TERMS OF REFERENCE 
 
Client: NZ Police Air Support Unit Expansion project  
Business Owner: Superintendent Karyn Malthus  
 
1.  
CONTEXT 
 
An Air Support Unit planned deployment is proposed for the 17th February to 20th March in Canterbury 
district.  
 
Auckland  Air  Support  will send  a  fully  equipped  helicopter  and  crew  (Police  staff  and  Pilots)  to  be 
based  in  Christchurch  to  deploy  to  events  which  occur  throughout  the  5  week  timeframe.    Road 
Policing and road related activity will be one of the incident types the unit attends along with other 
incident requests/demands and prevention activity. 
 
The location chosen best fits the geographical range being covered.  The shifts worked will be planned 
to provide the most effective service delivery within Canterbury and beyond.   
 
Staff from Auckland and Canterbury districts as well as service centres will work in collaboration to 
provide a policing experience to ground crew and operational decision makers that a fully equipped 
helicopter makes available.   
 
Aside from the deployment activity, the trial will give an opportunity for the residents of Canterbury 
to interact with the Air support crew gaining an understanding of the capability and how it supports 
community safety. 
 
 
 
 
Page 1 of 4 
 

Air Support Unit Canterbury Trial 
 
2. PURPOSE 
 
The 5 week trial is to provide an overview of and support to the NIC demand profile for Canterbury 
and the wider south island and is part of the already approved in principle ASU expansion process.   
 
The  information  obtained  from  the  trial  will  help  determine  the  wider  than  Tamaki  Makaurau  Air 
Support expansion process and information required for our partner agencies. 
 
3. AIM 
 
To deliver a safe and effective Air Support Capability to Canterbury between 17th February 2020 and 
20th March 2020. 
4. OBJECTIVES 
 
  To scope, plan and implement what is required to provide Air Support capability in 
Canterbury for the trial period 
  To identify & develop resources to build knowledge of Canterbury police to understand the 
capability of an Air Support unit 
  To Support Canterbury to seek EOI’s for observers from AOS/STG/Frontline etc. 
  To support Canterbury workgroups to plan and prepare tasking’s and deploy to demand. 
  To liaise with Canterbury to maximise opportunity to increase Trust & Confidence 
  To liaise with key stakeholders to progress the planning and implementation 
  To ensure that deployment and reporting of activities meet the purpose 
  To ensure that Air Support capability is maintained in Tamaki Makaurau during this period 
5. KEY ACTIONS TO ACHIEVE THE OBJECTIVES 
 
 
The key actions to achieve the above objectives are as follows: 
  Appoint a logistics officer to support the project lead 
  To identify a liaison officer in Christchurch  
  Identify parameters of deployment, incidents/locations 
  To plan visits to Christchurch pre-deployment to build knowledge and capability  
  To communicate with and keep key stakeholders informed of  project progress 
  Establish clear understanding of required data and recording process. 
  Capability maintained in TM to manage TM deployment 
 
 
 
Page 2 of 4 
 

Air Support Unit Canterbury Trial 
7. STAKEHOLDERS 
 
 
Internal Stakeholders 
External Stakeholders 
Auckland District Commander 
AFL – Pilots/Mechanics 
 
Canterbury District Commander 
Airways 
 
Expansion Project Lead 
 
 
Air Support Unit 
 
 
National Intelligence Centre 
 
 
Christchurch Liaison Officer 
 
 
Media 
 
 
6. OUT OF SCOPE 
 
Media communications plans will be managed in the first instance by the National Media Team. 
7. TIMELINE OF ACTIVITIES 
 
Activity 
Completed by 
By Who 
Initial scoping 
23rd December 2019 
Logistics officer 
Planning 
31st January 2020 
Logistics officer 
Pre Deployment visit 
January 2020 
Logistics officer/project Lead 
Deployment 
17th February – 20th March 
ASU 
2020 
 
8. REPORTING 
 
Reporting requirements: 
1.  Superintendent Malthus and the Auckland City District Governance Group to be kept up to 
date with the progress of the work. 
2.  Deployment planning updates will be ongoing between the ASU logistics officer and the 
Expansion Project lead. 
 
3.  Stakeholders will be regularly updated, this includes the ASU team and the AFL operators. 
 
Page 3 of 4 
 

Air Support Unit Canterbury Trial 
9. BUDGET AND FINANCES 
 
There is no specific budget for this project.  Costs will be managed within current NZP budget 
baseline. 
 
10. MANAGING RISK 
 
 A risk register will be established 
Consultation with H&S advisor by the Logistics officer 
Each crew will establish a H&S officer and ensure they are briefed on their role 
Wellness and safety of staff is everyone’s responsibility and overseen by the Logistics officer 
 
TOR completed by Inspector Houliston 
Manager Operations 
Page 4 of 4