This is an HTML version of an attachment to the Official Information request 'Wellington railway station and heritage NZ'.

 
 
 
 
 
Assessment of Environmental 
Effects – validators 
Wellington Railway Station Platforms 
June 2021 
 
 
 
 
 
 
 
IAN BOWMAN 
Architect and conservator 
 
 
 

 
Contents 
1
  Introduction ..................................................................................... 3 
1.1  Commission ....................................................................................................... 3 
1.2  Limitations ......................................................................................................... 3 
1.3  Framework for this HIA ..................................................................................... 3 
2  Statutory recognition and heritage values ............................................ 5 
2.1  Heritage listings .................................................................................................. 5 
2.2  Heritage values of the platforms .......................................................................... 6 
2.3  Heritage values of the railway station .................................................................. 8 
3  Proposal description, objectives, alternatives ....................................... 9 
3.1  Project Objectives .............................................................................................. 9 
3.2  Proposal ............................................................................................................. 9 
3.3  Validator Post Design ......................................................................................... 9 
3.4  Wellington Station Validator Installation .......................................................... 10 
3.5  Alternatives considered ..................................................................................... 11 
4  Assessment criteria .......................................................................... 13 
4.1  Section 176A Outline Plan , Resource Management Act 1991 ......................... 13 
4.2  Wellington City District Plan (WCDP) ............................................................ 13 
4.3  Heritage New Zealand Pouhere Taonga (HNZPT) .......................................... 13 
5  Assessment of impacts ..................................................................... 15 
5.1  WCDP criteria ................................................................................................. 15 
5.2  HNZPT Heritage Guidance Sheet 16 Assessing Impacts on the Surroundings associated 
with Historic Heritage
, 2007 ......................................................................................... 17 
5.3  Evaluation of impact ........................................................................................ 18 
6  Conclusions and mitigation ............................................................. 19 
6.1  Conclusions ..................................................................................................... 19 
6.2  Mitigation measures ......................................................................................... 19 
Appendix 1 .......................................................................................... 20 
Assessment of values and effects ................................................................................. 20 
Grading of heritage values ......................................................................................... 20 
Magnitude of effect ................................................................................................... 20 
Significance of effect ................................................................................................. 21 
Appendix 2 .......................................................................................... 23 
Wellington City District Plan Appendix P Conditions ............................................... 23 
Appendix 3 .......................................................................................... 24 
Heritage values of the railway station ......................................................................... 24 

 
 

 

Heritage Impact Assessment • Validators, Wellington Railway Station  


 

Introduction 
1.1 
Commission 
This heritage impacts assessment (HIA) of the installation of six validators was 
commissioned by Peter Wells, Project Manager, Metlink on 22 April 2021. 
1.2 
Limitations 
The assessment is based on the following documentation: 
• 
Interact Architects, WRS Ticketing Validator Project, Ground Floor platform 
2&3, Wellington Railway Station, Building Consent Issue – Rev- 0, April 
2021, sheets A-G.01, G.02, G.03; 
• 
Stantec, Wellington Station Validator Assessment, Prepared for Greater 
Wellington Reginal Council, March 2021; 
• 
photos taken by Laura Kellaway, Heritage New Zealand Pouhere Taonga 
(NZHPT); 
• 
four photo montages of four validators; 
• 
drawing by Colin Robson, 9/11/2020, Snapper Metlink Rectangular Column 
Act Top

• 
Greater Wellington Regional Council, Wellington Railway Station – Validator 
Plan – Stage 2
, undated 
1.3 
Framework for this HIA 
The objective of an HIA is to evaluate the potential impacts a proposed development 
may have on the heritage values of a listed building.   The following national and 
international best practice guides have been considered for preparing this heritage 
impact assessment. 
• 
ICOMOS, Guidance on Heritage Impacts Assessments for Cultural World Heritage 
Properties
, ICOMOS, January 2011 (ICOMOS Guide) 
• 
Buhring C., and Bowman I., Guide to assessing historic heritage effects for state 
highway projects, 
NZTA, March 2015 (NZTA Guide) 
• 
City of Toronto, Heritage Impact Assessment Terms Of Reference, 2010 (Toronto 
HIA)  
• 
The Highways Agency, Scottish Government, Welsh Assembly Government 
LLywodraethg Cynulliad Cymru, Design Manual for Roads and Bridges, HA 
285/07, Volume 11 Environmental Assessment, Section 3 “Cultural 
Heritage”.  See appendix 1. 
• 
Queensland Government Department of Environment and Heritage 
Protection, Guideline Heritage Preparing a heritage impact statement, October 
2015 (Queensland Guide).   
Based on these guides, the following framework is used for this AEE. 
• 
statutory recognition and heritage values; 
• 
proposal description and reasons for the development; 
 
 


 
• 
alternatives explored; 
• 
regulatory assessment criteria; 
• 
best practice assessment criteria;  
• 
an assessment of the impacts using best practice criteria; and 
• 
mitigation options with means of implementation.  
 

