By email
Shed 39,
2 Fryatt Quay
Pipit
ea, Wellington 6011
PO Box 1
1646
5 April 2019
Manners St
reet
Wellingt
on 6142
T 04 384 5708
File Ref: OIAP-7-10277
F 04 385 6960
www.gw.govt.nz
Michael
[FYI request #9795 email]
Dear Michael
Request for information 2019-083
I refer to your request for information dated 7 March 2019, which was received by Greater
Wellington Regional Council (GWRC) on 7 March 2019. You have requested the following
information:
“
I would like to know the budgeted and actual costs associated with the work being undertaken
currently at bus stop 5319 (Karori Tunnel Stop B).
Please include the cost of tearing down the old bus stop as well as building the replacement, and if
possible ancillary costs such as signposting nearby stops etc.
Ideally a degree of itemisation would be provided (e.g. this much spent on labour, this much spent
on earthworks, this much spent on materials etc).”
GWRC’s response follows.
The full budgeted cost of constructing Karori Tunnel Stop B is $302,057. The aggregated budgeted
costs for Karori Tunnel Stop B are as follows.
The existing shelter at Karori Stop B was owned by Adshel, which operates in Wellington
under a contract administered by Wellington City Council. Adshel installs, manages, and,
where necessary, removes shelters free of charge in exchange for the revenue it gains from
advertising. Therefore there was no cost to the project for removal of the existing shelter.
Design and project management costs arise from the use of Greater Wellington Regional
Council personnel and a third party supplier of professional services. The external contract for
design and project management of the Bus Hubs project (including this Karori site) is for a
fixed fee and is not broken down on a per-stop basis. If the fee is divided equally across all
stops on the project the design and management budget for Stop B is approximately $16,094.
2019-083 MICHAEL RESPONSE
Civil works are priced on a per-hub basis. The Karori hub, which incorporates two stops,
averages out at a budgeted cost of $100,385 per stop.
The budgeted cost of shelter manufacture and installation at this stop is $145,123.
The costs of signage notifying customers of temporary arrangements during the construction
phase of Stop B is difficult to specify accurately as printing was procured as part of a larger run.
The estimated maximum total budgeted cost of signage for the hub is $200.
The shelters being used as temporary facilities on the Karori side of the tunnel were installed as
part of an ongoing network facility upgrade and will remain in situ following the completion of
the project. They are therefore not project costs.
The budgeted cost of the electrical connection for the stop is $21,000.
ICT equipment and network connection serve both stops at the hub. The average cost for ICT
equipment and installation for one stop is $7,667. The budgeted cost for systems design, testing
and ICT project management for the stop is $11,588.
Work on Karori Tunnel Stop B is currently ongoing. Greater Wellington Regional Council has not
yet been billed for all work relating to this site, so I am unable to advise on all actual costs. As no
contract variation claims specific to this stop have been submitted to date, actual costs can be
reasonably expected to be the same as (or very close to) the budgeted costs above.
I note you have also requested an itemised breakdown of this information. Contractors provide
itemised costs in confidence during the competitive tender process, and the details are commercially
sensitive. I am therefore withholding an itemised breakdown of costs under section 7(2)(b)(ii) of the
Local Government Official Information and Meetings Act 1987, as releasing this information would
be likely unreasonably to prejudice the commercial position of the person who supplied or who is
the subject.
We have considered whether the public interest in the requested information outweighs GWRC’s
need to withhold certain aspects of the information requested. As a result, we do not consider that
the public interest outweighs GWRC’s reason for withholding parts of the information under the
grounds identified above.
2019-083 MICHAEL RESPONSE
PAGE 2 OF 3
If you have any concerns with the decision(s) referred to in this letter, you have the right to request
an investigation and review by the Ombudsman under section 27(3) of the Local Government
Official Information and Meetings Act 1987.
Yours sincerely
Greg Pollock
General Manager, Public Transport
2019-083 MICHAEL RESPONSE
PAGE 3 OF 3