2021-24 NLTP MODERATION PROCESS 
 

PURPOSE 
Provide an overview of, and outline key milestones for, the moderation and optimisation of the National Land Transport Programme for Waka 
Kotahi as the investor. 
INFORMATION 
 
BACKGROUND 
Waka Kotahi NZ Transport Agency has a responsibility under the Land Transport Management Act 2003 for setting dates for developing the 
National Land Transport Programme (NLTP) every three years.  OFFICIAL 
Investment Advisors at Waka Kotahi col aborate with Approved Organisations (AOs), and Waka Kotahi  as applicant, to support them in 
developing their continuous programmes, Low Cost Low Risk improvement (LCLR) programme and any other improvement activities, 
programmes or packages that are seeking inclusion for the 2021-24 NLTP. It’s important for Investment Advisors and applicants to keep in touch 
THE 
with each other throughout the development of the NLTP and adopt a no-surprises approach.  
 
FUNDING  BIDS AND MODERATION WORKSHOPS 
UNDER 
Prioritisation of programmes and activities is subject to the Waka Kotahi Board making a final decision when it adopts the NLTP. Activities are 
assessed for inclusion in the NLTP through a series of bid stages. Initial and final bid stages have fixed deadlines to ensure that applicants get a 
reasonable amount of certainty, or signals, about: 
•  the quality of their supporting information  
•  how Waka Kotahi wil  subsequently determine the funding al ocation in the NLTP. 
RELEASED 

This staged bid and assessment process enables applicants to plan with greater certainty, respond to assessment feedback and adjust their 
evidence and/or planned programmes before the NLTP is adopted by the Waka Kotahi Board. While it is uncommon to have any material 
changes between the initial and final al ocations, there is room for review and adjustment between these deadlines. Al  bids should pr
1982 ovide 
evidence-based proposals that demonstrate the BCA principles. 
Moderation is an internal Waka Kotahi business process that ensures a consistent approach is used to assess al  funding requests. Typical y, 
ACT 
moderation takes place in stages, focusing initial y on the strategic drivers and qualitative assessment of high-level business case material. This 
ensures the most appropriate activities are progressed to subsequent stages with confidence. 
What 
Description 
Initial bids – Continuous Programmes  Critical in providing Waka Kotahi and regional transport committees (RTCs) a first look at funding 
proposals. Initial bids are expected to be a robust, realistic signal of the investment proposal. 
Setting the scene 
Setting the scene is about obtaining a view of the upcoming NLTP from a strategic lens and provides 
an initial view of the pressures within the system. 
The workshop analyses AO and Waka Kotahi bids and submissions to provide a view across the 
activity classes on the committed and available funding. 
INFORMATION 
Continuous programmes - 
Preliminary prioritisation and moderation is to chal enge the continuous programme bids including a 
preliminary prioritisation and 
focus on the quality of the supporting information. An initial moderation of the continuous 
moderation 
programmes is undertaken. 
Reset - Setting the scene 
After each moderation workshop has been undertaken Waka Kotahi should take stock of its current 
position across the activity classes on the committed and available funding. The workshop will also 
include indicative balancing of activity classes. 
OFFICIAL 
Initial submissions – new 
We wil  require applicants submit their improvement activities which includes their Low Cost Low Risk 
improvement activities 
programme and new activities being included in the NLTP. 
For each new improvement activity an Investment Prioritisation Method (IPM) profile should be 
THE 
provided.  
For Low Cost Low Risk activities, the IPM profile is set at a programme level.  During this step, 
applicants will confirm their improvement activity submissions. 
Note: For continuous programmes an IPM profile is not required to be provided as a default profile is 
used for these programmes. 
UNDER 
Improvement activities - preliminary  Preliminary prioritisation and moderation involves chal enging Low Cost Low Risk programmes and 
prioritisation and moderation 
new improvement activities. An initial moderation of these activities is undertaken. 
Final bids – Continuous Programmes  Determined through negotiations between Waka Kotahi and the AOs fol owing submission of initial 
 
bids. Final bids should have: 
Final submissions – improvements 
-  more detail than the initial bid 
activities 
-  be supported by more robustly developed evidence  
RELEASED 

