing button. 

Request 3, part 5, email 2
 
-----Original Message----- 
From: Ree Anderson [mail to:[email address]] 
Sent: 2 March 2021 5:55 PM 
To: Rachael Hurzeler [mail to:[email address]] 
CC: Neil Mayo [mail to:[email address]],Clive Manley [mail 
to:[email address]],Margaret Hawthorne [mail 
to:[email address]],Rebecca Van Orden [mail 
to:[email address]],Ewen Skinner | Morrison Low [mail 
to:[email address]],Tessa Owen [mail 
to:[email address]] 
Subject: Information for Tei Tei Drive-Project 2 Ohakune 
Kia ora Rachael 
 
Please find responses to your information requests as follows: 
 
1. CE Clive Manley has confirmed that there is flexibility in having some lots that are sold at 
market price to offset overal  costs to council.  
OFFICIAL 
 
2. An urgent LIM report has been requested and will be available on the 8 March 2021 
 
1982
3.  There has been no master plan / bulk and location studies for Tei Tei Drive.  An aerial shot of the 
site is attached below – general y the thinking was development would start on the northern 
THE 
sections of the site.  
 
ACT 
4.   The site is 9.4536Ha in total size.  This area contains a waterway that will reduce the land 
available for development.   
 
5.  The CIP funding sought for TeiTei was $5,303,341 for the site development (Civils, infrastructure, 
building platforms and planning) for 44 lots.  There was also a component of project establishment / 
UNDER 
due diligence costs that we were seeking to recover – indicatively this would have been an additional 
$200K. 
 
6.   Attached below  is the Cheal feasibility report that has all geotechnical information on the site. 
 
Hope this helps. Any queries please let me know. 
 
 
Kind regards, Ree 
INFORMATION 
 
Click to Download 
RELEASED Feasibility Report - Teitei Dr_Full.pdf 
24.1 MB 
 
 
Ree Anderson | Director |  [email address] 
  
Tel: +64 s 9(2)(a)
 | PO Box: 56097 Dominion Road, Auckland, 1446 
CAUTION: External email. Do not click or open attachments unless you recognise the 
sender and know the content is safe. If unsure use the Report Phishing button. 

Document Outline