Heritage Impact Assessment • Validators, Wellington Railway Station  


 
2  Statutory recognition and heritage 
values  
2.1 
Heritage listings 
Wellington City District Plan Chapter 21 Appendix Heritage List Buildings1 
Street 
Number  Building and date of construction 
Map 
Symbol 
Ref 
Ref 
Bunny 
 
Wellington Railway Station 1933-37 (The three street 
17 
44 
Street 
facades, including the Thorndon Quay addition, the 
main concourse, the roof line without the air-
conditioning units, the plaques in the office entrance, the 
Social Hall, the platforms, including all canopies)  
Wellington City District Plan Designations\Tables-Schedule of Designations2 
Desig  Map ref  Desig 
Building & date of 
Legal 
Comments/conditions 
no 
title 
construction 
description 
and gazette 

R4 
17&18 
Railway 
Wellington 
Part Lot DP 10 
For condition refer to 
purposes 
Railway Station 
550 
Appendix P (see 
appendix 2) 
R5 
15, 18, 
Railway 
North Island Main 
Railway land 
Includes tunnels and 
21, 22, 
purposes 
Trunk Railway. 
pursuant to 
bridges  
24, 26, 
Starting at the 
various 
30 & 
Wellington 
proclamations, 
31 
Railway Station, 
gazettes, & 
through 
statutory 
Kaiwharawhara, 
ownership  
through number 1 
& 2 tunnels 
emerging at 
Glenside, Tawa and 
Northwards and 
including the 
Waiarapa line from 
Kaiwharawhara to 
the city boundary at 
Horokiwi.  
 
 
                                                 
1 https://wellington.govt.nz/-/media/your-council/plans-policies-and-bylaws/district-
plan/volume01/files/v1chap21list.pdf?la=en&hash=A9A9EFA75DF19F3EC7D31A0BBEE00CE02AE5
4DFA 
2 https://wellington.govt.nz/-/media/your-council/plans-policies-and-bylaws/district-
plan/volume01/files/v1chap24sch.pdf?la=en&hash=324EEE5140AD9FC0C7CC26F53D4933FB1753F
683 
 
 


 
HNZPT Register 
Name 
Address 
List 
Entry type 
Category 
number 
Wellington 
Bunny Street, Waterloo Quay And 
1452 
Historic 

Railway Station 
Featherston Street, Wellington 
Place 
2.2 
Heritage values of the platforms3 
Criteria 
Values 
Description 
Ranking of 
significance 

Physical 
Archaeological 
“No archaeological sites have been recorded within 
Not assessed 
values 
information 
the footprint of the current railway station; as the 
building’s construction pre-dates 1900AD it is not 
archaeological itself.  However, sites have been 
recorded in the vicinity of the railway station”4 
Mary O’Keeffe has determined that, following the 
construction of the railway station, nothing pre-1900 
is likely to exist.   
 
Architecture 
The platforms are well-designed, functional elements 
High, national 
critical to the operation of the Wellington Railway 
Station and are integral with “the most important 
railway station in New Zealand”, providing areas for 
embarking and disembarking from trains.  The 
architecture of the canopies is simple and utilitarian 
and was described in the opening of the station as 
having a “simple and airy dignity” and “attained 
efficiency without ugliness”.   
Gray Young has demonstrated an effective use of the 
architectural device of contrasting spatial experiences 
in the design of the station.   There is a dramatic 
sequential transition from the practical, unadorned, 
small-scale platform space to the elegant, soaring, 
complex spaces of the interior and then to the 
expansive, dignified, civic space outside.   
The use of curved railway irons to support the 
canopies was a common design since at least 1906 and 
the architects have successfully interpreted this historic 
typology. 
 
Technology and 
The use of railway irons to support the canopies 
Moderate, 
engineering  
maintains a technology common in the Troup era 
local 
stations.  Similarly the use of concrete line platforms 
was known from at least 1880 in New Zealand. 
                                                 
3 Bowman, Ian, Heritage Assessment, Platforms, Wellington Railway Station, March 2021 
4 Mary O’Keeffe, Heritage Solutions Archaeological desktop assessment: installation of validator posts at 
Wellington Railway Station
, 14 March 2012 

Heritage Impact Assessment • Validators, Wellington Railway Station  


 
Criteria 
Values 
Description 
Ranking of 
significance 

 
Scientific  
Based on current research, it is unlikely that the 
Low, local 
platforms contribute scientific information about the 
history of the region.  
 
Rarity 
The platforms at the Wellington Railway Station are 
High, national 
unique in New Zealand in having multiple platforms 
serving more than two railway tracks.  It is one of two 
original stations of the four major cities in New 
Zealand to be retained and the only one of these to 
have maintained all original platforms..  
 
