This is an HTML version of an attachment to the Official Information request 'Auckland Harbour Bridge active modes decision'.

From:
Connie Rowe
To:
Kathryn King
Subject:
AHB events
Date:
Sunday, 4 April 2021 12:07:34 PM
Attachments:
Harbour bridge event notes.docx
image001.jpg
Hiya – see attached which I hope is helpful. I have made some very big guesses but it is hard
without knowing for example the scale – can we have 500 people participate per event or 5000?
That will make a big difference on the level on investment that can be justified.
Happy to chat further.
 
1982
Ngā mihi nui,
Connie
 
ACT 
Connie Rowe / Practice Manager Upper North Island
Te Waka Kōtuia Engagement and Partnerships  
M s 9(2)(a)
E [email address] / W nzta.govt.nz
Waka Kotahi NZ Transport Agency
Auckland / Level 5, AMP Tower, 29 Customs Street West, Auckland, 1143
Private Bag 106602, Auckland 1143, New Zealand
_________  _____________________________________________   
 
INFORMATION 
 
OFFICIAL 
THE 
UNDER 
RELEASED 

Auckland Harbour Bridge – active modes event  
Communications, engagement, marketing plan  
Scope  
This scope is based on a summer programme of five events with a similar format to the Auckland 
Marathon. Five Sunday mornings between 6am – 11.30am.  
The series will be agreed to proceed by May in order for the necessary planning and publicity for 
the series to start in November. Events to be held monthly November, December, January, 
February, March. If successful, the programme could be rolled out each year.  
1982
Opportunities  
WK demonstrate a commitment to building the Northern Pathway and responding to public calls ACT 
for walking and cycling access at this location. 
Secure a branding partner who can fund, or part fund the event series. There could be 
opportunities with Vector to extend the lighting partnership. Establishing this sort of model could 
provide the opportunity for it to be used for other active mode activation events in other parts of 
Auckland.  
WK demonstrate a commitment to building active modes mode share across the Auckland 
network. The events provide the opportunity to demonstrate how the wider network will function 
with this ‘missing link’ as people start and finish their journey from locations North, Northwest, 
East and centrally (South to a lesser extent). Creates good ongoing stories about other projects in 
INFORMATION 
the planning and design phase, including AT and AC projects.  
Allow more trialling and modelling of the route during the planning phase of the Northern 
Pathway. Provides information about patronage, journeys, customer profiles and opportunities 
for mitigations.   
Raises the profile of the role WK is playing to fund and develop Auckland’s walking and cycling 
network; AT and other WK projects.  
OFFICIAL 
Increase partnership working with AT, AC, Panuku, ATEED, PT operators as well as the private 
sector through a partnership model.  THE 
Rebuild relationships with key partners in the active modes space such as Bike Auckland 
Contribute to WK’s reputation.  
Risks 
Mitigations  
We are unable to secure a funding partner 
Look early for a funding partner  
UNDER 
and there is no current budget; the optics of 
Secure the right expertise to ‘package up’ the 
WK funding are not acceptable  
series of events and secure a partner  
There is low uptake for the events which could  Good promotion of the events 
undermine the Northern Pathway 
Context that there will be other high demand 
from users for commuting (who may not 
participate in the events)  
RELEASED 
Demand exceeds the max capacity for the 
Create a ticketing system to manage the event 
event  
Provide five opportunities to participate  
Increased calls for permanent reallocation of 
Modelling to show the full impact of full-time 
lanes  
reallocation of lanes on the network including 
the PT network  

Cost of the events is seen as a poor use of 
Similar key messaging used for other 
taxpayer funds  
largescale free public events 
Funding partner covers some/ most of the 
cost  
Insufficient budget and or planning for 
Anticipate sufficient budget and allow time for 
marketing and PR for the event leading to 
a comprehensive plan to be developed and 
poor update   
implemented   
 
1982
Marketing / communications / public relations 
The following is a very draft/ indicative overview of activities and costs – based on a funding 
partner being secured quickly  
ACT 
Timeframe 
Event programme approved 
May 2021  
Marketing, engagement, PR programme 
June 2021  
drafted and approved  
Public warn up for the event (PR based)  
July – August 
Tickets go on sale / marketing programme 
September  
begins  
INFORMATION 
Marketing/ ticket sales for the programme / 
October – March  
positive PR around events as they roll out 
Comms around thanks to Aucklanders to 
March – April  
taking part  
 
OFFICIAL 
Costs – marketing, comms/ PR, engagement, partner working  
Doing a multi event programme will create cost efficiencies. We will use inhouse resources to 
reduce spend where possible.  
THE 
Costs based on: 
Contractor(s)s 9(2) per hour 
(b)(ii)
Government rates on placement  
UNDER 
Some internal design supports 
Using ‘free’ WK and partner channels  
Strategy development (including internal and 
20k  
partner collaboration, sign off)  
PR including content creation, below the line 
15-20k  
media placement, partner collaboration to 
RELEASED 
increase reach    
Marketing activities (execution of the below)  
10k  
Advertising including design, production,  
30-40k 
radio, print, digital 
Contingency  
15k  
  
WAKA KOTAHI NZ TRANSPORT AGENCY 
DOCUMENT TITLE // 2