This is an HTML version of an attachment to the Official Information request 'Voltage upgrades to existing lines'.

 
 
 
 
 
 

NORTH ISLAND GRID UPGRADE PROJECT 
 
AMENDED PROPOSAL 
 
APPLICATION FOR APPROVAL 
 
 
 

20 OCTOBER 2006 
 
 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
Contents 

Introduction 9 
1.1 
Purpose of this project 

1.2 
Background to this document 

1.3 
Purpose of this document 

1.4 
References to Original Grid Upgrade Plan 


Approval sought 
11 
2.1 
The Amended North Island Grid Upgrade Proposal 
11 
2.2 
Transpower’s Intended Approach to Project Management 
12 
2.3 
Regulatory context, and structure, of this application for approval 
12 
2.4 
Suggested process and timetable for a draft decision 
13 

Needs assessment 
14 
3.1 
Load forecast 
14 
3.2 
Reliability criteria and timing 
15 

Options considered 
16 
4.1 
Options considered by Transpower in the 2005 Grid Upgrade Plan 
16 
4.2 
Alternatives considered by the Electricity Commission 
16 
4.3 
Developing transmission augmentation projects - technology 
16 
4.4 
Transmission Augmentation Projects 
17 
4.4.1 
Option 1: 220 kV into Pakuranga and Otahuhu. 
17 
4.4.2 
Option 2: 400 kV into the South Auckland urban boundary, 220 kV into 
Pakuranga and Otahuhu 
18 
4.4.3 
Option 3: Augmentation of existing 220 kV assets. 
18 
4.4.4 
Option 4: Augmentation of existing 220 kV assets using high temperature 
conductor 
19 
4.4.5 
Option 5: 400 kV into Otahuhu. 
20 
4.4.6 
Option 6: 220 kV into Otahuhu. 
20 
4.4.7 
Option 7: 400 kV into Pakuranga and Otahuhu. 
20 
4.4.8 
Option 8: 400 kV into the vicinity of the South Auckland urban boundary, 220 
kV into Pakuranga and Otahuhu – early conversion to 400 kV. 
21 
4.4.9 
Common augmentations 
21 
4.5 
Non-transmission alternatives 
21 
4.6 
Limiting the options 
21 
4.6.1 
Diversity 21 
4.6.2 
Capital Cost 
23 
4.7 
Non-qualifying alternatives 
23 
4.7.1 
HVDC alternatives 
23 
4.7.2 
Option 4: Duplexing of Whakamaru-Otahuhu A&B lines with high temperature 
conductor 
25 
4.8 
Electric and magnetic fields: transmission design issues for the options 
25 
4.9 
Alternatives for further analysis 
26 
4.9.1 
Option 1: 220 kV into Pakuranga and Otahuhu 
26 
4.9.2 
Option 2: 220 - 400 kV staged to Pakuranga: 
27 
4.9.3 
Option 3: Duplexing of Whakamaru-Otahuhu A&B lines 
27 
4.10  Selecting the Proposed Investment 
27 
 
October 2006 
© Transpower 2006 
 Page 2 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 

Transpower’s Amended Proposal 
29 
5.1 
Proposal description and timetable 
29 
5.2 
Proposal costs 
33 
5.2.1 
Method for Estimating 90% Cost Limit 
35 
5.2.2 
Assumptions for Key Variables 
36 
5.2.3 
Comparison of Costs with September 2005 GUP 
37 
5.3 
Proposal is a reliability investment 
38 
5.4 
Proposal is an amendment 
39 

The Amended Proposal meets the requirements of the Rules 
41 
6.1 
Rule 13.4.1.1: The Amended Proposal demonstrates GEIP in meeting the 
GRS 
41 
6.1.1 
The GRS 
41 
6.1.2 
Definition of “Good Electricity Industry Practice” 
44 
6.1.3 
GEIP in meeting the GRS 
45 
6.2 
Rule 13.4.1.2: The Original GUP complies with Rule processes 
46 
6.3 
Rule 13.4.1.3: The Amended Proposal satisfies the Grid Investment Test 
48 
6.3.1 
Discussion on Options 1 & 2: new line WKM-PAK 
51 
6.3.2 
Discussion of the potential ranges of outcomes 
51 
6.3.3 
Other non-quantified benefits favouring the proposal 
53 
6.3.4 
Discussion on Option 3: Duplex WKM-OTA A and B 
56 
6.3.5 
Discussion on Option 4: Duplex WKM-OTA A and B with HTC 
58 
6.3.6 
Comparison with non-transmission alternatives 
60 
6.3.7 
Impact of the draft GPS 
61 
6.3.8 
Conclusion of the GIT analysis 
62 

The Amended Proposal is appropriately sequenced and timed 
63 
7.1 
Probabilistic method of determining project timing 
63 
7.2 
Deterministic method of determining project timing 
63 
7.3 
Grid Development Projects 
63 
7.4 
Short-term projects 
64 
7.4.1 
Arapuni-Pakuranga 110 kV line 
65 
7.5 
Appropriate timing 
65 
7.5.1 
Probabilistic approach - Transpower 
66 
7.5.2 
Probabilistic approach – Electricity Commission 
66 
7.5.3 
Deterministic analysis 
66 
7.5.4 
Conclusion on timing 
67 
7.6 
Accounting for delivery risk 
67 
7.7 
Timing of the Proposal 
69 

The Amended Proposal is consistent with wider policy objectives 
70 
8.1 
The purpose of Part F 
70 
8.2 
The GPS 
71 
8.3 
The Commission’s objectives 
83 

Recommendation 84 
 
October 2006 
© Transpower 2006 
 Page 3 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
Appendix A 
Glossary of Terms 
85 
Appendix B 
Cross Reference with September 2005 GUP 
88 
Appendix C 
Cost breakdowns of alternative projects 
93 
Appendix D 
Short Term Augmentation Projects 
101 
Appendix E 
Assessment of the value of deferring investments 
104 
 
 
Attachments 
 

Attachment A 
Diversity Into the Upper North Island  
Attachment B 
Treatment of the Arapuni – Pakuranga Line  
Attachment C 
Project Delivery Risk 
Attachment D 
Technical Assessment of Modified Options  
Attachment E 
Economic Assessment of the North Island Grid Upgrade Project 
Attachment F 
Costing Report  
Attachment G 
High Temperature Conductor Report  
Attachment H1 
Timing of Auckland Grid Supply Upgrade 
Attachment H2 
Pre-Augmentation EUE Assessment (ROAM Report)  
Attachment I 
Otahuhu – Whakamaru A & B Duplexing Report  
Attachment J 
Assumptions List from the Independent Working Party 
Attachment K 
Economic Analysis of Non-Transmission Alternatives 
Attachment L 
Discount Rate for the Grid Investment Test Report 
Attachment M 
Assessment of the Value of Unserved Energy 
Attachment N 
Foreign Direct Investment Effects 
 
October 2006 
© Transpower 2006 
 Page 4 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
Executive Summary 
 
This document represents Transpower’s Amended Proposal for the North Island Grid 
Upgrade Project, and updates (and replaces where defined), Transpower’s original 
proposal that was submitted to the Electricity Commission as part of a full Grid 
Upgrade Plan in September 2005. 
 
Amended Proposal - Works 
The following works make up the Amended Proposal for which Transpower is now 
seeking approval: 
 
The following works make up Transpower’s Amended North Island Grid Upgrade 
Proposal (the Amended Proposal): 
•  Procure, construct, commission and operate a 220 kV switching station in the 
vicinity of Drury and upgrade the 220kV Otahuhu – Whakamaru C line by 
2010.  
•  Procure, construct, commission and operate 350 MVAr of new static reactive 
plant at Otahuhu substation by 2010. 
•  Procure, construct, commission and operate a new double-circuit, steel lattice 
tower, overhead transmission line of approximately 190km from a new 
substation near the existing Whakamaru substation to a new transition station 
in the vicinity of the South Auckland urban boundary, that is capable of: 
o  220 kV operation 
o  future 400 kV operation of around 2700 MVA, subject to later Commission 
approval of and Transpower commissioning of 220 
kV-400 
kV 
transformers and associated switchyards near the existing Whakamaru 
substation and in the vicinity of the South Auckland urban boundary. 
•  Procure, construct, commission and operate two underground cables from the 
new transition station in the vicinity of the South Auckland urban boundary to 
Pakuranga substation that: 
o  are capable of 220 kV operation; and  
o  have a continuous rating of around 660 MVA per set of cables 
•  Procure, construct, commission and operate the necessary substation / 
transition station facilities near the existing Whakamaru substation (Air 
Insulated Switchgear [AIS]), a transition station in the vicinity of the South 
Auckland urban boundary (AIS), and Pakuranga substation (Gas Insulated 
Switchgear [GIS]).  
•  Plan the works, including the acquisition of designations, consents and 
easements to allow for future upgrade to 400 kV operation through future 
addition of: 
o  new 400/220 kV transformers and associated works near the existing  
Whakamaru substation to interconnect with the existing 220 kV system; 
o  a new switchyard in the vicinity of the transition station with new 
400/220 kV transformers and associated works; and 
o  new overhead lines or underground cables to connect the new switchyard 
with the new transition station. 
 
October 2006 
© Transpower 2006 
 Page 5 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
o  new 220 kV underground cables to Otahuhu substation. 
o  extensions to the Otahuhu switchyard(s) 
•  Carry out the works necessary to convert and connect the existing 110 kV 
Otahuhu-Pakuranga line to 220 kV operation, for which it is already designed 
and consented;  
•  Dismantle the existing 110 kV Arapuni to Pakuranga transmission line  
 
•  Obtain designations, easements, resource consents and property purchases 
necessary for all the above works. 
•  Plan for a commissioning date for the major projects above of 2011 to 
prudently allow for potential delays due to delivery, designation, consenting 
and easement risks.  
 
 
Amended Proposal – Cost 
 
Transpower is seeking Electricity Commission approval for costs incurred by 
Transpower in the implementation of the Amended Proposal in accordance with the 
90% limit of project costs in 2011 dollars, estimated at $824 million.  The table below 
provides a breakdown of that cost: 
 
Amended Project   
Cost Category 
$ 2011 (million) 
Investigations 
27 
Property  
116 
Environmental 

Transmission Works: 
  
- Lines 
400 kV line 
203 
 
Up-rate OTA-WKM C 

 
OTA-PAK 110kV Circuits 
1* 
 
Drury 

- Substations 
Otahuhu 
12 
  
Whakamaru 
13 
  
Pakuranga 
55 
 
Drury 
16 
  
Static Compensation 

- Cable  
110 
Dismantling 

Project Management 
34 
Subtotal  
614 
Contingency 
105 
Exchange Rate 
25 
 
October 2006 
© Transpower 2006 
 Page 6 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
Interest During Construction 
80 
TOTAL 
824 
 
*This cost will increase by between $7M and $10M if the Otahuhu diversity project does not proceed. 
 
 
Rule Requirements 
Transpower considers the Amended Proposal as described above meets the 
requirements of the Rules in that: 
 
The Amended Proposal reflects good electricity industry practice in meeting 
grid reliability standards.  
Specifically, the proposal and approach is consistent with international 
practice as being a prudent investment given the size, nature and importance 
of the Auckland load. 
 
The Amended Proposal complies with the Rule processes 
Transpower considers that the Amended Proposal follows the processes set 
out in Section III, Part F of the Electricity Governance Rules. 
 
The Amended Proposal satisfies the Grid Investment Test 
Under the Grid Investment Test, the Amended Proposal has a net market 
cost that is $10 million lower than the closest other option (220 kV into 
Pakuranga).  Under sensitivity analysis across a wide range of assumptions, 
the Amended Proposal was better than other options in a significant majority. 
 
 
Timing 
Two methods for determining the actual timing of the proposed project – probabilistic 
and deterministic.  The outcome from the timing analysis is as below: 
 
Requirement 
Method 
Date 
Probabilistic (EC model): 
2013 
(combining the Grid Reliability Standards and Grid Investment Test) 
Deterministic: 
2013 
(using an n-g-1 security criteria and a prudent forecast) 
 
 
When delivery risk is included, the timing for the project is as below: 
 
Project Delivery:  (allowing for delivery risk) 
2011 
 
 
 
 
 
 
 
October 2006 
© Transpower 2006 
 Page 7 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
Recommendation 
It is recommended that the Commission approve the Amended Proposal on the 
grounds that it: 
•  complies with the Rules; 
•  meets the GRS;  
•  passes the GIT; and  
•  is consistent with GEIP.  
Further, it is the project that is most aligned with the draft changes proposed to the 
GPS, particularly with respect to an emphasis on renewable generation, provision of 
diversity of supply to Auckland and minimisation of the number of corridors required 
for transmission. 
 
 
October 2006 
© Transpower 2006 
 Page 8 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
1 Introduction 
1.1  Purpose of this project 

The purpose of the North Island Grid Upgrade project is to maintain reliable bulk 
electricity supply for the upper North Island. 

The purpose of this document is to obtain approval from the Electricity 
Commission for delivery of this upgrade, and for the recovery of the cost of doing 
so. 
1.2  Background to this document 

On 30 September 2005 Transpower submitted a Grid Upgrade Plan (the “Original 
GUP”) to the Electricity Commission (the “Commission”), which included a 
proposal for a “reliability investment” to construct a new 400 kV double circuit line 
between Whakamaru near Tokoroa, and Otahuhu in South Auckland (the 
“Original Proposal”).  

The Commission commenced a consultation process on the Original Proposal on 
27 April 2006 and also commenced consultation on its draft decision to decline 
approval. 

On 31 May 2006 Transpower informed the Commission of its intention to amend 
the Original Proposal. Transpower also asked the Commission to suspend its 
consideration of the Original Proposal and the Commission agreed to such 
suspension. 
1.3  Purpose of this document 

This document is Transpower’s submission to amend the Original Proposal 
contained in the Original GUP. The amendment relates solely to the Original 
Proposal and, except as set out in this submission, the Original GUP remains 
otherwise unchanged.  

Transpower notes that the approval processes for the other investments 
contained in the original GUP are currently suspended, with the agreement of the 
Commission. Transpower confirms that it may submit amendments to those other 
investments in the Original GUP at appropriate times in the future.  

Transpower suggests the timetable and process for consultation as outlined in 
Section 2.4 in relation to this amendment submission, for consideration by the 
Commission.  Transpower also suggests that the consultation process which was 
suspended on 31 May 2006 be reinstated and continued. 

Transpower notes that the Commission has withdrawn its draft decision to decline 
approval of the application for the Original Proposal as proposed in the Original 
GUP. 
 
1.4  References to Original Grid Upgrade Plan 
10  This proposal is an amendment to the Original GUP of September 2005. A full 
cross reference between the Original GUP and this Amended Proposal is 
provided in Appendix B, and is summarised below: 
 
 
October 2006 
© Transpower 2006 
 Page 9 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
Volume of 
Amended by 
Original 
Section 
this proposal 
GUP 
Vol I 
Executive summary 
Yes 
Asset Management Plan 
No 
Contracted Investments 
No 
Vol II 
400 kV Grid Upgrade Plan 
Yes 
Vol III 
HVDC Inter Island Link 
No 
Vol IV 
Grid Development Proposals 
No 
 
 
 
October 2006 
© Transpower 2006 
 Page 10 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
2 Approval 
sought 
11  Transpower seeks approval from the Commission to recover the actual costs 
incurred in delivering the project through the transmission pricing methodology 
following commissioning of the project.  Transpower will not exceed the amount 
approved for the project without further approval from the Commission.  Costs are 
to include the accrued interest charged on works under construction. 
2.1  The Amended North Island Grid Upgrade Proposal 
12  The following works make up Transpower’s Amended North Island Grid Upgrade 
Proposal (the Amended Proposal): 
•  Procure, construct, commission and operate a 220 kV switching station in the vicinity 
of Drury and upgrade the 220kV Otahuhu – Whakamaru C line by 2010.  
•  Procure, construct, commission and operate 350 MVAr of new static reactive plant at 
Otahuhu substation by 2010. 
•  Procure, construct, commission and operate a new double-circuit, steel lattice tower, 
overhead transmission line of approximately 190km from a new substation near the 
existing Whakamaru substation to a new transition station in the vicinity of the South 
Auckland urban boundary, that is capable of: 
o  220 kV operation 
o  future 400 kV operation of around 2700 MVA, subject to later Commission 
approval of and Transpower commissioning of 220 kV-400 kV transformers and 
associated switchyards near the existing Whakamaru substation and in the 
vicinity of the South Auckland urban boundary. 
•  Procure, construct, commission and operate two underground cables from the new 
transition station in the vicinity of the South Auckland urban boundary to Pakuranga 
substation that: 
o  are capable of 220 kV operation; and  
o  have a continuous rating of around 660 MVA per set of cables 
•  Procure, construct, commission and operate the necessary substation / transition 
station facilities near the existing Whakamaru substation (Air Insulated Switchgear 
[AIS]), a transition station in the vicinity of the South Auckland urban boundary (AIS), 
and Pakuranga substation (Gas Insulated Switchgear [GIS]).  
•  Plan the works, including the acquisition of designations, consents and easements 
to allow for future upgrade to 400 kV operation through future addition of: 
o  new 400/220 kV transformers and associated works near the existing 
Whakamaru substation to interconnect with the existing 220 kV system; 
o  a new switchyard in the vicinity of the transition station with new 400/220 kV 
transformers and associated works; and 
o  new overhead lines or underground cables to connect the new switchyard with 
the new transition station. 
o  new 220 kV underground cables to Otahuhu substation. 
o  extensions to the Otahuhu switchyard(s) 
•  Carry out the works necessary to convert and connect the existing 110 kV Otahuhu-
Pakuranga line to 220 kV operation, for which it is already designed and consented;  
 
October 2006 
© Transpower 2006 
 Page 11 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
•  Dismantle the existing 110 kV Arapuni to Pakuranga transmission line  
 
•  Obtain designations, easements, resource consents and property purchases 
necessary for all the above works. 
•  Plan for a commissioning date for the major projects above of 2011 to prudently 
allow for potential delays due to delivery, designation, consenting and easement 
risks.  
 
 
2.2  Transpower’s Intended Approach to Project Management  
13  On approval of the package listed in paragraph 12, Transpower intends  to: 
•  Deliver the package listed in paragraph 12. 
•  Conduct for the Transpower Board independent periodic audits of its project 
management, procurement and commercial processes to demonstrate that 
cost controls are in place, with a demonstration of the process of business 
improvement in response to any issues identified. 
•  Report periodically to the Transpower Board on progress against both 
expected costs and cost with contingencies, and reasons for any divergence 
(e.g. foreign exchange), allowing for indexed escalation or deflation of linked 
costs.   
•  Transpower acknowledges that to manage the project risk it is essential that a 
high degree of quality assurance is applied in planning, design, manufacture, 
commissioning, testing and maintenance activities in accordance with good 
electricity industry practice.  
14  Transpower recognises that, following approval, if it transpires that it cannot meet 
some aspect of the approved project above, such as the cost ceiling, it has the 
option to seek the Commission’s agreement to an amendment under Rule 17.2.  
2.3  Regulatory context, and structure, of this application for approval 
15  This is an amendment to an application for approval of a reliability investment 
under Part F of the EGRs.  Section 1 introduces the application, while section 2 
specifies what Transpower is seeking Commission approval for. Section 3 sets 
out the need for investment while the options assessed to meet that need and 
Transpower’s Amended Proposal are covered in sections 4 and 5 respectively.  
16  Transpower acknowledges that in order to be approved, the proposed reliability 
investment must satisfy the following criteria: 
13.4.1.1 
“reflects good electricity industry practice in meeting grid 
reliability standards”; and  

13.4.1.2 
“complies with the processes set out in these Rules”; and  
13.4.1.3 
“meets the requirements of the Grid Investment Test”.  
17  The justifications of the Amended Proposal against these three criteria, 
respectively, are described in section 6.  
18  This is followed by section 7 that addresses the timing of the investment.  
 
October 2006 
© Transpower 2006 
 Page 12 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
19  In section 8 Transpower sets out a number of factors that it considers to be 
relevant to the Commission’s assessment of the proposal. 
20  Finally, section 9 sets out Transpower’s recommendations to the Commission. 
2.4  Suggested process and timetable for a draft decision 
21  In order to make full use of the work already done by interested parties in making 
relevant submissions to date on the Original Proposal, Transpower requests that 
the Commission makes it clear to interested parties that they should indicate the 
extent to which of their earlier submissions or comments are to apply to the 
consultation and consideration by the Commission on the Amended Proposal.  
Transpower is of the view this will help make the consultation process more 
timely. If the proposal is to be built in time to minimise negative impact on grid 
security and reliability in the upper North Island, a draft decision is desired by the 
end of 2006. If a draft decision is not reached by Christmas 2006, this may have 
negative implications for the lodging of a Notice of Requirement and acquisition of 
easements by the deadline required by the project implementation timetable, 
which in turn will have knock on effects to the project management of the 
Amended Proposal, which may impact on Transpower’s ability to implement the 
project in time to maintain reliability into the upper North Island.  
 
October 2006 
© Transpower 2006 
 Page 13 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 

Needs assessment  
22  The needs analysis concludes that there is a risk of some electricity demand not 
being supplied to the upper North Island region at times of peak loading from 
2013 and that new investment is required to maintain security of supply into that 
region. This date assumes that projects already approved by the Commission are 
commissioned by their target dates or, alternatively, no later than 2010. In 
particular, these projects include: 
  Establishment of Ohinewai substation (Huntly East); 
  Thermal upgrade of the 220 kV Otahuhu-Whakamaru A and B lines;  
  Bombay bus split ; and 
  The reactive power investments in the Upper North Island as approved by the 
Commission. 
23  The September 2005 Grid Upgrade Plan, Volume 2, Part 2, “Establishing the 
Need for New Investment” provided details on how the need for the new 
investment is assessed. 
24  The technical analysis of transmission options was carried out using the same 
assumptions as in the September 2005 GUP, with the exception of the items 
listed below: 
 
Item 
September 2005 GUP 
Amended Proposal 
Load 
2005 SoO with medium load 
2005 SoO with a ‘prudent’ high 
forecast 
growth scenario 
demand forecast 
Security 
n-1 with allowance for reduced 
Two assessments are made: 
criteria 
generation 

Grid Reliability Standard as 
applied in the draft decision 
on the 400 kV project; and 

n-1 with allowance for the 
Otahuhu CCGT to be out of 
service  
 
Table 3.1: Comparison of assessment assumptions 
3.1 Load 
forecast 
25  The Commission provided the load forecast used for this Amended Proposal. The 
load data is based on the 2005 Statement of Opportunities. This is the same as 
the September 2005 GUP but with a higher growth scenario. The growth scenario 
used was changed for the following reasons: 
•  experience gained from higher than predicted loads during winter 2006; 
•  alignment with good electricity industry practice (i.e. use of a high or ‘prudent’ 
rather than a medium forecast ); and 
•  improvements in forecasting technology and methods. 
 
26  The impact of these changes is that the load forecast used for the Amended 
Proposal is higher than used for the September 2005 GUP, as illustrated below: 
 
 
October 2006 
© Transpower 2006 
 Page 14 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
6,000
5,000
4,000
W
 M 
3,000
ak
Pe

2,000
1,000
2005 SoO with prudent high demand
2005 SoO medium load forecast
-
2007 2009 2011 2013 2015 2017 2019 2021 2023 2025 2027 2029 2031 2033 2035 2037 2039 2041 2043
Year
 
 
Figure 3-1: Comparison of load forecasts used for the Original and Amended Proposals 
3.2  Reliability criteria and timing 
27  The September 2005 GUP used a reliability criterion of n-1 with “an assessment 
of the likely level of actual generation that can be reasonably and prudently 
assumed to be available”. 
28  Two security criteria are used in this assessment: 
•  A probabilistic assessment using the Grid Reliability Standards and the Grid 
Investment Test together to determine the required timing of projects; and 
•  A deterministic criterion that, in Transpower’s view, is consistent with the Grid 
Reliability Standards in that it makes the ‘reasonable’ allowance that the 
largest generator in the Auckland area may not be available at the same time 
peak demand occurs. 
29  The probabilistic assessment is based on the methods outlined in the draft 
determination and calculates the required date for the project by assessing and 
balancing the cost of expected unserved energy (EUE) against the net cost of the 
proposed investment. 
30  The deterministic security level applied to Auckland for the technical analysis in 
the Amended Proposal is n-g-1 where g is the Otahuhu CCGT generator and n is 
the worst single credible transmission line or generator contingency. 
31  Both methods are used because Transpower, when it was preparing this 
application, had concerns that the probabilistic approach would not deliver an 
investment timing that was commensurate with the more widely used and 
historically proven deterministic standard. 
32  Transpower agreed to provide both sets of results to inform a comparison of the 
outcomes. Transpower agrees with the Commission’s conclusion in its draft 
decision that an outcome that meets n-g-1 is appropriate for a critical load centre 
like Auckland.  
 
