This is an HTML version of an attachment to the Official Information request 'Lawfulness of WasteWater Pipes and Discharges'.
link to page 2 link to page 14 link to page 39 link to page 41 link to page 42  
 
Table of Contents 
1. 
 
1. Paremata Wastewater Update Email 

2. 
 
2. Paremata Wastewater Rising Main 
13 
3. 
 
3. Copy of Aotea pipe breakParamata overflow Enteroccoci monitoring (cfu100mL) 
38 
4. 
 
4. Email correspondence between WWL and PCC 
40 
5. 
 
5. Email correspondence between PCC and WWL 
41 
 
 


21-108
Page 1 of 44
UPDATE 19 20:30 25 July 2021 
 
Good Evening 
 
The team were successful in completing the repair this evening and the rising main is now 
operational.  Our team will be monitoring the repair overnight.  Note that we will still have some 
carparks coned off in the turning circle of the carpark due to machinery being onsite for monitoring 
purposes.  Please see the picture below for approximate location of pumps (in blue) and carparks in 
red. 
 
 
 
The principal of Paremata School has been advised that we will have Station Road open with traffic 
management operators on site to assist parents at pick-up and drop-off time. 
 
Below is a media statement which is being released at approximately 21:00. 
Attribute to Steve Hutchison Chief Advisor Wastewater, Wellington 
Water 
Our crews have completed the repair to the burst wastewater main between the 
Aotea turnoff and Paremata. 
While the repair has been successful and has enabled us to begin reusing the 
main, our investigations have shown that it remains in a very poor condition. We 
are continuing to investigate the extent of this while exploring options for a 
permanent replacement or repair.  
As the bursts caused wastewater to overflow, on Saturday 24 July, a rāhui (ritual 
prohibition) was put in place by Ngāti Toa, banning the taking of shellfish or fish 
in and around Porirua harbour. It will be in place for two weeks.  
State Highway One, northbound, will remain reduced to one lane while work to 
clear the site continues. Traffic management will be in place, off peak, while we 
do this. Some car parks at the end of Station Road, by the service station, will 

21-108
Page 2 of 44
also be coned off while pumps remain on site, as a contingency. Please avoid the 
area if possible. 
Further information on recreational water quality is available at lawa.org.nz. 
We’d like to thank the public for their continued patience while we work to fix 
this issue. 
Media contact: [email address] or 021 302 259 
Kind regards 
Glenis 
 
UPDATE 18 12:30 25 July 2021 
 
Good afternoon 
 
The team are working hard on the repair today and works are progressing well.  Because of the 
complex nature of the repair it is anticipated we will be working into the evening. 
 
Overnight there was no discharge into the harbour.  The rising main was kept in operation and 
excess flow was well controlled by the use of sucker trucks.  The rising main has had to be taken 
offline to make the repair today and we are using sucker trucks to minimise overflow although there 
has been  some discharge to the harbour. 
 
Traffic Management remains in place and we are liaising with Capital Journeys.  Currently the 
carpark at the railway station is closed and we will advise when this is open for use again. 
 
A further update will be provided in the early evening. 
 
Thank you for your patience and we apologise for the inconvenience. 
 
Kind regards 
Glenis 
 
UPDATE 17 11:25 
 
Good morning 
 
Unfortunately there has been a delay in the arrival of the specialised fittings from Auckland, which 
will now arrive after 21:00 (9pm) tonight.  Consequently we are putting today’s work on 
hold.  Sucker trucks have been mobilised to assist with minimising overflows at peak times and work 
will resume tomorrow morning. 
 
Thank you for your patience and we apologise for the inconvenience. 
 
Kind regards 
Glenis 
 
UPDATE 16 11:10 24 July 2021 
 
Good Morning 

21-108
Page 3 of 44
 
Works are continuing today at the Rising Main repair on SH1 Paremata.  Repairs today consist of 
replacing a longer (12 meter) section of pipe in the area with specialist internal reinforcement joints 
which have been sourced and flown in from Auckland to enable connection to the fragile pipe.  This 
work is expected to continue into the evening. 
 
Flows were contained overnight with no overflows to the harbour.  Leakage from the repair site was 
contained by the use of sucker trucks.  We anticipate there may be some overflows today while the 
repair work is underway.  Sucker trucks have been mobilised to reduce the overflow, however there 
are likely to be some overflows during peak times today.   
 
Ngati Toa are planning to place a Rahui on the harbour area which will be conducted at the Titahi 
Bay Boating Club at 1pm today. 
 
Sampling is continuing and we are liaising with GWRC to keep recreational water advice updated on 
lawa.org.nz.  
 
A media release will be going out at 11:30 (see below). 
Attribute to Steve Hutchison Chief Advisor Wastewater, Wellington 
Water 
Our crews are continuing to work on a repair to the burst wastewater main 
between the Aotea turnoff and Paremata. 
State Highway One, northbound, will be reduced to one lane over the weekend 
while work continues.  
Traffic management is in place and we encourage the public to avoid the area if 
possible. 
Our investigations have shown the pipe, which has failed twice this week, is in a 
very poor condition. Staff and machinery were on site overnight to monitor the 
situation. 
We are continuing to investigate the cause and extent of the degradation while 
exploring options for a permanent replacement or repair.  
Due to the complexity of the repair, and fragile nature of the pipeline, we expect 
there to be some additional overflow today. We are working to minimise this as 
much as possible. 
To reduce potential wastewater overflow, we ask residents in Whitby, Paremata, 
Plimmerton, Pukerua Bay, and in the northern parts of Papakowhai to minimise 
water use as much as possible. 
We ask members of the public to avoid contact with water in the area and to not 
gather shellfish in the area. Health warning signs are in place. 
Further information on recreational water quality is available at lawa.org.nz. 

21-108
Page 4 of 44
We’d like to thank the public for their continued patience while we work to fix 
this issue. 
Media contact: [email address] or 021 302 259 
Kind regards 
Glenis 
 
UPDATE 14 – 20:15 – 23 July 2021 
 
Good Evening 
 
Due to the complexity of the job, fragility of the pipe and the fact that several different options have 
considered and tried today, our team have made a temporary repair to hold the pipe overnight 
whilst they arrange for resources to enable a more robust repair to be undertaken tomorrow. 
 
The majority of the teams have been stood down for the night but we have people on site to 
monitor the situation throughout the night.  Some leakage is expected from the temporary repair 
and we will endeavour to contain that using sucker trucks. 
 
One lane of the State Highway northbound will remain closed. 
 
We will provide a further update tomorrow morning. 
 
Thank you for your patience and we apologise for the inconvenience. 
 
Kind regards 
Glenis 
 
UPDATE 13 - 17:45 – 23 July 2021 
 
Good Evening 
 
Work to repair the wastewater main between the Aotea turnoff and Paremata is continuing.   
Traffic management has remained in place through rush hour and the disruption has been 
manageable. 
Due to the condition of the pipe and the complex repair it’s taking longer than anticipated to 
complete.  We do not expect to be able to complete a permanent repair this evening and will 
evaluate whether work will continue tomorrow depending on the effectiveness of the repair tonight.  
Close attention is being paid to fatigue of our staff and contractors. 
We will update you further later this evening.  
Kind regards 
Glenis 
 
UPDATE 12 – 14:00 23 July 2021 
 
Good afternoon 

21-108
Page 5 of 44
 
Repair work on the rising main is progressing but has not yet completed.  We are liaising with Waka 
Kotahi to get the site clear as soon as possible for the afternoon peak traffic flows. 
 
Please note that the repair work is complicated and we may have to continue work tomorrow 
depending how the repair holds. 
 
We will provide a further update following the next status meeting later this afternoon. 
 
Kind regards 
Glenis 
 
UPDATE 11 – 09:30 23 July 2021 
 
Good Morning 
 
Work continued overnight in preparation for repair of the Paremata rising main and enabled us to be 
track for repair today. Crews are now established on site to commence excavation and sucker trucks 
deployed at key sites to minimise discharge during the course of repairs.  Due to the fragile nature of 
this pipe the repair is complicated and further failures are possible.  We will make all efforts to 
contain wastewater however expect some overflow is likely to occur.  
 
The leaking rising main was kept in limited operation overnight and with the assistance of sucker 
trucks working through the night contained further wastewater discharge from the stormwater 
network overflow point beneath the Paremata railway bridge crossing. 
 
The cross harbour pipeline was put into emergency operation for a short period overnight which 
identified a leak further south towards Onepoto which required recommissioning to be abandoned. 
An overflow into the adjacent stormwater sump did occur for a short period, pumping was ceased 
which stopped the overflow and the site cleaned up and signage placed. This fault is being 
investigated today and repair work will be undertaken when possible. 
 
North bound traffic is currently reduced to one lane on SH 1 while repairs are 
being  undertaken.  We are asking residents in the area to minimise water use to assist with our 
efforts to minimise overflows. 
 
We are sending the below update at 9.45am to media and uploading to our website and social 
media platforms. 
 
 
Attribute to Steve Hutchison Chief Advisor Wastewater, Wellington 
Water 
Our crews are making further repairs this morning to the burst wastewater main 
on State Highway One, northbound, between the Aotea turnoff and Paremata. 
To reduce potential wastewater overflow, we ask residents in Whitby, Paremata, 
Plimmerton, Pukerua Bay, and in the northern parts of Papakowhai to minimise 
water use as much as possible. 
We are making all efforts to contain wastewater, but due last night’s heavy rain 
fall there was some overflow into the harbour. 