 
-  have strong local governance support for inclusion in the NLTP  
-  applied the BCA in developing information and supporting evidence 
-  self-evaluated that evidence using assessment of the business case models. 
1982
Continuous Programmes 
Funding is effective immediately at the start of the NLTP period, so all information required for Waka 
Kotahi assessment needs to be provided with final bids. There should be no outstanding issues. 
ACT 
Low Cost Low Risk 
Funding is al ocated to an AO or Waka Kotahi at the start of the NLTP period. AOs or Waka Kotahi will 
need to have completed their three-year detailed LCLR programme in order to draw down their 
al ocated funding. 
Improvement Activities 
Funding is only prioritised against new activities at the start of the NLTP period. AOs or Waka Kotahi 
should discuss next steps with their investment advisor. 
Note: Some business cases may have progressed sufficiently to be recommended for funding approval 
when the Board adopts the NLTP. Where possible Waka Kotahi should align funding approval with 
NLTP adoption to provide greater certainty that the NLTP represents the three-year investment 
INFORMATION 
programme of Waka Kotahi. 
Continuous programmes - final 
Final prioritisation and moderation is a further chal enge of continuous programme bids, while 
prioritisation and moderation 
looking to resolve outstanding issues and confirm the programme. 
During the session there is also a focus on the results from a review of finalised programmes and 
includes comparisons (benchmarking) between similar proposed programmes and their pairs. 
Improvement activities - final 
Final prioritisation and moderation is a further chal enge of Low Cost Low Risk programmes and new 
OFFICIAL 
prioritisation and moderation 
improvement activities, while looking to resolve outstanding issues and confirm programmes and 
submissions. 
The session includes a final moderation of these activities/programmes which involves ensuring 
THE 
critical parts of dependent projects are above the cut-off and confirming prioritisation ratings for 
activities. 
Suggested al ocations across activity classes and scenario planning is also undertaken. 
Optimisation 
Process to confirm al ocations between the funding ranges set by the GPS for each activity class. This 
is an outcome view to ensure we are optimising value for money while meeting our requirements 
under the GP
UNDER  S. 
 
After each moderation session (workshop) feedback is provided within Waka Kotahi and to AOs to ensure they can firm up their investment bids. 
For example, the focus of the Investment Advisor when progressing from initial to final bids for a road maintenance programme is to improve 
the quality of the AMP as a business case. 
RELEASED 

MODERATION DEADLINES AND RESPONSIBLITIES 
1982
The moderation and optimisation of the NLTP has the fol owing steps and responsibilities. 
 
ACT 
What 
Timeline 
Waka Kotahi Responsibilities 
Investment templates  18 August 2020 
Lead Role 
available 
NLTP Development Lead - NLTP Development Team develops and prepares the templates for 
release 
Supporting Roles 
•  Inform and support applicants: 
o  Public  Transport Team 
o  Regional Investment Advisors 
o  Partnership Investment 
INFORMATION 
o  Activity Class Managers 
•  Inform and support Waka Kotahi: 
o  Design Practice Solutions 
o  Activity Class Managers 
Initial bids – continuous  21 September 2020  Lead Role 
Programmes 
Manager Treasury & Cashflows - Treasury Cashflow Team Manage and analyse data within 
TIO 
OFFICIAL 
Primary Roles 
•  Operational Policy & Standards Team – Responsible for the State Highway Maintenance 
Programme 
THE 
•  Road Safety Partnership Team – Responsible for the Road Safety Partnership Programme 
•  Regional Investment Advisors – Support Approved Organisations in developing their LCLR 
and Maintenance Operation & Renewals (MOR) programmes 
•  Partnership Investments - Support regional and unitary authorities in developing their 
Public Transport (PT) programmes. 
UNDER 
•  Technical Services Team – Supports Waka Kotahi in developing their continuous 
programmes 
Setting the scene 
6 October 
Lead Role 
Manager Treasury & Cashflow – The Treasury & Cashflow Team will provide information on 
committed and new activities by activity class 
Supporting Role 
RELEASED 

•  Activity Class Managers - Represent their activity class and their current position in terms 
of committed and new activities 

