This is an HTML version of an attachment to the Official Information request 'Queen St Northcote Cycleway, contractors program of works, cost benefit analaysis'.
link to page 1
Memorandum 
Memorandum 
To: 
Ali Rajaiy 
Date: 
14 March 2017 
From: 
Harriet Priddey 
Our Ref: 
3124347 
Copy: 
Fariz Rahman, Ahmad Issa 
Subject: 
Northcote Safe Cycle Route - Economic Evaluation 
 
 

Evaluation Framework 
The economic evaluation has been undertaken in accordance with the NZ Transport Agency’s 
Economic Evaluation Manual (EEM) using a customised version of the full procedures. The 
economic analysis for the project has included the following benefits displayed in Table 1.  
Table 1: Components of economic benefits and evaluation procedure adopted 
Benefit Component 
Evaluation Procedure 
Cycle routes cycling health and environment 
Full procedure 
benefits 
Cycle routes cycling safety benefits 
Cycle journey time benefits 
Road traffic reduction benefits (decongestion) 
The evaluation was peer reviewed by MWH and recommendations incorporated. The peer review 
response is attached in Appendix A. 

Assumptions 
2.1 
General 
The following assumptions have been made in the economic analysis: 
  Project opening year: 2018 
  Construction time of 12 months 
  The width available before and after has been estimated at 1.5m and 3.0m respectively 
  Total expected cost estimate of $17,587,188 
  SkyPath opening year: 2019 
The assumptions in the economic benefit components are further described in the following 
sections. 
2.2 
Demand  
2.2.1  Base 
The cycle demand for the Project has been estimated based on the 2015 Auckland Region Manual 
Cycle monitor (North Shore Ward) report and Worksheet A20.1 from the EEM. The catchment area 
and population inputs to the worksheet have been based on the previous Scheme Assessment 
 
 
Beca // 14 March 2017 // Page 1 
 
3124347 // NZ1-13282586-7  0.7 
 

link to page 2
Memorandum 
Report (which was peer reviewed). This number is deemed appropriate as the previous numbers 
were derived based on the 2013 census data, which would still represent the most recent census 
data available.  
The worksheet estimates 255 existing cyclists. However, after reviewing cyclist counts from 
Taharoto Road/Northcote Road it appears that current cycling numbers are supressed. Therefore 
existing cyclists have been reduced to 193, based on assumption that half of the Taharoto 
Road/Northcote Road intersection count would use the route in the project area.  
As currently cyclist numbers are suppressed the number of new cyclist will be greater than the 121 
calculated from the spreadsheet. Hence an increase of 183 has been chosen in order to match the 
initial total of 376 (existing plus new) derived from the worksheet. 
2.2.2  School Students 
Instead of relying on census data only, we have allowed for new school students using the route 
once improvements are completed. This was done based on the number of students on the roll for 
each school which has a catchment that overlaps with the catchment for this project. More details 
are shown in Table 2. 
 
Table 2: Breakdown of School Students Using the Route 
School Name 
School Roll 
Assumed 
Percentage of 
Number of 
percentage 
school students 
school 
within 
(new) likely to cycle 
cyclists 
catchment 
with safe facilities 
Northcote College 
1076 
15% 
10.0% 
16 
Westlake Girls' High 
2181 
5% 
10.0% 
11 
School 
Northcote Intermediate 
278 
75% 
5.0% 
10 
Northcote School 
478 
75% 
2.5% 

(Auckland) 
Onepoto School 
108 
75% 
2.5% 

St Mary's School 
424 
75% 
3.25% 
10 
(Northcote) 
Takapuna Normal 
602 
5% 
5.0% 

Intermediate 
Rosmini College 
1050 
10% 
7.5% 

St Joseph's Catholic 
381 
10% 
2.5% 

School (Takapuna) 
Northcote College 
1076 
15% 
10.0% 
16 
Total 
 
 
 
69 per 5 days 
49 per 7 days 
2.2.3  SkyPath 
The SkyPath project has recently received resource consent, and as such has been included in the 
Do Minimum for the economic analysis. SkyPath will bring new cyclists to the project area. These 
cyclists will also benefit from the proposed Northcote Safe Cycle Route facility improvements. 
 