21-108
Page 6 of 44
Due the complexity of the repair, and fragile nature of the pipeline, we expect 
there to be some additional overflow today. We are working to minimise this as 
much as possible. 
Traffic management is in place and we encourage members of the public to 
avoid the area. 
We also advise members of the public to avoid contact with coastal water in the 
area. 
The latest advice on recreational water quality can be found at lawa.org.nz 
 
Thank you for your patience and we apologise for the inconvenience. 
 
Kind regards 
Glenis 
 
UPDATE 10 - 19:05 22 July 2021 
Good evening 
Below is a media release regarding a further burst on the 525mm main. 
Attribute to Steve Hutchison Chief Advisor Wastewater, Wellington Water 
We are currently responding to a burst wastewater main on State Highway One, 
northbound, between the Aotea turnoff and Paremata. 
Traffic management is in place and we encourage members of the public to 
avoid the area if possible. 
This pipeline previously burst last Saturday and a repair was carried out on 
Sunday evening. 
Despite the repair, our investigations showed the pipeline was in a fragile 
condition, and this evening’s heavy rainfall has caused a further failure. 
Some wastewater is overflowing into the harbour and work is underway to 
minimise this overflow. 
Our crews will be preparing throughout the night to undertake a further repair in 
the morning.  
We advise members of the public to avoid contact with coastal water in the area. 
The Incident Response team will be meeting later this evening and further updates will be provided. 
Kind regards 
Glenis 
 
UPDATE 9 17:45 21 July 2021 
 

21-108
Page 7 of 44
Good Evening 
 
The clean-up of the walking track has been completed today.  Contractors will continue working on 
the walking track and Station Road tomorrow to enable us to conduct a CCTV investigation of the 
Cross-Harbour Pipeline.  The walking track will be reopened to the public once contractors have 
finished their machine works. 
 
Arrangements have been made to transition the current portable pump set up at Station Road to 
align with the Cross-Harbour Pipeline being offline and its effect on the existing pump stations.  This 
will be done before the school holidays end this weekend to minimise impact on the Paremata 
School.  The school has a side entrance off Station Road. 
 
The next update will be provided once pressurised testing has been completed. 
 
Kind regards 
Glenis 
 
UPDATE 8 – 15:48 Tuesday 20th July 
 
Good afternoon 
 
In taking pressure off the  Paremata rising main, we recommissioned the cross-harbour pipeline 
from Station Road to Onepoto.  In doing this, a blockage occurred on the walking track (Onepoto 
side), resulting in overflow into the Harbour for under two hours. In response, the pumps were 
turned off and the flow diverted back to the rising main. 
 
This means that the rising main continues to operate under stress and we are monitoring the 
situation. We have ordered additional fittings to enable further repairs. 
 
We will also work towards making the cross-harbour pipeline serviceable by pressure testing with 
potable water, as a viable alternative to the Paremata rising main should it be needed. 
 
The walking track has been temporarily closed. 
 
Kind regards 
Glenis 
 
UPDATE 7 – 15:05 
 
Good afternoon, 
  
We have now completed the repair and backfilled the excavation, which has contained the discharge 
of wastewater. 
  
It has been identified that the condition of the AC main is in very poor condition and likely to fail at 
some stage in the near future. 
  
To manage this risk, we are arranging for specialised repair fittings and pipe to be available on site. 
  
Temporary mobile pumps have been established in Station Road to manage any high wet weather 
overflows that may occur. 

21-108
Page 8 of 44
  
The two north bound lanes on State Highway 1 will be open this afternoon by 3:30pm. 
  
Thank you for your patience and we apologise for the inconvenience. 
 
Kind regards 
Josh       
 
 
 
UPDATE 6 – 15:45 
 
Good Afternoon 
We’ve made good progress on the repair to the wastewater pipe in Paremata with the pipe 
excavated and the new pipe being installed now. 
The work involves digging a trench in the SH1 median strip, removing the damaged section, and 
replacing it with a new pipe, then infilling and cleaning up the area ready for north lane of SH1 to be 
reopened. 
While we’re expecting to be able to complete the repair today, we’re going to need to revisit the site 
to complete some tidy up work. This will be carried out in the next week and during off peak traffic. 
A further update will be provided approximately 18:30 this evening. 
 
Thank you for your patience and we apologise for the inconvenience. 
 
Kind regards 
Glenis 
 
UPDATE 5 – 13:15 
 
Good Afternoon 
 
We currently have 4 pumps on site at Station Road pumping to the stormwater over flow point, 
Station village pump station pumping through the Cross Harbour Pipeline as well as 12 Wastewater 
tanker trucks carting from upstream to Porirua City Centre pump stations.  This has enabled us to 
control the flow of wastewater at the burst site sufficiently to commence repairs. 
 
We are now starting on the excavation work in preparation for the repair of the pipe.   
 
Further updates will be provided as the work progresses during the afternoon and early evening. 
 
Kind regards 
Glenis 
 
UPDATE 4 – 11:10 
 
Good Morning 
 

21-108
Page 9 of 44
We’ve had sucker trucks on site helping to reduce the overflow to Porirua Harbour and keep 
contaminated water away from Paremata school. Overnight they have managed to keep up with the 
flow with less rain and stormwater infiltration into the network. 
 
Work continued overnight on diverting the wastewater flow through an emergency line underneath 
the harbour. This line was successfully opened, and some wastewater diverted through it to relieve 
the pressure on the broken main.  As the main could not be fully isolated repair work was unable to 
be completed. Additional pumps are being installed to assist with the diversion of the flow. 
 
This work has been challenging due to heavy rainfall and high levels of stormwater infiltration into 
the wastewater network. 
 
Today: 
Contractors are on site again today working towards an urgent repair on the Rising Main. 
 
This involves digging a trench in the SH1 median strip, removing the damaged section and replacing 
it with a new pipe. 
 
As we need the pipe to be drained when we do this, the timeframe is dependent on the weather and 
the amount of infiltration we experience due to rainfall.  
 
We hope to complete the permanent repair completed today before the rain starts again later 
tonight. 
 
Works are expected to go into late evening tonight. A no swimming notice has been put up onsite 
near the harbour entrance which will remain in place for 48 hours after the overflow stops. 
 
We’re also asking residents in Whitby, Paremata, Plimmerton, Pukerua Bay, and in the northern 
parts of Papakowhai to minimise water use as much as possible. 
 
To work on the repair, State Highway 1 has been reduced to one lane north bound (between the 
Aotea turnoff and Plimmerton, 200 meters north of Aotea intersection).  
 
We’re asking people to find alternative routes or delay travelling if possible. 
 
The Incident Response Team is meeting regularly and I will be sending out updates as the work 
progresses today. 
 
Thank you for your patience and we apologise for the inconvenience. 
 
Kind regards 
Glenis 
 
UPDATE 3 – 17:30 
 
Good Evening 
 
Our crews have been onsite all day working to fix the burst rising main on SH1.  This work has been 
challenging due to the continued heavy rainfall.  We are currently undertaking temporary works to 
direct the wastewater flow from the main  through the Cross Harbour Pipeline as an alternative path 
to the treatment plant outfall.   

21-108
Page 10 of 44
 
Our teams will be working through the night to carry out a temporary repair of the rising main with 
the aim to implement the permanent repair tomorrow once the rain has eased. 
 
Traffic is very congested currently in the affected area of SH1 (between the Aotea turnoff and 
Plimmerton, 200 meters north of Aotea lagoon).  
 
We’re asking people to find alternative routes or delay travelling if possible. 
 
Signs have been placed to warn people to avoid swimming in the Porirua Harbour and Social Media 
has warnings for pedestrians to avoid any local areas with surface flooding as this could contain 
some wastewater overflow.   
 
We’d like to thank the public for their continued patience while we work to fix this issue. 
 
Kind regards 
Glenis 
 
UPDATE 2 – 15:30 
 
Hi All 
 
Work continues on the burst wastewater rising main.  Contractors are on site and sucker trucks are 
operating to assist in reducing the overflow.  Below is the media release sent out at 15:30 this 
afternoon. 
 
Update – 3.30pm 
Further investigation by Wellington Water around the burst wastewater main on SH1 in Paremata 
has found that the incident has also caused a wastewater man hole to overflow wastewater on to 
Station Road, Paremata Crescent and on some areas near the entrance of the Paremata Primary 
School grounds.  
 
We are asking pedestrians to take extra care and avoid these areas.  
 
We have a team on the ground who have cordoned off these areas with cones and people on site 
with signage. We also have suction trucks working in this area to control flows.  
 
ENDS 
 
The Incident team will be meeting again approximately 16:30 and we will provide a full update 
following that meeting. 
 
Kind regards 
Glenis 
 
 
UPDATE 1 – 11:30 
 
The Incident Response Team has met and work is underway to excavate and repair the broken 
pipe.  A media release is going out now and is shown in it’s entirety below: 

21-108
Page 11 of 44
Media Release 
Wastewater main burst on State Highway 1 in Paremata 
Public are being asked to expect delays on State Highway 1 (SH1) in Paremata and avoid swimming 
in the Paremata harbour due to a burst wastewater main between the Aotea turnoff and 
Plimmerton, 200 meters north of Aotea lagoon. 
 