October 2006 
© Transpower 2006 
 Page 15 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
4 Options 
considered 
4.1  Options considered by Transpower in the 2005 Grid Upgrade Plan 
33  For the Original Proposal submitted as part of the Original GUP in September 
2005, Transpower undertook an analysis of a number of transmission options and 
alternatives to transmission (including generation and demand side management) 
to meet the need for investment. These options included: 
•  330 kV development 
•  500 kV development 
•  Classic HVDC development 
• HVDC 
Light 
development 
•  Under-grounding (either HVDC or HVAC) 
•  Peaking generation plant 
34  The analysis carried out for the Original Proposal regarding these options 
concluded that they did not pass the assessment criteria. This conclusion 
remains unchanged and therefore these options (other than classic HVDC 
development and peaking generation plant) are not analysed further in this 
proposal. 
4.2  Alternatives considered by the Electricity Commission 
35  As part of their assessment of the 2005 Grid Upgrade Plan including the North 
Island 400 kV Upgrade Project, the Commission consulted widely on alternatives 
to the project. 
36  The Commission narrowed the projects down to a short list and ultimately a set of 
alternatives to which the North Island 400 kV Upgrade Project was compared. 
These alternatives comprised 220 kV, 400 kV and HVDC projects1. 
37  This Amended Proposal builds off the analytical results obtained in the 
Commission’s draft determination. 
38  In their draft determination, the most cost effective alternative was the 220 kV 
project, with the HVDC and 400 kV (in 2010) being more costly. 
39  Transpower, in considering alternatives for the Amended Proposal, has used the 
results of the draft decision and selected their best alternative – the 220 kV 
project – as the reference case for the economic analysis.  
40  On the basis that both Transpower and the Commission analysis showed HVDC 
was not as cost effective, an HVDC alternative has not been considered in the 
economic analysis for the Amended Proposal. 
41  Further discussion on the HVDC options is provided in Section 4.7. 
4.3  Developing transmission augmentation projects - technology 
42  The development of possible projects that would meet the demand is challenging 
because of the number of potential options that exist using various permutations 
and combinations of technologies, routes and forecasts. 
                                                      
1 http://www.electricitycommission.govt.nz/opdev/transmis/400kv/400kValternatives 
 
October 2006 
© Transpower 2006 
 Page 16 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
43  The choice of technology is of interest because, over the period of the analysis, it 
is likely that some new or refined technologies will emerge. In addition, the long 
life of the assets involved, and the staging of developments associated with those 
assets, means that there will be a number of decision points through the study 
period. 
44  While there may be a high level of confidence that the first investment is a sound 
decision, technological and other change introduces uncertainties for all future 
decision points. 
45  It is possible that at each of these decision points, the decision makers of the day 
could be faced with compelling reasons to change technologies or to depart from 
what today’s decision makers would regard as a ‘normal course of action’. 
46  Unless the analysis period is short – say 10 years or less – most if not all possible 
projects to meet the need will be subject to the same uncertainties. 
47  The approach taken by Transpower, and the Commission in their draft decision, 
is to select a project option based on a known technology and for future stages 
and development to be consistent with this technology. For example, choosing a 
220 kV line of certain design characteristics would be followed by a similar 
development when required. 
48  Changing technology at a decision point has been avoided in the analysis on the 
assumption that relative rankings of technologies do not change over time. For 
example, if 220 kV technology is less costly than HVDC for a comparative 
capacity, it is assumed this will remain true over the study period unless there is a 
compelling reason to believe otherwise. 
49  The adoption of project staging delivers future opportunities to optimise 
investments to take account of actual outcomes and technological change. 
Staging thus provides opportunities to cap project downside while enabling 
upside. 
50  The development of transmission augmentation projects has thus focused on 
providing: 
•  technology consistency through the study period; and 
•  staging to cap downside risks and provide opportunities to optimise 
future developments. 
51  This approach in defining possible projects is based on using the best available 
information at the time of decision making and delivering a ‘low regret’ outcome.  
 
4.4  Transmission Augmentation Projects 
52  For the Amended Proposal, a total of eight transmission augmentation projects 
were analysed in terms of their technical feasibility. All projects share a common 
set of augmentations and are described in broad terms below: 
 
4.4.1 
Option 1: 220 kV into Pakuranga and Otahuhu.   
53  This project involves: 
  Building a new 220 kV double circuit transmission line between Whakamaru 
and the South Auckland urban boundary with 220 kV underground cables 
from the South Auckland urban boundary to Pakuranga; 
 
October 2006 
© Transpower 2006 
 Page 17 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
  Building additional 220 kV cables from the South Auckland urban boundary to 
Otahuhu when required; 
  Installing series compensation on the transmission line, when required, to 
increase the transfer capacity to the upper North Island; and  
  Building an additional 220 kV double circuit transmission line between 
Whakamaru and Otahuhu when the transfer capacity to the upper North 
Island is exhausted. 
54  The line design chosen for any new 220 kV line options was intended to meet the 
intent of the (draft) GPS requirement 88E for fewer corridors of high capacity. The 
heaviest conductor in use on 220 kV lines at present is Chukar and the line was 
optimised to give the greatest available capacity with this conductor for the lowest 
practicable implementation cost. 
55  The resulting tower heights are up to 58m. Lower tower heights are possible but 
with a significant increase in the number of towers and therefore cost. 
56  Transpower believes if the proposed project can be shown to have greater 
benefits than this optimised 220 kV line, it will also be superior to a sub-optimal 
and higher cost line. 
 
4.4.2 
Option 2: 400 kV into the South Auckland urban boundary, 220 kV 
into Pakuranga and Otahuhu 

57  This project involves: 
  Building a 400 kV double circuit transmission line between Whakamaru and 
the South Auckland urban boundary then 220 kV underground cables from 
the South Auckland urban boundary to Pakuranga;  
  Building additional 220 kV cables from the South Auckland urban boundary to 
Otahuhu when required; and 
  The transmission line would initially operate at 220 kV with series 
compensation to increase the transfer capacity to the upper North Island first 
and then convert to 400 kV operation when required. 
58  The 400 kV line design is a result of optimisation and the requirements to meet 
technical guidelines relating to audible noise, electric and magnetic field 
strengths. Audible noise was a limiting factor and required the adoption of a 
triplex conductor configuration. 
59  The conductor configuration provided a significant increase in the thermal 
capacity of the line, increasing from 1600 MVA of the original proposal to 2700 
MVA for the current design. 
60  The provision of a 400 kV substation in the South Auckland urban boundary 
region allows the full capacity of this line to be utilised in the proposal as 220 kV 
cables can be added as required to match the line capacity. 
 
 
4.4.3 
Option 3: Augmentation of existing 220 kV assets.   
61  This project involves: 
•  Duplexing the 220 kV Otahuhu – Whakamaru A & B single circuit lines; 
and  
 
October 2006 
© Transpower 2006 
 Page 18 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
•  Re-terminating the Otahuhu-Whakamaru A and B transmission lines to 
Pakuranga from a point near the South Auckland urban boundary using 
220 kV underground cables2. 
•  Building additional 220 kV double circuit transmission lines between 
Whakamaru and Otahuhu when the transfer capacity to the upper North 
Island is exhausted. 
62  The degree of strengthening required was determined using a factor representing 
the criticality of the line.  Other factors affecting the degree of strengthening 
required were the age (40-50 years old) and design of these lines. 
63  In this case, Transpower has used the same factors it would apply to any such 
significant 220kV (or indeed, 400kV) line. It is assumed the tower members are 
all in place and structurally competent when calculating the strengthening 
requirements. 
64  Strengthening the towers to any lower level would imply some agreed programme 
to retire the towers and line before a typical line life of 40 (additional) years. This 
is in line with the (draft) GPS requirement to provide solutions that are consistent 
with good electricity industry practice (clause 87C) and provide long-term 
confidence in the reliability of supplies (clause 87 G). 
65  A lower level of structural strength would create uncertainty about both the life of 
the line and its ability to withstand more onerous weather conditions, resulting in 
departures from good industry practice and provision of short-term rather than 
long-term solutions. 
66  Transpower considered a variant to this option whereby the existing assets from 
the transition station would be utilised, saving the cost of one set of cables. This 
option would require additional space to effect the connection between one of the 
duplexed circuits and the two remaining sections of simplex construction 
extending into Otahuhu. 
67  The first suitable location for this transition station would be at Redoubt Road, 
approximately 1 km further south than the currently proposed transition station. 
68  Transpower considered there would be two primary effects of this variant: 
•  Reduction in cost gained by removing one cable, which would be offset 
by the additional costs of between $5M and $8M for the increased 
length of cable; and 
•  A reduction in diversity as only one cable, representing approximately 
660 MVA of capacity, would terminate at Pakuranga. 
69  Given the weight attributed in the (draft) GPS to the provision of diversity, 
Transpower did not consider this variant further. 
4.4.4 
Option 4: Augmentation of existing 220 kV assets using high 
temperature conductor 

70  This project is a variant on Option 3 and involves 
•  replacing the conventional aluminium steel core conductor (ASCR) with 
high-temperature conductor (HTC) on the Otahuhu – Whakamaru A, B 
and C lines. This would permit higher transfer capacities over existing 
assets; and 
                                                      
2 The line section from Otahuhu to the South Auckland urban boundary  would not be 
duplexed and would be disconnected but will remain in place. 
 
October 2006 
© Transpower 2006 
 Page 19 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
•  building an additional 220 kV double circuit transmission line between 
Whakamaru and Otahuhu when the transfer capacity to the upper North 
Island is exhausted. 
 
4.4.5 
Option 5: 400 kV into Otahuhu.   
71  This project involves: 
  Building a new 400 kV double circuit transmission line between Whakamaru 
and the South Auckland urban boundary and 400 kV underground cables 
from the South Auckland urban boundary to Otahuhu.   
  The transmission line would initially operate at 220 kV with sub options as 
follows: 
Sub option 5.1: Converting to 400 kV operation first and then installing 
series compensation to increase the transfer capacity into Upper North 
Island when required; or 
Sub option 5.2: Installing series compensation to increase the transfer 
capacity to the upper North Island first and then converting to 400 kV 
operation when required.  
 
4.4.6 
Option 6: 220 kV into Otahuhu.   
72  This project involves: 
  Building a new 220 kV double circuit transmission line between Whakamaru 
and the South Auckland urban boundary with 220 kV underground cables 
from the South Auckland urban boundary to Otahuhu.   
  Installing series compensation on the transmission line, when required, to 
increase the transfer capacity to the upper North Island.   
  Building an additional 220 kV double circuit transmission line between 
Whakamaru and Otahuhu when the transfer capacity to the upper North 
Island is exhausted. 
 
4.4.7 
Option 7: 400 kV into Pakuranga and Otahuhu.   
73  This project involves: 
•  Building a 400 kV double circuit transmission line between Whakamaru and 
the South Auckland urban boundary and 400 kV underground cables from the 
South Auckland urban boundary to Pakuranga.  
•  Building additional 400 kV cables from the South Auckland urban boundary to 
Otahuhu when required. 
•  The transmission line would initially operate at 220 kV with sub options as 
follows: 
Sub option 7.1: Converting to 400 kV operation first and then installing 
series compensation to increase the transfer capacity into the upper 
North Island when required; or 
Sub option 7.2: Installing series compensation to increase the transfer 
capacity to the upper North Island first and then converting to 400 kV 
operation when required.  
  
 
October 2006 
© Transpower 2006 
 Page 20 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
4.4.8 
Option 8: 400 kV into the vicinity of the South Auckland urban 
boundary, 220 kV into Pakuranga and Otahuhu – early conversion 
to 400 kV. 

74  This project involves: 
  Building a 400 kV double circuit transmission line between Whakamaru and 
the South Auckland urban boundary with 220 kV underground cables from the 
South Auckland urban boundary to Pakuranga.  
  Building additional 220 kV cables from the South Auckland urban boundary to 
Otahuhu when required. 
  The transmission line would initially operate at 220 kV and convert to 400 kV 
operation early-on and then install series compensation when required to 
increase the transfer capacity into the Upper North Island.  
4.4.9 Common 
augmentations 
75  A number of augmentations are common to all of the projects. These common 
projects are drawn from the Annual Planning Report 2006 (Sections 5 to 13). The 
common projects are listed in the technical report (Attachment D). 
4.5 Non-transmission 
alternatives 
76  Three non-transmission alternatives were identified and analysed: 
  155 MW OCGT, 3 shaft, peak load option; 
  240 MW CCGT, single shaft, base load option; 
  380 MW coal fired steam turbine, single shaft, base load option. 
77  Transpower specified the capital, fuel and other assumptions used in the 
analysis. The approach was to bias assumptions towards the generation option to 
ensure any close options would be identified.  
 
4.6  Limiting the options 
78  An assessment of the projects was carried out in order to limit the number of 
projects against which the Grid Investment Test (GIT) would be applied, in 
accordance with schedule F4, item 11 of the Electricity Governance Rules 
(EGR’s). 
79  The criteria used to assess and limit the number of projects were: 
• Diversity; 
and 
•  Capital cost.  
 
4.6.1 Diversity 
80  Following the 12 June 2006 event in which approximately half of the Auckland 
load was lost due to earth-wire conductors dropping across busbars, concerns 
were raised about the dependence of the Auckland load on a single substation. 
81  A review of the Auckland supplies indicated a lack of diversity in relation to: 
• Substation 
switchyards; 
•  Substation locations; and 
•  Transmission line corridors. 
82  Options to address the lack of diversity in relation to each of the three points 
above were documented in the aftermath of the 12 June 2006 event. A more 
detailed discussion on the benefits of diversity is provided in Attachment A. 
 
October 2006 
© Transpower 2006 
 Page 21 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
83  The draft GPS has an objective to provide adequate alternative supply routes to 
larger load centres and to be resilient against low probability but high impact 
events (Clause 80). 
84  Transpower decided to terminate options at Pakuranga but to assess the cost 
differential of providing this diversity against the Original Proposal of initially 
terminating the options at Otahuhu.  
 
New line terminates at 
New line terminates at 
Item 
Pakuranga 
Otahuhu 
($2006 million) 
($2006 million) 
Lines 
215 
215 
Cables 
104 
104 
Substations 
102 
53 
Property 
96 
96 
Consenting 


Investigation 
23 
23 
Project management 
34 
34 
Dismantling 


Total 
586 
535 
Table 4-1. Capital cost comparison of terminating the new line at  
Pakuranga and Otahuhu 
 
85  Table 4-1 shows that the proposal, including a new line terminating at Pakuranga 
in 2011, has a total substation capital cost of approximately $102 million. This 
provides improved diversity of supply for Auckland consumers by reducing 
reliance on the Otahuhu substation. 
86  Alternatively, the new line could terminate at Otahuhu in 2011, which would 
reduce the total substation capital cost to approximately $53 million, but without 
any improvement in diversity.  
87  Good Electricity Industry Practice (GEIP) requires reducing reliance on Otahuhu 
substation in the future and this is reflected in the long term development plans 
for Auckland, which show that Pakuranga substation would be developed by 
2021 under all scenarios. 
88  The cost of providing diversity of supply now, by terminating the new line at 
Pakuranga instead of Otahuhu is $15 million.  This is the difference in present 
value terms between spending $102 million in 2011, or spending $53 million in 
2011 followed by a further $49 million in 2021.  
89  It should also be noted that Pakuranga substation may be upgraded to 220 kV 
sooner than 2021, regardless of where the new line is terminated. This is due to 
the way in which Penrose substation may be reinforced as part of the North 
Auckland and Northland project.  
 
October 2006 
© Transpower 2006 
 Page 22 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
90  One of the possible options identified in the recent North Auckland and Northland 
request for information (RFI) for reinforcing supplies into Penrose is to go via 
Pakuranga at 220 kV. The estimated cost for this option is the lowest of the five 
possibilities presented in the RFI. 
91  If this lowest cost option were to be selected then Pakuranga would have to 
convert to 220 kV by around 2013. Under this scenario, the cost of diversity that 
could be attributed to the North Island Grid Upgrade project is the cost of bringing 
the Pakuranga substation conversion works forward by two years, which is 
approximately $7m. 
92  Based on the above analysis, Transpower believes that terminating future options 
at Pakuranga rather than Otahuhu is sensible, prudent and consistent with the 
(draft) GPS (Clause 80).  Therefore options 5.1, 5.2 and 6 should be discarded. 
4.6.2 Capital 
Cost 
93  Option 7.1 and option 7.2 (400kV into Pakuranga and Otahuhu) although 
technically feasible, are more costly due to their requirement for two 220/400 kV 
substations in Auckland, one each at Otahuhu and Pakuranga. 
94  The capital cost of option 8 (early conversion to 400kV) is higher than for option 2 
due to the comparative costs of building the 220/400 kV substations earlier. 
95  Therefore, options 7.1, 7.2, and 8 should be discarded because they are more 
costly than equivalent options 
4.7 Non-qualifying 
alternatives 
96  The Grid Investment Test defines an ‘alternative’ in clause 19. Transpower 
believes the options defined in section 4.4 meet the requirements of clauses 19.1, 
19.4 and 19.5. 
97  As discussed below, Transpower concludes that HVDC options and the High 
Temperature Conductor option (Option 4) are not likely to proceed (Clause 19.3) 
and not reasonably practicable (Clause 19.2) and therefore do not qualify as 
alternatives. 
4.7.1 HVDC 
alternatives 
98  Based on Tables 8.1 and 8.3 in the Commission’s draft determination, the HVDC 
alternative in 2017 is more costly than either their 220 kV or 400 kV alternatives 
in 2017. On this basis, Transpower has concluded that the 220 kV alternative 
considered in this Amended Proposal is a reasonable surrogate for the HVDC 
option. In other words, if the Transpower proposal is shown to be more cost 
effective than the 220 kV proposal, then it will also be better than the HVDC 
proposal. 
99  Transpower has, as part of its Grid Vision3 considerations, assessed the options 
of relocating the Haywards HVDC converter station to Bunnythorpe or Auckland 
and found HVAC options to be more cost effective. 
100 Transpower has also submitted an HVDC upgrade project in the September 2005 
GUP. It has been suggested that there could be synergies between this project 
and the North Island Upgrade project. 
                                                      
3 The summarised finding of the Grid Vision considerations were published in the Transpower 
documents ‘Future of the National Grid’ December 2003 and October 2004.  
 
October 2006 
© Transpower 2006 
 Page 23 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
101 Moving one pole of the existing HVDC link to a point further north of Haywards, 
including Auckland, would require the construction of a new HVDC line or 
conversion of existing 220 kV lines to HVDC operation. 
102 The time taken to consent a new HVDC line and the comparative costs of 
building a line from Wellington to Auckland, in Transpower’s view, rule this option 
out. 
103 Converting existing 220 kV lines to HVDC operation is costly, would increase 
congestion on the 220 kV grid and potentially restrict the ability to provide for both 
southward transfers and the Wellington load. 
104 In addition to the cost based arguments, Transpower has considered the 
implications of the (draft) GPS. Clause 34A of the (draft) GPS requires that the 
national transmission grid should be planned in such a way as to facilitate the 
potential contribution of renewables to the electricity system and in a manner that 
is consistent with the Government’s climate change and renewables policies. 
Clauses 87A and 87B refer to facilitating renewables and requirements for 
consistency with government policy relating to renewable generation and climate 
change. 
105 There is potential for significant development of renewables – mainly wind and 
geothermal – in the central and southern North Island. Converting existing 220 kV 
lines for HVDC operation would reduce the options for renewables to connect to 
the 220kV grid because of the reduced capacity. Connection to HVDC is 
expensive because of the cost of the converter stations. 
106 HVDC links are generally point-to-point solutions and multi-terminal HVDC 
installations are rare and not considered a mature technology, as indicated by the 
following4: 
“… the adoption of a three terminal dc link of the conventional type 
for the Whakamaru-Auckland system would be a very costly 
solution with limited flexibility for future transmission expansion. 
On the other hand, …, the more flexible PWM multi-terminal 
alternative is not really a contender for the large power rating 
involved. Apart from the components (particularly the cable) costs, 
the switching (due to high frequency) and transmission (due to the 
high current) losses would be extremely high. “ 

 
“New Zealand’s previous commitment to dc (with the Cook Strait 
scheme), was an obvious decision, as there was no practical 
economic ac alternative at the time. However, the case for further 
dc, and particularly the multi-terminal option, is far from obvious at 
the moment and I would suggest a prudent “wait and see” policy in 
this respect.” 
 

107 Transpower has concluded that even if the proposed project does not proceed, it 
is unlikely that this option would be built. The option is thus classed under Rule 
19.3 as not qualifying as an alternative for formal comparison with the proposal. 
                                                      
4 “Use Of HVDC Multi Terminal Options For Future Upgrade Of The National Grid?” Jos Arrillaga 
Emeritus Professor, FIEE, FIEEE, MNZM, 24-May-2006. 
 
 
 
October 2006 
© Transpower 2006 
 Page 24 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
4.7.2 
Option 4: Duplexing of Whakamaru-Otahuhu A&B lines with high 
temperature conductor 

108 This involves:  
  duplexing the Otahuhu – Whakamaru A & B single circuit lines with high 
temperature conductor and connecting to Pakuranga from a transition station 
in the vicinity of the South Auckland urban boundary through 220 kV cables. 
The line section from Otahuhu to transition station will not be duplexed and 
will be disconnected but not dismantled;  
  re-conductor other existing circuits (for example, the Otahuhu - Whakamaru C 
double circuit line) with high temperature conductor as required; 
  utilising series compensation to maximise the sharing of transmission flows 
and extend transmission capability; and 
  details of the project and the sequencing of modelled projects are provided in 
Attachment D. 
109 Although Transpower considers this a non-qualifying alternative, Transpower 
decided to undertake a comparative economic analysis because of the interest 
shown in the option by some landowners and interest groups. The economic 
analysis shows the option is not competitive and reasons for this are discussed 
later in this document. 
110 Aside from the economic results, Transpower has no experience with this type of 
conductor and is not aware of any transmission lines of comparable length where 
the conductor is relied on to operate for extended periods at high temperatures.  
111 Transpower is therefore concerned at the potential risks of conductor failure, 
particularly where the lines in question – the Otahuhu -Whakamaru A, B and C 
lines – all have significant levels of residential under-build. 
112 An increase in magnetic field of between two and three times is associated with 
the substantial increase in current that is required to deliver the deferral benefits. 
Transpower believes that ‘prudent avoidance’ of such substantial increases in 
magnetic fields is appropriate, particularly where there are significant levels of 
under-build. 
113 Transpower has concluded that even if the proposed project does not proceed, it 
is unlikely that this option would be built. The option is thus classed under Rule 
19.3 as not qualifying as an alternative for formal comparison with the proposal, 
although analysis in this application allows this comparison to be made to 
demonstrate the economic cost of the project. 
 
4.8  Electric and magnetic fields: transmission design issues for the 
options 
114 Transpower has adopted the ICNIRP Guidelines5 in designing 400 kV and 220 kV 
options. Transpower expects the current standards to be relatively stable in the 
long term but is aware that some utilities are voluntarily adopting lower standards 
for magnetic field levels. 
                                                      
5 International Commission on Non-Ionizing Radiation Protection;  “Guidelines For Limiting Exposure To 
Time-Varying Electric, Magnetic, And Electromagnetic Fields (Up To 300 Ghz)” – 1998. 
 