Representative  
The concrete lined platforms are of a representative 
High, regional 
design as is the use of railway irons for the canopy 
structure.  
 
Integrity 
The platform form, alignment, and canopy structure are 
High, local 
original however, the roofing materials and timber 
structure of the canopies is recent, while the concrete 
edging to the platforms has been cut back.  The 
platform adjoining the concourse has been extended 
into the tracks while additional metal stanchions have 
been installed through the platform roofs to support 
electrical cables and a walkway above. 
 
Context or group   The immediate context of the platforms is the 
High, national 
Wellington Railway Station complex comprising the 
station building, platforms, tracks, the landscaped 
entry from bunny Street and the Social Hall.  The 
complex is considered as having national significance.  
The wider context includes the stadium with raised 
concourses to the north and the underpass and bus 
interchange to the east.  
Historic 
People 
The building and platforms are associated with the 
High, local 
Values 
New Zealand Railways Department, which played a 
significant role in the early and subsequent 
development of the New Zealand economy.   The 
platforms and station building are also associated with 
architectural firm, Gray Young, Morton and Young 
and builders, Fletcher Construction Co. Ltd. 
 
Events 
The platforms are associated with mundane events such 
Low, local, 
as daily commuting from within the region and 
high national 
occasional travel further afield as well as national events 
such as providing the location for the Michael Joseph 
Savage funeral cortege. 
 
Patterns  
The station platforms have been modified to a minor 
High, regional 
 
 


 
Criteria 
Values 
Description 
Ranking of 
significance 

extent over time but remain essentially unchanged 
demonstrating the success of the original design and the 
current high demand for regular railway commuting 
from as far away as Palmerston North.  It is likely that 
this demand will increase.  It appears that Wellington is 
unique in New Zealand to have built and retained a 
large inner city railway hub.  
Cultural 
 
 
 
Values 
 
Public esteem 
Public esteem for the platforms is unknown, however 
Unknown 
as an essential elements within a nationally recognised 
landmark building and as a railway station where 
passengers begin or end their commute from 
Wellington, it will be known by many. 
 
Commemorative  
There are no known people commemorated on the 
Unknown 
platforms, however many Railways Department staff 
are commemorated in the war memorials in the office 
entry to the east. 
 
Education 
Given the high levels of significance in architectural, 
High, national 
representative, rarity, integrity, context, and patterns, 
the platforms have significant educational values. 
Summary statement of heritage significance 
The Wellington Railway Station platforms have high national significance as essential 
functional elements in the nationally significant Wellington Railway Station. The 
platforms are nationally unique having been designed with and retaining multiple 
railway platforms that are still in use.  
The platforms, as the station in general, are associated with the station architects, 
Gray Young, Morton and Young, the station builders, Fletcher Construction, and 
the owner, the New Zealand Railways Department.  
The architect has demonstrated considerable design skill in creating a series of 
moving, sequential, spatial experiences between the platforms and the exterior of the 
building.  
The structural design of the canopy has heritage values in the use of curved railway 
irons maintaining a railway tradition established at the turn of the century, although 
using a butterfly design rather than a gable.  
2.3 
Heritage values of the railway station 
The impacts on the railway station building, excluding the platforms are negligible.  
However for completeness the heritage values of the railway station itself is included 
in appendix 3. 
 

Heritage Impact Assessment • Validators, Wellington Railway Station  


 
3  Proposal description, objectives, 
alternatives5 
3.1 
Project Objectives 
To confirm viability of deploying an Electronic Ticketing solution onto the rail network, 
through an iterative program of piloting and testing of Snapper on a limited part of the 
network during 2021. 

• 
should enhance Metlink preparedness and resilience to operate in a COVID-
19 environment by reducing requirement to collect cash fares 

• 
should contribute to Metlink readiness for future transition to the NTS. 
• 
should be customer centric, simple and flexible, and does not deter customers 
from using public transport 

• 
should enhance Metlink service provision by strengthening ability to collect fares 
and improve quality and extent of patronage data 

• 
should be implemented within existing budgets 
In particular, it has been recognised, that the upcoming implementation of the National 
Ticketing Solution (NTS) will be a very significant transition process, and by carrying 
out a limited scale pilot of electronic ticketing on rail, there is the ability to develop 
knowledge and systems in advance. 

3.2 
Proposal 
It is proposed to trial Snapper on Rail on the Johnsonville Line, by installing validators 
at stations in order to allow customers with Snapper cards to pay for the rail journey by 
tagging on and off, at the platform based validators, at the start and end of their 
journeys. 

During the Pilot phase, the ability to use Snapper will be in addition to the existing 
paper based ticketing arrangements operated by Transdev.  Fares charged when using 
Snapper will be equivalent to the cost of single journeys paid for with a 10 trip ticket. 