Wellington Water was called out to a burst wastewater main on SH1 around 8am today.  
 
“This has caused wastewater to overflow across SH1 and into the Paremata harbour. State Highway 
1 is currently down to one lane north bound and people should expect delays,” says Sam Lister, 
Wellington Water’s Manager Customer Planning.  
 
“There are nine wastewater tanker trucks on site which is helping to reduce the overflow on SH1 and 
crews are planning to do an urgent repair.”  
 
Works are expected to go into late evening tonight. A no swimming notice will be put up onsite near 
the harbour entrance which will remain in place for 48 hours after the overflow stops. 
 
“With the heavy rainfall likely to cause more overflows, we’re also asking residents to conserve 
water as much as possible. 
 
“We’d like to thank the public for their patience as we work to repair the burst.” 
 
ENDS 
 
Further updates will be provided as work progresses on the repair. 
 
Kind regards 
Glenis 
 
BURST WASTEWATER RISING MAIN  
 
Response:          Level 4 
Response Lead: Sam Lister  
Supported by:   Service Delivery Team 
 
Kia Ora Koutou 
 
The 525mm diameter Wastewater  Rising Main on SH 1 has ruptured.  At this stage we are planning 
to do an urgent repair.  There is currently a flow of wastewater across the State Highway.  The burst 
main has caused an overflow and will continue to do so until repaired. 
 
The Incident Response team is being formed to manage the response.  A further update will be 
provided approximately 10:30. 
 
Kind regards 
Glenis 
 
 
  Glenis Bruin – Incident Coordinator   


21-108
Page 12 of 44
   Customer Experience Team 
      
 
 
  Ph 04 912 4470 Mob 021 346 438 
  Private Bag 39804, Wellington Mail Centre 5045 
  Level 4, IBM House, 25 Victoria Street, Petone, Lower Hutt 
  www.wellingtonwater.co.nz 
  
 
 
 

21-108
Page 13 of 44
SITREP – Paremata Wastewater Riser 
EMT Activated 11.00 AM Saturday 17/7 
Incident Coordinator: Garry Butler 
Network Controller: Gary O’Meara 
Comms: Vanessa MacFarlane / Grace Christinson & Julie Alexander (Senior GWRC/PCC/Ngati 
Toa) 
Intelligence: Sam Lister (support Dylan Hopkins, Glenis Bruin)  
Planning: Sam Lister / Steve Hutchison 
Ops/Logistics: Sean de Roo / Paul Davison (Paremata) Grant Ngarewa (COG region) 
Health and Safety: Rob Mackie / Luke Taylor 
Environment: Paul Gardiner  
 
Saturday 17/7  10.00 am 
BURST WASTEWATER RISING MAIN  
Response:          Level 4 
Response Lead: Sam Lister  
Supported by:   Service Delivery Team 
The 525mm diameter Wastewater Rising Main on SH 1 has ruptured.  At this stage we are planning 
to do an urgent repair.  There is currently a flow of wastewater across the State Highway.  The burst 
main has caused an overflow and will continue to do so until repaired. 
The Incident Response team is being formed to manage the response.  A further update will be 
provided approximately 10:30. 
 
Saturday 17/7 10.30 am 
EMT Activated 
 
Saturday 17/7 11.30 am 
UPDATE 1 – 11:30 
The Incident Response Team has met, and work is underway to excavate and repair the broken 
pipe.  A media release is going out now and is shown in its entirety below: 
Wastewater main burst on State Highway 1 in Paremata. 

21-108
Page 14 of 44
Public are being asked to expect delays on State Highway 1 (SH1) in Paremata and avoid swimming 
in the Paremata harbour due to a burst wastewater main between the Aotea turnoff and 
Plimmerton, 200 meters north of Aotea lagoon. 
Wellington Water was called out to a burst wastewater main on SH1 around 8am today.  
“This has caused wastewater to overflow across SH1 and into the Paremata harbour. State Highway 
1 is currently down to one lane north bound and people should expect delays,” says Sam Lister, 
Wellington Water’s Manager Customer Planning.  
“There are nine wastewater tanker trucks on site which is helping to reduce the overflow on SH1 and 
crews are planning to do an urgent repair.”  
Works are expected to go into late evening tonight. A no swimming notice will be put up onsite near 
the harbour entrance which will remain in place for 48 hours after the overflow stops. 
“With the heavy rainfall likely to cause more overflows, we’re also asking residents to conserve 
water as much as possible. 
“We’d like to thank the public for their patience as we work to repair the burst.” 
 
Saturday 17/7 12.00 noon 
 
 
EMT Current status -  
A wastewater pipe has fractured in the vicinity of SH1 Aotea Lagoon/ Paramata. There are SH 1 
traffic disruptions as a result and wastewater is discharging into the harbour and neighbouring 
surface areas including a school playground (unoccupied). Heavy rain continues and forecast to 
ease this evening. Situation being monitored for any further escalation. 
Traffic – Traffic management is in place with northbound SH 1 down to 1 lane. Liaison 
implemented with NZTA (Paul D) 
Comms – Comms has been undertaken including media release re status (Vanessa /Julie) 
•  Board/SLT 
•  GWRC 
•  PCC 
•  NZTA 
•  Ngati Toa 
•  RNZ, TV 
•  FB channel 
Planning (Sam / Sean) 
•  Pumps being controlled to minimise effects 
•  Sucker trucks mobilised 
•  Repair is contingent on supply of parts being sourced from Wanganui. Delivery unknown. 
GP Friel on site and advising 

21-108
Page 15 of 44
•  Alternative wastewater flow path being investigated 
•  The work may take 24 hours to effect, further resources being investigated 
•  H&S issues being monitored 
Environment / Public Safety (Nick) 
•  Signage is being placed around the affected area and harbour (Alistair) 
•  Keep out of flooded areas to be emphasised 
 
 
Saturday 17/7 3.30 pm 
 
UPDATE 2  
Work continues on the burst wastewater rising main.  Contractors are on site and sucker trucks are 
operating to assist in reducing the overflow.  Below is the media release sent out at 15:30 this 
afternoon. 
Further investigation by Wellington Water around the burst wastewater main on SH1 in Paremata 
has found that the incident has also caused a wastewater manhole to overflow wastewater on to 
Station Road, Paremata Crescent and on some areas near the entrance of the Paremata Primary 
School grounds.  
We are asking pedestrians to take extra care and avoid these areas.  
We have a team on the ground who have cordoned off these areas with cones and people on site 
with signage. We also have suction trucks working in this area to control flows.  
ENDS 
The Incident team will be meeting again approximately 16:30 and we will provide a full update 
following that meeting. 
Saturday 17/7 5.30 pm 
 
UPDATE 3  
Our crews have been onsite all day working to fix the burst rising main on SH1.  This work has been 
challenging due to the continued heavy rainfall.  We are currently undertaking temporary works to 
direct the wastewater flow from the main  through the Cross Harbour Pipeline as an alternative path 
to the treatment plant outfall.   
Our teams will be working through the night to carry out a temporary repair of the rising main with 
the aim to implement the permanent repair tomorrow once the rain has eased. 
Traffic is very congested currently in the affected area of SH1 (between the Aotea turnoff and 
Plimmerton, 200 meters north of Aotea lagoon).  
We’re asking people to find alternative routes or delay travelling if possible. 

21-108
Page 16 of 44
Signs have been placed to warn people to avoid swimming in the Porirua Harbour and Social Media 
has warnings for pedestrians to avoid any local areas with surface flooding as this could contain 
some wastewater overflow.   
We’d like to thank the public for their continued patience while we work to fix this issue. 
 
Kia ora Board, 
 As reported earlier, our teams have been dealing with a burst waste water pipe at Paremata – see 
the attached media release on the latest update. We have had two media enquiries (Newstalk ZB 
and Stuff) since issuing these updates but we’re getting pick up on all the main media outlets (NZ 
Herald, Stuff, Newshub, and Newstalk ZB) with these outlets just reporting what’s being provided 
from our statements. We’ve also been providing the public with regular updates on our social 
media channels and our website.  
 The weather event has put considerable pressure on our crews across the region, with many calls 
coming in that we have needed to respond to. For example, we have had 88 jobs within the Hutt 
City area, 89 within Wellington City, and around 30 within Porirua City. The jobs relate to flooding 
and waste water bursts.  
 In addition to the event in Paremata, our teams are working on another significant event in 
Petone, where the pressure culvert has burst causing significant flooding in some surrounding 
streets. The flooding is stable at the moment but we are monitoring it closely.  
We are also monitoring the Hutt River levels as these are predicted to increase. A higher than 
usual tide is also predicted for later tonight. If these eventuate, the risk of flooding increases.  
 We are actively monitoring the health and safety of our people, and drawing on resources across 
our contractor panel to supplement our crews. 
 Our teams are doing a great job in difficult conditions. It’s been a very busy 24 hours, with 
potentially more impacts from the weather to come. I’ll keep you updated as needed. 
 
