This is an HTML version of an attachment to the Official Information request 'Official Information request - Branz report to MOE dated 7 June 2011 Regarding Top-Vented Cavity Construction'.


 
 
 
 
 
 
(1982)
 
 
 
Act 
Weather-tightness and Durability Requirements  
for School Property 
 
 
 
 
Information 
For  
 
Project Managers 
 
Designers 

Official 
 
Contractors 
 
Principals and Boards of Trustees 
 
the   
 
Ministry of Education   
Revised -  June 2014 
under 
Amended – August 2014 
 
 
 
 
 
Released 
 
 
 
Weather-tightness and Durability Requirements – August 2014   
1 | P a g e  
 
 

Contents 
INTRODUCTION 

Background 

Scope 

Compliance  

How to use this document  

Materials and features whose use is Restricted  

Weather-tightness / Durability Checksheet 

Sign-off Report 

Review Process 

Submission to the Ministry  

Responsibility for Weather-tightness and Appropriate Design 

Amendments to Design, Materials Substitutions etc 
Section 1 
SURFACE WATER 
1.1 
Overland Flow Paths 
Section 2 
RETAINING WALLS 
2.1 
Retaining Walls as Separate Structure 
2.2 
Retaining Walls as Integral Part of Building Envelope 
Section 3  
CONCRETE SLAB ON GRADE 
Section 4 
SUSPENDED TIMBER  FLOORS 
4.1 
Sub-floor areas 
4.2 
Sub-floor fixings 
4.3 
Slatted Decks 
4.4 
Flooring 
Section 5  
EXTERIOR WALLS 
5.1 
Blockwork 
5.2 
Concrete 
5.3 
Timber or Steel Framing – Design Principles 
5.3.1  Timber Treatment and Fixings 
5.3.2  Plywood treatment 
5.3.3  Cavity Construction 
5.3.4  Top Venting 
5.3.5  Air Barrier 
5.3.6  Flexible Wall Underlay 
5.3.7  Rigid Sheet material 
Section 6  
CLADDING 
6.1 
Ground Floor Cladding Selection 
6.2 
Cladding As Bracing 
6.3 
Services penetrations through Walls 
under the Official Information Act (1982)
6.4 
Metal Wall Cladding 
Released 
Weather-tightness and Durability Requirements – August 2014  
2 | P a g e

 
Section 7 
ROOF 
7.1 
Metal Roofing 
7.1.1  Roof pitch 
7.1.2  Material Thickness 
7.1.3  Condensation and Thermal Bridging 
7.1.4  Roof Underlay 
7.1.5  Penetrations 
7.1.6  Eaves 
7.1.7  Flashings 
7.2 
Membrane Roofing 
7.2.1  Roof design 
7.2.2  Roof-water Outlets 
(1982)
7.2.3  Overflows 
7.2.4  Testing 
7.2.5  Roof-space Ventilation 
 
7.3 
Masonry Tiles 
Act 
 
7.4 
Parapets 
 
7.5 
Internal Gutters 
 
 
7.5.1  Gutter Capacity 
 
 
7.5.2  Gutter Outlets 
7.5.3  Gutter Overflows 
7.5.4  Testing 
 
7.6 
Valley Gutters 
Section 8 
EXTERIOR  JOINERY 
Section 9 
BALCONIES 
Information 
Section 10  JUNCTIONS  WITH  EXISTING  BUILDINGS 
Section 11  EXPOSED  STRUCTURAL  ELEMENTS 
Section 12  DURABILITY 
 
 
Official 
Appendix A – Weather-tightness / Durability Check Sheet     
 
the 
under 
Released 
Weather-tightness and Durability Requirements – August 2014   
3 | P a g e  
 
 

Introduction 
 
A.  
Background 
In recent years a large number of school buildings have suffered building envelope weather-
tightness failure and the Crown faces a significant cost for remedial work. 
The most common causes have been identified and this Weather-tightness and Durability  
Requirements for School Property publication (the Requirements) is the result and it: 
  focuses on those aspects of construction that have contributed to the failures and for 
which the Ministry now has specific requirements 
  prohibits the use of some materials or features and restricts the use of others 
  replaces the Ministry’s previous Weather-tightness requirements for schools April  (1982)
2011 publication which focussed on the major risks to school property,  
  covers all design features and materials that are known to create weather-tightness 
or premature durability failure.  
 
Act 
The Ministry has engaged the services of a Building Enclosure Specialist (BES) to peer-
review the construction details of projects that contain specific materials or features to help 
ensure that the building’s envelope is weather-tight and appropriately durable.  
Contact details of the BES may be obtained from any Ministry Regional office. 
B. 
Scope  
These Requirements apply to:  
  general school buildings ie administration, teaching spaces, gyms, halls 
  buildings to a maximum of 2 storeys (with height measured from lowest ground level 
adjacent to the building). Buildings above this height shall have the following 
Information 
submitted to BES 
o  full envelope construction details 
o  structural Design Features Report.   
They do not apply to:  
  ancillary buildings (ie storage sheds, non-integral garages) 
  covered walkways, canopies, shelters etc. 
The envelope of specialist buildings (ie enclosed swimming pools) requires design input from 
Official 
personnel who can demonstrate appropriate experience with the building type. Full envelope 
construction details for these buildings shall be submitted to the BES. 
the 
C.  
Compliance  
Building envelopes shall not contain materials or features that are not permitted.   
 
Materials or features which are not permitted, are shown with red background         .  
Where the building envelope includes materials or features whose use is restricted, full 
under 
construction details for these items shall be submitted to the BES.  
Materials or features which are restricted, are shown with blue background              . 
Where the design of any item does not comply with any clause or detail in these 
Requirements, full construction details for these items shall be submitted to the BES.  
 
