COVER REPORT - COMMITTEE MEETING 
 
Title of Report: 
 Tidal Barrier Pre-Feasibility Study Consultation 
 
Meeting of: 
 Infrastructure, Transport and Environmental (ITE) Committee 
Date of Meeting: 
Thursday 8 October 2015 
Date Required by Democracy 
 Monday 21 September 2015 
Services: 
Community Board Consultation:  Needed: 


Complete: 

 Meeting held 
Public Excluded 
N    if PUBLIC EXCLUDED the section below MUST be completed 
REASON UNDER ACT 
SECTION 
PLAIN ENGLISH REASON 
WHEN REPORT CAN BE 
RELEASED 

  
  
  
  
  
  
  
  
  
  
  
  
 
No of Attachments (must be cited in report) : Six 
  
Description of Attachments: 
 
Written submissions from: 
  Canterbury Earthquake Recovery Authority 
  Environment Canterbury 
  Avon-Heathcote Ihutai Trust  
  Christchurch Estuary Association 
  Avon Otakaro Network 
  Southshore Residents' Association 
  
  
  
  
  
  
 
Confirmation of Statutory Compliance 
 
Compliance with Statutory Decision-making Requirements (ss 76 - 81 Local Government Act 2002). 
(a) This report contains: 
(i)  sufficient information about all reasonably practicable options identified and assessed in terms of their 
advantages and disadvantages; and  
(ii)  adequate consideration of the views and preferences of affected and interested persons bearing in 
mind any proposed or previous community engagement. 
(b) The information reflects the level of significance of the matters covered by the report, as determined in 
accordance with the Council's significance and engagement policy. 
 
 
  
Name and title of signatories 
Signature 
Date 
Prepared by 
Sylvia Maclaren 
  
21/09/2015 
Project Manager 
 
Approved by 
Peter Langbein  
21/09/2015 
Finance Manager 
 
 
 
 
Approved by 
Keith Davison 
21/09/2015 
Storm water and Land 
Drainage Rebuild 

 
Approved by 
David Adamson  
21/09/2015 
Executive Leadership Team 
Member 

 
 
 
 
 
 
 
 


 
 

 
 
 
 
Tidal Barrier Pre-Feasibility Study Delivery 
Reference: 
TRIM 15/1127524 
Contact: 
Keith Davison 
[email address] 
03 941 8071 
 
1. 
Purpose of Report 
1.1. 
The Avon-Heathcote Tidal Barrier Pre-Feasibility Study was tabled at the ITE Committee on 6 
August 2015, and made publically available online on the same day. The recommendations 
of the committee to Council were that: 
1.1.1.  That the information in (the) report be received. 
1.1.2.  That the Council seek input from CERA, ECan, Ngai Tahu and the Avon Ihutai Estuary 
Trust and the Christchurch Estuary Association as partners and stakeholders on (the) 
technical report and its implications. 
1.1.3.  That staff report back their recommendations to the next ITE meeting. 
1.2. 
This report is to close out recommendation 1.1.2 by  providing the responses to the input 
requested. It is also to seek a recommendation to Council as to whether to proceed to a full 
feasibility study for the tidal barrier. 
2. 
Background 
2.1. 
The barrier is just one of a number of flood management options the Land Drainage Recovery 
Programme  (LDRP)  and  Council  Strategy  and  Planning  Group  are  investigating  as  flood 
mitigation measures for Christchurch.  
2.2. 
The purpose of the pre-feasibility study was to understand whether a tidal barrier was worthy 
of further consideration and if the Council would be justified in conducting a full feasibility 
assessment. 
2.3. 
The study states that a barrier is technically feasible, and would be within the capabilities of 
New Zealand contractors at a build cost in the range of $300 - $350M with operations and 
maintenance a further $2 - $7M per year. It will result in substantial impacts on the estuary 
environment. 
2.4. 
A tidal barrier would not remove the need for some additional defences. The likely costs of 
these combined with a barrier in the present day scenario are more expensive than potential 
alternatives (Table 1). A tidal barrier could be more cost effective in the long term as sea level 
rise eventuates.  
Table 1.  Summary of costs with / without a tidal barrier  
Present day climate 
1m sea level rise 
Alternative 
Alternative 
Tidal barrier 
Tidal barrier 
engineering solution 
engineering solution 
$211M 
$430M 
$571M 
$545M 
 