Wellington Station will require to have validator posts installed to support the 
Johnsonville Line Pilot and allow passengers to tag on and off at the start and end of 
their journeys. 

This will be a significant behavioural change for rail passengers, who are used to moving 
through Wellington Railway Station without any form of ticket check or validation.  
As such, one aspect of the project is to understand how and where validator posts should 
be deployed in the station in order to allow passengers to tag on and off at the station 
with minimum inconvenience to their journeys. 

3.3 
Validator Post Design 
Snapper is the existing ticketing system supplier to Metlink for all of the bus networks 
and would be the supplier for the pilot of electronic ticketing on rail. 

Snapper’s technology partner (TMoney) do not have an off the shelf post design, so 
Snapper have partnered with HTS to develop a design for a validator post that will 

                                                 
5 Description from Peter Wells emailed to Ian Bowman 23 May 2021 
 
 




 
meet with the technology and customer use requirements.  The design of the post 
should:- 

• 
enable the mounting of the Snapper Validator and Cradle units securely; 
• 
be physically suitable for installation in outdoor environments and resistant to 
damage; 

• 
make identification and location of the posts, and the validation point, easy for 
customers; 

• 
meet accessibility design standards; 
• 
support ease of maintenance and servicing. 
As the Pilot will only require a limited number of validator posts to be procured and 
installed (around 35), it is not practical to develop more than one design of prototype 
validator post at this time.  However the learnings from the pilot deployment will then 
be used to inform design and selection of validator posts under a full network roll out of 
National Ticketing Solution in the future. 

3.4 
Wellington Station Validator Installation 
For the purposes of the trial, GWRC are proposing that six validator posts are 
deployed in the Platform apron area at the end of platform 2, 3 & 4.  The location is 
on the natural walking pathway to and from platforms 1 & 2, which are the ones most 
commonly used for Johnsonville line services, and follows the natural alignment of the 
platform buffer stops. 

Following site inspections by GWRC’s preferred platform works contractor, the 
locations have been confirmed as being close to an existing in platform duct, which can 
be used to provide power and data cabling with only minimal trenching work. 

Modelling of the impact of the validator posts on passenger flows was commissioned 
with Stantec, who utilised a Legion model, to determine crowding levels resulting from 
the use of validators by Johnsonville Line customers.  

The modelling by Stantec, assumed a worst case scenario, whereby 100% of passengers 
on the Johnsonville Line used Snapper during the am peak period.  This situation is 
very unlikely to occur during the Pilot.  Despite this, the average journey time from 
platform 1 to exit the station was only increased by 15 seconds. 

 
 
10 
Heritage Impact Assessment • Validators, Wellington Railway Station  


 
3.5 
Alternatives considered 
Validator posts have been identified as the most appropriate solution for passengers to be 
able tap on and tap off to validate their fares for the rail journey.  Potential alternatives 
to this could be 

• 
Onboard validation – this is generally not recommended for metro and rail 
services, as it can leads to crowding and delays at the doors when in station. 

• 
Barrier Gates – most major metro terminal stations use barrier gate 
arrangements to control the flow of customers on and off the platforms.  This is 
not considered to be a good solution for the Pilot situation on a limited part of 
the network, would be intrusive to passenger flows, require additional staffing 
and be inflexible in the event trains need to arrive and depart from other 
platforms. 

Preliminary discussions with stakeholders involved in the stewardship of Wellington 
Railway Station identified that Validator Post locations in the concourse area, booking 
hall or in front of the station, could have detrimental impacts to the heritage fabric of the 
building and should be avoided.  As a result, solutions on the platform apron (are 
between platforms and the concourse) have been focused on. 

Three principle locations were investigated and modelled by Stantec. 
• 
Option A – three validator posts at the end of platform two.  This location was 
found to create severe crowding and unacceptable passenger impacts 

• 
Option B & C – With four or six validators arranged in a line on the apron.  
Both offered acceptable levels of performance, but option C (with more posts) 
offered best performance of all options considered.  

• 
Option D – four validators arranged in the centre of platforms 1 & 2.  This 
option performed reasonably well, but was inflexible if trains called at 
alternative platforms so was discounted. 

Option C was selected as the preferred option, as offered the best performance, with 
minimal impact to passengers on Johnsonville or other lines.  It also better reflects the 
level of availability passengers would experience at the outer stations on the line which 
have lower customer usage, but relatively high ratios of validators available to use. 

3.6 
Installation Requirements 
Engineers have reviewed the design of the proposed validator posts and 
proposed a footing design of reinforced concrete, 750mm square and to a depth of 
600mm.  The footings will be finished flush with the exiting platform level. 

An archaeological desktop assessment, has concluded that it is very unlikely that any 
archaeological materials would be located within the area where the footings would be 
prepared. 