 
Sunday 18/7 7.47 am 
Paremata 
Situation update, Over pumping at Station Road with one pump was insufficient due to 
manage flow due to the high wet weather flow. We trialed turning off both PS6a and PS6b and 
with both pumps off this did not reduce the flow into the failed riser main confirming flow is 
entering the risermain through other sources. Additional pumps are being sourced for 
tomorrow morning. GP Friel have gone home to rest to carry out repair tomorrow morning. 
Utilities staff have done their hours and fresh hands lined up for morning. PS6a wil  remain on 
overnight along with temporary over pumping to constructed overflow and suction trucks to 
continue flow management. 
 
 
 
 
Sunday 18/7 10.44 AM 
Paremata & Wider Flooding 
EMT Current status - A wastewater pipe fractured in the vicinity of SH1 Aotea Lagoon/ Paremata 
17/7. There are SH 1 traffic disruptions with one lane closed and wastewater is discharging into 

21-108
Page 17 of 44
the harbour and a school playground (unoccupied). Rain has stopped but may be more this 
evening 
Attempts during Saturday 17/7 to isolate the break were unsuccessful although flow was 
minimised through diverting some of the flow to an emergency pipeline across the harbour plus 
pumping 
Efforts continue this morning to stop the flow with extra pumps, sucker trucks so that repair can 
be enabled 
Traffic – Traffic management is in place with northbound SH 1 down to 1 lane. Liaison 
implemented with NZTA (Paul D) 
Comms – Ongoing comms implemented (Vanessa /Grace/ Julie/Glenis) 
•  Board/SLT 
•  GWRC 
•  PCC 
•  RPH 
•  NZTA 
•  Ngati Toa 
•  Media 
•  FB channel 
Planning (Sam / Sean) 
•  Pumps being controlled to minimise effects 
•  Further pumps being mobilised to further cut flow 
•  Sucker trucks mobilised 
•  Repair parts are on site. GP Friel on standby to commence repair 
•  The work may take further 12 hours to effect 
•  H&S issues being emphasised and monitored (Rob M) 
•  School property owner to be notified of contamination of grounds 
Environment / Public Safety (Nick) 
•  Signage has been placed around the affected area and harbour (Alistair) 
•  Keep out of flooded areas  
Wider Network 
A significant number of properties across the network have been flooded. 
Confirmed hot spots are Ava St which was significantly flooded but has subsequently drained, and 
property in Holly Grove.  
COG Hub to review customer calls (100 + across the region yesterday), establish contact with 
councils to identify areas of concern and determine extent and establish priorities forcontact/ 
response/recovery. (Grant/Glenis) 
 

21-108
Page 18 of 44
 
Sunday 18/7 11.10 am 
UPDATE 4  
We’ve had sucker trucks on site helping to reduce the overflow to Porirua Harbour and keep 
contaminated water away from Paremata school. Overnight they have managed to keep up with the 
flow with less rain and stormwater infiltration into the network. 
Work continued overnight on diverting the wastewater flow through an emergency line underneath 
the harbour. This line was successfully opened, and some wastewater diverted through it to relieve 
the pressure on the broken main.  As the main could not be fully isolated repair work was unable to 
be completed. Additional pumps are being installed to assist with the diversion of the flow. 
This work has been challenging due to heavy rainfall and high levels of stormwater infiltration into 
the wastewater network. 
Today: 
Contractors are on site again today working towards an urgent repair on the Rising Main. 
This involves digging a trench in the SH1 median strip, removing the damaged section and replacing 
it with a new pipe. 
As we need the pipe to be drained when we do this, the timeframe is dependent on the weather and 
the amount of infiltration we experience due to rainfall.  
We hope to complete the permanent repair completed today before the rain starts again later 
tonight. 
Works are expected to go into late evening tonight. A no swimming notice has been put up onsite 
near the harbour entrance which will remain in place for 48 hours after the overflow stops. 
We’re also asking residents in Whitby, Paremata, Plimmerton, Pukerua Bay, and in the northern 
parts of Papakowhai to minimise water use as much as possible. 
To work on the repair, State Highway 1 has been reduced to one lane north bound (between the 
Aotea turnoff and Plimmerton, 200 meters north of Aotea intersection).  
We’re asking people to find alternative routes or delay travelling if possible. 
The Incident Response Team is meeting regularly and I will be sending out updates as the work 
progresses today. 
 
Kia ora Board, 
 As a recap, our teams have been dealing with a burst wastewater pipe at Paremata. This caused 
wastewater to overflow alongside and onto SH1 and into the Porirua harbour. To work on the 
repair, State Highway 1 was reduced to one lane north bound. 
 Overnight we’ve had four sucker trucks on site helping to reduce the overflow to Porirua harbour 
and keep contaminated water away from Paremata school. They have managed to keep up with 
the flow with less rain and stormwater infiltration into the network. 

21-108
Page 19 of 44
 Work was also continued on diverting the wastewater flow through an emergency line 
underneath the harbour. This line was successfully opened, and some wastewater diverted 
through it to relieve the pressure on the broken main.   
 However, as the main could not be fully isolated repair work was not completed. This work will 
continue today. This  involves digging a trench in the SH1 median strip, removing the damaged 
section and replacing it with a new pipe. 
 As we need the pipe to be drained when we do this, the timeframe is dependent on the weather 
and the amount of infiltration we experience due to rainfall. We hope to complete the repair 
before the rain starts again. 
 We’ve had had two media enquiries (Newstalk ZB and Stuff) since issuing the updates yesterday 
but we’re getting pick up on all the main media outlets (NZ Herald, Stuff, Newshub, and Newstalk 
ZB) with these outlets just reporting what’s being provided from our statements so far. We’ve also 
been providing the public with regular updates on our social media channels and our website. 
 We are working closely with senior managers at PCC and GWRC (environmental regulator), as 
well as Waka Kotahi to coordinate messaging for transport and keeping Regional Public Health 
informed. I reached out to Ngati Toa yesterday, and will do so again today. 
 We are still under pressure across other parts of the network as a result of yesterday’s weather 
event, but the Paremata burst is the one that is causing me the most concern. 
 
 
Sunday 18/7 13.15 
Paremata UPDATE 5  
We currently have 4 pumps on site at Station Road pumping to the stormwater over flow point, 
Station village pump station pumping through the Cross Harbour Pipeline as well as 12 Wastewater 
tanker trucks carting from upstream to Porirua City Centre pump stations.  This has enabled us to 
control the flow of wastewater at the burst site sufficiently to commence repairs. 
We are now starting on the excavation work in preparation for the repair of the pipe.   
Further updates will be provided as the work progresses during the afternoon and early evening. 
 
 
Sunday 18/7 3.45 pm 
Paremata UPDATE 6  
 
We’ve made good progress on the repair to the wastewater pipe in Paremata with the pipe 
excavated and the new pipe being installed now. 
The work involves digging a trench in the SH1 median strip, removing the damaged section, and 
replacing it with a new pipe, then infilling and cleaning up the area ready for north lane of SH1 to be 
reopened. 
While we’re expecting to be able to complete the repair today, we’re going to need to revisit the site 
to complete some tidy up work. This will be carried out in the next week and during off peak traffic. 
A further update will be provided approximately 18:30 this evening. 
 

21-108
Page 20 of 44
Thank you for your patience and we apologise for the inconvenience. 
 
 
Kia ora, 
 Latest update, with good news. 
 We’ve made good progress on the repair to the wastewater pipe in Paremata with the pipe 
excavated and the new pipe being installed now. The work involves digging a trench in the SH1 
median strip, removing the damaged section, and replacing it with a new pipe, then infilling and 
cleaning up the area ready for North lane of SH1 to be reopened. 
 While we’re expecting to be able to complete the repair today, because of the waterlogged 
material, we’re going to need to revisit the site tomorrow to complete the infill and final clean up.  
We’ve had had no media enquiries today, although Stuff have published a story using our social 
media updates – link here: https://www.stuff.co.nz/dominion-
post/news/wellington/300360475/burst-water-main-at-paremata-north-of-wellington-spills-
wastewater-over-highway 
  
We have a media release ready to go – see attachment. We’ve also been providing the public with 
regular updates on our social media channels and our website. 
We are watching the health and safety of our crews, who are good spirits this afternoon – with an 
end almost in sight and drier working conditions.  
 We’ve also opened up a dialogue with Ngati Toa. 
 The weather event continues to put considerable pressure on our crews across the region, and 
customers will be experiencing delays for lower priority jobs. 
 We’ve also had reports that there has been storm damage at the Omāroro Reservoir site, with 
some erosion on the earth works face and water damage to vehicles from the stream bursting it’s 
banks. We are letting WCC know about this. 
 All in all a very busy weekend for the company, but a sterling effort from everyone involved and 
huge commitment from our staff and wider whanau. Ka pai! 
 