 
Released 
 
D.  
How to use this document. 
This document is intended for Project Managers, Designers, Principals and Boards of 
Trustees.  
Weather-tightness and Durability Requirements – August 2014   
4 | P a g e  
 
 

 
 If you are… 
You should… 
  understand the technical aspects of these Requirements 
 Project Manager 
  ensure Designers are aware of, and comply with them 
  at completion of Detailed Design, receive Appendix A from 
Designer together with 
o  construction details of materials or features whose 
use is Restricted  

construction details for any item that does not comply 
with any detail or clause in these Requirements  
  submit these details to the BES 
  ensure that documentation has been modified to address 
(1982)
any concerns identified by the BES before calling tenders   
  receive Weather-tight / Durability Review Sign-off Report 
from the BES 
  submit the report to MoE prior to calling tenders 
Act 
  ensure that the Contractor is aware of the specific areas of 
the project where these Requirements apply 
    understand these Requirements 
 Designer  
  at completion of Detailed Design, provide Project Mgr with 
 
o  Appendix A 
o  construction details of materials or features whose 
use is Restricted (with Technical info if appropriate) 
o  construction details for any item that does not 
comply with any detail or clause in these 
Requirements (with Technical info if appropriate) 
Information 
  modify the documentation to address any concerns 
identified by BES 
  ensure that the Contractor is aware of the specific areas of 
the project where these Requirements apply 
    have a general understanding of these Requirements 
 Principal or BoT 
 
and the responsibilities of The Project Manager and 
Official 
member 
 
Designer 
  ensure that Project Manager is aware of them 
    understand the Concept, Developed and Detailed Design 
the 
 
stages of project documentation  
  understand the effect that selection of materials / components 
 
can have on future maintenance budgets 
 
 
under 
Released 
Weather-tightness and Durability Requirements – August 2014   
5 | P a g e  
 
 

E. 
Materials and Features whose use is Restricted 
Prior to commencing Developed Design stage, Designer shall alert the Project Manager, to 
any materials or features whose use is Restricted by these Requirements, which will form 
part of the design. 
 
At completion of Detailed Design, Designer shall provide the Project Manager with finished 
construction details of these elements for submission to the BES for a Weather-tightness / 
Durability Review.      
 
To avoid delays, all information required for the BES to fully understand details, junctions 
etc, must be provided. Materials, flashings, wraps, air seals, etc shall be fully described, 
detailed, dimensioned etc.  
 
(1982)
Designers may wish to engage with the BES earlier in the design process to determine: 
  information required   
  any criteria that will reduce the likelihood that details will need to be modified  
  the  time that is likely to be required for the Review (so that this is anticipated in the 
Act 
overall project timeline). 
 
After assessing the information submitted, the BES may identify aspects considered at-risk, 
which require further consideration / modification by the Designer, to improve weather-tight 
or durability performance. Rationale supporting the requirement and guidance to resolve the 
risk, will be provided.  
 
F. 
Check Sheet. 
The Weather-tightness / Durability Check Sheet (Appendix A) shall be completed by the 
Designer and submitted to the Project Manager at completion of Detailed Design. 
Information 
G.  
Sign-off Report. 
At completion of the Review process, the BES will provide the Project Manager and Ministry 
Weather-tight Coordinator with a Weather-tightness / Durability Sign-off Report: 
  summarising the review process that was undertaken 
  confirming that the Designer’s responses to items raised, were satisfactory  

Official 
  confirming that there are now reasonable grounds to believe that the design of 
features reviewed, complies with sound weather-tightness practice and where 
specific materials have been used, they should have appropriate durability.  
 
the 
H. 
Review Process. 
Designer  
  submits Appendix A to Project Manager 
  identifies (from the Requirements) those materials or features requiring a Review 
and submits finished construction documentation for them, to Project Manager. 
under 
Project Manager  
  forwards documentation to Building Enclosure Specialist together with: 
o  School name  
o  School ID 
o  Project name 
o  Project ID (provided my MoE). 
Building Enclosure Specialist 
  Requests approval to commence Review from Ministry’s Weather-tight Coordinator. 
Ministry’s Weather-tight Coordinator 
Released 
  Authorises BES to undertake Review. 
Building Enclosure Specialist 
  Assesses details and identifies any aspects requiring further detail / information / 
consideration / amendment. 
Weather-tightness and Durability Requirements – August 2014   
6 | P a g e  
 
 

Designer  
  Amends materials / features as necessary to the Building Enclosure Specialist’s 
satisfaction.  
Building Enclosure Specialist 
  Provides Weather-tightness / Durability Sign-off Report once there are reasonable 
grounds to believe envelope is weather-tight and specific materials should be 
appropriately durable. 
 
I. 
Submission to the Ministry. 
The Project Manager shall submit the following information to the appropriate Ministry 
personnel, when seeking approval to call tenders: 
  sufficient documentation to confirm that the project complies with (and does not 
exceed) the scope of work approved by the Ministry 
(1982)
  copy of Weather-tightness / Durability Check Sheet (Appendix A) 
  copy of Weather-tightness / Durability Sign-off Report from BES, for those projects 
that have required a Review.   
Act 
 
J. 
Responsibility for Weather-tightness and appropriate Design. 
The  Ministry  encourages  innovative  designs  but  buildings  with  complex  floor  plans, 
complex roofs or complex elevations: 
  cost more  
  introduce greater risk of weather-tightness failure.  
 
Designers shall:  
  provide building envelopes which minimise: 
o  irregular or complex junctions  
Information 
o  junctions between different cladding materials and profiles 
o  features that will affect the durability of elements or materials 
  select envelope materials that will:  
o  minimise maintenance requirements 
o  minimise whole-of-life costs  
o  deliver appropriate performance throughout the life of the building. 
Official 
The ability to:  
  remove contaminants that will affect a materials durability  
  maintain the envelope to ensure warranty requirements are met 
the 
are important considerations for Designers.  
 
