This is an HTML version of an attachment to the Official Information request 'GWRC's Application to Environment Court - Extent of Coastal Marine Area'.

 
Before the Environment Court 
At Wellington 
I Mua I te Kōti Taiao  
Te Whanganui-a-Tara Rohe 
 
ENV-2019-346-103  
 
 
 
Under 
Clause 14, Schedule 1 of the Resource Management Act 
1991 
 
In the matter of
 
appeals on the Proposed Natural Resources Plan 
 
Between 
Various 
 
 

Appellants 
 
 
 
ENV-2019-000103, 105-133  
 
And 

Wellington Regional Council 
 
 
 
Respondent 
 
 
 
 
Memorandum of counsel on behalf of Wellington Regional Council:  
Updating Court as to consent order process  
Date: 23 April 2021 
 
Level 4, 20 Customhouse Quay, Wellington 6011  
 
PO Box 2791, Wellington 6140 
DX SP20002, Wellington 
Tel +64 4 472 6289 
Fax +64 4 472 7429 
 
Solicitor on the record 
Kerry Anderson 
[email address] 
Tel +64 4 474 3255 
Contact solicitor 
Emma Manohar 
[email address] 
Tel +64 4 918 3016 
6992236.3  

 
MAY IT PLEASE THE COURT: 
Introduction 

The purpose of this memorandum is to provide the Court with an update 
on the consent orders as directed by the Court in its Minute of 21 April 
2021.  In addition, this memorandum seeks directions on an issue with 
the Proposed Plan's approach to defining river mouths in the region.   
Consent orders 

At paragraph [4] of its Minute of 21 April 2021, the Court directed the 
following: 
The  Respondent  is  to  file  a  memorandum,  by  5pm,  23 
April  2021,  listing  matters  that  are  subject  to  consent 
memoranda  that  are  being  distributed  or  drafted,  and 
timeframes for their lodgement with the Court.   

At this stage, there are sets of consent order documentation outstanding 
on 37 appeal topics.  Of those 37 topics: 
3.1 
3 sets have been filed with the Court and are pending 
determination.  
3.2 
9 sets are with the parties for comment.  This includes topic 
40, which following receipt of the memorandum from 
 
 dated 22 April 2021, cannot yet be sent in final.  
Subject to any comments received, the others should be sent 
in final for signing by the end of next week.   
3.3 
7 sets are with the parties for signing.  This includes a set 
originally sent in mid-February and one on 24 March that are 
yet to be signed by all parties.   
3.4 
14 sets are currently being drafted by the Council for 
circulation to the parties.  7 of which have been drafted and 
should be circulated to parties for comment within the next 
two weeks.   


 
3.5 
4 sets cannot yet be drafted but will be drafted following 
confirmation of the outstanding issues on topics 42, 44 and 
NZCPS 11(a), which also has implications on topic 16.  
Council understands these issues are largely resolved subject 
to confirmation of final drafting by the parties.   

The relevant consent order status and topics they relate to are set out in 
Appendix 1 to this memorandum.   

The Council cannot confirm a timeframe for lodgement of the 
outstanding consent orders, as it is reliant on the parties signing and 
returning documentation.   

In that regard, the Council requests that the Court direct a timetable for 
finalising consent documentation as follows: 
6.1 
once circulated by the Council in draft, the parties have 5 
working days to provide comment or confirm agreement with 
the documentation; and 
6.2 
once circulated by the Council in final, the parties have 5 
working days to sign and return or be deemed to have 
accepted.  At which point, the Council will file, confirming 
who has signed, and who has not.   
Definition of River Mouth - proposed section 293 application 

The Council wishes to advise the Court that a new issue has arisen 
related to the identification of river mouths in the Proposed Plan.  
Council intends to file a section 293 application to seek this is remedied.   


 

In summary, the Operative Regional Coastal Plan (RCP) included the 
following statement after its list of specified river mouth and coastal 
marine area boundary locations:1 
For  the  remaining  rivers  in  the  Wellington  Region,  the 
mouth  is  deemed  to  be  a  straight  line  representing  the 
continuation of the line of Mean High Water Springs on 
each side of the river at the river outlet. 