 
Beca // 14 March 2017 // Page 2 
 
3124347 // NZ1-13282586-7  0.7 
 

link to page 3 link to page 4
Memorandum 
Based on the estimated numbers from a study by Angus & Associates for Auckland Council, it has 
been assumed that 40% of the cyclists from SkyPath could go through the Northcote Safe Cycle 
Route project area.  
2.2.4  Growth Rate 
For the base cycle demand growth rate, 4.0% has been chosen. This has been derived from 
historical census trends (+3.8% per annum) last collected in 2013. The SkyPath growth rate has 
been extrapolated from the study by Angus & Associates. 
2.3 
Safety Benefits 
A full crash-by-crash analysis was not considered applicable due to the significant changes that 
SkyPath will bring to existing conditions, by increasing the number of cyclists. Instead, the safety 
benefits have been calculated using the value from the EEM of $0.05 per cyclist km. Safety benefits 
for lower Queen St were not included in the EEM as only sharrows and speed calming devices were 
proposed. Therefore the total route length considered was 4.2km. 
2.4 
Health and Environmental Benefits 
2.4.1  Cycling 
Health and Environmental benefits for new cycling users have been calculated using the value form 
the EEM of $1.40 per cyclist km. 
2.4.2  Pedestrians 
There are no any significant benefits for pedestrians as new infrastructure is Copenhagen lanes, 
and marked cycle lanes. Shared paths which affect pedestrians have been repurposed from 
existing infrastructure. 
2.5 
Travel Time Benefits (Cyclists) 
2.5.1  Travel Time Cost 
A travel time value of $6.42 per hour has been adopted. This has been based on both the $/h 
values from the 2016 EEM Table 4.1(a) and the trip generation points surrounding the project. The 
values used to calculate the travel time value are displayed in Table 3. 
Table 3: Travel Time Value 
Travel Purpose 
At work 
Commuting 
Other 
Split assumed 
5% 
50% 
40% 
Cost ($/h) 
$21.70 
$6.60 
$4.25 
2.5.2  Relative Attractiveness 
The Relative attractiveness (RA) of 1.915 has been adopted. To obtain this value the project has 
been broken into 6 similar sections. Each section has been measured and an RA has been 
calculated based on the type of cycling facility present. To understand the RA for a certain facility 
information from table A20.2 of the EEM has been used. For a breakdown see Table 4 
 
 
Beca // 14 March 2017 // Page 3 
 
3124347 // NZ1-13282586-7  0.7 
 

link to page 4
Memorandum 
Table 4: Relative Attractiveness 
Section 






Length 
1.3 
0.98 
0.67 
0.48 
0.77 

RA 

1.887 
1.93 

1.95 
1.7 
Comments 
All shared 
One marked cycle 
One shared path 
All shared 
Cycle lane 
Semi-mixed 
path 
lane on one direction 
and one marked 
path 
with no 
use both 
and a shared path 
cycle lane with 
parking off 
directions 
and cycle lane in the 
limited parking 
street at some 
other 
points 
Assumptions: 
  Queen Street RA of 1.7 assumed as it is a shared space 
  Cycling lanes with partial parking along their length, RA of between 1.8 and 1.9 assumed 
depending on the percentage of parking 
2.5.3  Mean Speed 
The cycling speed for the current situation was assumed to be 15 km/h to reflect the delays that 
cyclists face when navigating the current route. The new cycling speed is assumed to be 18 km/h. 
The travel time savings doesn’t assume benefits for pedestrians as their travel time will not be 
affected. 
2.6 
Road Traffic Reduction Benefits 
Road traffic reduction (decongestion) benefits have been included for new cyclists who travel during 
the weekday peak periods i.e. commuters. It is assumed that 50% of new users are commuters. 
The diversion rate (vehicle km removed from road per new cyclist km) is assumed to be 72.5% and 
the reduction benefit $1.56 per vehicle km per year, both from the EEM. 