While the involvement of the Building Enclosure Specialist is provided as an aid to ensuring 
appropriate performance, overall responsibility for detailing an envelope that is weather-
tight under all weather conditions and materials perform appropriately over the life of the 
building, remains solely with the Designer. 
under 
 
 
 
 
 
 
 
K.  
Amendments to Design, Materials Substitutions etc 
The  Project  Manager  shall  draw  to  the  attention  of  all  personnel  involved  with  the 
Released 
construction,  that  any  party  who  makes  changes  to  any  aspect  of  the  contract 
documentation  (Specification  /  Materials  selection  /  Construction  details)  relating  to  the 
building’s  envelope,  without  obtaining  the  Designer’s  prior  approval  in  writing,  wil   assume 
Weather-tightness and Durability Requirements – August 2014   
7 | P a g e  
 
 

full responsibility for the weather-tightness and durability performance of the feature and that 
of any abutting construction. 
This process of substitution may involve re-submitting to the BES for further review. 
The designer should take the following into account when considering a substitution: 
  level of detail provided on the substitute product  
  shop drawings (where appropriate) to show how the installation will be carried out 
  product characteristics (strength, air leakage, assembly etc) as appropriate 
  the  risk  associated  in  departing  from  a  known  product  (or  one  which  has  been 
thoroughly researched at the design stage). 
 
It is particularly relevant to the selection / substitution of a branded window system where the 
designer  has  implied  (but  not  nominated)  a  brand  by  the  CAD  details  used  and  the 
contractor wishes to nominate its own preference, which may not be an equivalent. 
(1982)
A precise specification is needed in the contract documentation. 
Act 
Information 
Official 
the 
under 
Released 
Weather-tightness and Durability Requirements – August 2014   
8 | P a g e  
 
 

 
Section 1:  
Surface Water  
1.1 
Overland Flow Paths 
To protect against water damage when drainage systems become blocked or over-loaded, 
and in all developments where siteworks or re-contouring of the ground is being 
undertaken, configure site levels to provide stormwater overland flow paths away from 
buildings.  
Always be aware of the cut ground levels (CGL) and the finished ground levels relative to 
the buildings lowest RL or finished floor level (FFL).  
Expert advice from a Civil Engineer may be required. 
 
(1982)
Section 2:  
Retaining Walls  
Act 
2.1 
Retaining Walls as a Separate Structure 
A retaining wall shall be provided:  
  where the level of adjacent ground is above that required in Section 3 below. 
The retaining wall shall be separated from the exterior wall of the building by a 
minimum distance of 1.5 metres. The ground between the retaining wall and the 
building shall meet the surface finish, height and fall requirements of NZBC. 
  where the ground below a suspended timber floor is excavated as per clause 4.1 
below. 
 
Information 
2.2 
Retaining Walls as an integral part of Building Envelope  
Liquid applied products are not permitted as a means of waterproofing retaining          
walls that form part of the building envelope. 

Using the wall of a building to retain adjacent ground is a Restricted design          
element. 

Official 
Where a separate structure is not provided and the external wall of the building retains the 
adjacent ground, water ingress shall be prevented as follows. 
  Apply proprietary sheet tanking-membrane to exterior of wall: 
o
the 
  possessing a Code-Mark certificate 
o  holding valid  BRANZ Appraisal certificate. 
  Protect: 
o  top of membrane with a flashing chased into wall and sealed  
o  surface of membrane with proprietary drainage mat, fibre cement or 
polystyrene sheet. 
under 
  Provide:  
o  perforated subsoil drain with: 
  invert at the highest point 150mm (min) below floor level  
  fall of 1:200(min) to silt-trap end-outlet 
  access to the ends for water-jet cleaning 
o  polypropylene filter cloth to separate existing ground from backfill material  
o  clean and free draining backfill material   
o  filter cloth to separate any topsoil placed over backfill material. 
 
Released 
 
  Direct surface water away from the wall with mowing strip (refer Section 3 below) and 
if necessary provide a surface drain to its edge.   
Weather-tightness and Durability Requirements – August 2014   
9 | P a g e  
 
 


 
(1982)
Act 
Section 3:  
Concrete Slab on Grade 
Information 
Slot-drain channels are not permitted at the base of external walls                                
(except as noted below)  
There is a risk that dampness in channels may raise the moisture level in the adjacent wall 
cavity. 
Where new buildings are constructed with a concrete floor slab, the finished floor level 
(above the finished level of adjacent ground - 150 or 225mm as per NZBC) shall be set so 
Official 
that drainage channels or concrete nibs are not required.   
Drainage channels (complying with NZBC) may be fitted at Accessible Entries where 
adjacent paved surface is raised to provide level-entry threshold (≤ 20mm). 
the 
The total building perimeter including landscaped areas, shall have a minimum 500mm wide 
strip of permanent paving set 150mm below FFL with 30mm fall away from building. An edge 
drainage channel (complying with Fig 7.12 NZS 3604:2011) shall be provided if this gradient 
is not maintained for 1m 
Finished surface of landscaped areas (FGL) shall be no higher than the outer edge of the 
under 
permanent paving. 
 
 
 
Section 4:  
Suspended Timber Floors 
Released 
 4.1 Sub-floor Areas 
Where the ground floor is supported on piles, subfloor areas: 
  shall not be excavated or set below adjacent ground unless an impervious retaining 
wall is employed 
Weather-tightness and Durability Requirements – August 2014   
10 | P a g e  
 
 

  shall be graded or provided with surface drainage to prevent water ponding   
  shall be overlaid with 250 micron polyethylene sheets with all joints lapped and taped. 
Sheets shall be fitted tight to piles (and perimeter walls where present).   
Polythene may be omitted where subfloor ventilation (fully compliant with requirements of 
NZS3604) is provided on all 4 sides of the building (note restrictions imposed in 4.3 below). 
 
Vents in subfloor foundation walls shall be vandal resistant with care taken to ensure that the 
required free-ventilation area is achieved. 
4.2 Sub-floor Fixings 
All fixings for sub-floor areas shall be Type 304 stainless steel. 
4.3 Slatted Decks 
Where a slatted deck (ie rain permeable) is positioned adjacent to a piled building, provide a 
(1982)
sub-floor wall (without ventilation openings) to separate it from the subfloor area to prevent 
dampness from below the deck entering the building sub-floor area. (Polythene ground 
overlay will be required under the building as ventilation is not provided on all 4 sides). 
Act 
4.4 Flooring 
In any situation where there is a risk of intermittent dampness in sub-floor areas, plywood 
flooring shall be used (refer clause 5.3.2 for treatment). 
 
 
Section 5:  
Exterior Walls 
The following wall types are not permitted for building envelopes:                                  
  Walls that are curved. 
Information 
  Walls that have a primary structure other than timber, steel, concrete or  
concrete block. 
 