Power and data cabling will be required to be connected to the validator, this will be 
provided by short trenches from an existing in platform duct that closely follows the 
proposed alignment of the validators. 

The work to install the footings will likely take place 8-12 weeks prior to the proposed 
Go Live date in mid November.  Validator post installation would likely take pace 
around 3-4 weeks prior to the go live, with the posts being hooded until required. 

 
 
11 


 
3.7 
Pilot Duration and Follow on 
The Pilot is initially proposed to operate for up to around 15 months (end December 
22).  At the end of the Pilot period, it is intended that the system would be 
transitioned to the new National Ticketing Solution.  At this time, the validators 
would be replaced with updated validator posts, compatible with the selected national 
solution.  This work would be subject to new discussions with the stakeholders involved 
with the stewardship of the railway station and subsequent new consent applications. 

In the event that the Pilot is terminated early, or that the NTS solution is not yet 
available.  Then the Snapper validator posts would be removed, and the area made 
good by re-sealing over the footings to match with the surrounding apron areas and  
return the area to its original state.  Cable access points may be left flush with access 
covers in place if appropriate. 

 
 
12 
Heritage Impact Assessment • Validators, Wellington Railway Station  


 
4  Assessment criteria 
4.1  Section 176A Outline Plan , Resource Management Act 
1991  
(3) 
An outline plan must show— 
(a) 
the height, shape, and bulk of the public work, project, or work; and 
(b) 
the location on the site of the public work, project, or work; and 
(c) 
the likely finished contour of the site; and 
(d) 
the vehicular access, circulation, and the provision for parking; and 
(e) 
the landscaping proposed; and 
(f) 
any other matters to avoid, remedy, or mitigate any adverse effects on the 
environment. 

In order to consider (3) (f), the following assessment criteria are used. 
4.2  Wellington City District Plan (WCDP) 
Given that the application is for an Outline Plan, there are no specific WCDP 
assessment criteria.  However several of the assessment criteria for Discretionary 
Activities (Restricted) provide a useful guide.  These comprise: 
21A.2.1.3 
The extent to which the work significantly detracts from the values for 
which the building or object was listed.  
21A.2.1.5 
• respects the scale of the original building or object. The Council 
seeks to ensure new work is not visually dominant, particularly where 
rooftop additions are proposed.  
 
• avoids the loss of historic fabric and the destruction of significant 
materials and craftsmanship.  
 
• respects the historic or other values for which the building was listed.  
4.3  Heritage New Zealand Pouhere Taonga (HNZPT) 
An appropriate guide for assessing the installation of validators is HNZPT Heritage 
Guidance Sheet 16  Assessing Impacts on the Surroundings associated with Historic Heritage
2007. 
The relevant criteria from the guide comprise: 

The proposed activity should not visually dominate or distract from the 
qualities of the heritage place. 

The proposed activity should provide for adequate visual catchments, 
corridors or sightlines to the heritage item. 

Any new building should not affect the character and setting of the historic 
building. 

the height, location and proportions of any new building should be 
compatible with the existing historic environment, with heights and 
proportions reflective of the predominant height and proportions of adjacent 
buildings. 
 
 
13 

 

 The size, orientation, scale, massing, density, modulation, and shape of the 
new building or addition should be compatible with the existing historic 
building(s). These elements should relate to surrounding buildings. 
 

 Any new building or addition should adopt materials and colours that relate 
to and use as reference points, the materials, colour and details of adjacent 
buildings and the surrounding areas. 
 

The architectural style should be compatible with the historic design and 
should not imitate, replicate or mimic surrounding historical styles. 
 
 

 
14 
Heritage Impact Assessment • Validators, Wellington Railway Station  


 
5  Assessment of impacts 
5.1  WCDP criteria 
Criteria 
Relevant 
Description of change 
Magnitude of 
value 
effect on all 
platforms 
21A.2.1.3 
Architecture 
The will be no change to the platform 
Minor 
canopies, however there will be a visual 
change to the “simple and airy dignity” of 
the southern end of platforms 2, 3, 4 and 5 
with the installation of the temporary 
validators.  The design of the validators 
comprises 1280 mm (between waits and 
chest high) high by 350 wide by 
approximately 300 deep, cranked posts at 
between 1500 mm and 3000 mm centres.  
These are a little higher than other elements 
on the platform such as the seating and, 
while they will not be a solid barrier they 
will be more visible as they will be located 
across the platform. 
The validators are at an angle to the main 
station building but generally aligned with 
the south end of the platforms.  While angled 
connection with the ends of the platforms  
can be appreciated on drawings, it is less 
obvious on site as the platforms are staggered, 
rather than in a continuous line. 
There will be additional queuing time on 
weekdays of 15 seconds between 7.45 am 
and 8.00 am from the current situation 
without validators for the 15 month trial 
period. 
The colours of the validators are those of 
Metlink which will contrast with the colours 
of the painted elements on the platform, 
which are dark browns.  In addition Metlink 
are currently updating all signage so that it is 
consistent with the traditional colour pallet of 
the station which are dark browns and 
bronze.  The Trax bar and café colours are 
not consistent with the traditional colours of 
the station, however.  The yellow non-slip 
surface around the validators matches that on 
the edges of the platforms. 
 
