22 October 2021 
 
 
 
 
 
 Jonathan Brewer 
[FYI request #16812 email] 
REF: OIA-8821 
 
Dear Jonathan 
 
Request made under the Official Information Act 1982 
 
Thank you for your email of 20 September 2021 requesting the following information under the Official 
Information Act 1982 (the Act): 
 
Please release any information about telecommunications, ITS, or other utility ducts along the 
Transmission Gully Motorway. 
 
This should include the number of ducts, linear kilometres of ducts, whether any ducts were 
outfitted with subduct, number of vaults or chambers, cost of the works, and how costs were 
apportioned (i.e. entirely to utility operators, split between operators, etc.). 

 
The number of ducts required to be provided on the Transmission Gul y project is listed in Section 11 – 
Utilities, of the TG PPP Project Agreement - Schedule 11 – Works Requirements. This can be found at 
the following link: 
•  www.nzta.govt.nz/projects/wellington-northern-corridor/transmission-gully-motorway/about-
the-project/public-private-partnership/ppp-contract-development. 
 
At financial close the total length of duct banks being provided by the Builder was stated as being 
34.22km. The length of the project is nominally 27.5km. No sub-ducts were required to be provided or 
are being installed by the PPP Builder.  
 
Waka Kotahi NZ Transport Agency does not hold a record of the number of ducts, linear kilometres of 
ducts, or the number of vaults or chambers, as these are being provided by the Builder as part of 
delivery of the road. At this point in time the as-built information required by our Roading Assessment 
and Maintenance Management (RAMM) asset system has yet to be provided.  
 
The cost of the instal ation of the telecommunications, ITS and other utility ducts along the TG 
motorway was included as part of the PPP Contract Price, with any actual and reasonable costs for 
the administration, access (traffic management etc) and installation of any associated ITS 
infrastructure falling to the telecommunications utility supplier(s) as per the National Code of Practice 
for Utility Operators Access to Transport Corridors.  
 
 
  


The capital cost of the telecommunications, ITS and other utility ducts is considered to be commercial-
in-confidence between Waka Kotahi and the PPP Builder, and I am therefore withholding this 
information under Section 9(2)(b)(i ) of the Act, in order to protect information where making  the 
information available would be likely unreasonable to prejudice the commercial position of the person 
who supplied or who is the subject of the information. 
 
With respect to the information that has been withheld, I do not consider there are any other factors 
which would render it desirable, in the public interest, to make the information available. 
 
Under section 28 of the Act, you have the right to ask the Ombudsman to review my decision to 
withhold this information. The contact details for the Ombudsman can be located at 
www.ombudsman.parliament.nz. 
 
If you would like to discuss this reply with Waka Kotahi or to set up a meeting to discuss this topic 
further, please contact the Ministerial Services team by email to [email address]. 
 
 
Yours sincerely 
 
 
Andrew Thackwray 
National Manager – Infrastructure Delivery