 
October 2006 
© Transpower 2006 
 Page 25 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
115 Transpower notes that Option 3 and 4 involve duplexing and increasing the 
current flow in the Otahuhu-Whakamaru A and B lines. These lines have many 
dwellings and other buildings located directly under the lines and within the 
easement boundaries. 
116 While the electric field strength does not change (as the operating voltage 
remains in the same range), the current related magnetic field will increase 
(almost double) from existing levels. Nevertheless, the resulting magnetic field 
strengths remain below the ICNIRP guidelines. 
117 For the options in new corridors, the magnetic field strengths at the corridor 
boundaries are well below those experienced directly under existing lines or 
Option 3 or 4. 
118 A further safeguard is provided for new lines through the purchase of easements 
which ensure that the construction of dwellings or other substantial buildings are 
prohibited within the easement boundaries.  
4.9  Alternatives for further analysis 
119 Limiting the options has resulted in three alternative projects that will be 
compared against each other using the GIT with the aim of selecting a proposed 
investment. 
120 The projects are: 
 
Option 
Description 

220 kV into Pakuranga and Otahuhu  

220 kV – 400 kV  staged to Pakuranga 
400 kV into the South Auckland urban boundary and 220 kV 
cables to Pakuranga and Otahuhu (deferred conversion to 
400 kV) 

220 kV augmentation – duplexing of Otahuhu -Whakamaru A&B 
lines 
 
Table 4-2. Alternative projects for further analysis 
 
121 Each of these projects is, with respect to the Grid Investment Test Rule 19: 
• Technically 
feasible; 
• Reasonably 
practicable; 
and 
•  Reasonably expected to provide similar benefits. 
 
122 These projects are therefore considered as alternatives for the purposes of 
applying the GIT. The alternative projects are summarised below. 
 
4.9.1 
Option 1: 220 kV into Pakuranga and Otahuhu 
123 This involves 
•  Building a new high capacity 220 kV double circuit transmission line 
between Whakamaru and a transition station in the vicinity of the South 
Auckland urban boundary, which will be series compensated when required. 
•  Installing 220 kV cables from the transition station to Pakuranga substation.  
 
October 2006 
© Transpower 2006 
 Page 26 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
•  Building an additional 220 kV double circuit transmission line between 
Whakamaru and Otahuhu (on a new route and preferably providing corridor 
diversity) when the transfer capacity to the upper North Island is exhausted. 
•  Details of the project and the sequencing of modelled projects are provided in 
Attachment D. 
 
4.9.2 
Option 2: 220 - 400 kV staged to Pakuranga:  
124 This involves  
•  Building a 400 kV double circuit overhead line between a new substation 
(Whakamaru North) located near the existing Whakamaru substation and a 
transition station in the vicinity of the South Auckland urban boundary. Initially 
the transition station will be connected to Pakuranga using 220 kV 
underground cables.  
•  Subsequently, additional 220 kV cables will be used to transmit power from 
the transition station to Otahuhu.  The overhead transmission circuits will 
initially operate at 220 kV and convert to 400 kV operation when required by 
building 400 kV/220 kV switchyards at the South Auckland urban boundary 
transition station and also at Whakamaru North.  
•  The overhead transmission circuits will be series compensated when required 
to increase the transfer capacity to the upper North Island as long as possible 
before conversion to 400 kV. When the transfer capacity is exhausted, the 
transmission circuits will convert to 400 kV operation. 
•  Details of the project and the sequencing of modelled projects are provided in 
Attachment D. 
 
4.9.3 
Option 3: Duplexing of Whakamaru-Otahuhu A&B lines 
125 This involves  
•  duplexing the Otahuhu – Whakamaru A & B single circuit lines and 
connecting to Pakuranga from a transition station in the vicinity of the South 
Auckland urban boundary through 220 kV cables. The line section from 
Otahuhu to transition station will not be duplexed and will be disconnected but 
not dismantled;  
•  building a 220 kV line and subsequent investments after the capability 
following the duplexing is exhausted; and  
•  details of the project and the sequencing of modelled projects are provided in 
Attachment D. 
 
4.10  Selecting the Proposed Investment 
126 The three alternative projects identified above as well as the High Temperature 
Conductor variant, were compared against each other using the GIT.  
127 Transpower notes that there has been a considerable amount of discussion on 
the GIT and its interpretation. In light of these discussions, Transpower has 
agreed to use the GIT calculation tool designed by the Commission for selecting 
the Amended Proposal on the understanding that the tool is still evolving. 
Transpower hopes to continue to develop the GIT calculation tool with the 
Commission over time. 
 
October 2006 
© Transpower 2006 
 Page 27 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
128 A detailed description of how the GIT was applied and the results of the analysis 
is provided in Attachment E, which describes how the proposed investment was 
selected as being Option 2: 220 - 400 kV staged to Pakuranga. 
 
 
 
October 2006 
© Transpower 2006 
 Page 28 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 

Transpower’s Amended Proposal 
129 Transpower is seeking approval for the reliability investment as defined in 
paragraph 12.  This project is Option 2, 220 kV - 400 kV staged to Pakuranga, as 
described in the previous section. 
130 Many of the final design details will depend on, amongst other factors (and 
subject to this approval): 
•  The outcomes of the RMA approval process and requisite consultation phase; 
•  The availability of property and easements; 
•  Detailed design of substations,  towers and cable routes; and 
•  Commercial negotiations with suppliers and contractors.  
131 The purpose of this section is to set out a likely form that the proposal would take 
at a more detailed level, for the purposes of public information and the 
Commission’s approval process.  Transpower does not seek approval at the level 
of detail set out in this section, and Transpower confirms that it seeks approval for 
the project as defined and described in paragraph 12.  
5.1  Proposal description and timetable 
132 The proposed investment is for a 400 kV overhead transmission line from 
Whakamaru North into the transition station, with 220 kV cables into Pakuranga 
and Otahuhu substations (option 2 as described above).   
133 This option comprises building the new 400 kV transmission line, along with the 
projects identified as ‘common’ augmentations listed in Attachment D. 
134 The 400 kV transmission line has a system need date of 2013 and will be initially 
operated at 220 kV increasing the transfer limit to the Upper North Island to 
approximately 3,400 MW.   
135 In 2022, the new line may be 55% series compensated, which along with other 
developments, increases the transfer limit to approximately 4,500MW.  A further 
cable connection into Auckland will be provided at this stage. 
136 By 2034, the line needs to be upgraded to 400 kV operation, by commissioning 
new 400 kV sub-stations at Otahuhu and Whakamaru.  Along with other 
developments, the transfer limit increases  to approximately 5,500 MW.  
137 The thermal and the reactive development plans for the proposed investment are 
shown in the tables below and as well as pictorially in Figure 5.1.  
138 The ‘Year’ column represents the year in which the ‘Augmentation’ is required to 
be commissioned for a high load growth scenario.  Lower load growth would 
result in these augmentations being deferred.  With respect to dates, 2013 means 
the augmentation must be commissioned by winter 2013. 
139 Table 5.1 shows the development plan in terms of system needs dates. These 
dates represent the absolute latest that the augmentations must be 
commissioned by and it provides no allowance for risks caused by such events 
as delays in procurement or obtaining consents etc. 
140 Project risk and its effect on the timing in relation to the proposal is discussed in 
section 7. 
 
 
 
 
October 2006 
© Transpower 2006 
 Page 29 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
Year 
Augmentation 
2009  Install 250 MVAr static reactive plant at Otahuhu 
Decommission the 110 kV Arapuni - Pakuranga line 
2010 
Install 100 MVAr static reactive plant at Otahuhu 
Establish Drury switching station and implement thermal upgrade for 
2012 
Otahuhu-Whakamaru C line 
New substation at Whakamaru North 
2 x 400 kV Whakamaru North  – Transition Station circuits operated at 220 kV 
2 x 220 kV Cables, Transition Station - Pakuranga  
Cable Transition Station in the vicinity of the South Auckland urban boundary 
2013 
220 kV sub station at Pakuranga 
Increase operating voltage of Otahuhu -Pakuranga to 220 kV * 
Install 3 x 120 MVA supply transformers at Pakuranga 
First 220 kV Pakuranga-Penrose Cable  
2014  Reconductor 110 kV ARI-HAM 1 & 2 to Nitrogen 75°C conductors. 
2016 
Install 100 MVAr static reactive plant at Otahuhu 
2017 
Install 100 MVAr static reactive plant at Otahuhu 
Second Pakuranga-Penrose cable  
2018 
Install 100 MVAr dynamic reactive plant at Otahuhu 
2020  Install 100 MVAr static reactive plant at Huntly 
2 x 55% compensation on Whakamaru -Transition Station  circuits 
Install 110 kV OTA-WIR cable; close the  WIR bus breaker  
2022  1 x 220 kV Penrose- Otahuhu cable 
Commission switching station at South Auckland urban boundary 
1 x 220 kV Transition Station  - Otahuhu cable 
Install 200 MVAr static reactive plant at Otahuhu 
2024 
Second 220 kV Otahuhu - Transition Station  cable 
Install 100 MVAr dynamic reactive plant at Otahuhu 
2025 
Second Roskill 220 / 110 kV transformer 
2027  Re-conductor HAM-BOB 110 kV circuits to Nitrogen Conductors. 
 
Continued on next page 
 
 
 
 
October 2006 
© Transpower 2006 
 Page 30 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
Install 100 MVAr static reactive plant at Huntly 
2028  Thermal upgrade of HLE- Whakamaru section of Otahuhu - Whakamaru C line 
Second 220 kV Penrose - Roskill cable 
Install 150 MVAr static reactive plant at Otahuhu 
2029 
Install 20 Ohm reactor on Otahuhu - Whakamaru A&B lines 
2031  Install 100 MVAr static reactive plant at Huntly 
Install 300 MVAr dynamic reactive plant at Otahuhu 
2032 
Forced cooling on Transition Station  -Pak cables 
Install 150 MVAr static reactive plant at Otahuhu 
2033 
Third Roskill 220 / 110kV transformer 
Forced cooling on 220 kV Transition Station  - Otahuhu cables 
400 kV sub station at Whakamaru North 
400 kV sub station at the transition station in the vicinity of the South Auckland 
urban boundary 
Operate Whakamaru - Transition Station  at  400 kV  
2034 
6 x 400/220 kV 600 MVA transformers at Transition Station   
6 x 400/220 kV 600 MVA transformers at Whakamaru 
Reduce series compensation on the 400 kV line to 45% 
Second 220 kV Penrose-Otahuhu cable 
New Otahuhu 220/110 kV transformers in parallel with T3 and T5 
2038 
1 x 75 MVA phase shifting transformer on Arapuni-Bombay circuit 
Install 300 MVAr static reactive plant at Otahuhu 
2042  Post contingency Operational Measures to reduce Transition station - Otahuhu 
loading 
 
*  Transpower will consult on both AIS and GIS switchyard at Pakuranga.  Only if there is a clear 
public preference for a GIS switchyard at Pakuranga will the designation be limited to this option, 
and thus the GIS referred to above would have to be built. 
 
** This list excludes augmentations that are common to all of the alternatives. For the common 
projects, refer to Attachment D (Technical Assessment of Modified Options) 
 
Table 5-1: System need dates under the proposed investment,  
showing projects included in this proposal in bold. 
 
 
 
 
 
 
 
October 2006 
© Transpower 2006 
 Page 31 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
HOB
ROS
New 220 kV cables
New Transformer 
Existing 110 kV 
Reconnected 
New 220 kV cable
New 220 kV 
Decommissioned
circuits operated 
And Voltage Uprated
& series Reactor
New 220 kV 
Substation
at 220 kV
cables 
139/114 MVA
PEN
PEN
PAK
A
A
Replace OTA 
PAK
V
V
A
A
V
T2 & T4 
New 220 kV cables
V
 M
 M
9
9
 M
 M
3
7
46
46
7
MNG
ROS
HEN SWN
4
2/
2/
1/1
2/3
49
49
19
38
Uprated Circuits
Decommissioned
OTA
OTA Split
Uprated 
A A
Circuits
New cable
-OT
A
A
A
A
Y
V
V
V
TAK
A
HL
 MV
A
A
Bussing HLY-OTA 
4 M
V
New 220 kV 
 M
V
WIR
95 M
14
2
cables
A at Drury 
A
 MV
2
V
/6
/61
5/6
0
4 M
4 M
9
1/9
7
76
670
6
New 220 kV 
01/
10
95 M
0/61
0/61
cables
1
Series 
GLN
Drury
/6
Reactors
67
67
BOB
5
6
ORM
7
New Transformer 
HLY
HLE
A
A
Uprated 
V
V
Circuits
ORM
New 220 kV 
Substation 
 M
 M
2
WES
2
/12
/12
Bussing OTA-WKM C 
New 400 kV 
134
134
line at HLE
Substation 
A
A
 MV
TWH
HAM
 MV
HAM
1
5
/114
0
A
A
A
A
62/
14
V
 MV
 MV
0
Series 
 MV
 M
70
7
A
A
Compensation 
V
V
2
2
/4
2
2
3/4
1
1
4/
493
49
14 M
14 M
34/
/6
/6
1
13
Uprated Circuits
0
0
67
67
ARI
 A
 C
M
Phase Shifting 
Transformer
SFD
-WK
New 400 kV circuits 
Y-
- initially operated at 220 kV
KIN
HTI
ONG
HL
OTA
M B
M A
K
K
New 400/220 kV substation
-W
-W
OTA
OTA
WKM
MTI
MOK
Uprated Circuits
WKM
Uprated Circuits
Legend
TMN
TKU
WRK
ATI
400 kV
NPL
220 kV
Bussing second HLY-SFD 
110 kV
circuit at TMN
Cables
WKM
Generating Station
SFD
WKM
Substation
Common Augmentations
Option Specific Augmentation
BRK
Option Specific Decommission
 
 
Figure 5-1. Single Line Diagram for Proposed Investment 
 
 
 
October 2006 
© Transpower 2006 
 Page 32 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
5.2 Proposal 
costs 
141 Transpower is seeking Commission approval for costs incurred by Transpower in 
the implementation of the Amended Proposal.  The estimated capital cost for the 
Amended Proposal is $585m in $2006, including contingencies ($509m excluding 
contingencies).   
 
 
Estimated 
Estimated 
Cost 
Category 
Item 
Cost $m 
including 
(2006) 
Contingencies 
$m (2006) 
Preliminary engineering, environmental 
Investigations 
22 
22 
and property work. 
Property 
Acquisition of property rights 
96 
96 
Acquisition of designations and 
Environmental  


resource consents. 
2x400kV circuits from Whakamaru to a 
Transmission 
transition station in the vicinity of the 
168 
210 
Works 
South Auckland urban boundary 
operated at 220kV 
 
Other Lines Works 

7
  
Substation Works 
87* 
101* 
  
Cable 
91 
104 
Dismantling 
Arapuni to Pakuranga Line 


Project 
 
28 
33 
Management 
Total 
  
509 
585 
 
*This cost will increase by between $7M and $10M if the Otahuhu diversity project does not proceed. 
 
Table 5-2. Estimated Costs for Proposal 
(The projects included in these cost estimates are those described in Table 7-2.) 
 
142 To determine an amount for its approval request Transpower has estimated the 
mid-point and 90% limit of project costs using a simulation technique (see detail 
in 5.2.1) on commissioning of the first major stage of the proposal. 
143 The mean project cost estimate in December 2011 dollars is $764M.  The 90% 
limit of project costs has been estimated at $824M.  The chart below shows the 
distribution of project costs.  
 
 
October 2006 
© Transpower 2006 
 Page 33 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
Distribution of Simulated Capital Cost
8%
10%=$713m
Mean=$764m
90%=$824m
7%
6%
5%
y
nc
ue 
4%
q
re
F

3%
2%
1%
0%
654
677
699
722
744
767
789
811
834
856
879
$m 2011
 
Figure 5-2. Distribution of project costs 
 
144 The following table shows the Amended Proposal costs without simulation.  The 
total cost is expected to equal $764M, in $2011, which includes a $117M inflation 
adjustment. 
Fully 
Fully 
Cost 
Exchange 
Interest 
Conting
Adjusted 
Adjusted 
Category 
$m 
Rate 
During 
Inflation 
encies 
Cost $m 
Cost $m 
(2006) 
Variation 
Construction 
(2006) 
(2011) 
Investigations 
22 



22 

27 
Property 
96 


12 
108 
20 
128 
Environmental 






11 
Lines 
174 
43 

29 
246 
44 
290 
Substations* 
87 
13 


104 
18 
122 
Cable 
91 
13 


112 
21 
133 
Decommissioning 







Project 
Management 

28 



41 

47 
Total 
509 
76 

62 
647 
117 
764 
 
*These costs will increase by between $7M and $10M if the Otahuhu diversity project does not proceed. 
 
Table 5-3. Proposal costs without simulation 
 
145 Including simulation, a 90% upper limit on project cost is expected to equal $824 
M, in $2011, which includes a $141M inflation adjustment. 
 
 
 
 
 
 
 
October 2006 
© Transpower 2006 
 Page 34 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
Cost 
Exchange 
Interest 
90% Cost 
90% Cost 
Conting
Category 
$m 
Rate 
During 
Limit 
Inflation 
Limit 
encies 
(2006) 
Variation 
Construction 
$m (2006) 
$m (2011) 
Investigations 
22 



22 

27 
Property 
96 


13 
109 
23 
132 
Environmental 






11 
Lines 
174 
46 
14 
30 
264 
52 
316 
Substations* 
87 
18 


114 
22 
136 
Cable 
91 
16 


119 
27 
146 
Decommissioning 







Project 
Management 

28 



41 

50 
Total 
509 
87 
21 
66 
683 
141 
824 
 
*This cost will increase by between $7M and $10M if the Otahuhu diversity project does not proceed. 
 
Table 5-4. Proposal costs with simulation 
 
5.2.1 
Method for Estimating 90% Cost Limit 
146 The Monte Carlo technique was used to estimate the mid-point and 90% limit on 
project costs.  The cost of the Amended Proposal is simulated a large number of 
times, and the frequency of simulation results is used to establish costs for a 
given level of likelihood. 
147 Costs for projects and other elements of the proposal are broken down into 
components including: 
•  Costs denominated in New Zealand dollars 
•  Costs denominated in other currencies 
• Property 
costs 
 
148 The projects occur on a staggered basis and costs have been streamed over 
various dates to reflect project timing, and to allow calculation of interest during 
construction6. 
149 The model takes into account the following variables: 
• Exchange 
rates 
• Inflation 
•  Real interest rates 
•  Property cost escalation 
• Price 
accuracy 
• Scope 
contingencies 
 
150 Cost estimates also include an allowance for interest during construction. 
 
 
 
 
 
                                                      
6 For property purchases it has been assumed that if the proposal is approved the cost of land and easements can be 
included in Transpower’s revenue base once route acquisition has been completed.  Interest during construction 
costs will be higher if these costs must be incurred until completion of the transmission line, and lower if 
Transpower can recover these costs from the time of the land acquisition. 

 
October 2006 
© Transpower 2006 
 Page 35 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
5.2.2 
Assumptions for Key Variables 
Exchange Rates 
151 Point estimates of capital cost were based on 10 year average exchange rates.  
These were subsequently adjusted to smoothed spot rates using the average 
exchange rate 20 business days either side of 30 June 2006.  For the simulation 
runs exchange rates have been sampled from daily exchange rates over the 
period 1 July 1996 to 30 June 2006.  This approach ensures that the simulated 
exchange rates and cross-rates have a similar mean and variance to historical 
rates.  Over a large number of simulations the exchange rate will be close to the 
10-year average rate. 
 
Inflation 
152 Inflation is modelled by drawing from a uniform distribution in a range from 2% to 
4%. 
 
Real Interest Rates 
153 The real interest rate is modelled by drawing from a uniform distribution in a 
range from 6% to 8%.  The nominal interest rate is the real interest rate plus the 
inflation rate. 
 
Property Cost Escalation 
154 Real property cost escalation (i.e. price escalation over and above the inflation 
rate) is modelled by drawing from a uniform distribution in a range from 2% to 
4%. 
 
Price Accuracy 
155 As regulatory approval occurs prior to the issuing of tenders, there is uncertainty 
over the price of equipment to be installed.  This has been modelled by 
expressing the accuracy of estimates as a triangular distribution.  The point 
estimate of costs is given as the most likely outcome, and lower and upper 
bounds are expressed as percentages of the midpoint. 
Lower 
Upper 
Price Accuracy Parameters 
Limit 
Limit 
Static compensation 
-12.5%
12.5% 
Decommission 110kV ARI-PAK Line 
-5.5%
5.5% 
Drury Switching Station 
-12.5%
12.5% 
OTA-WKM C thermal upgrade 
10.0%
10.0% 
2x400kV WKM-ORM ccts operated at 220kV 
-5.5%
5.5% 
WKM & WKN Sub work 
-11.5%
11.5% 
OTA Enabling Work 
-10.0%
10.0% 
OTA Subs Work 
-10.0%
10.0% 
2x220kV ORM-PAK cables 
-10.0%
10.0% 
Cable Termination at ORM 
-11.5%
11.5% 
220kV substation at PAK 
-9.5%
9.5% 
Convert OTA-PAK 110kV ccts to 220kV 
-10.0%
10.0% 
 
Table 5-5. Price accuracy 
 
October 2006 
© Transpower 2006 
 Page 36 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
Scope Contingency 
156 Scope contingencies have been included to cover two distinct categories of costs: 
Costs for works which are planned, but which have not been included in the cost 
estimates except through a general allowance, and costs for works not 
anticipated at the time costs were estimated. 
157 For the purpose of simulation modelling, scope contingencies have been treated 
as fixed percentages, i.e. scope contingencies as a percent of costs do not vary 
between simulations.  They may vary in dollar terms because of changes in other 
input variables.  This is consistent with the definition of expected costs used in 
the economic analysis. 
5.2.3 
Comparison of Costs with September 2005 GUP 
158 This subsection compares the approval cost estimates in Transpower’s original 
April 2005 submission, and September 2005 GUP7 with the new approval cost 
estimates for the Amended Proposal. A straight comparison is meaningless as 
the GUP cost estimates were expressed in nominal terms and the amended 
project costs are in December 2011 dollars, consistent with the Commission’s 
approach in its Draft Decision. 
April 2005 Submission/ 
Amended Project 
Cost Category 
Sept 2005 GUP 
Sept 2006 
$2005
Nominal  $2011
$2006 
$2011 
Investigations 
20
  
25
22 
27
Property    
97
  
121
96 
116
Environmental 
11
  
14

8
Transmission Works 
  
  
  
  
  
- Lines  400kV Line 
120
  
150
168 
203
  
Uprate section of Ota-Wkm C 
  
  
  

4
  
Ota-Pak 110kV Circuits 
  
  
  
1* 
1*
  
Drury Switching Station 
  
  
  

2
- Subs 
Otahuhu 
66
  
82
10 
12
  
Whakamaru 
33
  
41
11 
13
  
Pakuranga 
  
  
  
46 
55
  
Drury Switching Station 
  
  
  
13 
16
  
Static Compensation 
  
  
  

8
- Cable  
84
  
105
91 
110
Dismantling 
4
  
5

5
Project Management 
25
  
31
28 
34
Subtotal    
460
460
575
509 
614
Inflation 
  
  
39
104*
  
141*
Contingency 
60
65
75
87 
105
Exchange Rate 
-6
-6
-7
21 
25
Interest During Construction 
59
64
74
66 
80
Total 
  
573
622
716
683 
824
Adjustment for difference in Limits** 
  
  
-7
  
  
Total 
  
573
622
709
683 
824
 
*This cost will increase by between $7M and $10M if the Otahuhu diversity project does not proceed. 
Table 5-6. Cost summary 
                                                      
7 Volume 2, Section 5, Tables 6.1 and 7.2. 
 
October 2006 
© Transpower 2006 
 Page 37 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
Note that for the orange columns inflation figures are included to show the scale of the price 
adjustments made to the original estimates.  They are not included in the summation. 
** The April 2005 estimates were 95% upper limits compared to the 90% limit Transpower is now using.  
Analysis of the September 2005 GUP calculations suggest that the difference between 95% and 90% 
cost limits would have been $7m in $2011.  
 
159 Table 5-6 shows both sets of figures adjusted to December 2011.  These are the 
orange columns.  The other columns show the amounts in dollars at other points 
in time so that they can be compared to costs in the September 2005 GUP, and 
this proposal. 
160 The important differences between the costs for the original proposal and those 
for the Amended Proposal are: 
•  Lines costs rise $60m – reflecting the higher carrying capacity of the line, and 
costs to convert the Otahuhu – Pakuranga 110kV lines to 220kV, and to 
up-rate sections of the Otahuhu-Whakamaru C line to 80˚C. 
•  Substation costs drop $19m.  This would be more but the 2005 GUP 
submissions did not include short term augmentation projects, or static 
compensation costs prior to the major project. These costs amount to $26m. 
•  Contingency allowances rise $30m.  This reflects the use of fixed “Scope” 
contingencies in the estimates for the Amended Proposal.  In preparing the 
2005 GUP estimates these were assumed to be variable with a mean of zero.  
•  Exchange rate allowances rise $32m.  This reflects an alternative treatment of 
exchange rate volatility.  The original estimates covered Transpower for 
relatively modest exchange rate swings. 
 