 
15 

 
Criteria 
Relevant 
Description of change 
Magnitude of 
value 
effect on all 
platforms 
 
Technology and 
There will be no change to the canopies nor 
No change 
engineering 
the concrete lining to the platforms 
 
Rarity 
There will be no change to the uniqueness 
No change 
nor rarity of the platforms.  
 
Representative 
There will be no change to the concrete 
No change 
lined platforms.  
 
Integrity 
The integrity of the platforms will be 
No change 
temporarily reduced the addition of the 
validators. 
 
Context or 
There will be no impact on the group of 
No change 
group 
buildings associated with the railway station. 
 
People 
There will be no impact on the people 
No change 
historically associated with the platforms. 
 
Events 
There will be no impact on events 
No change 
historically associated with the platforms. 
 
Patterns 
The validators demonstrates the current 
No change 
pattern of increasing demand for rail 
passenger use in Wellington. 
 
Public esteem 
The slight increase in queuing times may 
Negligible 
have the potential to impact public esteem 
for the platforms, with a slight delay in 
exiting the station. 
 
Commemorative 
There will be no change to the 
No change  
commemorative values of the platforms. 
 
Education 
The proposal will not affect the education 
No change 
values of the platforms. 
21A.2.1.5 
Scale 
The scale of the validators is insignificant in 
Negligible 
comparison with the platforms and canopies 
 
Loss of historic 
There will be no loss of historic fabric with 
Negligible 
fabric 
the installation of the validators given that 
the surface material is not historic fabric and 
their material in which the footings will be 
installed is not significant.  Services will be 
laid in existing underground ducts. 
16 
Heritage Impact Assessment • Validators, Wellington Railway Station  


 
Criteria 
Relevant 
Description of change 
Magnitude of 
value 
effect on all 
platforms 
 
Respects values 
See above 
 
5.2  HNZPT Heritage Guidance Sheet 16 Assessing Impacts on 
the Surroundings associated with Historic Heritage, 2007   
Clause 
Description and assessment of effect 
Magnitude 
of effects 
a, no visual 
The scale and number of validators will not visually dominate 
Minor 
dominance or 
the platforms, however, as described above there may be 
distraction 
visual impacts on the impression of openness at the southern 
from qualities 
end of platforms 2, 3, 4 and 5.  The bright yellow non-slip 
of heritage 
surface matches that elsewhere on the platforms and will 
place 
create minimal additional distraction. 
b, appropriate 
Given the size and location of the validators there will be 
Negligible 
visual 
little if any visual impact on significant catchments, corridors 
catchments, 
or sightlines. 
corridors or 
sightlines 
c, effect on 
The immediate setting of the platforms will not change. 
Minor 
character and 
However there will be a slight change in the character of 
setting 
platforms southern end of  2, 3, 4 and 5 from being open and 
largely unobstructed accessways from trains to the station, 
with the validators creating a small but permeable barrier that 
will create short, temporary queues to the exit.  
d, 
The existing historic environment comprises the platforms 
Negligible 
compatibility 
and the railway station building.   There will be no impact on 
with the 
the exterior or interior of the railway station but there will be 
existing 
a slight, temporary, visual impact on the southern end of 
environment 
platforms 2, 3, 4 and 5. 
e, 
A definition of compatible is “capable of existing together in 
Minor 
compatibility 
harmony”.   
of new and 
The proposed validators are at an angle generally aligned with 
old 
the southern ends of the platforms, however the platforms are 
stepped rather than a continuous line.  Thevalidators are small 
in relationship to the platforms and canopies, however they 
will provide a slight barrier to egress from the platforms and 
their cranked form is not consistent with other elements on 
the platforms.  
f, adoption of 
As discussed above, the colours are not consistent with the 
Minor 
colours and 
palette of colours used in the remainder of the railway station, 
 
 
17 

 
Clause 
Description and assessment of effect 
Magnitude 
of effects 
materials that 
however the use of metal for the construction of the 
relate to those 
validators is not inconsistent with the platform canopies and 
of adjacent 
furniture such as seating and rubbish bins. 
buildings 
5.3  Evaluation of impact 
Appendix 1 describes a methodology for evaluation of effects.  Based on this 
methodology the following are the assessed effects on building heritage: 
Value of the building 
Magnitude of impacts 
Significance of impacts 
The Railway Station, including 
The highest magnitude of 
Based on the matrix in 
the platforms have a HNZPT 
proposed validators to the south 
Appendix 1 the magnitude of 
category 1 listing and it is listed 
of platforms 2, 3, 4 and 5 is 
impact is assessed as 
on the WCDP. This equates to 
assessed as minor. 
moderate/slight 
a rating of high heritage values, 
based on the ICOMOS Guide. 
 