This statement enabled the Council and plan users to determine where 
the mouth of a river was for the purpose of defining the landward 
boundary of the coastal marine area where that river mouth was not 
expressly listed in the RCP.   
10 
This is important given the RMA defines the CMA as: 
coastal  marine  area means the  foreshore,  seabed,  and 
coastal water, and the air space above the water— 
(a) 
of which the seaward boundary is the outer limits 
of the territorial sea: 
(b) 
of  which  the  landward  boundary  is  the  line  of 
mean  high  water  springs,  except  that  where  that 
line crosses a river, the landward boundary at that 
point shall be whichever is the lesser of— 
(i)  1  kilometre  upstream  from  the  mouth  of  the 
river; or 
(ii) the  point  upstream  that  is  calculated  by 
multiplying the width of the river mouth by 5 
11 
'Mouth' is also defined in the RMA: 
for the purpose of defining the landward boundary of the 
coastal marine area, means the mouth of the river either— 
(a) 
as  agreed  and  set  between  the  Minister  of 
Conservation,  the  regional  council,  and  the 
appropriate  territorial  authority  in  the  period 
between  consultation  on,  and  notification  of,  the 
proposed regional coastal plan; or 
(b) 
as 
declared 
by 
the Environment 
Court under section 310 upon application made by 
the Minister of Conservation, the regional council, 
or  the  territorial  authority  prior  to  the  plan 
becoming operative,— 
and  once  so  agreed  and  set  or  declared  shall  not  be 
changed  in  accordance  with  Schedule  1 or  otherwise 
 
1 Regional Coastal Plan, p221.   


 
varied, altered, questioned, or reviewed in any way until 
the  next  review  of  the  regional  coastal  plan,  unless  the 
Minister  of  Conservation,  the  regional  council,  and  the 
appropriate territorial authority agree 
12 
Similar to the RCP, the Proposed Plan expressly identifies some, but not 
all, river mouths in the region.  Unlike the RCP, there is no equivalent 
general statement as to location for the remaining rivers in the region.  
As a result, in some cases the Proposed Plan does not identify the 
location of all river mouths in the region.  That, in the Council's view, 
provides an area of uncertainty for the Council and plan users as 
determining where the coastal marine area is (and therefore, where the 
RCP provisions apply) is not possible.  
13 
The failure to include the text was an inadvertent error.  The text was not 
included in the notified version of the PNRP or picked up during the 
decision-making process.  Therefore, the clause 16 correction process is 
unavailable as the correction goes beyond scope of that provision.   
14 
In addition, the Council has reviewed the scope of all appeals filed and 
does not consider the addition of the above text to be within scope of 
any appeal or appeal point.  As the Proposed Plan was a replacement for 
the five existing regional plans, including the RCP, the change is 
considered to be within the scope of the Proposed Plan.   
15 
Given the appeals on the Proposed Plan remain live, the Council would 
like to rely on the section 293 process to address this issue.  It does not 
wish to delay resolution of the appeals by notifying a variation to the 
Proposed Plan, or by waiting until the conclusion of the appeals process 
to notify a new plan change to address this issue.   
16 
The Council has contacted the Minister and the territorial authorities 
within the Wellington region.  All support the inclusion of the amended 
text as the method to identify river mouths in the region.   
17 
The Council intends to formally apply to the Court for the utilisation of 
this process, which would include the specific amendment sought, why 
it is necessary and an assessment against section 32.  However, in the 



 
interests of transparency, the Council wished to draw the Court's 
attention to this issue now.   
18 
The Council is aware of the limitations of the section 293 process, and 
the necessity for it to follow a hearing on the Proposed Plan.  In 
addition, as noted above, while this is not directly related to a specific 
appeal, the Council is raising it in the context of the appeals more 
generally.  These matters will be addressed in further detail at the time 
of formal application.   
 
Date: 
23 April 2021 
 
 
. . . . . . . . . . . . . . . . . . . . . . . . . . 
K M Anderson / E L Manohar / K H Rogers  
Counsel for Wellington Regional Council