5.3  Proposal is a reliability investment 
161 Part A of the Electricity Governance Rules defines a reliability investment as 
“investments by Transpower in the grid, or alternative arrangements by 
Transpower, the primary effect of which is, or would be, to reduce expected 
unserved energy
”. Expected unserved energy is defined in Part A as meaning “a 
forecast of the aggregate amount by which the demand for electricity exceeds the 
supply of electricity at each grid exit point as a result of likely planned or 
unplanned outages of primary transmission equipment”. 
162 The need for new investment to reduce expected unserved energy in the upper 
North Island is demonstrated in Part II, Volume II of Transpower’s September 
2005 GUP and in section 3 of this proposal. The “needs analysis” in the original 
Volume II of the GUP concluded that “there is some risk of electricity demand not 
being supplied into the upper North Island at times of peak loading from 2010 and 
that new investment is required to maintain security of supply into the region.”8 
The Commission, in paragraph 5.1.6 of its draft decision on the original Volume II 
proposal, stated it was “satisfied … that the proposal would have the primary 
effect of reducing unserved energy and therefore it is appropriate to consider it as 
a reliability investment under rule 13.” 
163 The Amended Proposal outlined in this application is also designed to reduce the 
expected unserved energy identified in the needs analysis referred to above, 
therefore the Amended Proposal is, in Transpower’s view, also a reliability 
investment. 
                                                      
8 P5, Volume II, Transpower GUP, September 2005 
 
October 2006 
© Transpower 2006 
 Page 38 of 106 


NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
164 The Amended Proposal is for a new transmission link between 
Pakuranga/Otahuhu and Whakamaru. The Commission’s determination on the 
Core Grid defines this line as being included within the Core Grid. Because the 
line is part of the Core Grid both parts of the Grid Reliability Standards (GRS) , as 
defined in the glossary of this application, are relevant to this Amended Proposal. 
That is both the probabilistic (identified in rule 4.1 of Schedule F3) and the 
deterministic (identified in rule 4.2 of Schedule F3) standards are applicable to 
the assessment of the Amended Proposal. 
 
5.4  Proposal is an amendment 
165 On 31 May 2006 Transpower informed the Commission of its intention to amend 
the 400 kV Project in response to, among other things, various requests for 
information from the Commission. This current application, of an amendment to 
the 400 kV Project in the Original GUP, has been agreed with the Commission. 
166 A salient difference between the Original Proposal and the Amended Proposal is 
that the new line initially terminates into Pakuranga substation, with a termination 
into Otahuhu being provided in the future. This is illustrated in the diagram below. 
The Original Proposal included the termination of the new line into Otahuhu only.  
 
 
Figure 5-3. New line into Auckland (indicative only) 
 
167 Other principal ways in which the Amended Proposal varies from the Original 
Proposal include: 
•  The overhead line component is amended such that it will be staged.  Rather 
than operate at 400 kV from commissioning, it will operate initially at 220 kV. 
When it becomes economic to do so, approval will be sought for installation of 
the 220/400 kV transformers to enable 400 kV operation; 
 
October 2006 
© Transpower 2006 
 Page 39 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
•  The transmission capability of the overhead line has been increased to 
2700 MVA to improve the utilisation of the transmission corridor and defer the 
need for a further corridor; 
•  The underground cable components are amended to operate at 220 kV rather 
than 400 kV; 
•  Short term projects are included in the proposal to defer the need for the 
major project to 2013 (details in paragraph 12); and 
•  Commissioning of the short term projects is targeted for 2010 with the major 
works in 2011; and  
•  A new 220kV substation is required at Pakuranga. 
168 This application presents for approval this Amended Proposal by reference to the 
Asset Management Plan and information on investment contracts contained in 
the Original GUP. 
 
 
 
October 2006 
© Transpower 2006 
 Page 40 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 

The Amended Proposal meets the requirements of the 
Rules 

 
169 Rule 13.4 sets out three criteria that a proposed reliability investment must meet 
in order to gain approval from the Commission. These criteria, and a discussion 
as to why Transpower’s Amended Proposal meets these criteria, are set out in 
the following subsections. 
 
6.1  Rule 13.4.1.1: The Amended Proposal demonstrates GEIP in 
meeting the GRS 
170 The first criteria for approval under Rule 13.4.1 requires that the proposed 
reliability investment: 
13.4.1.1 
“reflects good electricity industry practice in meeting grid 
reliability standards” 

171 In its draft decision, the Commission considered that Rule 13.4.1.1 is not entirely 
clear, but took a view that in determining whether the Rule has been complied 
with, the Commission must turn its mind to whether it is satisfied that the 
proposed investment both:  
•  meets the GRS; and  
•  in so doing, reflects good electricity industry practice (GEIP).  
172 Transpower agrees that the proposed investment must meet both of these 
criteria.  Transpower’s view is that this GEIP applies in addition to how one 
interprets the GRS, i.e. that under this Rule GEIP and the GRS are not 
independent.  In other words, this rule is more than two independent rules “reflect 
good electricity industry practice” and “meet grid reliability standards”. 
173 The following three sections are therefore ordered to cover in turn: 
• the 
GRS 
•  reflects GEIP; and 
•  reflect GEIP in meeting the GRS 
6.1.1 The 
GRS 
174 The GRS are contained in Schedule F3, which states that:  

“For the purpose of clause 3, the grid satisfies the grid 
reliability standards if:  

4.1 
the power system is reasonably expected to achieve a 
level of reliability at or above the level that would be 
achieved if all economic reliability investments were to be 
implemented; and  

4.2  
with all assets that are reasonably expected to be in 
service, the power system would remain in a satisfactory 
state during and following any single credible 
contingency event occurring on the core grid.”  

175 Rule 4.1 is the so-called “probabilistic limb of the GRS”, and Rule 4.2 the 
“deterministic limb of the GRS”.  On a case by case basis, whichever limb 
provides the higher standard drives the reliability standard. 
 
October 2006 
© Transpower 2006 
 Page 41 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
176 Transpower notes that on occasion the terms “economic limb” and “standards 
limb” of the GRS have been used instead.  This is potentially misleading, as both 
limbs have economic and standards-based components in their formulation and 
application.  
177 The deterministic limb provides a safety net for the probabilistic limb for 
contingencies on the core grid.  
The probabilistic limb of the GRS 
178 As defined in the GRS: 
“Economic reliability investments” means investments in the grid and 
transmission alternatives that would satisfy the Grid Investment Test:  

8.1.  
reading each reference to a proposed investment in the 
Grid Investment Test as a reference to the grid 
investment or transmission alternative (as the case may 
be); and  

8.2.  
having regard to part C of these rules including the policy 
statement set out in schedule C4. 

179 The proposal (and the alternatives under the GIT being considered) is for a grid 
investment.  For the proposal, clause 4.1 of the GIT therefore implies: 
the power system is reasonably expected to achieve a level of 
reliability at or above the level that would be achieved if: 

•  all investments in the grid that would satisfy the GIT were to 
be implemented,  
•  having regard to part C of these rules including the policy 
statement set out in schedule C4. 
180 The proposal satisfies the GIT, as detailed in section 6.3 “Rule 13.4.1.3: The 
Amended Proposal satisfies the Grid Investment Test”, so the first part of the test 
would be achieved were the proposal to be implemented. 
181 The relevant components of Part C including C4 of the Rules detail the manner in 
which security is maintained for contingent events.  In essence, the system is 
operated in real time to a security level of n-1 with all assets made available to 
the System Operator.  It is the asset owners, principally the grid owner and 
generators, who determine what assets are made available.   
182 These are not reasons not to use the GIT as part of the reliability standards.  
However they are relevant factors in considering how to interpret the deterministic 
“safety net” limb of the GRS.   
183 For example, if one had total confidence in the accuracy and applicability of the 
GIT, one would not need a deterministic safety net.  This is not the case in New 
Zealand, nor anywhere to Transpower’s knowledge.  The Rules accept that this is 
the case, as did the Commission in recommending those Rules: 
184 Limitations of a pure probabilistic approach and a similar Grid Investment Test 
have been recognised by VENCorp, the transmission planner for Victoria, 
Australia: 
“This 25 year vision indicated: 
• The long term economic benefits of efficient high capacity 
infrastructure such as the 500 kV electricity transmission network 
established by Victoria three decades ago.  It is not clear that this 

 
October 2006 
© Transpower 2006 
 Page 42 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
backbone network would have emerged if current transmission 
planning approaches had been used at the time
.9 

 
The deterministic limb of the GRS 
185 The “deterministic limb” of the GRS requires that  
The grid satisfies the grid reliability standards if, with all assets that 
are reasonably expected to be in service, the power system would 
remain in a satisfactory state during and following any single credible 
contingency event occurring on the core grid.”  

186 This is akin to the manner in which the system is operated, as described above. 
187 Transpower has interpreted this deterministic limb to mean n-1 (the power system 
would remain in a satisfactory state during and following any single credible 
contingency event occurring on the core grid) with one generator out of service 
(with all assets that are reasonably expected to be in service).  This standard is 
known as n-g-1, being short-hand for n-1 with the largest generator out of service. 
188 The Commission, in its draft decision, appears to have misinterpreted 
Transpower’s position, stating that: 
“[Transpower considers it] reasonable to expect that a generating unit 
(eg a unit at Otahuhu B) will always be out of service. The 
Commission accepts that generating plant will be out of service from 
time to time, but does not consider it reasonable to assume that one 
generating unit will always be out of service” 

189 For clarity, Transpower does not consider it reasonable to expect that a 
generating unit will always be out of service.  Transpower does consider it 
reasonable and prudent to plan on being able to maintain n-1 security when a 
generating unit (e.g. a unit at Otahuhu B) is out of service. 
190 The Commission, in its draft decision, argues that its interpretation of the GRS 
delivers the same outcome as Transpower’s interpretation of the deterministic 
limb of the GRS: 
“As it happens, while Transpower’s and the Commission’s 
interpretation of the GRS is different, there is no practical difference in 
this case: in analysing the need for investment in respect of providing 
supply into Auckland, both approaches result in the same n-g-1 supply 
security outcome” 

191 Transpower does not fully agree with this assessment, as Transpower believes 
that GEIP in meeting the GRS requires meeting n-g-1 at a prudently high demand 
forecast, whereas Transpower understands that the Commission’s assessment of 
the alternative proposals that it used in its draft decision met n-g-1 at a medium 
growth forecast.   
192 Notwithstanding this, Transpower agrees that this potential difference is not 
relevant to approving this proposal under Rule 13.4.1.1, because if the proposal 
meets n-g-1 at a prudently high demand forecast it will certainly meet n-g-1 at a 
medium growth forecast. 
                                                      
9  “Vision 2030 – 25 year vision for Victoria’s Energy Transmission Networks” October 2005, 
VENCorp, Australia. 
 
 
October 2006 
© Transpower 2006 
 Page 43 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
6.1.2 
Definition of “Good Electricity Industry Practice”  
193 Good electricity industry practice or GEIP is not a defined term in the Rules.  In its 
draft decision, the Commission developed a definition of GEIP through reference 
to Transpower’s definition in its posted terms and conditions, and the Australian 
definition, as:  
“the exercise of that degree of skill, diligence, prudence, foresight and 
economic management, as determined by reference to good 
international practice, which would reasonably be expected from a 
skilled and experienced asset owner engaged in the management of a 
transmission network under conditions comparable to those applicable 
to the relevant grid assets consistent with applicable law, safety and 
environmental protection.  The determination is to take into account 
factors such as the relative size, duty, age and technological status of 
the relevant transmission network and the applicable law.”  

194 The Commission in its draft decision considered that this definition is appropriate 
for the purposes of the application of Rule 13.4.1.1, with some additional factors 
including: 
•  Performance criteria such as voltage stability margins, steady state bus 
voltage ranges and transmission asset loading limits.  The Commission 
considers that many of the performance criteria detailed in Transpower’s 
“Main Transmission Planning Guidelines”10 are sufficient to ensure that the 
grid is planned to GEIP.  
•  Reliance, for substantial power system investments, on the use of equipment 
and designs whose performance can be directly related to proven service 
experience.  
•  A high degree of quality assurance applied in planning, design, manufacture, 
commissioning, testing and maintenance activities.  
•  In its draft decision, the Commission considered that for a proposed 
investment to meet GEIP, the following would be required:  
o  a robust design process, with consultation and involvement of customers 
and stakeholders;  
o  well developed specifications and design documents;  
o  high-quality manufacturing and software development processes;  
o  extensive co-ordination and testing before and after system integration 
phase;  
o  as far as possible, full factory testing of complete finished control and 
protection systems;  
o  thorough checking and testing at site/commissioning; and  
o  ongoing validation and diagnostic maintenance.  
195 Transpower agrees that the Commission’s definition provides a useful working 
basis, and that the above factors are relevant considerations of GEIP.  However, 
Transpower’s view is that for transmission planning, there is more to GEIP than 
included in these factors.   
                                                      
10This report is available as a supporting document to the Proposal on Transpower’s website: 
www.transpower.co.nz.  
 
 
October 2006 
© Transpower 2006 
 Page 44 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
6.1.3 
GEIP in meeting the GRS 
196 In particular, GEIP requires amongst other things prudence as determined by 
reference to good international practice.  In the case of the proposal, GEIP also 
would require consideration of the size, nature and importance of the Auckland 
load.  
197 Transpower maintains that for a critical load like Auckland, the minimum 
acceptable standard for reliability would be one where peak demands could be 
reliably supplied even with a critical generator, such as the Otahuhu CCGT, out of 
service. 
198 This approach is consistent with the short- and medium-term operational planning 
processes used by the System Operator to ensure supply adequacy and 
reliability. The System Operator has used this approach historically and has 
demonstrated its efficacy over many years. 
199 International references confirm the n-g-1 approach, or a standards-based 
equivalent, to be consistent with international practice11,12 and therefore an 
important indicator of GEIP.  
200 In the Australian National Electricity Market, supply adequacy is treated 
separately from grid reliability by means of a minimum reserve margin (in MW) 
that must be maintained. For regions at the ends of the NEM power system 
(Queensland and South Australia), the minimum reserve margin is at or greater 
than the size of the largest unit. The approach is therefore consistent with an n-g-
1 approach for Auckland. 
201 Transpower maintains further that, even if the Commission disagrees with 
Transpower’s interpretation of the GRS and interprets it as n-1, assuming all 
generation is available at 100% of its rated capacity, the requirement to consider 
GEIP would necessitate taking into consideration international practice described 
above. 
                                                      
11 PJM CETL process described at http://www.pjm.com/planning/downloads/cetlproc.pdf 
12http://www.electricitycommission.govt.nz/pdfs/opdev/transmis/400Kv/supdocs/memoreport0

4.pdf 
 
October 2006 
© Transpower 2006 
 Page 45 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
6.2  Rule 13.4.1.2: The Original GUP complies with Rule processes  
202 The second criterion for approval under Rule 13.4.1 requires that the proposed 
reliability investment: 
13.4.1.2 
“complies with the processes set out in these Rules”. 
203 In its draft decision, the Commission considered that this Rule should be 
interpreted as requiring Transpower to comply with the processes stipulated by 
Section III of Part F in relation to the submission of a proposed investment under 
a GUP. The relevant processes are summarised by the Commission in its 
consultation paper on the draft decision, in paragraph 6.3.5. Table 6.1 below re-
states these processes, and the actions Transpower undertook to meet the 
process requirements:  
 
Processes required by  
Transpower fulfilled these requirements: 
Rules 12 and 13 
• 
submitting a GUP to the 
On 23 May 2005 the Commission sent a written 
Commission within three 
request to Transpower to prepare a GUP, and to 
months of receiving a  submit this by 24 August 2005. Following 
written request from the 
discussions between the Commission and 
Commission, or such  Transpower, in August 2005 this deadline was 
other date as the extended to 30 September 2005. The Original GUP 
Commission agrees (Rule 
was submitted on this date. 
12.2);  
• 
providing such content in 
Rule 12.3 requires a GUP to include: 
the GUP as required by 
12.3.1 a comprehensive plan for asset management 
Rule 12.3;  
and operation of the grid 
12.3.2 information on investment contracts 
12.3.3 the proposed reliability and / or economic 
investments, with supporting information 
12.3.4 such other information as prescribed by the 
Commission Board. 
The Original GUP submitted on 30 September 2005 
included Transpower’s most recent Asset 
Management Plan (Vol. I), a list of bi-lateral 
investment contracts that had been entered into up 
to September 2005 (Vol I), the proposed 400 kV 
upgrade into Auckland as a reliability investment 
(Vol. II), and the proposed upgrade to the HVDC 
link as an economic investment (Vol. III). Two other 
investment proposals were included as economic 
investments in Vol. IV, which was submitted on 31 
October 2005. There was no extra content 
prescribed in writing from the Commission Board, 
under rule 12.3.4.  
• complying with the In its consultation paper on its draft decision, the 
timetable for consultation 
Commission summarised the development of the 
and approval of the  consultation timetable, including extensions to this 
investment under 
timetable. In paragraph 7.2.8 of the consultation 
consideration as agreed  paper the Commission confirmed it was satisfied 
by the Commission and 
Transpower had complied with the extended 
 
October 2006 
© Transpower 2006 
 Page 46 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
Transpower or stipulated 
timetable. 
by the Commission (Rule 
13.2); and  
• answering 
the Appendix 2 of the draft decision consultation paper 
Commission’s questions  lists in a table key relevant events and processes, 
and carrying out 
up to the publication of the consultation paper itself. 
investigations and 
This table includes the various requests for 
evaluations as required  information made by the Commission under Rule 
by the Commission under 
13.3.3. In paragraph 7.2.10 of the consultation 
Rule 13.3.3.  
paper the Commission stated it believed 
Transpower had endeavoured to respond to these 
requests to the extent practicable. 
 
Table 6.1: Compliance with the Rule processes (‘Commission’ refers 
to the Commission’ 
 
204 Transpower notes that in its draft decision, with respect to Transpower’s Original 
Proposal, the Commission determined that: 
“On balance, the Commission is … satisfied that Transpower has 
complied with the processes set out in the relevant Rules.” 

205 That the Amended Proposal follows the Rules process for an amendment by 
Transpower to a reliability proposal is demonstrated in this section of the 
application. 
206 The Original Proposal and the amendment of it to form this Amended Proposal 
therefore comply with the processes set out in the Rules. 
207 Transpower considers that the Original GUP submitted on 30 September 2005, 
and the Amended Proposal which is the subject of this application, demonstrate 
compliance with the Rules for amending the Original Proposal, and hence meet 
the requirements of Rule 13.4.1.2 that the “proposed reliability investment … 
complies with the processes set out in these Rules”. 
 
October 2006 
© Transpower 2006 
 Page 47 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
6.3  Rule 13.4.1.3: The Amended Proposal satisfies the Grid Investment 
Test 
208 The third criteria for approval under Rule 13.4.1 requires that the proposed 
reliability investment: 
13.4.1.3 
“meets the requirements of the Grid Investment Test”. 
209 Clause 4 of the GIT states that a proposed investment that is necessary to meet 
the reliability standard13 satisfies the Grid Investment Test if the Board is 
reasonably satisfied that:  
4.1.1.  
the proposed investment maximises the expected net 
market benefit or minimises the expected net market cost 
compared with a number of alternative projects; and  

4.1.2.  
if sensitivity analysis is conducted, a conclusion that a 
proposed investment satisfies clause 4.1.1 is sufficiently 
robust having regard to the results of that sensitivity 
analysis; 

210 The purpose of this section is therefore to satisfy the Commission that the 
Amended Proposal maximises the expected net market benefit, or minimises the 
expected net market cost, compared with a number of alternative projects, in a 
robust manner with respect to sensitivity analysis14. 
211 The remainder of the GIT consists of the methodology for applying the GIT 
(clauses 5 to 17) and the definitions to be used (clauses 18 to 32).    
212 Table 6-2 presents the summarised rankings of the proposal and alternatives as 
a result of the application of the Grid Investment Test.  
213 The results in table 6-2 show that the proposed investment (Option 2) passes 
Clause 4.1.1 of the GIT by having the lowest expected net market cost of the 
three alternatives.  The results in table 6-2 are in 2006 dollars; results in 2011 
dollars are presented in Attachment E. 
 
 
 
 
 
 
 
 
 
 
                                                      
13  Different GIT clauses apply to economic investments.  The Amended Proposal is a 
reliability investment, and hence clauses 4.1.1 and 4.1.2 apply.  See section 5.3. 
14  Assuming that, given the size of the proposal, sensitivity analysis is conducted.  
Transpower has conducted sensitivity analysis, and the Commission conducted sensitivity 
analysis in its draft decision. 

 
October 2006 
© Transpower 2006 
 Page 48 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
 
 
 
 
Option 1 
Option 2 
Option3 
Item 
220kV 
400kV 
Duplex 
WKM-PAK 
WKM-PAK 
OTA-WKM A&B
 
 
PV $ 2006 (millions) 
Mean capital cost (A) 
687
682
737
Mean O&M costs (B) 
24
25
21
Mean unserved energy cost (C) 
0
0
0
Mean relative loss cost (D) 
0
-1
60
Mean terminal benefit (F) 
12
13
4
Strategic benefit (G) 
0
-5
0
Mean NPV cost 
698
688
813
(A+B+C+D-F+G) 
Difference v 220kV 
-
-10
115
 
Table 6-2: Ranking of the Transpower proposal and alternatives with the 220 kV 
alternative as the reference case. 
 
214 Table 6-3 presents a summary of the sensitivity studies used to confirm the 
rankings of the proposal and the alternatives for a variety of changes to key 
parameters. 
 
 
 
October 2006 
© Transpower 2006 
 Page 49 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
Option 3 
Option 1 
Option 2 
Difference 
Duplex 
-$2006 million- 
220kV 
400kV 
400kV-
WKM-PAK 
 WKM-PAK 
OTA-WKM 
220kV 
A&B 
Mean NPV costs 
698
688
813 
-10
Sensitivity: 
 
$2011 
1112
1096
1296 
-16
Capital cost +20% 
835
824
961 
-11
Capital cost -5% 
664
654
777 
-10
System SRMC 
698
687
827 
-11
Loss cost +30% 
698
687
834 
-11
Loss cost -30% 
698
689
793 
-9
Discount rate 4% 
934
883
1159 
-51
Discount rate 10% 
545
553
602 
8
Property escalation 0% 
682
680
784 
-2
Property escalation 6% 
724
697
857 
-27
Exchange rate 10 yr average 
691
687
807 
-4
Hydro/Renewable scenarios - 0 
750
722
903 
-28
new generation 
Reduced demand scenario - 1 
714
701
846 
-13
new generation 
Coal scenario – 2 new 
674
674
776 
0
generation 
Gas scenario - 3 new 
629
640
688 
11
generation 
Gas scenario only, rated up 
-
-

41
 – 6 new gen 
40%, 20%, 20%, 20%, 0,2,4,6 
-
-

2
new gen 
New generation prior 2030 only 
680
675
793 
-5
20 year analysis period 
613
634
696 
21
Urban sprawl 10km 
701
688
813 
-13
Upper 50% runs 
747
721
882 
-26
Lower 50% runs 
653
658
753 
5
Risk adjusted timing 
758
753
839 
-5
10% POE Demand path only 
769
737
924 
-32
Table 6-3: Sensitivity of expected net market cost of the Transpower proposal and 
alternatives and expected net market cost difference between the proposal and 220kV 
reference case 
 
 
 
October 2006 
© Transpower 2006 
 Page 50 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
215 The sensitivity studies show that the benefit of the proposed option is even 
greater under a social discount rate of 4% and for the renewable and hydro 
scenarios. The proposal also improves under a lower demand scenario with only 
one generator going into the upper North Island area. 
216 The proposal is less economic under scenarios with high levels of generation in 
the upper North Island (gas scenario with 3 or more new generators). 
217 The result is robust to changes in capital cost as all projects are similarly affected. 
218 Re-running the GIT calculation tool with the risk adjusted project timing described 
in section 7 does not change the ranking of alternatives.  Refer to Attachment E 
for further details. 
6.3.1 
Discussion on Options 1 & 2: new line WKM-PAK 
219 From a GIT perspective, even though Option 2 passes the GIT, there is very little 
separating Option 1: 220 kV and Option 2: 400 kV WKM-PAK (Proposed) given 
that the cost estimates are limited to 20-25% accuracy and the number of 
assumptions made with respect to costs generally. 
220 Given the closeness of the comparison, Transpower believes it is appropriate to 
examine the sensitivity studies and the ranges in outcomes that they provide.  
Transpower also believes the two projects can be differentiated by considering 
non-quantified benefits that are discussed below.  
221 Another significant differentiator between these two projects is the requirement in 
the 220 kV option for an additional corridor in later years. 
222 The maximum ‘corridor capacity’ for the 220 kV option is 1200 MVA compared 
with 2700 MVA for the 400 kV proposal. This latent capacity may provide 
additional comfort to potential investors that there is a greater likelihood, in the 
longer term, for capacity to be readily available from the 400 kV option. The lead 
time for establishing substations is of the order of 2 years and designation, 
consenting and easement issues are less likely because only substation works 
will be required. The 220 kV option will face significantly more challenges in this 
area as a new easement will be required. 
 