 
 
 
Sunday 18/7 5.31 pm 
 
Metservice in touch and advised that a heavy band of rain coming very soon, could be up to 
15mm an hour for a couple of hours, temperature wil  drop with a southerly 
 
 


21-108
Page 21 of 44
 
Sunday 18/7 9.15 pm 
 
Paremata 
EMT agreed actions and operating status for 525 risermain overnight 
Bora Cres and Aotea lagoon pump stations to remain operational 
PS6a Station Road to remain pumping across the harbour pipeline 
PS6b one pump operating only to minimise discharge to Porirua harbour and minimise operating 
pressure 
Temporary over pumping to stormwater and Station Road will remain in place to deal with 
additional flows 
Single lane traffic management remains in place over night 

21-108
Page 22 of 44
EMT agree one maintain one pump in operation at PS6b as preferred option to minimise 
discharge 
Operating pressure of the 525 reduced to risk further AC failure 
EMT agreed actions and operating status for 525 risermain overnight 
Bora Cres and Aotea lagoon pump stations to remain operational 
PS6a Station Road to remain pumping across the harbour pipeline 
PS6b one pump operating only to minimise discharge to Porirua harbour and minimise operating 
pressure 
Temporary over pumping to stormwater and Station Road will remain in place to deal with 
additional flows 
Single lane traffic management remains in place over night 
EMT agree one maintain one pump in operation at PS6b as preferred option to minimise 
discharge 
Operating pressure of the 525 reduced to risk further AC failure 
 
 
 
Kia ora Board, 
 Unfortunately, the latest update is that the pipe replacement has not gone as well as expected. A 
photo from the site shows that there is severe corrosion at the top of the pipe. Because of the 
instability, it has not been possible to complete the repair. 
 The focus is on stabilising the situation as best we can overnight, and we will regroup in the 
morning. Our aim is to minimise the overflow into the harbour, we will have people on site 
overnight to monitor and sucker trucks present. Our crews are fatigued and we are resting them. 
 Apologies for raising hopes earlier. 
 
 
 
 
Monday 19/7 00.21 am 
Paremata 
Due to rainfall, the volume of sewage coming in from 6B was too much and whilst we do not 
have the all the big sucker trucks operating there was a risk to overwhelm and flood the school. 
The emergency standby sucker trucks would in be in a position to cope. After discussion with 
Paul W, they have turned on all the diesel pumps, i.e. pumping to stormwater again and also 
turned on the 2nd pump at 6B. The leak on the main pipeline has not increased as a result of 
turning on the 2nd pump. This has been status quo for circa the past half-hour. The plan for now 

21-108
Page 23 of 44
to leave both pumps pumping from station 6B. The risk of stop-starting pumps too much would 
be concern. Sean wil  check with Paul re what auto mode of pump station would do. In summary 
therefore status at moment: 2 pumps pumping at Station 6B. All diesel pumps operational and 
pumping excess to stromwater. 
 
 
Monday 19/7 00.43 am 
Paremata 
The rain situation in Porirua has resulted in most of the significant pump stations overflowing 
such as city centre, Rukutane at present. We wil  keep both pumps operating at station 6B and 
this status quo wil  remain for the rest of night whilst watching the main pipeline status. Once the 
wet wel  levels at station 6A start dropping we wil  turn off the diesel pumps to stop the 
discharges to stormwater. Joe wil  take a note of what time that wil  be. 
 
Monday 19/7 9.12 AM 
Paremata 
Two pumps running at PS6b currently managing flows, Leakage has been confirmed as beyond 
new section of pipe at both ends Planning to repair using clamp fittings to avoid further 
shutdown and discharge.  
 
Monday 19/7 10.00 AM 
EMT - Paremata Wastewater Incident 
Current state on site – Setting up for another shutdown to remove the joint from yesterday to 
repair. Stainless steel wrap on either side to seal and support – leak coming through top of the 
pipe. Achieved without shutdown. Next step to turn the pumps back on to see how the pipe fairs. 
One of two pump stations in service – 6B is in service 6A is not.  
Not back in full service as 6A is valved off from main – when all pumps are back on risk that the 
repair won’t stand up against high pressure. 
Last night – another rain event and 6A nearly overflowed into the school, 6B nearly overflowed 
into the roundabout. This informed decision to turn on second pump. System can’t handle heavy 
rain.  
Current discharges to environment – discharging last night, flows in network dropped off 
overnight. Flows are being managed with two pumps running at pump station 6B. Material has 
discharged into harbour overnight with rain – now pumping through cross harbour main with 
flows levelling out.  
Sewerage is getting to Titahi Bay – severity of flow unknown. If the flow is going through Harbour 
line it is excessing somewhere unknown. Need to re-look at configuration to gain understanding 
of what is happening/going wrong.  
Plan is road open by 3pm this afternoon – contingency planning for future occurrence needed.  
Decision on how many pumps we allow to operate from 6B – live with some overflow to avoid 
high pressure risk.  
Short term plan – run with two pumps to keep adequate flow going. Will cope with dry weather 
not with rainfall. If we get rainfall we allow to overflow and assist with diesel pumps. Dry 
weather we will cope with no discharges to environment.  
Water screening: beyond 24 hours – get into contingency of setting up additional pumping over 
land would mitigate water screening issue. No short-term mitigation within the next 24 hours.  
No visible signs of rags on beaches thus far.  

21-108
Page 24 of 44
Steve – go across harbour to ease pressure on pump station 6B in the short term. Want to verify 
where the flow is getting to. Known contamination from significant overflows – based on 
observations it is most likely getting through. Key objective – working to minimise wastewater 
contamination into the harbour.  
Dye testing on outgoing tide – to find possible leaks.  
This morning – getting sucker trucks organised, isolating pump station. Going over to isolate 
station 6B – sucker trucks at 6B and station road utilising diesel pumps. Close outlet valves on 6B 
to reduce flow – then work can go ahead with moving the connection.  
Waiting on 2 bolts to come in – should be bolted up in next 30 mins. Replacing bolts from earlier 
repair.  
Key commissioning steps – in service with two pumps running in 6B. First identify if flow is going 
across harbour before deciding whether to configure. Leave harbour link on until flow is verified. 
6B is operating as designed at the moment.  
If we get rainfall, we are going to discharge wastewater into the harbour.  
Objectives for the morning – repair almost complete. Once repair is done – if it is holding up, we 
will knock off sucker trucks. Continue pumping across harbour and explore what is happening with 
flow. Unless there is wet weather – the flows are contained.  
Main objective – verify what is happening with cross harbour link. Environmental side of things is 
in control unless high rainfall. If repair goes to plan the highway will be open by 3pm. Full steam 
on contingency plans.  
Key message – It is a temporary repair – delicate situation and we expect it to fail again.   
Colin - Bring in a whole new contractor for the renewal of the pipe.  
Proactive comms – stressing that it is an ongoing issue. Dealing with flows for today but operating 
on limited capacity. Behave as though it will break – extra precaution. Pipe is fragile – we are 
working on additional contingency measure. We are doing the least environmental impact. Ngati 
toa agreement.  
The orca will come back into conversation – managing risk to the orca. Huge public interest. Paul 
Gardiner to contact DOC about this issue – should assume that the water has been contaminated 
for the last 48 hours.  
The school has been notified – signs are up around the school about contamination risk. School 
will be reimbursed for tidy up. Buildings are safe.  
Sam Lister to document configuration – with a contingency that we will operate pumps if needs 
arise.  
State of the pipe – struggling to hold onto existing pipe because of the condition. Pipeline is 2km. 
Assume that majority of the pipeline will be in poor condition. 2012 LTP – this had been raised as 
a critical issue.  
Not being looked at as a renewal – it is an upgrade in the PCC network upgrade programme.  
Contingency plan - get some more fittings and pipe in the case of another burst short term for 
smaller repairs ASAP – get the long-term upgrade in plan asap – fast-track CAPEX.  
Fittings must be custom made and delivered – there may be a week delay. Ordering 2 sets of 
fittings now.  
Sampling continuing once a day at 5 sites – Nick Hewer-Hewitt in charge of this.  
Clean up of lagoons – several tide cycles to get wastewater out. Need support in that space – 
connect water. Increase signage.  
 
 
 
Kia ora Board, 

21-108
Page 25 of 44
 This morning’s update is that the pipe has been repaired, but it is very fragile and there is a high 
chance it will burst again. The discharge to harbour has been stemmed for now, but could occur 
again either as a result of heavy rain and/or a further burst. 
 We have had some media interest this morning looking for an update – see our response 
attached.  
 We are prepping a media and engagement strategy on the assumption there will be a burst / 
further discharge.  
 We have turned our minds to implementing a two phased approach that recognises the condition 
of the pipe and the risks we are managing – a more reliable interim solution and a more 
permanent and longer-lasting solution – and options for accelerating both approaches.  
 Colin is arranging to meet with Ngati Toa, hopefully first thing tomorrow morning. As well as the 
cultural harm that has occurred from the discharge itself, Ngati Toa have had a long term 
opposition to the use of the old cross harbour pipeline that we have pressed into service to help 
stem the discharge. We  consider that using the old pipeline in this emergency has given us a 
better environmental outcome overall, and the aim is to talk this through with them. 
 We will also reach out to DOC today to liaise in regards the well-being of the baby orca, Toa, who 
is being cared for in a large holding pool, and the volunteers who are looking after him. The 
holding pool is being refreshed using sea water from the harbour. We understand the orca is 
being located back into the marine environment today. Whilst peripheral, we are keen to manage 
any associated risk between the Paremata burst and anything to do with the orca and the 
volunteers, as this is likely to have significant media interest. 
 
