Minutes 
 
Devonport to Takapuna Green Routes 
Date: 
23 August 2016 
Time: 
10.00am 
Venue: 
HSBC 
Attendees: 
Patricia Vasconcelos, (PV) Ina Stenzel (IS), Melissa Clark (MC) 
Apologies: 
  
 
Item 
Topic 
Update / Actions 
Responsible 
1   
Progress 
 
1.1  
Ina has received the tool from MCgney – we can use it although 
 
it is still work in progress 
2.2 
Agreed  using  the  road  widths  from  GIS  is  appropriate  at  this 
 
stage of the design process 
2.3 
IS  &  MC  had  a  site  visit  –  discounted  route  at  northern  end 
 
eastern  side  (Hauraki/Ewen/Cliffton)  as  an  alternative  to  Lake, 
not possible due to topography. 
2.4 
Options around Old lake Rd/Park discussed – check if park is AC 
 
or private. A connection could also be provided to the café/beach 
2.5 
Investigate  Buchanan/Rattray  for  option  for  route  to  avoid 
 
Devonport town centre 
2.6 
Stanley Ferry link – future project, outside of our scope 
 
2.7  
Look  at  changing  priority  of  Victoria/Abbortsford  to  allow  cycle 
 
priority up the hill. 
2.8 
Consider saety in parks/lighting when using as alternatives- note 
 
about Ngataranga Park 
2.9 
Seabreeze – future link to consider 
 
2.10 
Change to Regent from Wesley (avoid walkway) 
 
2.11 
Liam Winter – Panuku contact re. Takapuna 
 
Next Meeting – 6 September 2016 -  10am - Henderson 
 