The following wall type is a Restricted design element: 

  Walls that are not vertical. 
 
Official 
5.1 
 Blockwork  
Honed-face structural concrete blockwork is not permitted for exterior walls of           
the 
interior spaces. 
Honed-face blocks rely on a clear coating to display their unique appearance, but the on-
going integrity of the clear coating cannot be readily visually assessed. 
Honed-face block veneer may be used, but must be protected by an anti-graffiti coating to 
minimum height of 3m. 
under 
 
 
Stack-bonded concrete blockwork is not permitted for exterior walls of interior           
spaces. 

Laying in this manner has not proven to be as crack-resistant as running (stretcher) bond. 
Concrete blockwork forming the exterior walls of interior spaces is a Restricted 
Released 
design element. 
Additional Observation by a Structural Engineer is required at all stages of block laying and 
grouting. 
Weather-tightness and Durability Requirements – August 2014   
11 | P a g e  
 
 

The base course of blockwork shall be set in a rebate 50 -100mm below finished floor level. 
All blockwork shall be laid and solid-filled under the supervision of a Brick and Block 
Licensed Building Practitioner. 
A rain-screen cladding fixed over a cavity:  
  is mandatory on the exterior face of blockwork which supports a concrete upper floor  
  is encouraged in other circumstances, because blockwork is considered prone to 
transfer moisture when, over time, cracks occur through settlement, coatings degrade 
etc. 
All blockwork (without a rain-screen) forming the exterior walls of interior spaces, shall be 
coated on the exterior face with a pigmented (ie not clear-coated so that the integrity of the 
coating can be visually assessed) acrylic high-build elastomeric water-proofing paint system 
(formulated to fill surface pores, bridge fine cracks etc) to achieve a dry film-build of 180 
microns minimum. 
(1982)
Additional Observation and film thickness measurement is required during the application of 
the high-build membrane, to ensure appropriate film-build is achieved. 
 
Act 
5.2 
Concrete  
The use of concrete (precast or cast insitu) for exterior walls is a Restricted        
design element. 

Walls constructed of this material do not require a rain-screen on cavity. 
Walls constructed to be watertight by fully complying with CCANZ CP 01:2014 Weathertight 
Concrete and Concrete Masonry Construction cl 4.5 Watertight Concrete

  must be protected by an anti-graffiti coating to minimum height of 3m 
  may be clear coated with Silane or Siloxane water repellent sealers to protect and 
Information 
enhance remaining surfaces. 
 
Clear coatings will require regular re-coating to maintain the integrity of the surface. 
 
All other concrete walls shall be coated on the exterior face with: 
  a pigmented acrylic high-build elastomeric paint system to achieve a dry film build of 
180 microns 
Official 
  a pigmented acrylic paint system to achieve a dry film build of 80 microns. 
 
Precast panels shall be minimum 125mm thick. 
the 
 
 
 
 
 
 
under 
 
Panel joints shall be: 
  front sealed with the joint able to drain at the base (ie finishing above surrounding 
paving level) 
  back sealed (to create effective air-seal and establish pressure moderation). 
Released 
Weather-tightness and Durability Requirements – August 2014   
12 | P a g e  
 
 



(1982)
Act 
The flashing of roofs (or other surfaces) which abut precast panels, require particular 
attention (particularly at vertical panel joints which are inevitably recessed). 
Information 
Option B (shown below) is less preferred because sealant is exposed to elements with 
consequential degradation over time. 
Official 
the 
under 
Released 
 
Weather-tightness and Durability Requirements – August 2014   
13 | P a g e  
 
 


5.3  
Timber or Steel Framing – Design Principles 
These principles apply without exception, (irrespective of the cladding material chosen), to:  
  new buildings  
  extensions to existing buildings. 
Refer below for circumstances where a cavity may be omitted when altering an existing 
building. 
All timber and steel framed exterior walls shall be detailed to incorporate. 
Exterior Rain-screen cladding 
  to deflect all / majority of moisture.  
 
Drained cavity with top ventilation  
  drained to allow any moisture that penetrates the rain screen to escape  
  top vented to assist drying by allowing air movement, to aid evaporation. 
(1982)
 
Internal air barrier  
  to reduce air pressure differential between the drained cavity and exterior, to prevent 
Act 
air pressure driving moisture into the building. 
Information 
Official 
the 
under 
 
An Exemption from the requirement to provide a cavity may be given for alterations to existing 
buildings that have been constructed without a cavity, such as where: 
  windows are being removed and in-filled to match an adjacent surface 
  existing cladding is being replaced with an alternative type. 
 
In these circumstances: 
Released 
  any new wall framing that is required shall be H3.2 
  the permitted cladding type shall be determined by the Risk Score for that wall, given 
by NZBC E2 / AS1 Table 3.  
 
Weather-tightness and Durability Requirements – August 2014   
14 | P a g e  
 
 

Window or cladding change to existing buildings constructed without a cavity, is 
a Restricted design element. 

5.3.1   Timber treatment and fixings 
In all situations where copper-bearing preservatives are used (ie CCA, CQ [previously 
ACQ] CuAz) to achieve required treatment levels (ie H3.2), fixings shall be stainless 
steel (nails, staples, bolts etc). 
 
(Galvanised steel will react with timber treated with copper-bearing preservatives and must not be 
placed in contact with it). 
 
 
 
(1982)
 
5.3.2   Plywood Treatment 
Act 
LOSP treated plywood is not permitted                                                               . . 
Plywood used as sarking shall have thickness determined by span, with minimum: 
  15mm under profiled metal roofs 
  17mm as substrate for membrane roofs 
  20mm as substrate for decks. 
 
Plywood shall have the following minimum treatment and fixings shall be stainless steel. 
 
