This is an HTML version of an attachment to the Official Information request 'NZUP Northern Pathway'.

MINISTERIAL BRIEFING NOTE 
Subject 
Auckland Harbour Bridge shared path – Interim findings presentation 
Date 
6 August 2021 
Briefing number 
BRI-2265 
Contact(s) for telephone discussion (if required) 
Name 
Position 
Direct line 
Cell phone 
1st contact 
s 9(2)(a)
Brett Gliddon 
General Manager, 

Transport Services 
Action taken by Office of the Minister 

Noted

Seen by Minister

Agreed

Feedback provided

Forwarded to

Needs change [please specify]

Withdrawn
under the Official Information Act 1982

Overtaken by events
Released 

BRI-2265 
6 August 2021 
 
Hon Michael Wood - Minister of Transport 
 
AUCKLAND HARBOUR BRIDGE SHARED PATH – INTERIM 
FINDINGS PRESENTATION 
Purpose 
1. 
In early-2021, you asked Waka Kotahi to investigate options to accommodate a shared path on 
the Auckland Harbour Bridge as interim solution for walking and cycling across the Waitemata 
Harbour until the Northern Pathway is complete. 
2. 
The purpose of this briefing is to formally provide you with a copy of the presentation given to you 
verbally by Brett Gliddon, General Manager, Transport Services on 12 July 2021.  
3. 
This briefing also sets out the challenges identified in the presentation and confirms the decision-
making process that will be followed for selecting an interim solution.  
Background 
4. 
As part of the NZ Upgrade Programme, the Government has confirmed funding of $785m to 
deliver the Northern Pathway Westhaven to Akoranga project.  
5. 
The preferred option for the Waitemata Harbour crossing section is a standalone bridge 
alongside the existing Auckland Harbour Bridge (AHB). The soonest construction is expected to 
be able to begin is mid-2022, subject to the approval process, and will take four to five years to 
construct. 
6. 
Waka Kotahi is now working hard to deliver the Northern Pathway, with a large team engaged on 
design, consenting and construction planning.  
7. 
In the meantime, Waka Kotahi has been asked to investigate an interim solution to provide a 
suitable walking and cycling connection across the Waitemata Harbour until such time that the 
under the Official Information Act 1982
Northern Pathway is completed. This includes the use of buses or ferries, as well as the 
reallocation of lanes on the AHB to provide a shared path for walking and cycling. 
8. 
The attached presentation sets out a range of options explored for repurposing lanes on the 
AHB, including an assessment of the outcomes, challenges and costs for each option. 
9. 
The objective of the investigation to date was to consider the health and safety implications for 
people on the bridge and our staff, what could be accommodated without impacting the overall 
structural integrity, operational considerations and implications across the wider transport 
Released 
network. 
10.  Waka Kotahi is continuing work to consider other interim options, including dedicated bus and 
ferry services.  
Page 2 
 

BRI-2265 
Key findings 
11.  As detailed in the Interim Findings presentation, a combination of single lane and two-lane 
configurations, as well as short term (weekend) and permanent options to accommodate a 
shared path on the Auckland Harbour Bridge have been considered as part of the investigations.  
12.  While it is not impossible to implement either a short-term or permanent walking and cycling 
solution, we have identified a number of very significant challenges, including: 
•  Structural implications 
•  Width and gradient challenges (one lane options) 
•  Health and safety concerns 
•  Significant network implications 
•  Restrictions for large vehicles 
•  Operational challenges 
13.  To ensure the safety of all users, provision of a shared path on the clip-on structure would 
require barriers to be installed to separate general traffic from shared path users. The weight of 
such a barrier would require limitations to be imposed on heavy vehicle use of the clip-on lanes 
in a one lane configuration.  
14.  Due to structural limitations preventing the fixing of any structures to the bridge deck, a barrier 
system similar to the current movable lane barrier would be required. The procurement and 
installation of a suitable barrier system would take time and make a summer trial a challenge to 
achieve. 
15.  One lane options also have challenges on health and safety for users due to width and gradient, 
and also have wider network implications and operational challenges. 
16.  Due to demand on bridge capacity, two-lane options have significant impacts on the wider 
transport network, unless access to the shared path was limited to periods of low demand (i.e. 
Sunday mornings).   
under the Official Information Act 1982
17.  Historically, Waka Kotahi has allowed access to the bridge for special events, such as the 
Auckland Marathon. These events are accommodated during periods of low demand, typically 
before 10am on Sunday, and enable measures to be put in place to ensure the safety of users, 
as well as managing the impact across the wider network.  
18.  We consider that such events could continue to be accommodated for walkers and cyclists. 
However, as noted above, this is far from delivering the level of service being sought by 
delivering an interim solution.  
Released 
Decision making 
19.  While use of lanes on the Auckland Harbour Bridge is an operational matter and decisions 
ultimately fall with the Waka Kotahi Board, Waka Kotahi recognises the significance of this and 
Page 3 
 


BRI-2265 
the upcoming decisions for the Government and community. We will therefore wait for your 
feedback before a decision is sought from the Board.  
20.  Waka Kotahi is committed to working closely with you to identify and deliver a suitable interim 
solution. 
It is recommended that you:  
1.  Note the contents of this briefing. 
Noted 
 
 
........................................................................... 
Brett Gliddon 
General Manager, Transport Services 
 
 
 
 
............................................................................ 
Hon Michael Wood, Minister of Transport  
Date:    
2021
under the Official Information Act 1982
Released 
Page 4