6.3.2 
Discussion of the potential ranges of outcomes 
223 The sensitivity studies show there is a range of possible outcomes. 
224 In view of the closeness of the results between the proposal and the next best 
alternative, the 220 kV Option 1, Transpower has considered other factors to 
inform the selection of the preferred alternative. 
Demand Analysis 
225 The demand analysis using the lower and upper 50% of runs shows that the 
range of outcomes can be considered to be in the range of $5M to -$26M.  The 
GIT analysis was carried out using the 2005 SoO load forecasts and observations 
in the 2006 winter were on the high side of the 2005 SoO load forecasts.  
Transpower’s view is that there is no basis to assume that future load outcomes 
will be on the low side and that 2006 observations suggest outcomes are more 
likely on the higher demand side of the range (i.e. more in favour of the proposal).  
If demand is in the lower range (<50%), it is likely there will be less generation 
and this will have a compensating effect. 
 
 
October 2006 
© Transpower 2006 
 Page 51 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
Renewable energy sources 
226 The (draft) GPS makes it clear that it is the Government’s intention to facilitate 
and promote renewable energy sources, as per clauses 34A, 87A and 87B. The 
range of potential outcomes are for three new thermal generators in Auckland to 
zero new generators under the renewables scenario, giving possible outcomes in 
the range $11M to -$28M. 
227 Further analysis has considered up to six new thermal generators in Auckland 
(Refer to Attachment E) which expands the range to approximately $41M to -
$28M.  Arguments have been raised about the need for ‘conventional’ generation 
to ‘back-up’ intermittent renewable generation (such as wind).  Transpower notes 
the initiative by Genesis and Contact to seek consent for a potential LNG terminal 
in Taranaki. 
228 If additional thermal generation is required, as argued, the prospect of all this 
generation going into Auckland is unlikely, given the requirement for gas pipeline 
capacity into Auckland. 
229 Furthermore, unless the HVDC inter-island link is downgraded, an obvious choice 
for providing back-up to intermittent renewables is hydro generation, available in 
both the South and North Island. 
230 Transpower therefore argues that the prospect of many new generators in 
Auckland is low and that the higher probability outcome, particularly in the light of 
the (draft) GPS, is at the lower end of the thermal generation outcomes in 
Auckland.  
231 Transpower believes the appropriate range of outcomes thus lies in the range  
-$13M to -$28M, representing up to one new thermal generator in Auckland. 
 
Property escalation 
232 The property escalation range is from -$2M to -$27M depending on whether 
property is escalated at 0% or 6% relative to CPI. The base results use 3% 
escalation. 
233 The 200 km line route passes through a range of land usage types from rural to 
developed. The actual escalation will vary between land usage types with rural 
being closer to 0% and developed being closer to 6%. 
234 The increasing popularity of ‘lifestyle’ blocks south of Auckland, together with 
increasing urbanisation, add weight to a higher escalation rate. Transpower notes 
that there is already significant development up to the ’40 year urban boundary’ in 
the vicinity of the proposed transition/substation. 
235 If the South Auckland urban boundary is revised, as would appear likely, 
development further south would necessitate future corridors to terminate further 
from Otahuhu or Pakuranga substations. The increased cost of cabling from 
these termination points would significantly increase net project costs. 
236 Considering the cost of the corridor for the proposal is approximately $80M and 
the cost per km of underground cable is in the order of $5-8M/km per circuit, cost 
escalation at the higher rates would seem, on average, to be justified.  
Discount rates 
237 Varying the applicable discount rates shows a range of outcomes between $8M 
and -$51M. 
 
October 2006 
© Transpower 2006 
 Page 52 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
238 Transpower believes the discount rate for long-term investments with an element 
of ‘social good’ requires a lower discount rate than the standard 7% used in the 
base case. The argument for a discount rate in the vicinity of 4% is supported by 
advice from independent consultants15  
239 Transpower believes that the adoption of a lower discount rate would favour the 
proposal. 
6.3.3 
Other non-quantified benefits favouring the proposal 
240 There are a number of other benefits that Transpower believe additionally favour 
the proposal and which if quantified, would be included in the GIT results.  
241 They are difficult benefits to defensibly quantify. Work is underway to quantify 
these benefits and the results of this work will be advised once available. 
242 They are broadly grouped as competition benefits and capacity benefits, further 
described below.   
 
 
Competition benefits: 
243  In its draft determination of Transpower’s original 400kV investment proposal16, 
the Commission argued that since the 400kV proposal and the alternative 
projects provided similar levels of unconstrained transmission capacity, 
competition benefits would be equal for each alternative, therefore making it 
unnecessary to quantify them as they would net out in the economic analysis. 
244 In a recent paper, The Energy Centre17 point out that: 
“…this argument is based on the mistaken assumption that the intensity of 
competition in an electricity market can be improved by transmission investment 
only if an absolute transmission constraint is relieved. Under the Commission’s 
reasoning, a transmission line that had 1000MW of unused capacity…would not 
generate any additional competition benefits over and above those generated by 
a transmission line that…had 1MW of spare capacity…” 

245 They go on to show that recent economic research supports an argument that 
since the 400kV project provided more actual capacity than the alternatives it 
would be expected to generate greater competition benefits.  
“The key idea is that a transmission line provides a threat of competition to 
generators located in different areas…[provided] the line has sufficient capacity 
that generators do not find it profitable to ignore the possibility of output 
expansion by a rival…”. 

                                                      
15 “Discount Rate for the Grid Investment Test” Report to Transpower, August 2006, Castalia 
Strategic Advisors. Refer to Attachment L 
16 “Economic assessment of Transpower’s Auckland 400kV grid investment proposal”, May 
2006. 
17 “Submission to the Electricity Commission and the Minister of Energy on: Transpower’s 
Auckland 400kV investment proposal draft decision”, 22 June 2006  
 
October 2006 
© Transpower 2006 
 Page 53 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
246 Transpower agrees with The Energy Centre’s analysis and consider that the 
same arguments will apply to the Amended Proposal in this Application for 
Approval. The Amended Proposal has significantly more thermal capacity than 
the alternatives and this capacity can be released at relatively short notice 
compared to the alternatives. This becomes particularly noticeable in the years 
leading up to the need for a second new 220kV line in the reference case, and 
the years leading up to the need for new 220kV lines in the duplexing alternative. 
Therefore, Transpower believes the proposal does have a competition benefit 
compared to the alternatives.          
247 The benefits that arise from such a situation are categorised into two groupings: 
•  benefits which reduce the overall supply cost of electricity. These arise 
because heightened intensity of competition forces generators to become 
more efficient operationally. 
•  benefits which reduce the price of electricity to consumers. These also arise 
because of heightened intensity of competition, but are differentiated from the 
previously discussed benefits because they are wealth transfers between 
generators and consumers and cannot be included in the GIT.       
248 Transpower is working to quantify both types of benefit, because even though 
only the first can be included in the GIT, the Commission are required under the 
GPS to “…promote and facilitate retail competition…”, hence Transpower would 
expect the Commission to take into account information which demonstrates the 
extent to which limited competition is affecting consumers.    
249 The GIT requires Transpower to estimate the direction and magnitude of non-
quantifiable benefits.   
250 Competition benefits accrue in a direction that favours the proposal, because of 
the higher latent capacity.  Transpower is unable at this stage to quantify the 
magnitude of this benefit.  Accounting for the competition benefits arising from the 
latent capacity is also consistent with the requirements of the (draft) GPS.     
 
Capacity benefits 
251 As discussed above, the Amended Proposal has significant amounts of unused 
thermal capacity, particularly in the earlier years, compared to the alternatives. 
Although there is a cost in investing in such a large line (the initial capital costs of 
the Amended Proposal are higher than the alternatives) Transpower believes 
there are capacity benefits associated with having large amounts of surplus 
capacity, compared to alternatives which provide smaller amounts, or just 
sufficient, capacity. These are categorised into three different potential benefits. 
The Energy Centre paper18 discusses two aspects of transmission investment 
analysis, categorised as capacity benefits: 
 
1)  The first relates to the interdependence between transmission and generation 
investments. The paper points out that, in general, transmission investments 
drive generation investments. Potential investors in generation pay 
considerable attention to (expected) decisions on transmission investment 
and these decisions “…influence the profitability of different generation 
investments (technology as well as location) differently. More specifically the 
signal not to build a new transmission line, will stimulate…generation 
investments near Auckland…”
. Such an outcome may or may not be 
                                                      
18 “Submission to the Electricity Commission and the Minister of Energy on: Transpower’s 
Auckland 400kV investment proposal draft decision”, 22 June 2006  
 
October 2006 
© Transpower 2006 
 Page 54 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
economic for New Zealand. It will only be economic if building generation 
near Auckland is the cheapest option. If building generation in Taranaki (say) 
is cheaper, but the possibility of being able to exercise market power, at least 
for a short time, leads to a generator building in Auckland instead, then the 
outcome is sub-optimal for New Zealand. 
 
Transpower agrees with this assessment and considers that the Amended 
Proposal and reference case are similar in this regard and that both have a 
capacity benefit over the duplexing alternative until 2020. However, the higher 
latent capacity of the proposal favours this option.  The duplexing alternative, 
which limits transmission capacity into Auckland prior to a new 220kV being 
built in approximately 2020, may stimulate (sub-optimal) generation 
investment in the Auckland region.  
 
2) The second capacity benefit relates to the impact of uncertainties on 
transmission and generation investments. In their draft determination, the 
Commission have correctly identified that postponing major transmission 
investment decisions creates more time for clarity to emerge with respect to 
future generation investment. This is termed transmission option value and if 
correctly identified, may be added as a benefit in GIT analysis. The Energy 
Centre paper points out however, that creating an option value for 
transmission investment may do so at the expense of option value for 
generation investment i.e. where options for transmission are kept open, 
uncertainties increase for new generation investors, thereby increasing their 
risks/costs.  
 
The Amended Proposal has significantly more latent thermal capacity than 
the alternatives (two years as opposed to seven years for a new line) and this 
capacity can be released at relatively short notice compared to the 
alternatives. Whilst this may mean the Amended Proposal has less 
transmission option value than the alternatives, it reduces the uncertainty for 
generation investors compared to the alternatives and thereby gives a higher 
generation option value.    
 
Considering the relative capital intensity of generation and transmission 
investments, Transpower believes it is better to provide higher generation 
option value through certainty of transmission investment.  In this context, 
Transpower believes the direction of the benefit favours the proposal.  
Transpower has not been able to estimate the size of this benefit at this 
stage. 
 
3)  The third capacity benefit relates to the flow-on effect to the economy from 
having good infrastructure in place. Transpower has a view that “just-in-time” 
infrastructure development creates, at the very least, a perception of 
uncertainty to potential investors in New Zealand. Castalia was commissioned 
to consider an approach for quantifying such effects and their paper is 
attached to this application as Attachment N – Foreign Direct Investment 
Effects19. Quoting from that paper: 
 
Because it is difficult to predict the likely increase in Foreign Direct 
Investment (FDI) that the Upgrade will generate, we have cast the proposition 
as the following question: 

                                                      
19 At Transpower’s request, Castalia focussed on foreign investment in New Zealand, but it 
should be noted that similar arguments could be developed for local investment. 
 
October 2006 
© Transpower 2006 
 Page 55 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
What increase in investor confidence and FDI would result in the Earlier 
Option delivering $100m more welfare than the Later Option (in present value 
terms, taking into account only the different effects on investor confidence of 
the two options)? 
 
We chose $100m as the order of magnitude of the cost differences being 
debated in the Auckland Supply Upgrade. 
 
We find that an increase of about $2.3m in the annual flow of FDI would 
generate the additional $100m in welfare. To put this in perspective, the 
$2.3m figure represents a 0.09 percent increase in FDI.” 
 
Castalia’s reference to Earlier and Late Options is a reference to the 
Commission’s draft determination where a comparison was made between 
building a new transmission line in 2010 (Earlier Option), or by using 
incremental investments, deferring the new line until 2017 (Later Option).  
 
Castalia go on, in their paper, to acknowledge that there is no way of knowing 
what the FDI effect of one transmission investment versus another will be.  
 
“Rather, we think the assessment can be left with the Electricity Commission 
and the Government. To decide to save some tens of millions of dollars by 
opting for a just-in-time transmission upgrade plan—rather than a plan with 
more surplus capacity, decision makers have to be confident that the increase 
in FDI from an earlier upgrade will be less than one tenth of one percent.” 

 
Clearly, the Amended Proposal, with its large amount of surplus capacity, will 
enable a significantly higher level of investor confidence with respect to 
Auckland infrastructure and will therefore encourage higher levels of FDI. 
 
Transpower believes the direction of this benefit favours the proposal, 
because of the investor confidence provided by the higher latent capacity than 
the 220 kV reference case.  Transpower believes that any long term investor 
would appreciate the availability of this latent capacity.  The discussion above 
shows this is a significant benefit for even very small changes in FDI. 
 
6.3.4 
Discussion on Option 3: Duplex WKM-OTA A and B 
252 This option has high initial costs that offset the initial attraction of a medium-term 
remedial measure. 
253 The Otahuhu-Whakamaru A and B transmission lines are over 50 years old and 
require substantial refurbishment and tower replacement works in order to reliably 
support double the conductor weight and increased wind loading. 
254 The physical works are $97.7M of the of the total project cost estimate. 
255 The property costs for this line are estimated to be $83.0M. Transpower is 
satisfied that this is a reasonable estimate and consistent with costs assessed for 
options 1 and 2. 
256 Even if, in an extreme case, the property costs for this option were considered to 
be zero, the GIT analysis shows that the project would still lag options 1 and 2 by 
approximately $40M. 
 
October 2006 
© Transpower 2006 
 Page 56 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
257 Similarly, if the variant discussed in Section 4.4.3 were adopted – using only one 
cable into Pakuranga and retaining in service the existing lines – the cost savings 
of around $50M would, on its own, be insufficient to warrant adoption of this 
variant. 
258 A significant cost for this option is attributable to the relatively high losses 
incurred on the line. This arises initially in the first ten years prior to the 
construction of a new greenfield 220 kV line. During this period, Options 1 and 2 
both benefit from having two low-loss circuits delivering energy to the Auckland 
environs. 
259 Given that losses quadruple when current doubles, the generally higher loading 
on all the parallel transmission lines in the initial years, and in later years before a 
second 220 kV line is required, accumulate loss costs that prejudice this project 
against Options 1 and 2. 
260 In addition, the lower latent capacity in the initial years would not provide the 
same level of confidence to investors (GPS clause 87G and benefits described in 
6.3.3) than would Options 1 and 2.  
261 It is also arguable that the lower latent capacity would reduce competitive 
pressures in the generation sector and provide less to renewable generation in 
central and southern North Island access to upper North Island markets. 
262 Further suggestions to reduce cost include the use of high temperature conductor 
(HTC) for those components of the Otahuhu-Whakamaru line that would require 
easements. This constitutes about one third of the line length, or 70 km, on the 
current assumptions for consenting and easements. 
263 The use of HTC for one third of the line would increase capital costs by 
approximately $31M, being the difference between the cost of duplexed 
conventional conductor and simplex HTC. Further increases in cost would be 
required to install 13 extra strain towers (at a cost of $1.6M) plus a fund of $5M to 
cover the expected increase in Environment Court costs. 
264 It is not clear that avoiding duplexing these sections will, of itself, be sufficient to 
avoid having to obtain easements. Factors that might trigger a requirement to 
obtain easements are not clear but could include consideration of: 
• Conductor 
Diameter; 
• Conductor 
Swing; 
•  Electric and Magnetic Fields; 
• Temperature; 
and 
•  Conductor Sag/Tower heights. 
265 Even if easements were not required over these sections, Transpower believes at 
least $18M would still be required for the removal of structures under the line. 
266 The higher losses on these sections of the line would offset cost savings, with an 
estimated loss component rising from $60M to approximately $80M, based on 
interpolation of the Option 3 and Option 4 loss costs. 
267 In addition, the higher reactance of the resulting composite line would increase 
the net reactance and therefore the reactive losses. This would require additional 
reactive compensation in the Auckland area, increasing costs further. 
268 In addition to all the above considerations, Transpower, in section 4.7 has 
indicated its concerns about using a relatively new conductor technology, with 
limited international application, in precisely those locations of under-build where 
concerns of conductor failure are the greatest. 
 
October 2006 
© Transpower 2006 
 Page 57 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
6.3.5 
Discussion on Option 4: Duplex WKM-OTA A and B with HTC 
269 This option is virtually identical to Option 3 in the initial years prior to the need for 
the next major augmentation. 
270 The initial capital cost is affected by the costs of: 
•  remedial and refurbishment works ($80M); 
•  the high temperature conductor ($179M); and 
• easements 
($83M). 
271 Comparative results for this option are provided in Table 6.4.  
Option 4 
Option 1 
HTC on 
220kV 
OTA-WKM 
Item 
WKM-PAK 
A,B,C 
2006$ (Millions) 
Mean capital cost (A) 
687
808 
Mean O&M costs (B) 
24
20 
Mean unserved energy cost (C) 
0

Mean relative loss cost (D) 
0
126 
Mean terminal benefit (F) 
12
-9 
Strategic benefit (G) 
0

Mean NPV cost 
698
963 
(A+B+C+D-F+G) 
Difference v 220kV 
-
265 
 
Table 6-4: Comparative assessment of the non –qualifying alternative Option 4 with the 
220 kV alternative as the reference case. 
 
272 Sensitivity results for option 4 are given in Table 6.5. 
 
 
October 2006 
© Transpower 2006 
 Page 58 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
Option 1 
Option 4 
Difference 
$2006 million 
220kV WKM-
HTC OTA-WKM 
HTC-220kV 
PAK 
A,B,C 
Base results 
698
963
265
Sensitivity: 
$2011 
1112
1534
422
Capital cost +20% 
835
1124
289
Capital cost -5% 
664
922
258
System SRMC 
698
1011
313
Loss cost +30% 
698
1009
311
Loss cost -30% 
698
917
219
Discount rate 4% 
934
1438
504
Discount rate 10% 
545
694
149
Property escalation 0% 
682
941
259
Property escalation 6% 
724
997
273
Exchange rate 10 yr average 
691
955
264
Hydro/Renewable scenarios - 0 
750
1092
342
new generation 
Reduced demand scenario - 1 
714
1010
296
new generation 
Coal scenario – 2 new 
674
903
229
generation 
Gas scenario - 3 new 
629
784
155
generation 
New generation prior 2030 only 
680
937
257
Urban sprawl 10km 
701
963
262
Upper 50% runs 
747
1044
297
Lower 50% runs 
653
890
237
10%POE demand path only 
769
1141
372
Table 6-5: Sensitivity of expected net market cost of the non-qualifying alternative 
Option 4 and 220kV reference case 
 
273 Subsequent to 2017, series capacitors will be required on these lines to ensure 
sharing between the six parallel 220 kV circuits. This will have the effect of 
directing more flow to these HTC circuits, increasing losses accordingly. 
 
October 2006 
© Transpower 2006 
 Page 59 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
274 The subsequent re-conductoring of the Otahuhu - Whakamaru C line (double 
circuit, duplex) would require a similar outlay for the conductors and potentially for 
easements and/or cable entries into Otahuhu. 
275 As the re-conductoring does not change the line impedance (of the C line), further 
series capacitors are required to direct flow onto these circuits, with the flow 
increasing the losses markedly on this circuit. 
276 The loss costs in Table 6.4 reflect the significantly higher losses incurred in this 
option. 
277 Transpower believes the high loss costs are contrary to the climate change 
imperatives outlined in the (draft) GPS clauses 34A, 87A and 87 B as these 
losses all require greater production from thermal generation that could otherwise 
be avoided. 
278 The higher flows also incur very high reactive losses which necessitate the 
installation of additional reactive support for voltage control. This is reflected in 
the project capital cost. 
279 The conclusion drawn from the economic analysis is that even in the extremely 
unlikely case where property costs were zero and the conductor was supplied for 
the same cost as conventional conductor, the project would still not be 
economically viable. 
6.3.6 
Comparison with non-transmission alternatives 
280 Attachment K shows the non-transmission alternatives are generally not as cost 
effective as transmission options 1 and 2. 
281 The exception appears to be the case where an existing peak load unit were 
moved to the Auckland region from elsewhere in New Zealand (e.g. Whirinaki). 
This is because the fixed annual costs of the plant may be treated as zero since 
they would have been incurred irrespective of the move. 
282 In the case of Whirinaki, for a relocation cost of $30 million this would give a net 
market benefit of $39 million. This however needs to be considered in light of the 
draft GPS which states that when considering non-transmission alternatives, the 
Commission should: 
“not consider alternatives which are only likely to proceed if they are 
assisted by the government….” 

 
283 A general finding with respect to base load generation is that even if adjusted for 
transmission deferral benefits, there are options with lower long run marginal 
costs (LRMCs) that are lower and should, in an efficient market, be built before 
Auckland base load plant.  
284 This finding does not include differences in reliability between transmission and 
generation (in favour of transmission). 
285 This finding does not necessarily take into consideration all the factors that a 
prospective generator may wish to consider before investing. The analysis is 
based on costs and benefits that would normally be considered in a centrally 
planned power system. 
 
October 2006 
© Transpower 2006 
 Page 60 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
6.3.7 
Impact of the draft GPS 
286 The (draft) GPS is discussed in Section 8. The changes proposed by the 
Government effectively add weight to the renewable and hydro energy futures. As 
such, Transpower believes these sensitivities should be weighted higher than the 
coal and gas scenarios. This favours the proposal as the renewable, hydro and 
low Auckland generation (low growth) scenarios deliver improved economies over 
the 220 kV alternative as illustrated in table 6-3. 
287 The(draft) GPS specifies two requirements in relation to diversity: 
•  [Clause 80] … where practical, the transmission grid should 
provide adequate alternative supply routes to larger load centres 
having regard to the load which could otherwise be disrupted and 
the duration of any disruption; and 
•  [Clause 88E] … to the extent the Commission considers the 
environmental effects of new lines, it should also take into account 
any longer term benefits that larger capacity lines may provide by 
avoiding multiple smaller lines. 
288 Transpower has given effect to these requirements by: 
•  Specifying Pakuranga as the termination point of the proposal and 
alternatives, providing the first stages of a longer term 
establishment of an ‘eastern corridor’ to supply Auckland; and 
•  Adopting high capacity designs for both the proposal and the 
alternatives to maximise the corridor utilisation. 
289 Transpower recognises the tension between the requirements of (draft) GPS 
clauses 80 and 88E in that higher corridor capacity reduces the level of diversity. 
That is many low capacity lines provide more diversity than fewer high capacity 
lines. 
290 Transpower believes in this instance the requirements of clause 88E take 
precedence over clause 80 because the current concentration of supplies in one 
substation – Otahuhu – and limited corridors, will benefit from having a reliable 
alternate supply (corridor and substation) of equivalent rating to the current 
supply arrangements. This will balance the supply capability of the two corridors 
and ensure at least half of the load can be supplied for a low probability event 
causing the failure of a corridor. 
291 Transpower considers that in the first stage of the proposal, with operation at 
220 kV, there is little difference in the diversity of the 220 kV Option 1 and the 
proposal, other than the proposal retains the ability to deliver greater capacity 
with a shorter lead time than Option 1. 
292 Once converted to 400 kV operation, and well into the analysis period, loss of the 
corridor (for example a tower failure causing loss of both circuits) will have a 
higher impact than loss of a tower on a 220 kV double circuit line. 
293 However, the higher capacity of the 400 kV line also provides a degree of 
resilience for the failure of one of the existing 220 kV double circuit lines, 
considered a higher probability as the age of these lines would be approaching 
80 years. 
294 Analysis of this high impact, low probability event is provided in Attachment A 
(Diversity into the Upper North Island). 
 