50 year durability 
Information 
Use 
Exposure 
Treatment 
Sub-floor foundations 
In contact with ground 
H5 
Rigid air barrier 
Protected / risk of moisture penetration 
H3.2 CCA 
Bracing -   Sub-floor  
Protected / exposed to ground atmosphere 
H1.2 
-     Exterior walls 
Protected / risk of moisture penetration 
H3.2 
Official 
             -    Interior walls 
Protected  
None 
Flooring –  Dry areas 
Protected / exposed to ground atmosphere 
None 
              –  Wet areas 
Protected / exposed to ground atmosphere 
H3.1 
the 
Sarking  
Protected / risk of moisture penetration 
H3.2 
Support (valley boards etc) 
Protected / risk of moisture penetration 
H3.2 
 
15 year durability 

Exterior finishing  
Exposed / not in ground contact 
H3.2 
Cladding  
Exposed / not in ground contact 
H3.2 
under 
Exterior stairs, floor surfaces 
Exposed / not in ground contact 
H3.2 
etc (easily replaced) 
Interior Stairs  
Protected  
None 
 
 5 year durability 

Interior finishing, joinery etc 
Protected 
None 
(easily replaced)  
 
Released 
5.3.3   Cavity Construction 
Cavities shall be:  
  compartmentalised to provide separation from cavities on opposite sides of walls (ie 
where parapets occur) and on adjacent walls   
o to avoid undue wind pressure differentials  
Weather-tightness and Durability Requirements – August 2014   
15 | P a g e  
 
 


o to allow pressure equalisation / moderation to occur. 
  separated from roof, subfloor and sub-deck areas  
o  to allow pressure equalisation / moderation to occur  
o  to avoid transfer of moisture from the ground 
  top vented on buildings up to 2 storeys in height (refer below).   
 
Cavities may be continuous for a maximum of 2 storeys in height.  
Battens to provide horizontal support for cladding, flashings or wall penetrations, shall be:   
  short lengths, fixed vertically with tops bevelled to shed water toward the outer face 
(refer below for exemption for profiled steel fixed vertically)  
  installed to maintain the openness of the wall cavity (for drainage and ventilation) 
  positioned to support the cladding at the centres required by the manufacturer. 
Where profiled steel sheets are fixed vertically, products such as Cavity Batten Systems Ltd 
Cavibat may be fixed horizontally. 
(1982)
Act 
Information 
 
Official 
5.3.4   Top Venting 
All cavities on buildings up to 2 storeys in height, shall be vented in a manner similar 
the 
to that illustrated below (the Ministry has obtained Determination 2013/046 to allow 
top-venting). 
Buildings which exceed this height:  
  shall only have a method of draining cavities at each floor level  
  shall have full envelope construction details submitted to the BES for review. 
under 
Released 
Weather-tightness and Durability Requirements – August 2014   
16 | P a g e  
 
 




 
 
 
 
 
 
 
 
 
 
(1982)
 
 Act 
 
 
 
 
 
 
 
 
Information   
 
 
 
Official 
 
 
the 
 
 
 
 
under 
 
 
 
 
 
 
Released 
 
 
 
Weather-tightness and Durability Requirements – August 2014   
17 | P a g e  
 
 


 
 
 
 
 
 
 
 
 
 
(1982)
 
 
Act 
 
 
Where a parapet forms the top of a cavity, air pressure differentials between the 
cavities on each side of the parapet shall be prevented by an air seal placed beneath 
the parapet capping: 
 
 
 
Information   
 
 
 
 
Official 
 
 
the 
 
 
 
 
under 
 
 
5.3.5  Air Barrier   
a)  
If using NZS3604 and/or E2/AS1 to assess wind exposure 
 
Low and Moderate wind zones 
 
The air barrier can be provided by interior wall linings provided sheet 
joints and penetrations (ie switches and socket outlets) are sealed-off 
Released   
High, Very High, Extra High and Specific Design wind zones  
 
Air Barrier shall be Rigid Sheet Material in accordance with NZBC 
E2/AS1 Table 23. 
Weather-tightness and Durability Requirements – August 2014   
18 | P a g e  
 
 

On external walls where no internal linings are fitted (ie gable-end of roof void), 
an Air Barrier must be provided 
 
 
Low and Moderate wind zones: Flexible Wall Underlay (which meets 
Air Barrier requirements in E2/AS1 Table 23) may be used provided 
the Underlay is not likely to be damaged. Where damage is possible 
(stores, garages etc) a Rigid Sheet Material is required (as above) 
 

 
High, Very High, Extra High and Specific Design wind zones: Rigid 
Sheet Material is required. 
b) 
If undertaking a cladding pressure study to AS/NZS 1170 – install RAB 
when the ULS cladding pressures obtained are above 1000 Pa. 

 
Note: Cladding pressures include all relevant pressure coefficients and 
are not ‘basic pressure’ 

(1982)
 
5.3.6  Flexible Wall Underlay  
Act 
The following products are not permitted                                                                     : 
 
Kraft paper (including Bitumen impregnated or Fire resistant)  
 
Flexible Wall Underlay shall: 
 
have a current BRANZ Appraisal 
 
be water resistant, absorptive (hydrophobic), permeable synthetic non-woven 
(Polymeric) type complying with Table 23 E2/AS1 
 
be laid horizontally 
 
have side and end laps of 150mm. 
 
Information 
5.3.7  Rigid Sheet Material  
Rigid sheet material shall be 7mm H3.2 plywood or 6mm fibre cement in accordance 
with NZBC E2/AS1 Table 23, overlaid with Flexible Wall Underlay (building wrap). 
 
Rigid Sheet Material may be fixed to provide sheet bracing requirements. 
 
Official 
 
Section 6:  
Cladding 
the 
6.1 
Ground Floor Cladding Selection 
Cladding at ground floor level shall be selected to withstand impact damage. 
The following products are not permitted at Ground Floor level 
 
Fibre-cement cladding less than 8mm thick (depth at grooves not counted) 
under 
 
EIFS cladding. 
 
uPVC systems. 
 
EIFS used in any other situation is a Restricted material. 
 