1982
  External Engagement & Communications Team – Communicate the latest investment 
signals to the sector 
Continuous programme  October/ 
Lead Role 
Investment Quality 
November 2020 

ACT 
  Senior Manager System Management – Regional Investment Advisors complete IQA 
Assurance (IQA) initial 
reviews over the Approved Organisation activity management plans and initial 
bids 
maintenance operations & renewals programme 
•  Manager Partnership Investments – The team is responsible for completing IQAs over 
initial public transport continuous programmes and the documents that support the 
programme 
•  Manager Technical Services – The team is responsible for completing IQAs over Waka 
Kotahi continuous programmes and the documents that support the programmes 
•  Team Lead Road Safety Partnership – The team is responsible for lead the development 
of the Road Safety Partnership Programme and supporting the programme’s IQA. 
 
INFORMATION 
Primary Role 
External Quality Assurance – An assessor with NZ Police experience completes the IQA review 
over the programme. The reviewer is independent to Waka Kotahi and NZ Police. 
 
Supporting Role 
•  Design Practice & Solutions – the team wil  support the Manager Technical Services in 
OFFICIAL 
completing IQAs over Waka Kotahi continuous programmes and carry-out the 
IQA/Assessment of Waka Kotahi Road Safety Promotion activities. 
•  Investment Assurance – the team supports assessors in completing their IQA over the 
THE 
continuous programmes. 
 
Note: Oversight of Low Cost Low Risk programmes wil  be managed by Regional Investment 
Advisors for road control ing authorities, the Partnership Investment for regional councils and 
Investment Assurance for Waka Kotahi. 
UNDER 
Initial submissions – 
21 September until  Lead Role 
new improvement 
the 30 October 
Manager Treasury & Cashflows - Treasury Cashflow Team Manage and analyse data within 
activities 
TIO 
Primary Roles 
•  Operational Policy & Standards Team – Responsible for the Waka Kotahi Investment 
Proposal and the State Highway Maintenance Programme 
RELEASED 

•  Planning & Performance Team – Responsible for the Waka Kotahi Low Cost Low Risk 
programme 

1982
  Road Safety Partnership Team – Responsible for the Road Safety Partnership Programme 
•  Waka Kotahi Investment Proposal Team – Responsible for identifying and incorporating 
nationally delivered activities into the NLTP 
Supporting Roles 
ACT 
•  Regional Investment Advisors – Support Approved Organisations in developing their LCLR 
and MOR programmes 
•  Partnership Investments – Support Approved Organisations with any new starts for 
inclusion into the 2021-24 NLTP 
•  Public Transport Team – Support regional and unitary authorities in developing their PT 
and LCLR programmes. 
•  Technical Services - Support Waka Kotahi in developing its and LCLR programmes 
•  Design, Practice & Solutions - Support Waka Kotahi with its new starts 
Continuous 
9 November 2020 
Lead Role 
INFORMATION 
programmes - 
Assessment & Prioritisation Lead – Assessment & prioritisation team facilitates the 
preliminary 
moderation and optimisation process 
prioritisation and 
Primary Role 
moderation 
•  Partnership Investments – Represents the public transport continuous programmes 
•  Regional Investment Advisors – Represents maintenance operations and renewals 
continuous programmes 
•  Technical Services Team – Represents Waka Kotahi continuous programmes 
OFFICIAL 
•  Activity Class Managers – Lead the prioritisation and moderation process workshop. 
Represent their activity class and chal enge programmes and new starts within their 
activity class 
THE 
Supporting Role 
•  Investment assessment working group - reviews and agrees the assessment profiles and 
prioritises activities nationally. The working group develops recommendations for 
inclusion and/or funding allocations for  the Waka Kotahi Board’s final approval. The group 
should be made up of representatives from: 
UNDER  o  Transport Services - System Planning 
o  Transport Services - System Management 
o  Transport Services - System Design 
o  Transport Services – Operational Policy, Planning & Performance 
o  Corporate Support  – Enterprise Change 
o  Corporate Support  – Investment & Finance 
RELEASED 

o  Safety Health & Environment  – Road Safety and Environment and Sustainability 
teams 