October 2006 
© Transpower 2006 
 Page 61 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
295 On balance Transpower acknowledges the higher impact of losing a heavily 
loaded 400 kV circuit, but believes the impacts can be contained using special 
protection systems and having fast response repair strategies in place. 
 
 
6.3.8 
Conclusion of the GIT analysis 
296 Transpower has demonstrated that the Amended Proposal satisfies the Grid 
Investment Test because: 
•  as a reliability investment, it maximises the expected net market benefit when 
compared with the alternative projects; 
•  it is robust having regard to the results of a sensitivity analysis; and 
•  satisfies the intentions outlined in the GPS. 
297 Of the three alternatives, Transpower believes the non-quantified benefits 
identified in 6.3.3 all act in a direction to favour the proposal and some of these 
benefits are potentially very significant.   
298 In meeting all of the above criteria, the proposed project satisfies the third criteria 
for approval under Rule 13.4.1 that the proposed reliability investment “meets the 
requirements of the Grid Investment Test”. 
 
October 2006 
© Transpower 2006 
 Page 62 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 

The Amended Proposal is appropriately sequenced and 
timed 

299 As previously mentioned (section 5), the GIT calculation tool was used to ‘rank’ 
the alternative projects in order to select the proposed project, in accordance with 
rule 13.4.1.3. 
300 Once the proposed project is selected, two different methods of determining the 
timing of its implementation may be applied: 
•  the probabilistic method, combining the GRS and GIT; or  
•  the deterministic method using n-g-1 and a prudent forecast. 
 
7.1  Probabilistic method of determining project timing 
301 The GIT calculation tool is used to balance the cost of expected unserved energy 
resulting from delaying the proposed project against the deferral benefits. This is 
the approach used by the Commission in its draft decision. Details of how this 
was applied to the proposed and alternative projects are provided in Attachment 
E and H1. 
 
7.2  Deterministic method of determining project timing 
302 Power system analysis tools are used to determine the point at which the grid is 
no longer able to provide a secure supply in accordance with a predefined 
security criteria. Deferral of the project beyond this date may result in unserved 
energy.  A discussion of the criteria used and its justification is provided in section 
6.1. 
303 The deterministic method is preferred by Transpower as it aligns with GEIP as 
discussed in Section 6.1. 
7.3  Grid Development Projects 
304 Transpower has undertaken to implement a series of grid development projects in 
order to maximise the use of available capacity on the grid. These projects are 
regarded as ‘common’ projects, as they are required regardless of which major 
project is implemented. The Grid Development projects include: 
•  Establishment of Ohinewai substation (Huntly East); and 
•  Thermal upgrade of the 220 kV Otahuhu-Whakamaru A and B lines; and 
•  Bombay bus split; and 
•  The reactive power investments in the Upper North Island as approved by the 
Commission 
305 Each of these projects carries a delivery risk and the dates mentioned are subject 
to revision. Late delivery on any of these projects may have a bearing on the 
short term and major projects. 
 
 
October 2006 
© Transpower 2006 
 Page 63 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
7.4 Short-term 
projects 
306 In addition to the common projects there are also projects that may be cost-
effective to pursue (e.g. new switching station, transmission line upgrades; 
phase-shifting transformers) in the short-term prior to the major upgrade. 
Transpower accepts that such cost-effective short-term projects would form part 
of the proposed upgrade and alternatives in this application.  
307 Some short-term projects may assist in meeting regional demands and delay the 
need date for the major upgrade to the core grid but may not be cost-effective to 
pursue.  These types of projects should be regarded as contingency projects. 
308 Short-term projects may assist in meeting regional demand and delay the need 
for a major upgrade to the core grid. There are two types of short-term projects: 
•  Cost-effective (or economic) projects that are justified on the basis that their 
cost is lower than the unserved energy that would otherwise occur; and 
•  Projects that are not cost-effective (ie they would not normally be 
implemented) but could be implemented to manage unexpected 
(contingency) events. 
309 Transpower also accepts that cost-effective short-term projects will not be held 
back for risk management purposes, which could result in the need-date for the 
major upgrade project being brought forward. 
310 The actual timing and final commitment to short-term projects may be subject to 
revision in the future as uncertainties around the designation, consenting and 
easement risks are resolved or as they impact the need and value of the short-
term projects. 
311 Appendix D lists 11 sets of short-term projects that have been considered and 
gives: 
•  A description of the project; 
•  the improvement in transfer capability if the project is implemented; 
•  the approximate cost of the project; and 
•  Transpower’s classification of the project. 
 
312 The amount of deferral available from the short term projects in appendix D takes 
into account the impact and need for ON constraint of generation. It then 
compares the deferral benefits from each option against its cost. The economic 
projects are: 
  Option 5:  110kV phase shifting transformers 
  Option 7:  Drury switching station 
  Option 8:  Drury switching station + upgrade of OTA-WKM C line 
The greatest benefit to cost ratio is from short term project 8. 
313 In the case of short term project 8, the theoretical maximum deferral is three 
years, however in order to achieve this, Huntly power station must be constrained 
on to nearly 100% of its output (1314 MW) along with full output from New 
Plymouth and Stratford power stations (320 and 360 MW respectively). This 
amount of on-constraint is required by the System Operator to cover for the loss 
of a major generating unit and a transmission line (n-g-1). Reliance on this 
amount of on-constraint is considered impracticable, especially in light of New 
Plymouth power station having a long ‘warm-up’ time, therefore a deferral of three 
years is not recommended.  
314 A deferral of two years could possibly be achieved using option 8, but it still relies 
on near maximum Huntly output however this time without New Plymouth power 
station being constrained on. 
 
October 2006 
© Transpower 2006 
 Page 64 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
315 One year of deferral is possible without New Plymouth and without a major Huntly 
unit having to be constrained on. This is considered to be a reasonable condition 
in light of the potential market distortions that any amount of on-constraint may 
cause. 
 
7.4.1 
Arapuni-Pakuranga 110 kV line 
316 The proposed route for a new 220 kV or 400 kV transmission corridor into 
Auckland follows much of the route of the existing 110 kV Arapuni to Pakuranga 
Line (ARI-PAK line). 
317 Transpower has advised that the construction of the proposed new lines would 
require the retirement of the ARI-PAK line approximately 18 months prior to the 
in-service date of the new lines which would effectively bring the need date for 
the new lines ahead by up to two years. Analysis presented in Appendix D 
indicates that the benefit of retaining the ARI-PAK line is only one year. 
318 Various methods of maintaining the ARI-PAK line in-service were suggested as 
part of the Commission’s draft decision. 
319 It has been suggested that significant capital carrying costs could be saved if 
there were a means of keeping the ARI-PAK line in-service or finding alternative 
ways of mitigating the effect of their absence though the construction phase of 
the new line.  
320 Appendix E indicates the deferral benefits that could be captured by keeping the 
ARI-PAK line in service. It is only economic to undertake the works required to 
keep the line in service if the costs are lower than the deferral benefits. 
321 Given that the costs of keeping the ARI-PAK line in service are estimated to be 
$35M and the benefits are in the range of $15-$22M, Transpower has concluded 
that this project is not economic. 
322 There are operational, safety, easement and RMA issues which must be 
considered in determining the feasibility of concurrent operation of the ARI-PAK 
line during the construction of the new line. 
323 These implementation risks are further valid reasons why the ARI-PAK line 
retention is neither economic nor practicable in the sense that it would introduce 
significant risk and potentially prejudice the major project if delays are incurred 
with the retention works.  
 
7.5  Appropriate timing  
324 Transpower proposes a two step process in determining project timing, namely 
that: 
•  the first step of the project evaluations should be done based on a system 
that reflects the direct system needs (i.e. free of designations, consents and 
easements and other delivery risk); and 
•  the second step is to explicitly and transparently consider such risks in 
relation to project timing so that Transpower can adequately manage those 
risks. 
325 In completing the first step of the timing process, Transpower has calculated the 
timing for the direct system need using both the probabilistic and deterministic 
approach. 
 
October 2006 
© Transpower 2006 
 Page 65 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
326 Transpower’s assessment of the capacity of cost-effective short-term projects is 
that they could provide a project deferral of up to two years under an ideal 
generation dispatch scenario, but only one year for normal dispatch scenarios. 
Transpower considers it prudent to allow for one year of deferral.  
327 The set of short-term projects selected to provide an economic deferral of the 
major project is contained within Option 8 of Appendix D. This option including a 
Drury 220 kV switching station and upgrade of the OTA-WKM C line provides 
cost effective deferral of the major project by one year as previously mentioned.  
7.5.1 
Probabilistic approach - Transpower 
328 For this approach, Transpower engaged ROAM Consulting to analyse the 
unserved energy that could be expected as a result of generation contingencies 
in the Auckland region, including Huntly. The results of this analysis are reported 
in Attachment H2. 
329 Transpower used the unserved energy as a function of peak load from the ROAM 
report as an input into the GIT model.  The GIT model is discussed in Attachment 
E.  
330 The major project was moved back one year at a time in the GIT model and the 
calculated expected unserved energy was added as a cost.  The need-date for 
the project was found as the year that minimised the total cost, or equivalently, 
gave the optimum balance between deferral benefits and unserved energy cost 
331 Attachment H1 indicates the required service date for the major project using this 
analytical approach is around 2017. 
 
7.5.2 
Probabilistic approach – Electricity Commission 
332 The Commission provided an analytical model for an alternative approach to that 
adopted by Transpower. 
333 The alternative approach considers a similar load probability curve but the 
assessment of the unserved energy is extended to consider a wider range of 
demand outcomes. 
334 The rapid increase in unserved energy with increasing demand results in very 
high unserved energy for peak demands. This weights the average unserved 
energy and can result in higher levels of expected unserved energy. 
335 The timing as set by this alternative approach results in a project need of 2013 – 
the same outcome as the deterministic approach discussed below.   
336 This result is consistent with the Commission’s finding in their draft decision that 
the probabilistic approach yields similar results to the deterministic approach. 
 
7.5.3 Deterministic 
analysis 
337  This section describes the deterministic analysis used to set the need-date for 
the projects based on an n-g-1 criterion and the Commission’s ‘prudent’ forecast, 
The approach requires the determination of the n-g-1 capacity of the transmission 
system and the consequential demand that could be supported in the Auckland 
and Northland areas. 
 
October 2006 
© Transpower 2006 
 Page 66 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
338 The supportable demand was then compared with the ‘prudent’ forecast. The 
need-date is set at the year that supportable demand would be exceeded if the 
project were not implemented. 
339 Figure 7-1 shows the need-date for the proposal and alternatives using the 
deterministic approach, with short term projects included. Details are provided in 
Attachment D. 
340 Using this analysis, the proposed major project is thus required in 2013. 
7.5.4 
Conclusion on timing 
341 Transpower has concluded that, based on the Commission’s probabilistic 
approach and Transpower’s deterministic approach, the appropriate timing for the 
proposed major project is 2013. 
 
7.6  Accounting for delivery risk 
342 Figure 7-1 below shows the timing of the short-term projects and the major 
project as determined by the probabilistic and deterministic approaches. These 
dates align with those provide in table 5-1 “System need dates for proposed 
investment”. 
343 The dates shown in the diagram refer to the required commissioning dates based 
on need. Late delivery would result in significant levels of expected unserved 
energy, as shown in Attachment H1 and H2.. 
 
 
Short-
 
Major 
term 
 
project 
project 
 
 
 
 
2010 
2011 
2012
2013
 
 
 
Figure 7-1. Project timing based on need but excluding delivery risk 
 
 
344 The above analysis has considered only the technical need and neither method 
has made any allowance for the risk of delays in delivering the project. These 
risks include delays due to: 
•  designations ,consents and / or easements 
•  project and/or construction issues. 
 
345 Transpower has assessed a range of project delivery scenarios for each of the 
four projects. The outcome of this analysis, assuming approval is obtained this 
year (2006) is shown in Table 7-1. The supporting analysis is presented in 
Attachment C. 
 
 
 
 
October 2006 
© Transpower 2006 
 Page 67 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
Earliest 
Probable 
Latest 
Project 
completion 
completion 
completion 
Base (220 kV) 
2011 
2012 
2014 
Proposal (400 kV) 
2011 
2012 
2014 
Duplexing  
2012 
2013 
2016 
High temperature 
2012 
2013 
2016 
conductor 
Table 7-1: Potential delivery dates taking account of designation, consenting and 
easement risks (assuming project commencement early 2007) 
 
346 The approach taken was to explicitly and transparently recognise delivery risks. 
The most appropriate way of doing this is to : 
•  Work towards an earlier completion date with a view to increasing confidence 
that the project will be available by the need-date; 
•  Adjust, where possible, the delivery date as project risks are avoided or 
mitigated to avoid an unnecessarily early delivery date if risk do not transpire. 
 
347 Transpower believes that as this is the first major greenfield transmission project 
to be built under the Resource Management Act 1991 it would be prudent to take 
a risk averse position regarding delivery risk. In all cases this indicates that a two 
year advancement should be applied to the major project need-date. 
348 Note that some of the short-term projects described in Appendix D also have 
designation, property and easement risks – e.g. requiring a thermal upgrade of 
the Whakamaru-Otahuhu ‘C’ line, which could result in issues under the RMA. 
349 Using the Commission’s model and approach to determining expected unserved 
energy, the consequences of not delivering the major project in 2013 would be of 
the order of $32M (Attachment H1 and H2), equivalent to just under two year’s 
deferral benefit (Appendix E). A delay beyond 2014 would result in expected 
unserved energy rising rapidly to $89M, equivalent to more than 3 years deferral 
benefit. 
350 This is the first greenfield transmission line built under the RMA and will require 
the involvement of 7 councils, two regional councils and over 300 land owners. 
Given the lack of precedent for Transpower, the risks of delays are therefore 
considered to be high. 
351  For both the probabilistic and deterministic approaches, Transpower proposes 
that the explicit risk allowance should be to bring forward the need-date for the 
various projects.  This is shown diagrammatically in figure 7-2 below with a two 
year advancement for both the short-term projects and the major project.  
352 Transpower considers the proposed approach and resultant timing for the 
Amended Proposal to reflect good electricity industry practice and reasonable 
and prudent management of risk. 
 
 
 
 
 
 
October 2006 
© Transpower 2006 
 Page 68 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
353 A revised project timing comparison is provided in figure 7-2 below. 
 
Short-
 
Major 
term 
project 
project 
 
High 
expected 
 
unserved 
 
energy 
2010 
2011
2012
2013
 
 
 
Provision for project 
 
delivery risk 
 
Figure 7-2. Revised project timing diagram – including risk allowance 
 
 
7.7  Timing of the Proposal 
 
354 The revised timing of the proposal, including the short term projects and 
accounting for delivery risk is shown in table 7-2 below. 
 
 
Proposal  Timing 
(includes risk 
Augmentation 
allowance) 
Install 250 MVAr static reactive plant at Otahuhu 
2009 
Decommission the 110 kV ARI-PAK line 
2010 
Establish Drury switching station 
Implement thermal upgrade for Otahuhu-Whakamaru C line  
(short term 
projects) 
Install 100 MVAr static reactive plant at Otahuhu 
Establish 220 kV substation adjacent to existing Whakamaru 
substation (Whakamaru North) 
Cable Transition Station, South Auckland 
400 kV double circuit line from Whakamaru to cable transition station in 
2011 
South Auckland. Circuits operated at 220 kV. 
(major projects) 
2 x 220 kV cables from transition station to Pakuranga substation 
220 kV sub station at Pakuranga 
Install 3 x 120 MVA supply transformers at Pakuranga substation 
Increase operating voltage of existing 110 kV OTA-PAK line to 220 kV 
 
Table 7-2. Timing of proposal 
 
 
October 2006 
© Transpower 2006 
 Page 69 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 

The Amended Proposal is consistent with wider policy 
objectives 

355 Transpower notes the application is being submitted within the context of a wider 
regulatory framework. As such, points of reference within that wider framework 
that can reasonably be assumed to be relevant are: 
•  The purpose of Section III of Part F of the Electricity Governance Rules; 
•  The Government Policy Statement on Electricity Governance (GPS); and 
•  The Commission’s objectives 
356 These factors are considered further in the following subsections. 
8.1  The purpose of Part F 
357 Transpower submits that the following factors are relevant to the Commission’s 
consideration of the Amended Proposal: 
 
 
Would approval of the proposal contribute to this 
Purpose of Part F 
purpose? 

“facilitate Transpower’s ability to 
Yes 
develop and implement long term plans 
(including timely securing of land 
The proposal is a component of Transpower’s long term 
access and resource consents) for 
plans. 
investment in the grid” 

“assist participants to identify and 
Yes, albeit that any proposal following the Part F 
evaluate investments in transmission 
process will achieve this. 
alternatives” 
 
“facilitate efficient investment in 
Yes 
generation” 
The proposal will provide assurance of releasable 
capacity into the Upper North Island from the Lower 
North Island and the South Island.  This will provide both 
capacity and confidence to generation investors, 
particularly North Island investors in renewable 
generation. 
 
“facilitate any processes pursuant to 
Yes, albeit that any proposal following the Part F 
Part 4A of the Commerce Act 1986” 
process will achieve this. 
 
 
“enable the cost of approved 
Yes, albeit that any proposal following the Part F 
investments to be recovered through 
process will achieve this. 
the transmission pricing methodology 
applied in transmission agreements” 
 
 
Table 8-1. Alignment of Proposal with Part F of the Electricity Governance Rules 
 
October 2006 
© Transpower 2006 
 Page 70 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
8.2 The 
GPS 
358 Transpower submits that the Government Policy Statement (GPS) provides 
useful context for this Amended Proposal.  At the time of submitting this 
application, there is an extant 2004 GPS, and a draft 2006 GPS, which places 
additional emphasis on for example:  
• Facilitating 
renewables; 
•  Resilience against low probability but high impact events 
• Diversity 
 
•  Facilitating competition  
•  Early corridor acquisition 
•  Avoiding multiple low-capacity lines 
 
359 Table 8-2 considers how the proposal and alternatives address these wider policy 
issues by commenting on both the extant GPS and August 2006 Draft GPS. 
 
 
 
 
October 2006 
© Transpower 2006 
 Page 71 of 106 


 
 
 
 
Would approval of the proposal contribute to 
Government policy statement 2004 (extant) 
Government policy statement 2006 (draft) 
this purpose? 
Renewable Energy 
34A 
Encouraging the development of renewable 
Construction of the proposed project or the 220 
energy resources is a key part of the 
kV alternative would make the grid more robust 
Government’s strategy for managing climate 
through the provision of, or ability to provide, 
change and long term energy security. To 
spare capacity. This is required to better 
further this aim the Government’s objectives in 
withstand the specific characteristics and 
relation to renewable energy, are that: 
stresses placed on the system by intermittent 

generation such as wind power.  
  Undue barriers to investment in renewables 
should be reduced or removed 

•  The efficient uptake of renewable generation 
should be promoted and 
•  The national transmission grid should be 
planned in such a way as to facilitate the 
potential contribution of renewables to the 
electricity system and in a manner that is 
consistent with the Government’s climate 
change and renewables policies. 
Transmission 
Background 
79 
The way in which transmission services are 
No change 
 
provided and priced impacts directly and 
indirectly on all parts of the electricity industry, 
the economy and the environment. 
Transmission has strong natural monopoly 
characteristics, which makes it important that the 
Government sets out its policy expectations as 
October 2006                                         © Transpower 2006                                                          Page 72 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
Would approval of the proposal contribute to 
Government policy statement 2004 (extant) 
Government policy statement 2006 (draft) 
this purpose? 
to how transmission services should be provided 
and priced and how Transpower should operate. 
Poorly designed policies may, for example, 
encourage inefficient investment in generation, 
which would waste scarce capital resources and 
cause unnecessary environmental effects. 
Objectives for the provision of transmission services 
80 
The Government's objectives for the provision of 
The Government's objectives for the provision of 
 
transmission services are that: 
transmission services are that: 
 
•  the services are provided in a manner 
•  the services are provided in a manner 
It is Transpower’s view that the construction of 
consistent with the Government's policy 
consistent with the Government's policy 
the proposed project would improve grid security 
objectives for electricity 
objectives for electricity and in particular that 
and reliability into the upper North Island to a 
security of supply should be maintained at a 
level consistent with prudent planning standards. 
level required by residential, commercial and 
As a region, the upper North Island has a 
industrial users and the Government’s 
significant proportion of the residential as well as 
economic development objectives 
commercial and industrial customer base in New 
Zealand. 
 
•  the services should be provided at the 
 
standards of power quality and grid reliability 

required by grid users and consumers as 
determined by the Commission 
 
•  the transmission grid should be adequately 
The proposal – and Transpower’s wider 
resilient against the effects of low probability 
development plan in which the proposal sits – is 
but high impact events having regard to the 
designed to cover, to the extent technically and 

load which could be disrupted and the 
economically feasible, low probability but high 
duration of any disruption 
impact events. In addition, the flexibility provided 
by the eastern corridor, the Otahuhu substation 
development and the termination point at 
 
October 2006 
© Transpower 2006 
 Page 73 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
Would approval of the proposal contribute to 
Government policy statement 2004 (extant) 
Government policy statement 2006 (draft) 
this purpose? 
Pakuranga will provide flexibility that will: 

place less load at risk of a major 
substation failure; and 

improve recovery times because 
of the ability to transfer loads.  
 

The proposal and the 220 kV alternative both 
  where practical, the transmission grid should 
provide alternative supply routes (corridors) to 
provide adequate alternative supply routes to  Auckland. All three projects considered facilitate 

larger load centres having regard to the load 
a new supply point – Pakuranga- for Auckland. 
which could otherwise be disrupted and the 
duration of any disruption 
 

The proposal and 220 kV alternative both 
  competition in generation is facilitated and 
provide sufficient capacity initially to facilitate 
transmission constraints are minimised  
competition. The proposal has a slight 
advantage in that in later years there is an ability 

to readily release significant additional capacity 
whereas the 220 kV option will require the 
construction of a further line along the proposed 
or a new corridor. 
 

As mentioned above, a strong grid is required to 
  the transmission grid should be planned and 
allow for significant development of wind power 
operated in a way which helps achieve the 
and other intermittent generation. The proposal 
government’s climate change and renewable 
is part of a wider plan to upgrade the backbone 
energy objectives 

of the national grid. An anticipated outcome of 
this wider upgrade plan is that future renewable 
energy projects will be able to be incorporated 
into the country’s generation portfolio on a larger 
scale than is currently possible. 
 
October 2006 
© Transpower 2006 
 Page 74 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
Would approval of the proposal contribute to 
Government policy statement 2004 (extant) 
Government policy statement 2006 (draft) 
this purpose? 
 
•  the efficiency of transmission services 
No change 
 
should be continuously improved so as 
to produce the services grid users and 
consumers want at least cost, and 
 
•  the services are priced in a manner that:  
No change 
 
 
o  is transparent  
No change 
 
 
o  fully reflects their costs including risk  
No change 
 
 
o  facilitates nationally efficient supply, 
No change 
 
delivery and use of electricity  
 
o  promotes efficient investment in 
No change 
 
transmission or transmission 
alternatives  
 
o  promotes nationally efficient use of 
No change 
 
transmission services by grid users 
and consumers.  
 

 
  stakeholders and the public are kept well-
informed about how security of supply is to 

be maintained throughout the development 
and consideration of any grid upgrade plans. 
Investment in and maintenance of the transmission network 
 
October 2006 
© Transpower 2006 
 Page 75 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
Would approval of the proposal contribute to 
Government policy statement 2004 (extant) 
Government policy statement 2006 (draft) 
this purpose? 
86 
As part of its modeling and forecasting work, the 
No change 
 
Commission should provide for the development 
of statements of opportunities relating to 
transmission. These should: 
 
i.  incorporate electricity demand and supply 
No change 
 
forecasts  
 
ii.  enable identification of potential opportunities 
No change 
 
for:  
 

efficient management of Transpower's 
No change 
 
transmission network including 
investment in system expansions, 
replacements and upgrades  
 

transmission alternatives (notably 
No change 
 
investment in local generation, 
demand-side management, and 
distribution network augmentation)  
 
iii.  facilitate long term planning for timely 
No change 
 
securing of easements and resource 
consents  
 
iv.  be prepared at least biennially.  
No change 
 
87 
Transpower should submit grid upgrade plans to 
Transpower should develop and submit grid 
Transpower has developed and analysed the 
the Commission for approval. The grid upgrade 
upgrade plans to the Commission for approval. 
options from which the proposal and alternatives 
plans should be consistent with statement of 
have been derived. 
 