 
18 
Heritage Impact Assessment • Validators, Wellington Railway Station  



 
6  Conclusions and mitigation 
6.1 
Conclusions 
The magnitude of impacts of the temporary installation of six validators at the 
southern end of platforms 2, 3, 4 and 5 are assessed as being between no change and 
minor.  The significance of impacts to the platforms are assessed as being between 
slight to moderate from both visual and physical impacts and are direct. However, 
as the installation is a trial, the impact will be temporary for the duration of the trial 
and the installation is reversible. 
6.2 
Mitigation measures 
The following are recommended mitigation measures to reduce the impacts of the 
installation: 
• 
modify the design of the validators to a smaller, less bulky design and one that 
could have back-to-back validators to reduce the number of future 
installations required; 
• 
modify the colours to be consistent with the historic colour scheme that is 
currently being applied to signage; 
• 
align the validators with the wall of the railway station rather than the 
proposed diagonal alignment proposed; 
• 
confirm the length of the trial after which the validators will be removed. 
 
 
Ian Bowman 
8 June 2021 
 
 
 
 
19 

 
Appendix 1 
Assessment of values and effects 
Grading of heritage values 
Based on the ICOMOS Guide, the relative importance of built heritage is graded as 
follows: 
Value 
Descriptors 
Very high 
Very high importance and rarity, international scale, 
category 1 HNZ listing 
High 
High importance and rarity, national scale, category 1 HNZ 
listing 
Medium 
High or medium importance, regional scale, category 1 or 2 
HNZ listing or equivalent local authority listing 
Low 
Low or medium importance and rarity, local scale, not 
HNZ listed, local authority listing 
Negligible 
Very low importance and rarity, local scale, not listed 
Magnitude of effect 
The ICOMOS Guide recommends ranking the magnitude of the impact or effect 
(also called the degree of change) as follows: 
• 
Major 
• 
Moderate 
• 
Minor 
• 
Negligible 
• 
No change 
The approach used to assess significance of impact/effect is determined by two 
variables; the value of the receptor, as described below, and the magnitude of change 
upon the receptor. The consideration of value and magnitude takes into account the 
severity of the impact of the project, together with the vulnerability of the receptor 
to change. The table below summarises the possible types of change and their 
magnitude6. 
Effects can be direct and indirect; cumulative, temporary and permanent, reversible or 
irreversible, visual, physical, social and cultural, even economic.   
 
                                                 
6 UK Highways Agency, HA 208/07 
20 
Heritage Impact Assessment • Validators, Wellington Railway Station  



 
 
Possible effects could include changes to use, access, views, topography, structures, 
vegetation, sound environment, approaches and context.  The effect on the heritage 
resource has been ranked without regard to its level of significance.    
Significance of effect 
The matrix below illustrates that combining the magnitude of impact/effect (before 
mitigation) and the heritage significance of the heritage resource will determine the 
extent of impacts of the project.  Mitigation measures however influence the 
evaluation of effect. Where the matrix suggests more than one likely outcome, for 
instance moderate/slight, professional judgement has been used in conjunction with 
the descriptors in the following table to arrive at an appropriate result. 
The scale of possible effects is: 
• 
Very large (beneficial or adverse) 
• 
Large (beneficial or adverse) 
• 
Moderate (beneficial or adverse) 
• 
Slight (beneficial or adverse) 
• 
Neutral 
 
 
21 


 
The Magnitude of Impact shows the potential effect of the project on the heritage 
item or setting without mitigation.  
In general if the effects on all heritage resources were adverse the overall impact 
would be the highest impact.  Conversely if the effects were all beneficial, the 
average level of benefit would be selected, rather than the greatest, as assessments 
should be conservative.  
 
 
22 
Heritage Impact Assessment • Validators, Wellington Railway Station  


 
Appendix 2 
Wellington City District Plan Appendix P Conditions 
The following condition shall apply to the designation of the Wellington 
Railway Station (designation R4) in the Wellington District Plan: 
(i)  Nothing in this designation authorises the demolition or partial demolition 
of the following parts of the Wellington Railway Station: 
•  
the 3 streets facades including the Thorndon Quay addition • the main 
concourse 
• 
the roofline without air-conditioning units 
• 
the plaques at the office entrance 
which are heritage features. Any such proposal shall require Tranz Rail to 
either obtain any necessary resource consent or to seek the alteration of this 
designation by the removal of this condition. For the avoidance of doubt, this 
condition does not cover repairs or maintenance, or additions or alterations, 
or any other activity requiring an outline plan under section 176A. 
(ii)  Prior to the preparation of any proposal to undertake any additions or 
alterations to the identified heritage features of the Wellington Railway 
Station building, Tranz Rail shall meet with the NZ Historic Places Trust to 
discuss the proposal. 
(iii)  Tranz Rail shall provide any subsequent plan(s) of any additions or 
alterations, as specified above, for comment by the NZ Historic Places Trust 
within 15 working days. In the event that there are any points raised by the 
NZ Historic Places Trust, Tranz Rail shall arrange to meet with the Trust to 
discuss the points raised. 
(iv)  Tranz Rail shall provide a copy of any application for outline plan 
approved in respect of the identified heritage features of the Wellington 
Railway Station building to the NZ Historic Places Trust at the same time it 
is lodged with the Council. The Trust will then forward its comments on the 
proposal to the Council within 5 working days.  
 