All EIFS cladding shall: 
 
have been tested and have current BRANZ Appraisal 
 
be verified to E2 / VM1 (modified AS / NZS 4284 test). 
Released 
 
All Ground Floor cladding less than 16mm thick shall be provided with: 
 
bottom-edge protection of timber or metal  
 
external-corner protection of timber or metal. 
Weather-tightness and Durability Requirements – August 2014   
19 | P a g e  
 
 



 
(1982)
Act 
 
 
6.2  
Cladding as Bracing 
Cladding fixed over a cavity, is not permitted to be used as wall bracing. 
Information 
 
6.3  
Services Penetrations through Walls 
Pipes and cables which penetrate the wall cavity and cladding, shall be sealed with Vanluk 
Design Ltd MG-50 or MG-100 E2 Pipe and Cable Cavity Flashing  (or equivalent), as 
illustrated below. 
 
Official 
 
 
the 
 
 
 
under 
 
 
 
 
 
 
Released 
 
 
6.4 
Weather-tightness and Durability Requirements – August 2014   
20 | P a g e  
 
 

 
Metal Wall Cladding 
Except where more stringent requirements are given below, metal wall cladding shall be 
detailed and installed to comply with NZ Metal Roof and Wall Cladding Code of Practice 
Version 2.2 / 2012. 
 
Section 7:  
Roof 
The following requirements do not apply to covered ways, canopies, shelters etc which do not 
form part of the main building envelope. 
Roof: 
  shall be simple form with generous slope and overhang 
  shall be designed and constructed to minimise potential for leakage 
(1982)
  penetrations shall be kept to a minimum 
  when regular maintenance is anticipated, safe access must be provided on the roof. 
 
All joints / junctions shall be correctly lapped and shall not rely on sealant for weather-
Act 
tightness. 
 
7.1  
Metal Roof 
Curved metal roofs are not permitted                                                                                       
Climate change has resulted in more intensive rainfall and as a consequence, a conservative 
approach to roof design and rainwater collection systems is required. 
Except where more stringent requirements are given below, metal-clad roofs shall be 
Information 
detailed and installed to comply with NZ Metal Roof and Wall Cladding Code of Practice 
Version 2.2 / 2012. 
 
7.1.1  Roof pitch
 
The minimum roof pitch shall be as follows. 
  New buildings:  
o  trough and trapezoidal section roofs   
50 
Official 
o  corrugated roofs  
 
 
 
12º 
  Replacement of existing roofs (except where these pitches cannot be achieved 
without disproportionate cost and where there has been satisfactory 
the 
performance of the roof at the lower pitch): 
o  trough and trapezoidal section roofs   
3º  
o  corrugated roofs  
 
 
 
8º 
  
Re-pitched roofs which will result in windows having to be reduced in height, is a 
Restricted design. 
under 
Engage with BES at an early design stage to see if a less expensive alternative exists. 
Refer to clause 7.6 below for restrictions on use of valley gutters where roof pitch is 
less than 80. 
 
7.1.2   Material thickness
 
The minimum Base Metal Thickness (BMT) for all steel roofs shall be 0.55 mm. 
7.1.3   Condensation and Thermal Bridging 
Released 
The design of roof elements shall pay particular attention to preventing or mitigating the 
formation of condensation in roof cavities as a result of thermal bridging and other 
phenomena. 
Moisture is best controlled in the spaces where it is created, by ventilation and heating 
Weather-tightness and Durability Requirements – August 2014   
21 | P a g e  
 
 

within the space. 
This is particularly important where large numbers of students are present. 
BRANZ research has shown that condensation may occur on the underside of metal 
roofs and on roof-space steel structural members: 
 
when suspended ceilings are fitted 
 
where insulation is placed on the ceiling tiles 
 
when water vapour is likely to be present (ie from groups of students) 
 
when surface temperature of metal roofing falls (ie during clear-sky radiation) 
 
after periods of rain (even if timber purlins are used or timber thermal-break 
battens are fitted to steel purlins). 
 
Condensation that forms on the underside of the metal roofing is managed by the roof 
underlay which: 
(1982)
 
initially absorbs moisture, then 
 
releases moisture to be evaporated when roof-cavity temperature rises. 
 
Condensation that forms on steel purlins or roof-space structural members cannot be 
Act 
controlled. 
 
7.1.4  Roof Underlay 
The following underlays are not permitted                                                                    : 
 
Kraft paper (including Bitumen impregnated or Fire resistant)  
 
Roof underlay shall: 
 
have a current BRANZ Appraisal 

Information 
 
be fully supported (mesh shall comply with Safety Mesh Standard AS/NZS 
4389:1996)  
 
be separated from insulation by a 20mm air gap 
 
be water resistant, absorptive (hydrophobic), permeable synthetic non-woven 
(Polymeric) type complying with Table 23 E2/AS1 
 
have side and end laps of 150mm 
 
be laid horizontally (except on roofs < 80  where it may be laid vertically but 
Official 
all laps shall be sealed with window flashing tape): 
 
7.1.5   Penetrations 
 
the 
Penetrations shall be kept to a minimum (leaks are often associated with roof 
penetrations) 
 
the top face of large roof penetrations (ie skylights) shall be located within 
2.5m of the ridgeline to minimise the length of back flashing needed from the 
penetration to the ridge above it  
 
small penetrations (ie pipes) shall be directed within the roof structure to 
under 
emerge at sensible locations. 
Penetrations greater than 300 x 300mm shall be fully supported all round. 
 
Refer to details below for typical vent-pipe and skylight flashing detail. 
 
Released 
Weather-tightness and Durability Requirements – August 2014   
22 | P a g e  
 
 



(1982)
Act 
Information 
Official 
the 
under 
 
 
7.1.6  Eaves 
The provision of generous eaves is encouraged. 
 
Released 
Refer to Section 12 Durability for eaves / overhang design considerations. 
 
Reverse-slope eaves shall be fitted with a flashing or batten as illustrated in 5.3.4 Top 
Venting (above). 
 
Weather-tightness and Durability Requirements – August 2014   
23 | P a g e  
 
 


For corrugated roofing in Wind Zones Very High and Extra High (NZS 3604), provide 
the eaves flashings shown below. 
(1982)
Act 
Information 
 
7.1.7   Flashings 
Wherever  possible,  flashings  shall  be  powder-coated  aluminium  (painted  or  coloursteel 
flashings should be avoided, particularly in protected locations ie not rain-washed). 
 