October 2006 
© Transpower 2006 
 Page 76 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
Would approval of the proposal contribute to 
Government policy statement 2004 (extant) 
Government policy statement 2006 (draft) 
this purpose? 
opportunity forecasts and demonstrate the 
rationale for all expenditure (operation, 
maintenance and capital), taking into account 
the prescribed reliability standards. The plans 
should demonstrate that the proposed 
expenditure is required to meet reliability 
standards and/or deliver the greatest net benefit 
after taking into account transmission 
alternatives. The Commission should ensure 
that affected parties are fully consulted. 
87A 
Except where urgency is required for individual 
The submission of Transpower’s GUP on 30 
projects, any grid upgrade plan submitted by 
September 2005, and the submission of this 
Transpower should be as comprehensive as 
amendment, is consistent with this objective. 
possible, ideally covering short, medium and 
longer term proposals.  This will better enable 
consideration of the interrelationships between 
projects and the wider synergies from the grid, 

including facilitating renewables, least-cost 
provision of new generation and increased 
competition between generators.  It will also 
enable consideration and approval of proposed 
expenditure for the grid as a whole over an 
appropriate timeframe (for example, five years) 
within a longer term framework. 
87B 
The grid upgrade plan should also be consistent 
The 30 September 2005 GUP, and this 
with statement of opportunity forecasts and 
amendment, meet with this requirement, 

wider government energy policy including 
including being consistent with the wider 
applicable policies on renewable generation and  government energy policy, beyond Part F of the 
climate change. 
EGR’s. 
 
October 2006 
© Transpower 2006 
 Page 77 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
Would approval of the proposal contribute to 
Government policy statement 2004 (extant) 
Government policy statement 2006 (draft) 
this purpose? 
87C 
Grid upgrade plans should demonstrate the 
The 30 September 2005 GUP, and this 
rationale for all expenditure (operation, 
amendment, are consistent with this requirement 
maintenance and capital), taking into account 
the prescribed reliability standards and good 
industry practice for power system operation. 

The plans should demonstrate that the 
proposed expenditure is required to meet 
reliability standards and/or deliver the greatest 
net benefit after taking into account 
transmission alternatives and government 
energy policy requirements. 
87D 
In the development of grid upgrade plans, the 
Transpower, as grid planner, favours the 
Government’s objective is that Transpower 
Amended Proposal as it is part of a wider plan to 
should undertake the detailed planning role 
develop the national grid, which is expected to 
(including the assessment of transmission 
strategically place the grid in a position where it 

alternatives) and the Commission should 
is best able to meet the future challenges of 
assess and approve grid upgrade plans that 
growth (both demand and in renewables) and 
satisfy the required standards and evaluation 
uncertainty, while optimising the utility of the 
criteria and reject applications that fail them. 
assets involved, including transmission 
corridors. 
87E 
The Commission should make available to 
From Transpower’s perspective the Interim 
Transpower and other stakeholders clear and 
Working Phase has contributed significantly to 

specific criteria on how any grid upgrade plans 
meeting this requirement. 
in general and any particular plan specifically 
will be assessed. 
87F 
The Commission should ensure that affected 
Transpower supports transparency in the 

parties are fully consulted on grid upgrade plans 
transmission planning process. 
 
October 2006 
© Transpower 2006 
 Page 78 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
Would approval of the proposal contribute to 
Government policy statement 2004 (extant) 
Government policy statement 2006 (draft) 
this purpose? 
87G 
In developing and considering grid upgrade 
 In Transpower’s view the Amended Proposal 
plans, Transpower and the Commission should 
will achieve levels of grid security and reliability 
seek to maintain business confidence by 
in the upper North Island, required to maintain 

making it clear that adequate security of supply 
business and investor confidence in the region. 
will be maintained. 
The latent capacity of the proposal to meet 
projected demands for many years to come 
should engender confidence. 
88 
Where the Commission approves investment by 
No change 
Transpower has proposed a process for cost 
Transpower, the cost of that investment should 
recovery as part of its application of the 
be recoverable by Transpower in accordance 
Amended Proposal, that ensures Transpower 
with the pricing methodology determined by the 
recovers its full economic cost, while at the 
Commission. 
same time allowing for monitoring of and 
reporting on Transpower’s management of costs 
incurred. 
Planning ahead 
88A 
The current pressing need for a number of 
A timely decision to approve the proposal, and 
major upgrades on the transmission system 
the future implementation of Transpower’s wider 
reflects, in part, insufficient planning and 
strategic plan to develop the national grid of 

securing of consents (or designations) and land 
which this Amended Proposal is a part, will meet 
access rights in the past.  Government is 
the concerns addressed in this point. 
concerned to ensure that this situation is not 
Transpower’s Annual Planning Report provides 
repeated in the future. 
clear indications of future augmentation needs. 
88B 
The Government therefore expects Transpower 
A timely decision to approve the proposal will 
and the Commission to ensure that Transpower 
meet the concerns addressed in this point. Rule 
changes to allow corridor designation well in 

identifies and secures the necessary land 
corridors and, to the extent possible, resource 
advance of project approval and delivery would 
consents (or designations) well in advance of 
assist in this regard by providing the basis for a 
urgent need.   Transpower should be able to 
designation and resource consents.. 
 
October 2006 
© Transpower 2006 
 Page 79 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
Would approval of the proposal contribute to 
Government policy statement 2004 (extant) 
Government policy statement 2006 (draft) 
this purpose? 
recover the reasonable costs of doing so. 
88C 
This should help the essential process of 
A timely decision to approve the proposal will 
maintaining stakeholder confidence in ongoing 
meet the concerns addressed in this point. 
security of electricity supply even if, at times, 
Transpower is of the view construction of the 
Amended Proposal will minimise future costs, 

there is some loss of flexibility around 
investment choices and some additional cost for 
including among other things the costs and risks 
electricity consumers. 
associated with the acquisition of further 
transmission corridors, in maintaining an 
adequate level of grid security and reliability. 
Environmental effects 
88D 
Final environmental requirements are 
Transpower is of the view that the Amended 
determined by consenting authorities under the 
Proposal is the best alternative when 
Resource Management Act which provides the 
considering the trade-offs between cost, grid 
reliability, security, and other benefits, and 

statutory framework for dealing with 
environmental effects. 
environmental impacts, including impacts on 
residential areas. It is recognised that the 
proposal is subject to review through the RMA 
processes. 
88E 
To the extent the Commission considers the 
The proposal has been designed to optimise the 
environmental effects of new lines, it should 
trade off between costs, benefits and 
also take into account any longer term benefits 
environmental impacts, including optimising the 
number of transmission corridors required for 

that larger capacity lines may provide by 
avoiding multiple smaller lines. 
the grid as a whole, going forward into the 
future. Transpower’s proposal only requires one 
new overhead line corridor as opposed to two 
for the alternatives. 
 
Transmission alternatives 
Non-transmission alternatives to transmission 
 
 
October 2006 
© Transpower 2006 
 Page 80 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
Would approval of the proposal contribute to 
Government policy statement 2004 (extant) 
Government policy statement 2006 (draft) 
this purpose? 
89 
As part of its consideration of transmission 
As part of the consideration of transmission 
Transpower has cooperated with the 
investments, the Commission should ensure that 
investments, the Commission should ensure 
Commission to develop generic generation 
transmission alternatives are properly 
that, in addition to considering transmission 
projects as alternatives to transmission 
considered to the extent practicable 
alternatives, non-transmission alternatives are 
investments. These have been assessed and 
considered to the extent practicable subject to 
compared with the transmission proposal and 
the following conditions:. 
alternatives. The best of these options, 
relocation of Whirinaki to Auckland, is a 
government owned generator and is the lowest 
• 
the Commission should only consider 
cost generation option only because of the sunk 
alternatives which have a high probability 
capital cost of the plant.  
of the alternatives proceeding and the 
Commission has determined that on-going 
security of supply can be maintained if the 
alternative is delayed or does not proceed 
• 
the Commission should not consider 
alternatives which are only likely to proceed 
if they are assisted by the government or 
an agency acting on behalf of the 
government unless and until the 
government has explicitly authorised or 
agreed to provide such assistance. 
90 
As part of its consideration of transmission 
No change 
 
pricing, the Commission should consider 
whether there would be net benefits in providing 
for a mechanism whereby investments in 
transmission alternatives receive payments 
reflecting some or all of the value of avoided 
transmission investment. This is a complex 
subject, and the Commission will need to take 
into account, among other things, practicalities, 
 
October 2006 
© Transpower 2006 
 Page 81 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
Would approval of the proposal contribute to 
Government policy statement 2004 (extant) 
Government policy statement 2006 (draft) 
this purpose? 
effects on incentives to invest in alternatives, 
and the extent of assurance that grid reliability 
standards will be met. 
 
Table 8-2. Alignment of Proposal with Government Policy Statement 
 
 
October 2006 
© Transpower 2006 
 Page 82 of 106 


 
 
 
 
8.3 The 
Commission’s 
objectives 
360 Transpower submits that Commission’s two principal objectives under the 
Electricity Act 1992 provides useful context.  How approval of the proposal will 
contribute to each of these is summarised below: 
 
Commission’s 
Would approval of the proposal contribute to this purpose? 
objectives 
ensure that electricity is 
Yes 
produced and delivered 
to all classes of 
Production:  the increased capacity of the proposal will enable efficient 
consumers in an 
competition between generators, leading to productive efficiencies.  Over 
efficient, fair, reliable, 
time, the increased capacity of the proposal will enable efficient 
and environmentally 
investment in generation, including renewable generation, leading to 
sustainable manner 
dynamic efficiencies also. 
and  
Delivery:  the increased capacity of the proposal will enable efficient 
 
competition between and dispatch of generation, leading to allocative 
efficiencies. 
Efficiency:  the proposal will provide the efficiencies noted above, reduce 
transmission losses, and is the most economic means of delivering 
required reliability, as measured by the GIT. 
Fairness:  the increased capacity of the proposal will avoid tilting the 
“level playing field” towards particular producers or consumers. 
Reliability:  the proposal will significantly increase reliability of electricity 
supply for consumers in the Upper North Island. 
Environmental sustainability: the increased capacity of the proposal 
will: 
enable more efficient dispatch of existing renewable energy; 
reduce transmission losses; 
enable greater investment in renewable generation in the Lower North Island and 
South Island; 
In consequence, reduce greenhouse gas emissions relative to alternatives; and 
Minimise the requirement for additional transmission corridors into the Upper North 
Island over time. 
promote and facilitate 
Yes, albeit that any proposal following the Part F process will achieve this. 
the efficient use of 
electricity. 
 
Table 8-3. Alignment of Proposal with the Commissions 
objectives 
 
361 Transpower considers that the Amended Proposal is consistent with wider policy 
objectives and hence is likely to satisfy the Commission’s exercise of any 
discretion required in approving the proposal. 
October 2006 
© Transpower 2006 
 Page 83 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
9 Recommendation 
362 It is recommended that the Commission approve the Amended Proposal on the 
grounds that it: 
•  complies with the Rules; 
•  meets the GRS;  
•  passes the GIT; and  
•  is consistent with GEIP.  
Further, it is the project that is most aligned with the draft changes proposed to the 
GPS, particularly with respect to an emphasis on renewable generation, provision of 
diversity of supply to Auckland and minimisation of the number of corridors required 
for transmission. 
 
October 2006 
© Transpower 2006 
 Page 84 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
Appendix A  Glossary of Terms 
 
Term 
Description 
AIS 
Air Insulated Switchgear 
Alternative Project 
Projects that are reasonable to consider as alternatives to the 
 
proposed investment in applying the Grid Investment Test (GIT), in 
accordance with rule 19, Schedule F4, Part F Section III, 
Electricity Governance Rules (EGRs). 
 
Amended Proposal 
The proposal, for a new line between Auckland and Whakamaru, 
 
which is outlined in this application for approval, dated 30 
September 2006. (the “North Island Grid Upgrade project”). 
 
North Island Grid 
The project, for a new line between Auckland and Whakamaru, 
Upgrade Project 
which is outlined in this application for approval, dated 30 
September 2006 (the “Amended Proposal”). 
 
Commission 
The Commission, a Crown entity set up under the Electricity Act to 
oversee New Zealand’s electricity industry and markets. 
deterministic limb of the 
The deterministic limb of the GRS defines that the grid satisfies 
GRS 
the grid reliability standards if, with all assets that are reasonably 
 
expected to be in service, the power system would remain in a 
satisfactory state during and following any single credible 
contingency event occurring on the core grid. (Refer rule 4.2, 
Schedule F3, Part F Section III, Electricity Governance Rules 
(EGRs)). 
 
Draft Decision 
The Commission’s consultation paper explaining its draft decision 
 
on the Original 400 kV Project, dated 27 April 2006. 
economic investment 
Investments in the grid that can be justified on the basis of the 
 
Grid Investment Test under section III of part F, Electricity 
Governance Rules (EGRs), and are not reliability investments. 
 
EGRs 
Electricity Governance Rules. In the context of this document, it 
generally refers to Part F Transport, Section III Grid Upgrade and 
Investments, 16 February 2006. 
 
expected project costs 
Expected project costs (or expected costs) represent the 
estimated (P50) cost plus a contingency for scope accuracy. 
Scope accuracy allows for unexpected variations in the design 
scope and a standard allowance, based on experience, for items 
not considered in the design. 
 
 
October 2006 
© Transpower 2006 
 Page 85 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
expected unserved 
A forecast of the aggregate amount by which the demand for 
energy 
electricity exceeds the supply of electricity at each grid exit point 
as a result of likely planned or unplanned outages of primary 
transmission equipment. 
 
GEIP 
Good Electricity Industry Practice. Refer section 6.1.2 of this 
document. 
 
GIS 
Gas Insulated Switchgear 
GIT 
Grid Investment Test. A test for reliability investments and 
economic investments in the grid developed in accordance with 
rule 6 of section III of Part F, Electricity Governance Rules 
(EGRs). The specific rules defining the Grid Investment test, as 
developed according to the process in rule 6 of section III, are set 
out in Schedule F4 of section III of Part F. 
 
GPS 
Government Policy Statement on Electricity Governance. Refer 
section 8.2 of this document. 
 
GRS 
Grid Reliability Standards. Standards for reliability of the grid 
developed in accordance with rule 4 of section III of part F, 
Electricity Governance Rules (EGRs), including variations, but 
does not include interim grid reliability standards. The standards 
themselves as currently developed are detailed in rule 4 of 
Schedule F3, section III of Part F. 
 
GUP 
Grid Upgrade Plan. A plan for grid expansions, replacements and 
upgrades, developed in accordance with rule 12 of section III of 
part F, Electricity Governance Rules (EGRs). 
 
HTC 
High Temperature Conductor.  
A type of overhead transmission line conductor that is capable of 
sustained operation up to temperatures around 200 degrees 
Celsius 
HVDC Upgrade Project 
The proposal to upgrade the HVDC inter-island link between 
 
Benmore in the South Island and Haywards in the North Island, as 
detailed in Volume III of the Original GUP, submitted to the 
Commission on 30 September 2005. 
 
LRMC 
Long Run Marginal Cost 
modelled projects 
Transmission augmentation projects and non-transmission 
projects, other than the proposed investment and alternative 
projects, which are likely to occur in a market scenario, are 
reasonably expected to occur in that market development scenario 
within the time horizon for assessment of the market benefits and 
costs of the proposed investment and alternative projects, and the 
likelihood, nature and timing of which will be affected by whether 
the proposed investment or any alternative project proceeds. 
 
 
October 2006 
© Transpower 2006 
 Page 86 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
N-G-1 
System security standard which is achieved when the power 
 
system remains in a satisfactory state during and following any 
single credible contingency event occurring on the core grid 
(defined as N-1 security standard), whether Otahuhu ‘C’ generator 
is in or out of service. 
 
Original GUP 
Transpower’s first GUP, submitted to the Commission on 30 
September 2005, containing a number of projects including the 
Original 400 kV Project and the HVDC Upgrade Project. 
 
Original 400 kV Project 
The original proposal to build a 400 kV line between Otahuhu and 
Whakamaru, as detailed in Volume II of the Original GUP, 
submitted to the Commission on 30 September 2005. 
 
probabilistic limb of the 
The probabilistic limb of the GRS defines that the grid satisfies the 
GRS 
grid reliability standards if the power system is reasonably 
 
expected to achieve a level of reliability at or above the level that 
would be achieved if all economic reliability investments were to 
be implemented. 
 
reliability investment 
Investments by Transpower in the grid, or alternative 
 
arrangements by Transpower, the primary effect of which is, or 
would be, to reduce expected unserved energy. 
 
Transition station 
A site where the transition is made from an over-head 
transmission line to underground cables. 
Transpower 
Transpower New Zealand Limited, owner and operator of New 
Zealand’s high-voltage electricity network (the national grid). 
UNI or Upper North Island   Includes the Auckland and Northland regions. The Auckland 
region is the area bordered by and including Bombay 110 kV 
Substation in the south, and Penrose 220 kV Substation and 
Mount Roskill 110 kV Substation in the north. The Northland 
region covers the area north of and including Hepburn Road 110 
kV Substation. 
 
 
 
 
October 2006 
© Transpower 2006 
 Page 87 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
Appendix B  Cross Reference with September 2005 GUP 
 
If 400 kV GUP, 
If yes or in part, 
Part of 400 kV 
Section of September 
has it been 
which sections 
GUP or HVDC 
2005 GUP 
superseded by 
of this 
GUP? 
this application? 
application? 
Volume 1 
 
 
 
Executive Summary 
 
 
 
Section 1 
Both 
Part 
Executive 
Summary 
Sections 2 to 6 
Both 
No 

Section 7 
400 kV 
All 
Executive 
Summary 
Section  8 
HVDC 
No 

Section 9 
Both 
Part 
Executive 
Summary 
 
 
 
 
Comprehensive Plan 
HVDC 
No 

for Asset Management 
and Operation of the 
Grid 

 
 
 
 
Contracted 
HVDC 
No 

Investments 
 
 
 
 
Volume 2 
 
 
 
Executive Summary 
 
 
 
and Introduction 
Section 1 
400 kV 
Part 
Section 1 
Section 2 
400 kV 
All 
Section 2 
Section 3 
400 kV 
No 
Section 3 
Section 4 
Section 4 
400 kV 
Part 
Section 5.1 
Section 5 
400 kV 
All 
Section 7 
Section 6 
400 kV 
Part 
Section 3 
Section 7 
400 kV 
No 
Section 4 
Section 8 
400 kV 
All 
Section 5 
Section 9 
400 kV 
All 
Section 5 
Section 10 
400 kV 
No 

 
October 2006 
© Transpower 2006 
 Page 88 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
If 400 kV GUP, 
If yes or in part, 
Part of 400 kV 
Section of September 
has it been 
which sections 
GUP or HVDC 
2005 GUP 
superseded by 
of this 
GUP? 
this application? 
application? 
Appendix A 
400 kV 
All 
Attachments 
 
 
 
 
Part 1 
 
 
 
Section 1 
400 kV 
Part 
Section 5 
Section 2 
400 kV  
 
 
Section 2.1 
400 kV 
All 
Section 5 
Section 2.2 
400 kV 
Part 
Section 5 
Section 2.3 
400 kV 
Part 
Section 5 
Section 2.4 
400 kV 
Part 
Section 5 
Section 3 
400 kV 
No 

Section 3.1 
400 kV 
No 

Section 3.2 
400 kV 
No  

Section 3.3 
400 kV 
No  

Section 3.4 
400 kV 
Part 
Section 2.4 
Section 3.5  
400 kV  
All 
Section 7 
Appendix 1A 
400 kV 
All 
Section 5 
Appendix 1B 
400 kV 
No 

Appendix 1C 
400 kV 
All 
Section 5 
Appendix 1D 
400 kV 
All 
Section 7 
 
 
 
 
Part 2 
 
 
 
Section 1 
400 kV 
All 
Section 3 
Section 2 
400 kV 
All 
Section 3 
Section 3 
400 kV 
All 
Section 6 
Section 4 
400 kV 
All 
Section 6 
Section 5  
400 kV 
Part 
Attachment D 
Section 6  
400 kV 
Part 
Attachment D 
Section 7 
400 kV 
All 
Section 7 
Appendix IIA 
400 kV 
All 
Attachment D 
Appendix IIB 
400 kV 
No 
Attachment D 
Appendix IIC 
400 kV 
All 
Section 5 
Appendix IID 
400 kV 
No 

 
 
 
 
 
October 2006 
© Transpower 2006 
 Page 89 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
If 400 kV GUP, 
If yes or in part, 
Part of 400 kV 
Section of September 
has it been 
which sections 
GUP or HVDC 
2005 GUP 
superseded by 
of this 
GUP? 
this application? 
application? 
Part 3 
 
 
 
Section 1 
400 kV 
No 

Section 2 
400 kV 
Part 
Section 3 
Section 3  
400 kV 
No 

Section 4, 4.1, 4.2 
400 kV 
No 

Section 4.3  
400 kV 
All 
Section 4 
Attachment D 
Section 4.4 
400 kV 
Part 
Section 6 
Section 4.5 
400 kV 
All 
Section 5 
Section 6 
Attachment D 
Section 4.6 
400 kV 
No 

Section 4.7  
400 kV 
No 

Section 4.8  
400 kV  
No 

Section 4.9  
400 kV  
No 

Section 4.10 
400 kV  
No 

Section 4.11 
400 kV  
No 

Section 4.12 
400 kV  
No 

Section 4.13 
400 kV  
Part 
Section 6 
Section 5  
400 kV  
Part 
Section 6 
Appendix IIIA 
400 kV  
No 

Appendix IIIB 
400 kV 
All 
Section 7  
Appendix D 
 
 
 
 
Part 4 
400 kV 
All 
Section 6 
Appendix E 
Attachments 
 
 
 
 
Part 5 
400 kV 
All 
Section 5 
Appendix C 
 
 
 
 
Supporting 
 
 
 
Documents 
1. Request for 
400 kV 
No 

Information 
 
October 2006 
© Transpower 2006 
 Page 90 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
If 400 kV GUP, 
If yes or in part, 
Part of 400 kV 
Section of September 
has it been 
which sections 
GUP or HVDC 
2005 GUP 
superseded by 
of this 
GUP? 
this application? 
application? 
2. Grid development 
400 kV  
All 
Attachment D 
Plan – 400 kV – Part 1 
3. Grid development 
400 kV  
All 
Attachment D 
Plan – 400 kV – Part 2 
4. Grid development 
400 kV  
All 
Attachment D 
Plan – 2200 kV – Part 1 
5. Grid development 
400 kV  
All 
Attachment D 
Plan – 220 kV – Part 2 
6. Main Transmission 
400 kV 
Part 
Section 6 
System Planning 
Criteria 
7. Planning 
400 kV 
All 
Section 6 
Assumptions – Demand 
Attachment D 
and generation 
forecasting 
8. Security of supply 
400 kV 
No 

into Upper North Island 
– Comparison of High 
Voltage Direct Current 
and High Voltage 
Alternating Current Grid 
Upgrade Alternatives 
9. 300/400 kV 
400 kV 
No 

Transmission Line 
Upgrade Study 
10. Monte Carlo 
400 kV 
No 

Analysis of Auckland 
Area thermal Plant 
Availability 
11. Comparison of 
400 kV  
No 

reliability of 400 kV 
underground cable with 
an overhead line for a 
200 km circuit  
12. peer review of 
400 kV 
No 

choice of voltage for 
development of the 
New Zealand Grid 
13. Security of supply 
400 kV 
All 
Attachment D 
into Auckland – review 
of system capacity 
limitations 
14. Methodology to 
400 kV 
All 
Attachments 
calculate lower bound 
of competition benefits 
 