 
 
Monday 19/7 12.48 PM 
 
Paremata 
EMT Current Emergency State  
 

Pipe repair is complete with extra stainless steel reinforcing banding at each end, 
backfilling has commenced 

There is no (current) dry weather wastewater overflow to the environment 

The pipe is in a fragile state, there is high risk of another fracture at any time and 
therefore discharge of wastewater to the environment 

The proposed pump configuration will ensure reduced pressure in the pipe   Flow through 
the cross harbour pipeline will be continued.    Further periods of heavy rainfall will 
necessitate pumping wastewater to stormwater.  This arrangement to be documented 
(Sam) 

The closed lane on SH1 will be able to be re-opened before peak time this afternoon 

A LAWA warning on sea water quality in the area to be reviewed and updated 
(Steve/Nick) 

Environmental expert to be consulted regarding pond contamination (Gary C) 

School is aware of the issue and will be assisted with the clean-up (Sean) 
 
Short Term Ops Contingency Plans  
 

Further repair parts are to be ordered from Australia, lead time approximately 1 week 
(Paul D) 

21-108
Page 26 of 44

Some parts are on site to effect makeshift repair in the interim (Paul D) 

An ops action plan is to be prepared with H&S considerations (Sam/Sean/Rob M) 
 
Medium term (weeks) plans to Improve Resilience (GC) 
 

Investigation into laying a new section of PE pipe to be put into service in parallel with the 
fragile sections (Gary C/Ian) 
 
Long term plans (months/year) 
 

Acceleration and planning and pricing for longer term asset renewal/replacement (Gary 
C/Ian) 
 
Communications 
 

Key communications under preparation to all stakeholders / media / public 
(Julie/Vanessa) 
 
 
Monday 19/7 15.05 
Paremata UPDATE 7  
We have now completed the repair and backfilled the excavation, which has contained the discharge 
of wastewater. 
 It has been identified that the condition of the AC main is in very poor condition and likely to fail at 
some stage in the near future. 
 To manage this risk, we are arranging for specialised repair fittings and pipe to be available on site. 
  
Temporary mobile pumps have been established in Station Road to manage any high wet weather 
overflows that may occur. 
 The two north bound lanes on State Highway 1 will be open this afternoon by 3:30pm. 
  
 
Monday 19/7 5.15 PM 
Paremata 
EMT Current Emergency State  
 

Pipe repair is complete with extra stainless steel reinforcing banding at each end, 
backfilling completed 

There is no (current) dry weather wastewater overflow to the environment 

The pipe is in a fragile state, there is high risk of another fracture at any time and 
therefore discharge of wastewater to the environment 

Some unexpected flow behaviour has been observed and is to be further investigated 
(Paul W)     

Further periods of heavy rainfall will necessitate pumping wastewater to stormwater.   

The closed lane on SH1 has been re-opened  

A LAWA warning on sea water quality in the area to be reviewed and updated 
(Steve/Nick) 

Environmental expert to be consulted regarding pond contamination (Gary C) 

21-108
Page 27 of 44

Assistance has been provided to the school for its clean-up 
 
Short Term Ops Contingency Plans  
 

Further spare repair parts are to be ordered from Australia, lead time approximately 1 
week (Paul D) 

Some parts are on site to effect makeshift repair in the interim (Paul D) 

An ops action plan is to be prepared with H&S considerations (Sam/Sean/Rob M) 
 
EMT / Ops / PERT / Capital Projects 
 


EMT has stood down as impacts have been eliminated to near normal levels of 
service.  EMT will respond to any future major events 

Ops now lead incident management including establishing contingency plans and 
arrangements (Sam L) 

EMT Incident Coordinator has activated PERT to review medium and long strategies to 
improve resilience and levels of service(customer/environment) 

Capital Projects is planning for resilience and service level improvements 
 
Communications 
 

Key communications undertaken and ongoing to all stakeholders / media / public 
(Julie/Vanessa) 
 
 
------------------------------------------------------------------------------------------------------ 
 
Tuesday 20/7 3.48 pm 
Paremata UPDATE 8  
In taking pressure off the  Paremata rising main, we recommissioned the cross-harbour pipeline 
from Station Road to Onepoto.  In doing this, a blockage occurred on the walking track (Onepoto 
side), resulting in overflow into the Harbour for under two hours. In response, the pumps were 
turned off and the flow diverted back to the rising main. 
This means that the rising main continues to operate under stress and we are monitoring the 
situation. We have ordered additional fittings to enable further repairs. 
We will also work towards making the cross-harbour pipeline serviceable by pressure testing with 
potable water, as a viable alternative to the Paremata rising main should it be needed. 
The walking track has been temporarily closed. 
Tuesday 20/7 
EMT Incident Coordinator recommends that PERT also provide focus on the wider regional flooding 
events recovery 
 
Paul Gardiner contacts DOC re the Orca in Plimmerton advising of the situation with water quality to 
enable their decision making 

21-108
Page 28 of 44
Wednesday 21/7 5.45 pm 
Paremata UPDATE 9  
The clean-up of the walking track has been completed today.  Contractors will continue working on 
the walking track and Station Road tomorrow to enable us to conduct a CCTV investigation of the 
Cross-Harbour Pipeline.  The walking track will be reopened to the public once contractors have 
finished their machine works. 
 Arrangements have been made to transition the current portable pump set up at Station Road to 
align with the Cross-Harbour Pipeline being offline and its effect on the existing pump stations.  This 
will be done before the school holidays end this weekend to minimise impact on the Paremata 
School.  The school has a side entrance off Station Road. 
 The next update will be provided once pressurised testing has been completed. 
 
Thursday 22/7 5pm 
EMT Reactivated 
Paremata UPDATE 10 
•  Pipe burst at same location  
•  Wastewater coming out of area of original break – wastewater going through culvert and some 
spillage over SH1. 
•  2 pumps at 6B and 1 pump 6A (Station Rd) are running so some flow is still going through the 
rising main. The remainder is being pumped using the temporary pumps at Station St to the 
harbour. 
•  GP Friel ready to commence work tomorrow, WWL to do prep to enable work to start as early as 
possible.  Pipe available at Pomare - 6m length, Clamps will have to reused.   
•  Sucker trucks on their way. 
•  Work to put cross harbour back online 
•  The decision was made not to start the actual repair until Friday morning.  This was due the 
weather (heavy rain), night work involved, health and safety of the team involved and time need 
to set up the sites.  TM to be set up ready for a Friday morning start. 
Plan - 
The photo below documents the plan and responsibilities for the evening and overnight. 


21-108
Page 29 of 44
 

21-108
Page 30 of 44
Following is the agreement around the use of the cross harbour ww main….
-----Original Message----- 
From: Colin Crampton <[email address]>  
Sent: Tuesday, 20 July 2021 5:50 pm 
To: Helmut Modlik <[email address]> 
Cc: Wendy Walker <[email address]>; Ian McSherry 
<[email address]>; Paul Gardiner <[email address]> 
Subject: Paremata wastewater pressure main. 
Kia Ora Helmut, thanks for meeting with Wendy and I this morning. 
 As discussed the Asbestos Cement pressure main running from the Paremata roundabout south to 
the off ramp at Porirua is in a very poor state.  This led to a rupture of the pipe on Saturday 17th of 
July and an overflow of wastewater into the Porirua Harbour during the balance of Saturday, Sunday 
and part of Monday.  The total amount of wastewater to overflow was limited by the use of sucker 
trucks and the recommissioning of the old wastewater pressure main under the Porirua harbour 
which tracks back along the western side of the Onepoto arm to the rowing club in Titahi Bay.  A 
repair has been completed but it is expected further ruptures of this pipe are likely to occur. 
 There are two circumstances to account for should another failure occur; as follows: 
 1.  During dry weather, in which case we should be aiming for no wastewater overflow into the 
harbour using a combination of sucker trucks; the cross harbour pipeline and an expeditious repair; 
and 
 2.  During wet weather, mitigate the size of the overflow into the harbour using the same tools 
above. 
 We will now urgently investigate a permanent renewal and upgrade of this pipeline using a design 
philosophy that does not rely on spilling into the harbour as the contingency plan.  This work is likely 
to take 12 months to 18 months to complete. 
 So our request of Ngati Toa Rangitira is to recommission the cross harbour pipeline to be used as 
described above so as to avoid the discharge of wastewater into the Porirua harbour as far as possible 
in any subsequent failure. 
 To be clear we would use the cross harbour pipeline, as follows: 
 1.  In an emergency should a break occur;  
 2.  As a supplement to operations when we have checked it is water tight and durable; and 
 3.  We would decommission its use once the permanent solution has been effected. 
 At all times we use the Cross harbour pipeline we will record the times and advise you. 
 Thank you for meeting with us this morning and discussing this predicament. 
 Colin 
  

21-108
Page 31 of 44
Comms that went out to the media  
Attribute to Steve Hutchison Chief Advisor Wastewater, Wellington Water 
We are currently responding to a burst wastewater main on State Highway 
One, northbound, between the Aotea turnoff and Paremata. 
Traffic management is in place and we encourage members of the public to 
avoid the area if possible. 
This pipeline previously burst last Saturday and a repair was carried out on 
Sunday evening. 
Despite the repair, our investigations showed the pipeline was in a fragile 
condition, and this evening’s heavy rainfall has caused a further failure. 
Some wastewater is overflowing into the harbour and work is underway to 
minimise this overflow. 
Our crews will be preparing throughout the night to undertake a further 
repair in the morning.  
We advise members of the public to avoid contact with coastal water in the 
area. 
 