ITE Committee - 8 October 2015 - Tidal Barrier Pre-Feasibility Study Consultation 
 


 
 

 
2.5. 
The pre-feasibility tidal barrier study only considered two climate scenarios, the present day 
scenario and 1m sea level rise scenario. It did not determine if there is an intermediate point 
between these scenarios whereby a tidal barrier becomes cost effective. 
2.6. 
Previous  external  communications  during  the  preparation  of  the  report  had  included 
workshops with ECan for early evaluation and issues identification, information sessions with 
Te Ngāi Tūāhuriri Rūnanga and the Avon-Heathcote Ihutai Estuary Trust, and the sending of 
a memo on 13 July 2015 to the Hagley-Ferrymead and Burwood-Pegasus Community Boards 
informing them of the study. CERA was updated with copies of the draft and final report as 
they were received. Feedback was also received through the Long Term Plan (LTP) process. 
3. 
Commentary 
3.1. 
In response to the ITE Committee's recommendations the Mayor's office prepared a letter to 
seek  input  from  the  nominated  stakeholders.  This  letter  stated  Council  staff  would  be  in 
touch to arrange meetings with representatives of each organisation to discuss the study and 
receive feedback.  
3.2. 
From this, meetings were held with CERA, the Avon-Heathcote Ihutai Estuary Trust, and the 
Christchurch Estuary Association. A meeting with Ngai Tahu was scheduled for 29 September 
2015 (after the submission of this officer's report) so will be reported on verbally at the ITE 
Committee meeting. ECan declined a meeting request. 
3.3. 
In addition, Council staff were requested to present to the Hagley/Ferrymead Community 
Board and did so at the meeting of 14 September 2015.  
3.4. 
To  summarise  the  range  of  views,  written  responses  were  received  from  all  nominated 
partners / stakeholders. These responses are attached. Additional unsought feedback was 
received  from  Avon  Otakaro  Network  and  Southshore  Residents'  Association,  and  these 
submissions are also attached.  
3.5. 
Feedback has been mixed with proponents for, against and neutral towards progression to a 
full feasibility study on a tidal barrier. Generally, there has been a level of concern that earlier 
and more in-depth consultation did not occur.  
3.6. 
Commentary from the submissions, and from both GHD and Jacobs (who provided a peer 
review), propose a city-wide flood management strategy would provide a better option. This 
would include an assessment of all the possible engineering and non-engineering options. 
This could include a tidal barrier at a high level without the additional information provided 
by a full feasibility study.  
4. 
Recommendation 
4.1. 
That a full feasibility study on a tidal barrier does not proceed at this stage under the Land 
Drainage Recovery Programme.  
4.2. 
That the information in the pre-feasibility report on a tidal barrier be considered as one of 
the  engineering  options  for  flood  protection  in  the  development  of  the  Council's  Three 
Waters Strategy. 
4.3. 
The Council continue to work closely with CERA on the options for flood plain management 
as part of the technical work on the future use of the Residential Red Zone. 
 
 
 
ITE Committee - 8 October 2015 - Tidal Barrier Pre-Feasibility Study Consultation 
 






 
Signatories 
Author 
Sylvia Maclaren  
Project Manager 
 
 
Approved By 
Peter Langbein   
Finance Manager 
 
 
 
 
 
 
 
Keith Davison 
Unit Manager 
 
 
 
David Adamson 
Director 
 
 
 
 
 