1982
 
External observers - For example representatives from the Transport Special Interest 
Group, which is drawn from regional council staff 
Reset - Setting the 
16 November 2020  Same responsibilities as setting the scene. 
scene 
ACT 
Feedback preliminary 
November 2020 
Lead Role 
prioritisation and 
•  Senior Manager System Management – Regional Investment Advisors will provide 
moderation 
feedback to Approved Organisation’s MOR 
- Continuous 
•  Manager Partnership Investments – The team wil  provide feedback to AOs on there PT 
programme 
continuous programme 
•  Manager Technical Services – The team will provide feedback to Waka Kotahi, as 
applicant, on their continuous programmes. 
•  Team Lead Road Safety Partnership – The lead is responsible for providing feedback into 
the Road Safety Partnership Team on the Road Safety Partnership Programme. 
Final bids - continuous  11 December 2020  Same responsibilities as initial bids. 
INFORMATION 
Programmes 
Continuous programme  January/ February 
Same responsibilities as continuous programme Investment Quality Assurance (IQA) initial 
IQA Final bids 
2021 
bids 
Improvement activities  16 February 2021 
Lead Role 
- preliminary 
Assessment & Prioritisation Lead – Assessment & prioritisation team facilitates the 
prioritisation and 
moderation and optimisation process 
OFFICIAL 
moderation 
Primary Role 
•  Partnership Investment – Represent the new starts from Approved Organisations 
•  Design Practice & Solutions - Represents the Waka Kotahi new starts 
THE 
•  Regional Investment Advisors – Represent road Control ing authority LCLR programmes 
and provide feedback on these programmes to AOs 
•  Technical Services Team – Represents the Waka Kotahi LCLR Programme 
•  Activity Class Managers – Lead the prioritisation and moderation process workshop. 
Represent their activity class and chal enge programmes and new starts within their 
UNDER activity class 
Supporting Role 
•  Investment assessment working group - reviews and agrees the assessment profiles and 
prioritises activities nationally. The working group develops recommendations for 
inclusion and/or funding al ocations for  the Waka Kotahi Board’s final approval. The group 
should be made up of representatives from: 
RELEASED 

o  Transport Services - System Planning 
o  Transport Services - System Management 
1982
o  Transport Services - System Design 
o  Transport Services – Operational Policy, Planning & Performance 
o  Corporate Support  – Enterprise Change 
o  Corporate Support  – Investment & Finance 
ACT 
o  Safety Health & Environment  –Road Safety and Environment and Sustainability 
teams 
•  External observers - For example representatives from the Transport Special Interest 
Group (TSIG), which is drawn from regional councils 
Continuous 
25 February 2021 
Same responsibilities as the preliminary prioritisation and moderation workshop. 
programmes - final 
prioritisation and 
moderation 
Reset – Setting the 
4 March 2021 
Same responsibilities as setting the scene. 
scene 
INFORMATION 
Feedback final 
March 2021 
Same responsibilities as feedback initial prioritisation and moderation. 
prioritisation and 
moderation 
- Continuous 
programme 
Feedback preliminary 
March 2021 
Lead Role  OFFICIAL 
prioritisation and 
•  Senior Manager System Management – Regional Investment Advisors will provide 
moderation 
feedback to Approved Organisation’s LCLR programmes 
- Improvement 
•  Manager Partnership Investments – The team wil  provide feedback to AOs on there 
THE 
Activities 
public transport continuous programme 
•  Manager Technical Services – The team will provide feedback to Waka Kotahi, as 
applicant, on their continuous programmes. 
Team Lead Road Safety Partnership – The lead is responsible for providing feedback into the 
Road Safety Partnership Team on the Road Safety Partnership Programme. 
UNDER 
Indicative al ocations 
22 April 2021 
Lead Role 
for continuous & LCLR 
NLTP Development Lead – The NLTP Development Team drafts the Board paper to agree the 
programmes 
indicative al ocations for the continuous & LCLR programmes 
Primary Roles 
•  External Engagement & Communications Team – broad key  messages from the NLTP 
•  Investment Assurance – Input into the development of the Board paper 
RELEASED 