 
Thursday 22/7 10pm 
Paremata UPDATE 11 
•  Two breaks one on each side of the previous repair 
•  Cross harbour pipeline being commissioned – will turn on the pumps and see if can pump (2 
hours to commission) 
•  3 sucker trucks on site 
•  Temp pumps turned off 
o  Flows low 
o  Currently not discharging into the harbour 
•  Traffic management has been set up 
•  GP Friel on site Friday morning – lane to be closed to bring digger on at 6:30am 
•  Monitor set up – Luke and Silver linings 
 
Friday 23/7 8am 
Paremata UPDATE 12 
•  Cross harbour pipeline was turned on and a break occurred.  This resulted in a small 
discharge by Onepoto.   

21-108
Page 32 of 44
•  From 10pm there was no discharge to the environment except from the cross harbour 
pipeline break.  
•  Any discharge from the actual break is to the swale and doesn’t reach SH1 – leakage is less 
than previous break. 
•  Two breaks one on each side of the previous repair 
•  GP Friel is on site, the 6B pumps are still running, will be turned off when the pipe is 
uncovered to assess the extent of the failure. 
•  Questioned whether this was the best time to start work, ie should we wait until lower flows 
overnight.  It was decided starting was the best option as it was daylight, full complement of 
staff and we need to manage the risk of the pipe failing further. 
•  Managing the overflow through sucker trucks but will be still discharging to the harbour at a 
location that flushes well. 
•  Consider whether more condition information can be gained while the pumps are off - SR 
•  The ranger responsible for the orca has visited the site but has no concerns. 
•  Ensure we get as-built info - Francis has a schematic of the values and cross harbour pipeline 
connection.  Need to make sure this information is fed back to DPS. 
 
Plan B 
•  Determine how much pipe would be needed if a larger repair is needed?  
•  Determine if the pipe is available.   
•  Check to see if we can reinstate the cross harbour pipeline. 
 
Plan C  
•  polyethylene pipe on site in case we need an overland pipe (not yet actioned).  
 
Risk of comms escalation has been identified.  
 
Friday 23/7 11am 
Paremata UPDATE 13 
 
•  9am sucker trucks operational – 15 trucks 
•  Discharging to harbour  
•  First leak split on collar (12 to 3o’clock) – 4m south of previous leak looks like a blow out 
•  Ready to expose second leak - Second leak likely to be similar distance from repair – more of 
a worry. 
•  Marked out xhp for repair 
•  OF form for xhp leak last night 
•  Pot holed further south to see if any PE – AC.  Need to look north GIS shows PE (same as 
asbuilt) 
•  Traffic – moving alright 

21-108
Page 33 of 44
 
•  More wiser in an hour 
•  Ian to talk to PCC Roading 
•  Check signage for xhp break. – Sam  
  
Friday 23/7 1:30pm 
Paremata UPDATE 14 
•  Exposed break points – northern leak not obvious.  Putting clamp over collar and turn on 6A 
pump to put flow though the line to find leak 
•  6 in pump to harbour 
•  Harbour link – now what we need to do.  Need to get fittings – Monday. 
•  4-6 hours next three hours 
•  Traffic major problem  
•  Logging all overflows – these will be provided early next week 
•  Durafit clamp getting installed now – within hour can make a decision on whether it is 
effective or not.  Will need to charge up the other pumps. 
•  Check with capital journeys 
•  Job coming in from Paremata School – lowest point on gravity network. 
•  Call on installation 
•  Trying confirm where HDPE starts – not far from site of the break (10M). 
•  Chris and Amber on site – plan in place for 6A, 6B not plans for Bora, Tweed St.   C&A will 
prepare a plan.  
•  We will try to get off site as soon as possible due to traffic, need to liaise with capital 
journeys around requirements around the site. 
•  Rahui – being placed from tomorrow by Ngati Toa at the Onepoto site 
•  Sampling sites being extended. 
 
Friday 23/7 3pm 
Paremata UPDATE 13 
•  Have confirmed with capital journeys that equipment can be left on site. Hole needs to 
backfill. 
•  Won’t pursue northern leak  
•  Coupler compressed inside joint   
•  A photo of the crew in the trench raised concerns around trench stability.  It has been 
confirmed that the trench does not need shielding.  The hole is approx. 1.4m dept and the 
wall are solid and well compacted and not at risk of collapse. 
•  One lane closed for a section 50km speed limit 
•  Sucker trucks current there till 7 -8 pm one’s on last night will come back 
•  Keep pumping through then if major failure. 
•  Plan for tomorrow – need to check after 5pm. Likely to be as per Thursday night. 
•  Resources - 10pm – run out of resource – monitoring manholes, Valitha and Paul W to look 
at resourcing 

21-108
Page 34 of 44
 
Friday 23/7 5pm 
Paremata UPDATE 14 
•  Leakage from clamp so needing to depressurise and try and fix coupling, crushed side 
holding other side leaking.  Still trying to get a better seal, keeping pipe live  
•  Some back up of traffic – no worse than a normal Friday 
•  Sucker trucks off site from between 7 and 8. 
•  If don’t work, going to have to run with overflow.  South should hold.  North is slowly getting 
worse. 
•  Need to find out if work can continue tomorrow – ie if crews are available. 
•  Ensuring staff are available and briefed for overnight monitoring. 
 
Friday 23/7 7:30pm 
Paremata UPDATE 15 
•  The repair was unsuccessful the pipe is too fragile to maintain a solid connection (south side 
of the south repair).  The pipe is still leaking but less that it was last night.  Several 
connection options were tried. Have dug a swale to contain spill. 
•  Overnight we will continue to pump flow through the pipe (100L/s), use sucker trucks and 
temporary pumps to discharge through the SW culvert if needed (currently not being used).  
Sites will be monitoring. Consider sucking off SH1 if the failure increases. 
•  Day crew are vacating the site. 
•  We will need to get crews on site to replace pipe Sat morning (or sat night) although this 
cannot be the same crew as today due to fatigue. 
•  Reduced crew of sucker trucks (3) from now. 
•  Consider replacing with CLS across main failure and then provide internal pipe for integrity 
and something for the joint to bind to. Patches will provide the internal integrity. New 
section from southern and northern repairs approx. 12m.   
•  Confirm there are patches in Levin (2).  
•  Tartners will then help GP Friel with installation, Sean to get resource and material 
confirmation. 
•  It was agreed that we need to get have contractor present on site tomorrows 
 
Saturday 24/7 10am 
Paremata UPDATE 16 
•  Maf relieved by Royce 
•  Rob relieved by Ben (PS management) 
•  PS all operated fine overnight – a bit more flow than normal (Sat morning usual) 
•  No overflows to harbour  
•  Rahui – moved to 1pm 
•  Plan  
o  Attempt permanent repair  
o  Same sucker trucks (13-15) 

21-108
Page 35 of 44
o  12m length CLS being delivered (James Bulk Water team helping Hammonds with 
loading) with 2 step couplers, 
o  Internal pressure patches getting flown down from Auckland will need to be picked 
up at the airport with trailer (Sean) 
o  Tartners have the gear and will be on site 
o  GP Friel reduced staff (new team pulled off another job) 
o  Rambo’s on call for Sun morning if needed for tidy. 
o  Technique used before. 
o  CLS connected using pressure patches, step couplers, to AC – still a risk. 
o  Timeframes – likely to take till 8pm for backfill. 
•  Contingency – encasing in concrete – high risk could crush pipe, idea evolved could grout in 
repair and box in repair. 
•  Need to fully replace pipe ASAP 
•  Catch up at 2pm. 
Plan B –  
•  Run as per previous 2 nights.  Will need to monitor. 
•  Shifts need to be set up for Saturday night, Sunday day and Sunday night. Starting 8pm.  
Refreshments 
Approx 30 people lunch around 1, dinner around 6pm 
 
Comms 
•  May need someone near the railway bridge if discharge due to boating activity 
 
Longer term response/issues 
•  We don’t know condition of full length risk very high 
•  AC starts at repair and goes for 1km to nearest MH.   
•  Have tried 3 different types of repair and have struggles, have to think outside the square. 
•  Need to set up a separate team to come up with the med term repair 
•  Low level of cover but a risk that we cause damage by tracking over it. 
•  Water hammer is a risk of the substandard AC – what can we do to mitigate this? Paul W  
•  Wang clamps ideal for first choice of material 
 
Saturday 24/7 2pm 
Paremata UPDATE 16 
•  Could not get connections down from Auckland.  Now being transported by road and being 
picked up in Taupo.  Crews leaving site. 
•  Can keep one lane closed 
•  Site will run as it has previous two nights with utilities and monitoring support. 
•  Resources back on site 7am 
•  Tartners and GP Friel to be onsite tomorrow, Rambo’s on call 

21-108
Page 36 of 44
 
 
•  Walter will drop off food to monitoring staff. 
•  Rahui started at 1pm – 2 weeks 
 
Sunday 25/7 12pm 
Paremata UPDATE 17 
Unfortunately there has been a delay in the arrival of the specialised fittings from Auckland, which 
will now arrive after 21:00 (9pm) tonight.  Consequently we are putting today’s work on 
hold.  Sucker trucks have been mobilised to assist with minimising overflows at peak times and work 
will resume tomorrow morning. 
Thank you for your patience and we apologise for the inconvenience. 
 