 
 
 
23 

 
Appendix 3 
Heritage values of the railway station 
The summaries of heritage values is taken from the WCC on-line heritage 
inventory7.   
Aesthetic value 
Cultural value 
The Wellington Railway Station has significant architectural values. The 
design is bold and influenced by the world’s great railway stations, possessing a 
generous forecourt and sweeping driveways leading to the impressive 
colonnade. The internal spaces, particularly the booking hall, are a 
continuation of this tradition. It is a fine example of one the city’s leading 
architectural firms Gray Young, Morton, and Young. It has been recognised 
as one of the best 20th century buildings in New Zealand for its architectural 
qualities. 
The Railway station is associated with a number of historically important 
events including the focal-point of the funeral cortege for Prime Minister 
Michael Joseph Savage, as a casualty clearing station in the aftermath of the 
Wahine disaster, and as part of the home-front defence system during World 
War Two. 
This building has immense townscape value; it defines the Waterloo Quay, 
Featherston, and Bunny Street area. It is a landmark building that is used by, 
and seen by, thousands of commuters daily. 
Group  
With the Old Government Buildings, Waterloo Hotel and Shed 21, it forms a 
small precinct of heritage buildings in the Waterloo Quay/Bunny 
Street/Featherston Street area. 
Townscape  
This building has immense townscape value; it defines the Waterloo Quay, 
Featherston, and Bunny Street area. It is a landmark building that is used by, 
and seen by, thousands of commuters daily. 
Historic value 
Association 
The Railway station is associated with a number of historically important 
events including the focal-point of the funeral cortege for Prime Minister 
Michael Joseph Savage, as a casualty clearing station in the aftermath of 
the Wahine disaster, and as part of the home-front defence system during 
World War Two. 
This building has a range of historic associations that give it significant value. 
It is a fine example of one the city’s leading architectural firms Gray Young, 
Morton, and Young. It was designed as the main Railway Station and Offices 
for the Railways Department and was the culmination of 65 years of railway 
                                                 
7 https://www.wellingtoncityheritage.org.nz/buildings/1-150/44-wellington-railway-station?q= 
24 
Heritage Impact Assessment • Validators, Wellington Railway Station  


 
development in Wellington. 
Scientific value 
Technological 
This building has technical value for the innovation of its construction. It was 
designed using the latest technology utilising steel framing and reinforced 
concrete and bricks to withstand earthquakes. At the time it was constructed 
it was one of the largest buildings in New Zealand and its size, scale, and 
construction on reclaimed land provided a significant building challenge that 
was overcome by the architects and engineers. 
Social value 
Identity Sense Of Place Continuity  
This building is a focus of community identity as it is a major landmark 
building for the city of Wellington. The retention of this building has helped 
to promote a sense of continuity in Wellington with its history. As a major 
development for the Railways Department in the 1930s, it also contributes to 
a sense of continuity for the presence of the railways in Wellington. 
Public Esteem  
This building is held in high community esteem. It has significant heritage 
values for the people of Wellington. 
Sentiment Connection  
This building is a focus of community sentiment and connection – it is a 
public space that is still in use. 
Symbolic Commemorative Traditional Spiritual  
This building has traditional values for the community of commuters who use 
it daily. It has been in continuous use as a station since its construction. 
Level of Cultural Heritage Significance 
Authentic  
This building has authenticity and integrity as it retains significant original 
materials. Modifications and additions have been carried out in mostly 
harmonious ways. 
Rare  
This building is of outstanding heritage significance for its architectural, 
historical, townscape, technical, public education and esteem, values. 
Representative  
This building is an excellent example of the work of Gray Young, Morton, 
and Young designed in the Neo-Classical Revival style with Beaux Arts 
influenced interiors. It is also influenced by Modernism and Art Deco, 
making this building a good representative of New Zealand interpretations of 
these architectural forms. 
Importance  
This is a nationally important building for its architectural, historical, 
 
 
25 

 
townscape, technical, public education and esteem, values. 
 
26 
Heritage Impact Assessment • Validators, Wellington Railway Station