•  Waka Kotahi Board – Endorse the indicative allocations 
Supporting Roles 

1982
  Chief Financial Officer – Endorse the Board paper 
•  General Manager Corporate Support – Endorse the Board paper 
Final submissions – 
21 May 2021 
Same responsibilities as initial submissions. 
improvement Activities 
ACT 
NTLP Audit 
End of May 2021 
Lead Role 
Senior Manager Risk Assurance – Risk Assurance has oversight of the NLTP development 
process to ensure legislative compliance and robust process has been fol owed to develop the 
NLTP 
Improvement activities  10 June 2021 
Same responsibilities as the preliminary prioritisation and moderation workshop. 
- final prioritisation and 
moderation 
Reset – Setting the 
17 June 2021 
Same responsibilities as setting the scene. 
scene 
Interim funding 
24 June 2021 
Same responsibilities as indicative al ocations for continuous & L
INFORMATION  CLR programmes 
arrangement from 1 
July until 31 August 
2021 
Receipt final Regional 
End of June 2021 
Lead Role 
Land Transport Plans 
RLTP Development Lead – Ensure Regional Councils are aware of RLTP deadlines and liaise 
with TSIG to ensure RLTPs are finalised on time and submitted into TIO. 
OFFICIAL 
Supporting Role 
•  TSIG – Represents regional councils. Establishes the sector’s RLTP timeline and provides a 
forum to meet with Waka Kotahi. 
THE 
•  Treasury & Cashflow Team – Confirm final RLTPs have been submitted into TIO. 
Optimisation 
15 July 2021 
Lead Role 
NLTP Development Lead - Leads the discussion on the al ocations between the min/max 
ranges set by the GPS for each activity class. This is an outcome view  to ensure we are 
optimising value for money. 
UNDER 
Primary Role 
•  Activity Class Managers - Represent their activity class and provide detailed information 
on the programmes and new starts within their activity class 
•  Treasury & Cashflow Team – Presents information of the cashflow between the activity 
classes and the overal  financial position of the NLTF 
Supporting Role 
RELEASED 

Investment Assurance – oversight of the optimisation process. 
Approved NLTP 
31 August 2021 
Lead Role 
NLTP Development Lead – The NLTP Development Team drafts the Board paper to
1982  adopt the 
NLTP 
Primary Roles 
•  Risk Assurance – Endorsed NLTP audit report included with the paper to the Board 
ACT 
•  External Engagement & Communications Team – Key messages and an outline of now 
the NLTP wil  be launched 
•  Investment Assurance – Input into the development of the Board paper 
•  Waka Kotahi Board – Adopt the NLTP 
Supporting Roles 
•  Chief Financial Officer – Endorse the Board paper 
•  General Manager Corporate Support – Endorse the Board paper 
Finalise the NLTP 
September 2021 
Lead Role 
NLTP Development Lead – The NLTP Development Team leads the finalisation of the NLTP 
Supporting Role 
INFORMATION 
•  Treasury Cashflow Team – Al ocation funding within TIO against each AO and Waka 
Kotahi. Update status of new improvement activities. 
•  Enterprise Change Team – Appoint a date for when RLTPs are to be publicly released. 
•  External Engagement & Communications Team – Finalising messaging and Facilitating the 
launch of the NLTP and organisation of applicant communications. 
 
OFFICIAL 
The assessment and prioritisation workstream lead will be organising a meeting with process leads (lead roles) within the moderation process. 
The discussion wil  be focused on resourcing requirements to fulfil  the outlined roles. 
THE 
 
WAKA KOTAHI DECISIONS 
UNDER 
Waka Kotahi needs to weigh up and prioritise competing programmes of activities because the funding pool is limited. Al  the work leading up to 
and at moderation informs these decisions. Waka Kotahi provides advice on the NLTP al ocation in three stages: 
•  Indicative allocations: AOs are advised an indicative allocation for their continuous programmes prior to the adoption of the NLTP to 
help them finalise their long-term plans. Waka Kotahi wil  endeavour to provide this advice by the end of April 2021. 
•  Approved al ocation: AOs receive confirmation and advice of the approved al ocation when the NLTP is published. 
RELEASED 

•  Communicate activities that were not included in the NLTP or those activities that were included but at a different priority order. 
 
1982