This is an HTML version of an attachment to the Official Information request 'Lawfulness of WasteWater Pipes and Discharges'.



Ref: 21-108 
Richard Hopkins 
[email address] 
 
 
24 August 2021 
 
 
 
Brian Warburton 
 
Via email: [FYI request #16216 email] 
 
Dear Brian 
Official information request regarding the lawfulness of wastewater pipes and discharges 
I refer to your official information request dated 27 July regarding the recent failure of the wastewater 
(WW) main south of Paremata, and the diversion of wastewater flow to a redundant WW main on the 
western side of Porirua Harbour at Whitireia and Onepoto.  
 
The information you have requested is enclosed. The questions you specified have been included as 
numbered headings in bold below, with our response following each heading. 
1.  details of the work undertaken by WWL and/or PCC; 
Please see attached information. 
2.  a copy of the current consents under the RMA (if any) that PCC/WWL has relied upon for: 
the infrastructure; the work undertaken on it; and, the discharges from it, in respect of: 

the use of land in terms of section 9 of the RMA 
This information has been refused under section 17(e) the Local Government Official Information 
and Meetings Act 1987 on the grounds that the document does not exist. The emergency works 
were carried out under Section 330 of the RMA. The need for Resource Consent is yet to be 
determined and the Council is awaiting further information from Wellington Water. 

the use of land in terms of section 13 of the RMA 

restrictions imposed under section 12 of the RMA 

restrictions imposed under section 15 of the RMA. 
This part of the request was transferred to Greater Wellington Regional Council who have 
provided the information to you separately. 
 
Please note that overflow volumes were not able to be measured due to the lack of flow 
monitoring at the discharge locations for this emergency repair.  An estimate of the wastewater 
overflow has been prepared below by Wellington Water staff based on volumes measured at 
upstream pump stations and the estimated volume transferred with the use of sucker trucks 
while the Paremata pump stations were turned off to allow repair work on the pipeline.   
  
 




Dates 
Duration, 
Upstream 
Sucker truck 
Net estimated 
hrs 
pumped 
estimated 
overflow, m³ 
inflow,m³ 
volume,m³ 
17 – 18 
35.50 
10,500 
2,760 
7,740 
July 
23 July 
9.50 
2,080 
760 
1,320 
25 July 
11.50 
4,300 
920 
3,380 
 
3.  a copy of all correspondence within, and between, PCC/WWL about the lawfulness or 
otherwise of: the specifically in terms of: 
 
- the WW main as a structure;  
- the recent work undertaken on it; and,  
- the recent discharges from it. 
 
Please see attached information.  
 
We have redacted some information under section 7 (2) (a) to protect the privacy of natural persons. 
If you wish to discuss this decision with us, please feel free to contact Richard Hopkins on 04 237 5089. 
Ngā mihi 
 
 
 
Wendy Walker 
Chief Executive 
Kaiwhakahaere Matua