Complex roof junctions shall have compound flashings:   

Official 
  1.6mm aluminium 
  formed to-suit and welded 
  painted (preferably powder-coated).   
 
the 
Raking barge flashings may have lapped joints (not welded).    
 
Top fixing is only permitted on raking barge flashings. 
 
Refer below for typical details. 
under 
 
Released 
Weather-tightness and Durability Requirements – August 2014   
24 | P a g e  
 
 



(1982)
Act 
Information 
Official 
the 
under 
 
 
 
Released 
Weather-tightness and Durability Requirements – August 2014   
25 | P a g e  
 
 


(1982)
Act 
Information 
Official 
the 
under 
 
 
 
 
Released 
Weather-tightness and Durability Requirements – August 2014   
26 | P a g e  
 
 



(1982)
Act 
 
7.2  
Membrane Roofing 
Liquid applied membranes are not permitted                                                                 
The use of membranes for roofing or internal gutters, is a Restricted design element.                                                             
Information 
Projects which incorporate membrane roofing require precise detailing and an increased 
level of attendance and observation by the Designer at the time the substrate is fitted and the 
membrane installed. 
 
Where membranes are used they shall have:  
  current BRANZ Appraisal 
Official 
  minimum  15year material warranty  
  5 year installation warranty. 
 
the 
Membranes shall be selected from the following types: 
  Butyl and EPDM rubber in accordance with E2/AS1, or 
  2 layer fully-bonded torch-applied reinforced modified bitumen membranes with 
 
mineral chip finish, installed in accordance with the Code of Practice for Torch-on 
 
Membrane Systems for Roofs and Decks,  or 
  Synthetic plastic sheet membranes such as Thermoplastic Olefins (TPOs) and PVC. 
under 
 
Installation of the membrane shall only be by applicators licensed by the manufacturer. 
 
Ply substrate shall be fully protected to maintain dryness until membrane is laid. 
 
 
 
 

Released 
 
 
7.2.1   Roof Design
 
Internal gutters shall be avoided whenever possible (see below for simple roof 
Weather-tightness and Durability Requirements – August 2014   
27 | P a g e  
 
 


design without formed gutter). 
 
Contract documentation shall show the levels of the high and low points of the 
substrate at all edges and changes of plane. Work the levels back from the low point 
of membrane at the outlet. 
 
Membrane roofs shall have: 
 
minimum number of sheet joints 
 
minimum pitch of 1.50 (1:40). 
(1982)
Act 
Information 
7.2.2   Roof-water Outlets  
Official 
The membrane shal  terminate with a weir ‘drip-edge’ into an external rainwater 
head. 
 
the 
Outlet capacity shal  accommodate twice “1 in 50-year” rainfall intensity (ie 
100mm/hr for external gutters and 200mm/hr for internal gutters).  
 
Local rainfall intensity shall be obtained from NIWA or the Territorial Authority. 
Suitable design methods are provided in E1 / AS1 and BRANZ Bulletin 537 Sizing 
Gutters and Downpipes. 
under 
7.2.3   Overflows 
Overflows shall be provided as an opening in the rainwater head and: 
  cross-sectional area of overflow shall be1.5 times the area required for the 
outlet 
  height shall be set so that the overflow functions before water can enter the 
structure, if the downpipe becomes blocked. 
7.2.4  Testing 
Released 
Blocking the outlet and flood-testing to check the integrity of the membrane is 
recommended before internal linings are fitted. 
 
Weather-tightness and Durability Requirements – August 2014   
28 | P a g e  
 
 


7.2.5  Roof-space Ventilation 
Provide  
  cross ventilation between the roof-space voids below the membrane     
substrate 
  proprietary vapour vents from the voids at 1 / 40m2 of roof area (minimum 
vent area 400 mm2)  
 
Vents shall be designed to ensure roof remains water-tight. 
 
Any resulting reduction in R value of thermal insulation shall be taken into account. 
 
(1982)
Act 
Information 
Official 
 
the 
7.3 
Masonry Tiles 
All masonry tile roofs shall be fitted with underlay (irrespective of pitch). 
 
under 
 
 
 
7.4 
Parapets  
Parapets provide a high risk of weather-tightness failure. 
Parapets are a Restricted design element                                                                          . 
Released 
Where parapets are provided: 
  cap-flashing shall be:  
o  metal  
o  fully supported with 5º minimum cross-fall  
Weather-tightness and Durability Requirements – August 2014   
29 | P a g e  
 
 


o  secured with side fixings or concealed clips (no top fixing) 
  joins and junctions shall be under-flashed with welded 1.6mm aluminium flashings, 
rebated into plywood substrate  
  there shall be no  reliance on  sealant alone  for  weatherproofing. 
 
Refer to the following sketches for typical details. 
(1982)
Act 
Information 
 
Official 
 
 
 
the 
 
 
under 
Released 
Weather-tightness and Durability Requirements – August 2014   
30 | P a g e  
 
 



(1982)
Act 
 
Information 
Official 
the 
under 
 
 
 
Released 
7.5 
Internal gutters 
Significant damage can result when an internal gutter fails. 
Weather-tightness and Durability Requirements – August 2014   
31 | P a g e  
 
 


Internal gutters are a Restricted design element                                                                 . 
Projects which incorporate internal gutters require precise detailing and an increased level of 
attendance and observation by the Designer at the time the substrate is fitted and the gutter 
lining installed. 
Where internal gutters occur: 
  welded stainless steel is the preferred gutter lining  
  membrane gutter linings shall be one continuous length (ie without joints) 
  fall shall be 1:100  minimum (preferably more, depending on depth) 
  levels of the high and low points of the substrate shall be shown on the drawings.  
 
7.5.1   Gutter Capacity 

The gutter: 
 
design shall meet the requirements of NZBC Clause E1 – Surface Water 
(1982)
 
capacity shall accommodate twice the “1 in 50-year” rainfall intensity. 
 
Local rainfall intensity shall be obtained from NIWA or the Territorial Authority. 
Act 
Suitable design methods are provided in E1 / AS1 and BRANZ Bulletin 537 Sizing 
Gutters and Downpipes. 
 