Sunday 25/7 5pm 
Paremata UPDATE 18 
•  Need to notify GW Good progress 
•  Put in patches – blown up – gone in well and not cracked the pipe 
•  Pipes out of shape – 3m stub north 2m stub south, ready put in the final link ready to charge 
(probably around 1hr before we can turn on the pumps) 
•  Look in the pipe – can see bend northern end, pipe significantly deteriorated.  South side 
roof disappearing – goes quite a way 
•  When connect do slow charge up, get bedding in then expose gibaults to check integrity. 
•  Change over of staff at 8pm.  Reduced staff. 
•  Run 1 pump 6B and back in auto tomorrow morning.   
•  Tidy up works to do tomorrow. 
•  Gong to get cross harbour pipeline repaired tomorrow 
•  Need to ensure there is no overflow from 6A – manhole at the school is the lowest point. 
•  6A 1 pump operational with diesel pumps as back up for wet weather. 
•  Check out if level control can be put on diesel pumps (Rambo’s). 
•  Starting to backfill by 6pm. 
•  4 sucker trucks on standby for the night 
•  Effect on GP Friel planned work from this failure (Ian) 
 
Sunday 25/7 8pm 
Paremata UPDATE 19 
•  Traffic management working alright. 
•  Pipe up and running, patches provided the structural integrity, not leaking 
•  Backfilling 
•  Sucker trucks gone  
•  Traffic management still onsite - Station Rd, SH1   
•  Aim to remove TM mid  

21-108
Page 37 of 44
•  Monitor station Rd and drive by of site  
•  Alarm’s 6A (Station) have been reduced – will alarm earlier to avoid problems at the school, 
a bit of rain expected 
•  2 Sucker trucks on site 
•  Fence off diesel pumps 
•  SAP disinfect area around station rd (6:30pm) 
•  Keep GWRC informed about carparking. 
•  Traffic management on site to assist at school drop off and pick up. 
•  Have 6m left  
 
Next steps; 
•  Temp solution – procure ready for next break 
•  Longer term solution 
 

21-108
Page 38 of 44
Aotea pipe break/Paramata overflow Enteroccoci monitoring (cfu/100mL)
18/07/2021 19/07/2021 20/07/2021 21/07/2021 22/07/2021 23/07/2021 24/07/2021 25/07/2021
Final
Final
Final
Final
Final
Final
Final
Final
Wi Neera Drive boat ramp
3100
770
180
2100
4500
220
65
76
Pauatahanui Inlet Paremata Bridge
1300
980
320
130
44
560
48
16
Pauatahanui Inlet Water Ski Club
1200
1100
530
60
96
690
20
8
Plimmerton South Beach
1500
1100
400
120
1100
450
36
56
Karehana Bay Cluny Road (control site)
610
940
160
20
110
190
12
4
Plimmerton Beach @ Bath St
450
92
58
Takapuwahia Stream Outlet @ Te Hiko St
140
190
230
Porirua Harbour at Rowing Club
630
24
12
Weather
Overcast
Overcast
Rain
Clear
Clear
Clear

21-108
Page 39 of 44
Aotea pipe break/Paramata overflow Enteroccoci monitoring (cfu/100mL)
26/07/2021 27/07/2021 28/07/2021 29/07/2021 30/07/2021 31/07/2021
1/08/2021
2/08/2021 3/08/2021 4/08/2021 5/08/2021 6/08/2021
Final
Final
Final
Final
Final
Final
Final
Final
Final
Final
Final
Final
410
640
120
48
84
4
8
20
12
20
560
69
68
150
73
12
8
8
4
8
40
4
48
4
48
190
38
8
4
19
8
4
56
65
4
200
46
76
16
350
8
84
180
20
50
600
12
160
20
100
4
4
4
4
4
4
12
4
4
100
23
410
12
28
24
16
16
92
150
12
8
8
430
3400
110
38
40
220
12
12
3000
54
510
210
54
190
24
20
4
20
4
4
110
4
8
100
Rain
Rain
Clear
Clear
Clear
Clear
Partly cloudy
Clear
Rain
Overcast
Overcast
Overcast


21-108
Page 40 of 44
Hi James, 
 
I’ve left a message on your phone related to this, but we have made several decisions pursuant to 
s.330 emergency works since last Saturday morning. We are pulling together the documentation for 
the event and decision-making sequences – as I’m sure you can appreciate this has been a complex 
and evolving situation, which is still ongoing.  
 
Can you please confirm that the notifications and updates so far have been recorded as notification 
of the use of emergency powers? 
 
Nga mihi, 
Paul 
 
 
Paul Gardiner (he/him)  Manager (RMA, Consents and Environment) 
 
Tel 04 912 4400  DDI 04 912 4506  Mob 021 445 024  
Private Bag 39804, Wellington Mail Centre 5045 
Level 4, IBM House, 25 Victoria Street, Petone, Lower Hutt  
www.wellingtonwater.co.nz  
 
 
 


21-108
Page 41 of 44



21-108
Page 42 of 44
Team Leader Monitoring and Enforcement 
Kaiārahi Rōpū Aroturuki me te Whakaūnga 
 
 
 
Tel: 04 237 1404 I Mob: 021 948 720 
poriruacity.govt.nz 
 
  
From: Moana Wyatt <[email address]> 
Sent: Thursday, 29 July 2021 10:16 AM 
To: Hannah Toomaga <[email address]>; Derek Vos <[email address]>; David 
Down <[email address]> 
Subject: OIA 21-108 - Official Information request - Lawfulness of WasteWater Pipes and Discharges 
 
Morning Derek/David 
Please see the OIA below. 
I expect the first question is a part transfer to WWL? Please let me know if you agree and I wil  transfer it. 
  
Hannah 
I wil  assign to you for Derek’s team to respond to the second lot of questions. Please let me know if you want my 
assistance. 
  
Thanks  
  
  
Ngā mihi, 
 
Moana Wyatt 
Principal Advisor (Information) 
Kaitohutohu Matua (Pārongo) 
  
 
 
 
Tel: 04 237 1411 I Mob: 027 469 8532 
poriruacity.govt.nz 
 
  
From: [email address] <[email address]> 
Sent: Wednesday, 28 July 2021 8:54 AM 
To: Records Management <[email address]> 
Subject: FW: [EXTERNAL] Official Information request - Lawfulness of WasteWater Pipes and Discharges 
 
Hi Team 
  
An Official Information Act request for you. 
  
Kind regards 
Sandy Betham 
  
From: [FYI request #16216 email] 
Sent: Tuesday, July 27, 2021 5:57 PM 
To: [email address] 
Subject: [EXTERNAL] Official Information request - Lawfulness of WasteWater Pipes and 
Discharges 
Dear Porirua City Council, 
 
2

21-108
Page 43 of 44
In respect of recent failure of the wastewater (WW) main south of Paremata and the diversion of 
wastewater flow to a redundant WW main on the western side of Porirua Harbour at Whitireia and 
Onepoto, please provide me with the following information. 
 
- details of the work undertaken by WWL and/or PCC; 
 
- a copy of the current consents under the RMA (if any) that PCC/WWL has relied upon for: the 
infrastructure; the work undertaken on it; and, the discharges from it, in respect of: 
- the use of land in terms of section 9 of the RMA 
- the use of land in terms of section 13 of the RMA 
- restrictions imposed under section 12 of the RMA 
- restrictions imposed under section 15 of the RMA . 
 
- a copy of al  correspondence within, and between, PCC/WWL about the lawfulness or otherwise 
of: the specifically in terms of: 
- the WW main as a structure;  
- the recent work undertaken on it; and,  
- the recent discharges from it. 
 
Yours faithful y, 
 
Brian Warburton 
 
------------------------------------------------------------------- 
 
This is an Official Information request made via the FYI website. 
 
Please use this email address for al  replies to this request: 
[FYI request #16216 email] 
 
Is [email address] the wrong address for Official Information requests to Porirua 
City Council? If so, please contact us using this form: 
https://fyi.org.nz/change_request/new?body=porirua_city_council 
 
Disclaimer: This message and any reply that you make wil  be published on the internet. Our 
privacy and copyright policies: 
https://fyi.org.nz/help/officers 
 
If you find this service useful as an Official Information officer, please ask your web manager to 
link to us from your organisation's OIA or LGOIMA page. 
 
 
------------------------------------------------------------------- 
Disclaimer 
--- 
 
The content of this email is confidential, may be legally privileged and is intended only for the person named above. If this email 
is not addressed to you, you must not use, disclose or distribute any of the content. If you have received this email by mistake, 
please notify the sender by return email and delete the email. Thank you. 
 
--- 

 
Disclaimer 
3

21-108
Page 44 of 44
---  
The content of this email is confidential, may be legally privileged and is intended only for the person named above. If this email 
is not addressed to you, you must not use, disclose or distribute any of the content. If you have received this email by mistake, 
please notify the sender by return email and delete the email. Thank you.  
--- . 