Economic Analysis Results 
The economic analysis results are summarised in Table 5 
Table 5: Economic Analysis Results 
Item 
Cycleway 
Health and environment benefits for cycling facility 
$15,710,460 
Travel time cost savings (cyclists) 
$5,856,207 
Safety benefits for cycling facility 
$1,059,974 
Road traffic reduction benefits 
$2,941,050 
Total Benefits (NPV) 
$25,567,691 
Total Costs* (NPV) 
$16,584,736 
BCR 
1.5 
*including remarking every 10 years at a cost of $100,000 
 
 
Beca // 14 March 2017 // Page 4 
 
3124347 // NZ1-13282586-7  0.7 
 


Memorandum 
The economic analysis carried out produces a BCR of 1.5 which would suggest a low economic 
efficiency rating under the NLTP 2015/18.  

Sensitivity Testing 
Several sensitivity tests were carried out to investigate a number of different effects. The results are 
summarised in a memo responding to Peer Review comments (Northcote Safe Cycle Route – 
Economic Evaluation Peer Review Response, 08/12/2016). These are attached in Appendix B. 
 
 
Harriet Priddey 
Systems Engineer 
Direct Dial: +6493009681 
Email: [email address] 
 
 
 
 
Beca // 14 March 2017 // Page 5 
 
3124347 // NZ1-13282586-7  0.7 
 


Memorandum 
Appendix A – Peer Review Response 
The document “Northcote Safe Cycle Routes Economic Peer Review” (MWH, 16 November 2016) 
was reviewed and the recommendations considered. Our response to each of the 
recommendations is shown in the table below. 
Table 6: Recommendation Responses 
 
Reviewer’s 
Response 
Recommendations 
C1  
Provide Designs 
A parallel estimate has been undertaken by an external party (Stellar 
and Cost 
Projects). There parallel estimate was generally aligned with our 
estimates for 
estimate, this is considered sufficient review. 
review  
C2  
Provide basis for 
At this stage maintenance costs are assumptions. However they are 
maintenance costs   small in comparison to the other costs and benefits. This also has 
minimal impact on the overall BCR, when compared to other factors 
that are also raised by the peer reviewer.  A further sensitivity test has 
been carried out to demonstrate that this has negligible effect on the 
overall BCR. 
C3  
Confirm analysis 
Analysis duration has been extended from 2056 to 2057, which 
duration.  
increases the total benefit by 1.5%. 
Confirm 
We agree that midpoint of construction should technically be year 0.5, 
construction 
however as noted effect is modest as error applies to both costs and 
timeframes and 
benefits, so no changes has been made to the evaluation. 
consider preparing 
a WS1.1.  
C4  
Provide evidence 
Recently there has been a strong focus on cycling, prompted by the 
supporting 
Ministry of Transport’s Urban Cycleway Fund. In Auckland, the Council 
increase in school 
has committed $125m over three years towards cycling and walking. 
cycling above 
Auckland Transport is delivering a comprehensive programme of 
calculated 
behaviour change activities. This included training over 10,000 children 
generation.  
and 1,000 adults in 2015. 
In this context it is not unreasonable to assume that school cycling will 
increase. In addition, the actual numbers in the evaluation are fairly 
conservative, ranging from 1 to 16 extra students cycling per school. 
C5  
Consider factoring 
We agree and hence have carried out sensitivity test with no school 
school cyclists by 
cyclists.  
3/5.2, or, consider 
sensitivity test with 
no cyclists.  
C6  
Provide evidence 
We agree that the SkyPath numbers provided could be overly 
of claimed extra 
optimistic. We have revised them based on the review comments. We 
SkyPath-
have applied 30% as the number of SkyPath users who will walk or 
generated 800 
cycle to access it. The review suggests 20%, however we note this is 
cyclists per day  
based on unconstrained parking, which is unlikely to be the case. We 
have applied 75% of all walk/cycle users to be cyclists. This is based on 
cycling having a catchment area approximately 3x larger than walking. 
This has resulted in 165 cyclist trips per day along the Northcote route 
from SkyPath, on the opening year. 
C7  
Confirm effect of 
The SeaPath project is currently at the Investigation stage and has not 
SeaPath  
been granted consent. This has not been included in our economic 
 