7.5.2   Gutter Outlets 
 
Outlets from internal gutters shall penetrate the external wall to discharge into a 
rainwater head: 
 
full width of the gutter shall extend through the wall into the rainwater head 
 
gutter lining shall terminate with a drip-edge. 
 
7.5.3   Gutter Overflows 

Information 
Overflows shall be provided as an opening within the rainwater head and 
  cross-sectional area of overflow shall be1.5 times the area required for the 
outlet 
  height shall be set so that the overflow functions before water can enter the 
structure, if the outlet or downpipe becomes blocked. 
 
7.5.4  Testing 

Official 
Blocking the outlet and flood-testing to check the integrity of the gutter and operation 
of the overflow, is recommended before roofing or internal linings are fitted. 
 
the 
 
 
 
under 
 
 
 
 
Released 
 
 
Weather-tightness and Durability Requirements – August 2014   
32 | P a g e  
 
 


 
 
 
 
 
 
 
 
(1982)
 
Act 
 
 
 
 
 
 
Information 
 
 
 
 
Official 
 
 
the 
7.6 
Valley Gutters 
Valley gutters shall not be fitted where the roof pitch is less than 80 (internal gutters 
shall be constructed). 
Refer to section 8.4.5 of NZ Metal Roof and Wall Cladding Code of Practice   
Version 2.2 / 2012 for valley gutter design requirements. 
under 
 
Section 8 
Exterior Joinery 
Circular windows are not permitted                                                                                      . 
 
The following window types are Restricted design elements                                            . 
  complex shapes 
  raking or curved heads 
Released 
  curtain wall glazing exceeding 2 storeys in height 
  recessed, other than provided for in E2/AS1 (sill flashings tend to accumulate water 
rather than shield and drip away from opening between the window frame and sill 
flashing). 
Weather-tightness and Durability Requirements – August 2014   
33 | P a g e  
 
 

 
Windows shall comply with NZS 4211 
 
 
Section 9 
Balconies 
The following design elements are not permitted with upper floor balconies                  : 
  construction using cantilevered timber joists  
   cantilevered glass balustrade without a handrail  
 
Balconies constructed over occupied spaces are a Restricted design                                             
 
Balconies to which students have access
: 
(1982)
  shall be designed to discourage students from sitting on the balustrade 
  shall give special attention to safety-from-falling. 
 
Solid Balustrades: 
Act 
  shall be constructed with tops flashed and stopped as if a roof parapet. 
 
Section 10 
Junctions with Existing Buildings 
 
Attaching new construction to an existing building, is a Restricted design element          . 
The junction between the envelope of a new building and that of an existing, provides a 
potential source of water ingress, particularly when design requirements such as seismic 
junctions are involved. 
Information 
 
Section 11 
Exposed Structural Elements 
Structural (or other) elements which penetrate the exterior rain-screen, are                    
Restricted design elements. 
Official 
Penetrations  through  the  building  envelope  by  structural  elements  (ie  supporting  roof 
overhangs) are a potential source of water ingress. 
 
the 
 
 
Section 12 
Durability 
under 
Materials  are  expected  to  maintain  their  durability  over  the  life  of  the  building  and  not 
deteriorate from premature corrosion. 
The following factors will affect the long term durability of materials: 
  proximity to salt-laden atmosphere 
  industrial atmospheric contaminants  
   ability of rain to reach and wash contaminants from the surface of metals 
   the characteristics of the material selected. 
 
Eaves / overhangs are encouraged but they prevent rain reaching: 
Released 
  their underside 
  wall surfaces immediately below them. 
 
Weather-tightness and Durability Requirements – August 2014   
34 | P a g e  
 
 

Materials selected for walls under wide overhangs shall be selected / coated with this in 
mind. 
The underside of eaves up to 900 wide shall be lined. 
The following elements shall be protected with an appropriate industrial paint system  
(ensure that any Manufacturer’s warranty remains valid): 
  underside of exposed metal roofing on overhangs wider than 900mm  
  exposed structural elements that are not rain washed. 
Painted or coloursteel flashings should be avoided in protected locations (ie not rain-washed). 
 
The following details are Restricted design features. 
  metal cladding on walls under eaves wider than 900mm  
  exposed metal structural elements under eaves or overhangs. 
  overhangs wider than 900mm where the underside of metal roofing is 
(1982)
exposed. 
Act 
Information 
Official 
the 
under 
Released 
Weather-tightness and Durability Requirements – August 2014   
35 | P a g e  
 
 







 
Appendix A 
To be completed by the Designer and submitted to the Project Manager at completion of 
Detailed Design. 
Weather-tightness / Durability Check Sheet 
(1982)
SCHOOL NAME 
 
………………..….……………………………….. 
SCHOOL  I.D. 
 
……………….…………………………………… 
Act 
PROJECT  NAME 
 
……………………………………………………. 
PROJECT  I.D. 
 
……………………………………………………. 
PROGRAMME YEAR FUNDING ALLOCATED...……………………………. 
FUNDING SOURCE LISTED IN PMIS.…………………………………………. 
 
I / we confirm that:  
 
this project does not contain materials or features which are Prohibited in the 
Information 
Weather-tight and Durability Requirements for Schools – June 2014 publication  
 
this project does not contain materials or elements whose use is Restricted  
 
this project includes the following materials or features whose use is Restricted and 
full construction details for these items are appended 
 
 
 
 
………………..….……………………………….. 
Official 
 
 
 
 
……………….…………………………………… 
the 
 
where applicable, features and elements have been designed in compliance with 
details and clauses in the Requirements 
 
this project includes the following features or elements that have not been designed 
in compliance with details or clauses in the Requirements and full construction 
details of these items are appended 
under 
 
 
 
 
………………..….……………………………….. 
 
 
 
 
……………….…………………………………… 
COMPANY 
 
 
………………..….……………………………….. 
DESIGNER’S NAME   
……………….…………………………………… 
DESIGNER’S SIGNATURE  ………………..….……………………………….. 
Released 
 
DATE                                     ………………..….……………………………….. 

Weather-tightness and Durability Requirements – August 2014   
36 | P a g e  
 
 

Document Outline