Kia ora Adam, 
The information you requested - CAS-381485-H7B4Y8 
On 31 May 2021 Auckland Council transferred part of your request to Auckland Transport about the 
Galway Street improvements, a project which is part of the Auckland Council Group Downtown 
Infrastructure Development Programme. 
To date we have spent in total $5.5m on the Galway Street improvements, an outturn that is fully 
funded and approved by Auckland Council. A final target construction price of $3.7m was agreed for 
the project under the contractual model that was put in place with the Downtown Infrastructure 
Development Programme contractor to deliver the works, inclusive of agreed scope changes. The 
final target construction price of $3.7m has been certified by the programme cost consultants and 
agreed by the Engineer to Contract. There have been no material Variations post agreed scope 
finalisation and are all minor variations (in aggregate less than $5,000) which have been approved by 
the Engineer to Contract or Engineer’s Representative. 
The tables below show the breakdown of the total project costs and therefore expenditure on the 
improvements: 
Total spend to date by Category 
$ 
Galway St Consents, RMA and Planning 
48,002 
Galway St Design and Professional Services 
1,423,260 
Galway St Construction 
3,677,728 
Galway St MSQA 
289,885 
Galway St COVID costs 
105,875 
TOTAL 
5,544,751 
 
 
 
aucklandtransport.govt.nz 




Construction Spend 
$ 
Sediment & Erosion 
781,874 
Earthworks 
319,484 
Carriageway 
1,025,717 
Footpaths 
317,853 
Stormwater 
489,833 
Sewerage 
20,927 
Street Lighting 
282,277 
Traffic Systems 
11,920 
Seating 
34,465 
Infrastructure 
186,779 
Landscaping 
30,870 
Water Reticulation 
67,956 
Other general elements 
107,773 
Total Construction 
3,677,728 
The costs of Professional Services are further broken down and provided below: 
Professional Services 
$ 
Project Management 
153,824 
Design 
1,235,288 
Management, Surveillance and Quality Assurance (MSQA) 
289,885 
Maori Consultation and iwi cost 
4,500 
Traffic Management 
29,648 
Consents & Property 
48,002 
Total 
1,761,147 
Should you believe that we have not responded appropriately to your request, you are able to make 
a complaint to the Office of the Ombudsman in accordance with section 27(3) of the LGOIMA Act, 
and seek an investigation and review in regard to this matter. 
Yours sincerely 
 
 
Ben King 
Commercial Manager (Integrated Networks)