 
Beca // 14 March 2017 // Page 6 
 
3124347 // NZ1-13282586-7  0.7 
 


Memorandum 
 
Reviewer’s 
Response 
Recommendations 
assessment, but we have applied some conservatism in the analysis 
with applying 40% of the 412 SkyPath cyclists going through the project 
area.  A sensitivity test has been carried out with only 25% of the 
cyclists using the route, as may happen if the SeaPath alternative is 
built. 
C8  
Provide evidence 
Cycling counts across Auckland have recently been increasing. The 
of sustained 
most recent results of Auckland Transport’s monthly cycling numbers 
growth relevant to 
show 1.67 million cycle trips were recorded for the year of November 
Northcote, or 
2015 to October 2016, an increase of 8.9% on the previous 12 months. 
sensitivity test at a 
In addition, there is potential significant development in the area. The 
lower growth rate.   Northcote Strategic area was designated as a SHA in May 2014, with 
potential development of approximately 700 new sites and dwellings. 
In light of this, it is not considered unreasonable to use the 4% growth 
rate form the survey given the lack of better data. 
However, a sensitivity test at a lower growth rate has been included 
below. 
C9  
Justify 3kph speed  The speed increase is a high-level assumption. 
increase  
A sensitivity test has been provided below showing that this has no 
material impact on BCR. 
C10   Explain 10% work-
With little evidence, we have applied the assumption based on light 
related cycling 
vehicle composition on urban roads. However, we appreciate that this 
component 
could be slightly optimistic. With increasing drive from employers to 
increase their sustainability input, there could be increasing work 
related trips on bicycles.  The Northcote route connects directly to the 
Smales Farm employment precinct. Regardless, we have reduced this 
work related composition trips to 5%.  
This changes the overall value of time to $6.42/hour 
C11   Consider $TT 
Further sensitivity test included. 
testing with no 
work related 
component.  
C12   Use correct health 
Agree and amended in our evaluation. 
and environment 
rate $1.40  
C13   Consider method 
Refer response on C15. 
A modifications, 
including growth 
modelling as per 
the compendium.  
C14   Consider applying 
Refer response on C15. 
method C.  
C15   Consider reducing 
Agree. As per the Detailed Design Report, the cycleway can be split 
simplified safety 
into five sections. Four of these (1, 2, 3, 4a) have facilities expected to 
benefits length.  
provide the safety benefits through shared paths, Copenhagen cycle 
lanes or regular cycle lanes. The last section (4b) will have speed 
calming devices and “sharrow” markings, which may be less effective. 
This section measures 1km, so the length of safety benefits has been 
reduced to 4.2km. 
C16   Consider halving 
The evaluator agreed that this is a valid comment. However as noted by 
the claimed 
the reviewer, the net result does not change the BCR and hence 
 
 
Beca // 14 March 2017 // Page 7 
 
3124347 // NZ1-13282586-7  0.7 
 


Memorandum 
 
Reviewer’s 
Response 
Recommendations 
benefit for 
evaluation has been left as is. 
“decongestion” 
and removing the 
$0.10 
Environment rate 
component. 
Increase 
commuter 
component % 
 
Appendix B – Peer Review Sensitivity Tests 
Several sensitivity tests were carried out to investigate the effect of travel time values and cycling 
demand on the BCR. The results are summarised below. The BCR remains within the low 
economic efficiency rating range.  
Note that these tests were carried out as part of the Peer Review response when the cost estimate 
was slightly different to the current estimate. So the exact BCRs may have changed slightly 
however this provides a reasonable indication of the potential BCR range. 
 
Table 7: Sensitivity Test Results 
Sensitivity Test 
BCR 
Decrease travel time value from $6.42 to $5.54 by excluding work trips 
1.5 
Exclude the new school cyclists 
1.4 
Decrease cycle trips growth rate from 4% to 2% 
1.3 
Average speed to remain at 15kph rather than increase to 18kph 
1.5 
Option maintenance costs increase by 50% to $150,000 every 10 years  1.6 
Only 25% of SkyPath cyclists use Northcote Route 
1.5 
 
 
 
Beca // 14 March 2017 // Page 8 
 
3124347 // NZ1-13282586-7  0.7