 
 
 
 
October 2006 
© Transpower 2006 
 Page 91 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
If 400 kV GUP, 
If yes or in part, 
Part of 400 kV 
Section of September 
has it been 
which sections 
GUP or HVDC 
2005 GUP 
superseded by 
of this 
GUP? 
this application? 
application? 
Volume 3 
HVDC 
No 

 
 
 
 
Volume 4 
Grid Development 
No 

Proposals 
 
 
 
 
 
October 2006 
© Transpower 2006 
 Page 92 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
Appendix C  Cost breakdowns of alternative projects 
Option 1: 220 kV into Pakuranga and Otahuhu 
 
Total -Expected 
Year 
Augmentation 
Cost 
($ ,000) 
2009  350 MVAR Static compensation 
                9,185  
Upgrade OTA-WKM C 
                4,615  
Decommission 110kV ARI-PAK Line 
                5,032  
2010  Drury Switching Station 
              21,227  
Drury Switching Station - Lines 
                2,047  
220kV Line (2 Chukar @ 75C) WKM-ORM 
            277,068  
WHN 220 kV Substation 
              10,688  
WKM Subs Work 
                3,807  
OTA Subs Work 
                5,242  
OTA Enabling Work 
                3,417  
2012  ORM Cable Termination Station 
              10,755  
2x220kV cables ORM-PAK 
            117,888  
220kV Sub Station at PAK 
              54,231  
Shift existing OTA-PAK 110kV circuits to operate at 220kV 
                   688  
1st PAK-PEN cable 
              61,159  
PEN GIS Sub 
              40,033  
Reconductor ARI-HAM 1&2 to Nitrogen 75C conductor 
              12,324  
2013  BOB Interconnector 
                9,479  
100 MVAr Static compensation 
                4,297  
ORM Civil Works 
                8,532  
100 MVAr Dynamic compensation 
              25,159  
2017  2nd PAK-PEN cable 
              61,159  
PAK Subs Work 
                6,866  
PEN Subs Work 
                3,271  
2019  100MVAR Static compensation  
                4,282  
110kV OTA-WIR cable; close the WIR bus breaker 
              35,223  
50% series compensation on the ORM-WKM 1&2 ccts 
              42,021  
Switching station at ORM  
              12,478  
2021  One ORM-OTA 220kV cable 
              69,018  
1st OTA-PEN cable 
              60,949  
PEN Subs Work 
                3,271  
OTA Subs Work 
                6,122  
2022  200 MVAR Static compensation 
                6,541  
2nd ORM-OTA Cable 
              67,916  
2024  OTA Subs Work 
                   779  
ORM Subs Work 
                1,747  
100 Mvar Static compensation- 
                4,277  
2026  Series current limit reactor - 20 Ohm 
              18,874  
2027  100 MVAR Dynamic compensation 
              25,164  
100 MVAR Static compensation (HLY) 
                4,277  
2029  250 MVAR Static compensation (OTA) 
                7,422  
2nd 220kV Double Circuit between WKM-ORM 
            262,782  
WHN Subs work 
                4,386  
2031  ORM Subs Work 
                4,318  
1st 220kV cable between SAD-PAK 
            107,555  
PAK Subs Work 
                   610  
 
Continued next page 
 
 
October 2006 
© Transpower 2006 
 Page 93 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
 
2nd OTA-PEN cable 
              60,949  
2032  PEN Subs Work 
                3,271  
OTA Subs Work 
                1,444  
2035  250 MVAR Static compensation 
                7,422  
2036  PST on ARI-BOB 
                9,318  
1st cable SAD-OTA Cable 
              96,485  
2037  ORM Subs Work 
                2,381  
OTA Subs Work 
                6,639  
2038  150 MVAR Static compensation 
                5,535  
2040  Series Compensate WKM-ORM  3&4 circuits by 50%. 
              42,016  
2042  400 MVAR Static compensation 
              10,698  
Option 1 - 220 kV into Pakuranga and Otahuhu 
 
 
 
October 2006 
© Transpower 2006 
 Page 94 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
Option 2: 220 – 400 kV Staged to Pakuranga (Proposed Investment) 
 

Total - 
Expected 
Year 
Augmentation 
Cost 
($ ,000) 
2009 
350 MVAR Static compensation 
9,088
Uprate HLE-HAM-WKM section of OTA-WKM C line to twin Goat @ 80C 
4,573
Decommission 110kV ARI-PAK Line 
4,979
2010 
Drury Switching Station 
         21,227 
Drury Switching Station - Lines 
2,047 
2x400kV WKM-ORM ccts operated at 220kV 
335,219
WHN 220 kV Substation 
10,578
WKM Sub work 
3,770
OTA Enabling Work 
3,381
OTA Subs Work 
5,192
2012 
2x220kV ORM-PAK cables 
116,700
Cable Termination at ORM 
10,719
220kV substation at PAK 
57,233
Convert OTA-PAK 110kV ccts to 220kV 
680
1st PAK-PEN cable 
60,529
PEN GIS 
39,615
2013 
Reconductor ARI-HAM 1&2 to Nitrogen 75C conductor 
12,217
BOB Interconnector 
9,380
2015 
100 MVAr Static compensation 
4,232
ORM Civil Works 
9,092
100 MVAr Dynamic compensation 
24,896
2017 
2nd PAK-PEN cable 
60,529
PAK Subs Work 
1,115
PEN Subs Work 
3,237
2019 
100MVAR Static compensation  
4,232
1x220kV ORM-OTA cable 
68,329
ORM Subs Work 
13,305
2x55% compensation on WKM-ORM ccts 
45,684
2021 
Install 110kV OTA-WIR cable - close the WIR bus breaker 
34,855
1x220kV PEN-OTA cable 
60,316
PEN Subs Work 
3,237
OTA Subs Work 
6,058
2022 
200 MVAR Static compensation 
6,473
100 MVAr Dynamic compensation 
24,896
2nd 220kV OTA-ORM cable 
67,239
2023 
OTA Subs Work 
771
ORM Subs Work 
1,724
2026 
100 Mvar Static compensation 
4,232
2027 
150 MVAR Static compensation -reactive plan of 25/9 
5,477
2028 
Install 20 Ohm reactor on OTA-WKM A&B line 
18,672
ORM Civil Works 
10,391
2029 
100 MVAR Static compensation  
4,232
 
Continued next page 
 
 
 
October 2006 
© Transpower 2006 
 Page 95 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
 
2030 
300 MVAR Dynamic compensation  
48,179
150 MVAR Static compensation 
5,477
2031 
Install cable cooling ORM-PAK cables 
8,465
400kV sub at WKM 
112,295
400kV sub at ORM 
115,690
2033 
2nd PEN-OTA cable 
60,316
PEN Subs Work 
3,237
Install cable cooling ORM-OTA cables 
8,465
2037 
PST on ARI-BOB 
9,221
2040 
300 MVAR Static compensation 
8,216
2042 
300 MVAR Static compensation 
8,216
 
Option 2: 220 – 400 kV Staged to Pakuranga (Proposed Investment) 
 
 
October 2006 
© Transpower 2006 
 Page 96 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
Option 3: Duplexing of Whakamaru – Otahuhu A&B 
 
Total - Expected 
Year 
Augmentation 
Cost 
($ ,000) 
300 MVAR Static compensation 
               8,290 
2009  
100 MVAR Dynamic compensation 
             25,123 
BOB Interconnector 
               9,465 
2010  
Drury Switching Station 
              21,227 
Drury Switching Station - Lines 
                2,047 
Uprate HLE-HAM-WKM section of OTA-WKM C line to 
2011 
               4,473 
2xGoat 80C 
PAK 220kV sub station 
             58,242 
Convert existing OTA-PAK 110kV to 220kV  
                  687 
OTA Enabling Work 
               3,412 
2012 
OTA Subs Work 
               4,208 
1st PAK-PEN cables 
             61,071 
PEN GIS Sub 
             39,965 
Duplex OTA-WKM A&B ccts, deviate line from Sth 
            221,666 
2014  
Auckland to PAK 
PAK Subs Work 
               2,247 
South Auck Sub 
               3,357 
 2015 
Redoubt Rd - PAK cables 
            136,488 
100 MVAR Static compensation 
               4,271 
Second PAK-PEN cable 
             61,071 
PAK Subs Work 
               6,856 
2016 
PEN Subs Work 
               3,326 
200 MVAR Static compensation 
               6,537 
Reconductor ARI-HAM 1&c ccts to Nitrogen 75C 
             12,309 
2017 
Bussing of OTA-WKM A&B lines at HLE 
             10,541 
OTA-WIR 110kV Cable 
             35,172 
2019  
110kV ARI-PAK line decommissioned 
               5,025 
220kV D/C WKM-ORM line (twin Chukar 75C) 
            274,791 
WKM Subs Work 
               2,865 
2x220kV cables from ORM-PAK 
            146,655 
2020 
PAK Subs Work 
                  609 
3rd PAK-PEN cable 
             61,071 
PEN Subs Work 
               3,266 
Cable transition at ORM 
             10,600 
200 MVAR Static compensation 
               6,532 
2025 
PST on ARI-BOB 
               9,305 
2027 
100 MVAR Static compensation 
               4,271 
2029 
250 MVAR Static compensation 
               7,411 
50% Series Compensation on ORM-WKM 1&2 ccts 
             41,960 
Switching Station at ORM 
             15,898 
2031 
1st and 2nd ORM-OTA cables 
            128,974 
OTA Subs work 
               7,984 
2033 
50 MVAR Dynamic compensation 
             16,581 
 
Continued next page 
 
 
 
October 2006 
© Transpower 2006 
 Page 97 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
 
 
220kV Double Circuit between WKM-Sth AKL 
            272,882 
WKM Subs Work 
               2,609 
ORM Subs Work 
               4,488 
2035 
1st OTA-PEN cable 
             60,862 
OTA Subs work 
               7,233 
PEN Subs Work 
               3,266 
3rd OTA-Sth Akl cable 
            106,213 
2042 
450 MVAR Static compensation 
             10,682 
 
Option 3: Duplexing of Whakamaru – Otahuhu A&B 
 
October 2006 
© Transpower 2006 
 Page 98 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
Option 4: High Temperature Conductor 
 

Total – 
Year 
Augmentation 
Expected Cost 
($ ,000) 
250 MVAr static compensation 
                7,405  
2009  100 MVAr Dynamic compensation 
              24,840  
2010  BOB interconnector 
                9,359  
Drury Switching Station 
              21,227  
Drury Switching Station - Lines 
                2,047  
2011  Thermal Uprating of sections of OTA_WKM C south of 
                4,564  
HLE with Goat 80 C 
150 Mvar static compensation 
                5,047  
PAK 220kV substation 
              57,105  
3x120MVA supply transformers at PAK 
2012  1st PAK-PEN cable 
              60,394  
Convert existing 110kV OTA-PAK circuits to 220kV 
                   679  
operation 
OTA-WKM A and B lines - HTC Duplex 
Disconnect OTA-WKM A and B sections between SAK 
and OTA 
            436,225  
2014  OTA-WKM A and B lines redirected from SAK to PAK with 
1 cable per line 
SAK Cable transition station 
                3,417  
2x220 cable SAK-PAK 
            135,001  
2015  Second PAK-PEN cable  
              60,394  
Reconducting ARI-HAM 1 and 2 circuits to Nitrogen at 75C 
              12,194  
2016 
100 MVAr static compensation 
                4,274  
2017  OTA-WKM A and B lines 40% Series Capacitance 
              45,766  
110kV cable from OTA to WIR 
              34,776  
2019  Switching station at SAD 
              13,275  
150 Mvar static compensation 
                5,451  
2021  200 Mvar static compensation 
                6,477  
2022  350 Mvar static compensation 
                9,063  
200 Mvar static compensation 
                6,477  
OTA_WKM C – Duplex HTC (all sections but HLE to  
            275,388  
HAM)  
OTA-WKM C installed with 25% series capacitance on 
2023  OTA-HLE, and HLE-WKM sections and 30% series 
              80,730  
capacitance on HAM-WKM section. 
OTA_WKM A and B bussed at HLE 
              10,461  
1st Cable from OTA to PEN 
              60,181  
2025  PST on ARI-BOB 
                9,305  
2027  450 MVAr static compensation 
              10,537  
Decommission ARI_PAK 110kV line 
                4,968  
2028  1 Ohm series reactor on OTA_SAK bonded pair 
                2,484  
Construction new 2 duplex Chukar circuits from WKM to 
2029 
            272,637  
ORM 
2030  2nd Cable from OTA to PEN 
              60,281  
 
Continued next page 
 
 
 
October 2006 
© Transpower 2006 
 Page 99 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
 
 
Cable transition Station at ORM 
              10,712  
2032  New cable from ORM to OTA 
              68,183  
2035  150 Mvar static compensation 
                5,451  
2nd cable from ORM to OTA 
              68,183  
2039  450 MVAr static compensation 
              10,537  
150 Mvar dynamic compensation 
              31,050  
30% series compensation on ORM_WKM circuits 
              45,581  
2040  3rd Cable from PAK to PEN 
              60,394  
250 MVAr Dynamic compensation 
              43,470  
2041  500 Mvar static compensation 
              11,178  
 
Option 4: High Temperature Conductor 
 
 

 
October 2006 
© Transpower 2006 
 Page 100 of 106 


 
 
Appendix D  Short Term Augmentation Projects  
 
 
Assumptions: 

•  2010 High demand used as base and the loads scaled to obtain transfer limit (Huntly Generation re-dispatched to get maximum limit) 

•  Arapuni Generation dispatch at180 MW 

•  Huntly East (Ohinewai) switching station commissioned 

•  OTA-WKM A&B lines thermally upgraded to 75 degrees 

•  HVDC dispatch at 1400 MW 

•  PSTs set to have 95% flow post contingency where possible on 110 kV circuits out of ARI, phase shift range +/-30° 

•  PSTs set to have 100% flow post contingency on 220 kV circuits 

•  Transfer Limits quoted are approximate values and the accuracy may vary slightly due to the numerical algorithms used 
 
 
 
Deferral 
Deferral  Benefit 
ARI-PAK 
ARI-PAK 
Cost 
benefit 
benefit 
- Cost 
in 
out 
($m) 2 
No 
Description 
Comment 
(years) 3 
($m) 4 
($m)  
Upper North Island 
 
 
 
 
Transfer Capacity(MW) 

Base  
2668 
2510* 
  
 
 
 
 
By itself, this project has marginal 

PSTs on HLE-OTA 1 & 2 Circuits 
Minimal 
Minimal 
impact on the transfer capacity 



No benefit 
Thermal upgrade of OTA-WKM C 
By itself, this project has marginal 

Minimal 
Minimal 
line upgrade to 80 deg  
impact on the transfer capacity. 



No benefit 
700 MVA PSTs required (Phase shift 
PSTs on HLE-OTA 1 & 2 + OTA-

2753* 
2667* 
requirement to be ascertained).  
64.6 

31.9 
-32.7 
WKM C line upgrade. 
Lower  HVDC dispatch is likely to 
October 2006 
© Transpower 2006 
 Page 101 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
Deferral 
Deferral  Benefit 
ARI-PAK 
ARI-PAK 
Cost 
benefit 
benefit 
- Cost 
in 
out 
($m) 2 
(years) 3 
($m) 4 
($m)  
reduce the  transfer limit, but is not 
quantified.  
With ARI-PAK in the circuits into ARI 
from the south particularly KIN-LFD 
PSTs on ARI-HAM, ARI-BOB AND 
will overload for a HAM-WKM 

ARI-PAK+OTA-WKM C line 
2711 
2618 
outage. Overloading (up to approx 
32.8 

31.9 
-0.9 
upgrade 
165%) as far back as TRK ICTs, no 
overloading without ARI-PAK in 
service 
With ARI-PAK in the circuits into ARI 
from the south particularly KIN-LFD 
Re-conductoring of HAM-BOB 
will overload for a HAM-WKM 

circuits+PSTs+OTA-WKM C line 
2707 
2623 
outage. Overloading (up to approx 
57.2 

31.9 
-25.3 
upgrade 
165%) as far back as TRK ICTs, no 
overloading without ARI-PAK in 
service 
Increases transfer from Taranaki and 
Huntly  However, if the generation 
south of Whakamaru is replaced from 

Drury switching station 
2665* 
2659* 
the Central North Island generation 
23.3 

31.9 
+ 8.6 
then the transfer limit drops 
substantially. Low Huntly generation 
will also have a similar effect, 
 
October 2006 
© Transpower2006  
Page 102 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
Deferral 
Deferral  Benefit 
ARI-PAK 
ARI-PAK 
Cost 
benefit 
benefit 
- Cost 
in 
out 
($m) 2 
(years) 3 
($m) 4 
($m)  
Increases transfer from Taranaki and 
Huntly as well as from Whakamaru. 
However, if the generation south of 
Drury switching station+ OTA-WKM 
31.9 to 
+ 4.0 to 

2764* 
2736 1 
Whakamaru is replaced from the 
27.9 
1 to 2 5 
C line upgrade 
Central North Island generation then 
61.7 
+ 33.8 
the transfer limit is likely to reduce. 
The 110 kV circuits between Kinleith 
Re-conductoring of ARI-PAK+PST 
and Tarukenga and inter connector 

on ARI-PAK +OTA-WKM C line 
2751 




No benefit 
at Tarukenga overload up to approx 
upgrade 
160% and needs augmentation 
The 110 kV circuits between Kinleith 
OTA-WKM C line upgrade, Drury 
and Tarukenga and inter connector 
switching station, Recondutor ARI-
10 
2805 
2724 
at Tarukenga overload up to approx 
Over 80 

31.9 
< - 48.1 
PAK and HAM-BOB, PSTs on all 
200%, where ARI-PAK is in service 
110 kV circuits north of ARI 
and needs augmentation 
OTA-WKM C line upgrade, Drury 
The 110 kV circuits between Kinleith 
switching station, Recondutor ARI-
and Tarukenga and inter connector 
11  PAK and HAM-BOB, PSTs on all 
2879 
2803 
at Tarukenga overload up to approx 
Over 140 

61.7 
< - 78.3 
110 kV circuits north of ARI, PSTs 
205%, where ARI-PAK is in service 
on HLE-OTA circuits 
and needs augmentation 
 
Notes: 
1. BOB-WIR-OTA circuit breakers are open at BOB to prevent overloading on the HAM-BOB circuits reducing the transfer limit 
2. Costs are provided only for those options that provide more than one year of deferment of the major project. 
3. Deferment is assessed only for options with ARI-PAK out. Years of deferment is assessed on the basis of likely generation dispatch scenarios. 
4. Refer to Appendix D of this report “Assessment of the value of deferring investments” 
5. Option 8 provides at least one year of deferral, with possibly more under favourable generation dispatch scenarios. It also provides benefit during summer 
peak periods when Huntly generation is often constrained down. 
 
 
October 2006 
© Transpower2006  
Page 103 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
Application for Approval -  20 October 2006 
Appendix E  Assessment of the value of deferring investments  
Delaying the need for an investment may have a benefit if the cost of delaying the 
investment is less than the deferral benefit.  
 
The value of money to be spent now is higher than money that can be spent later as 
you could alternatively invest the money (e.g. in governmental bonds – considered a 
risk free investment) and get a return. Thus, the later an investment is made, the 
more other benefits (such as return of investments) could have been achieved in the 
meantime. Therefore, money spend in years to come are lowered by a discount rate 
to adjust for the benefits the capital can provide in the meantime. This is the origin of 
the deferral benefit.  
 
The deferral benefit arises from applying the discount rate on the given investment 
for a longer period of time. For example, if using a discount rate of 7%, delaying an 
investment by one year will cause the present value of the costs to be lowered by 
1/1.07 = 93.4%. For an investment with a present value of $100 million being 
delayed a year, the deferral benefit would then be $6.6 million.  
 
In the context of the Auckland Transmission Upgrade proposal, two types of deferral 
are of interest. They are explained below.  
 
 
Deferral of part of the investment 
In the economic analysis of the transmission alternatives, several short term options 
(see Appendix D) for deferring the need of the first major part of the proposed 
investment one or two years are analysed.  
 
The analysis is based on the year 2010 – i.e. the project need date in 2012 brought 
forward two years to reduce risks. The costs of those options are to compared with 
the deferral benefits, which are:  
 
400 kV in 2010 
Defer 1 year 
Defer 2 years 
Benefits in $million 2006 
31.9 
61.8 
 
Table E-1. Project deferral benefits 
 
The values arise from delaying the investments from the table below, which are all 
due in 2010 if no deferral projects are committed.  
 
Description 
2x400kV WKM-ORM ccts operated at 220kV 
WHN 220 kV substation 
WKN Sub work 
OTA Enabling Work 
OTA Sub Work 
2x220kV ORM-PAK cables 
Cable Termination at ORM 
October 2006 
© Transpower 2006 
 Page 104 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
220kV substation at PAK* 
Convert OTA-PAK 110kV ccts to 220kV* 
1st PAK-PEN cable* 
PEN GIS* 
 
* These projects are needed in 2012 at latest for the strengthening of the across harbour capacity. 
Hence, the can only be deferred two years.  
 
Table E-2. Deferral components 
 
 
The costs of those sum up to $559 million. This includes the associated property 
costs as well as the costs of investigations, project management and consenting. To 
this, scoped contingencies (between 15% and 25%) have been added to capital 
costs and project management costs. This gave a total of $642 million.  
 
Looking at the change of the net present value (NPV) of investing in either 2010, 
2011 or 2012, the following benefits NPV of delaying the investments are found:  
•  One year deferral: 
$29.9 million 
•  Two years deferral:  $58.0 million 
 
To this is added the change in NPV of the operations and maintenance costs, which 
is $2.0 million for one year and $3.8 million for two years. Hence, the value 
presented in the table for a one year deferral is $31.9 million and the value of two 
years of deferral is $61.8 million.  
 
Deferring the project more than two years adds around $19 million per year. This is 
lower than the value of each of the two first years, but is due to the fact than certain 
components are due in 2012 latest.  
 
Deferral of the full investment stream 
When analysing the generation alternatives, it has been assumed that these options 
delay all projected investments from the initial and on to 2042 (i.e. the full 
development plans presented in Appendix C). This might not be the case, either 
because parts of the investments may have been committed before an investor 
commits itself to building a generator (or potentially a contract can be signed with a 
supplier of a DSM initiative) – or because some of the components in the 
development plans will be needed anyway. However, to bias the analysis towards 
generation, this has been the assumption.  
 
The deferral benefits include both investments and operations and maintenance 
costs. The table below shows the deferral value of delaying the transmission 
reference case (building 220 kV lines) a different number of years.  
 
 
 
 
 
 
 
 
 
 
October 2006 
© Transpower2006 
 Page 105 of 106 

NORTH ISLAND GRID UPGRADE PROJECT–AMENDED PROPOSAL 
APPLICATION FOR APPROVAL -  20 OCTOBER 2006 
220 kV reference case 
Year of commissioning 
$million 2006 
2011                                2013 
NPV of capital costs and O&M costs 
770 
710 
Benefits – 1 year delay 
50 
46 
Benefits – 2 years delay 
97 
90 
Benefits – 3 years delay 
141 
130 
Benefits – 4 years delay 
183 
168 
Benefits – 5 years delay 
221 
204 
Benefits – 6 years delay 
257 
237 
 
Table E-3. Deferral value of delaying the transmission reference case 
 
 
A NPV of the capital costs and operation and maintenance costs (O&M) are based 
on the GIT model runs presented in Attachment E (Economic Analysis of 
Alternatives report). For the reference case, this states a mean NPV of the capital 
costs if the first part is commissioned in 2013 of $687 million while mean O&M costs 
is $24 million giving $710 million in total. A sensitivity analysis of this run was made 
when the first part of the investment, in general the parts due up to 2013, was moved 
advanced two years to a 2011 commissioning date. This gave $770 million in total 
based on $743 million in mean capital costs and $27 million in O&M costs. 
 
It can be seen that the deferral benefits are quite a lot higher than in the previous 
example, but here the full investment stream is deferred while it in the earlier case 
only the building of the first line was deferred.   
 
 
 
 
October 2006 
© Transpower2006 
 Page 106 of 106