August 2014
Proposed Construction car parking provisions for 2015
Background
The ongoing transformation of the UC campus will reach a new level or intensity during the 2014/15
summer break with both CETF and RSIC construction sites established along side 9 remediation and
2 infrastructure projects . It is estimated that this scope of work will need to be supported by approx
1200 construction staff all of which need to get to work. This is almost approximately double our
previous maximum construction staffing peak levels of 650 experienced in the summer of 2014. This
combination of a significantly increased scale of construction, the people it involves and the need to
OIA
provide a safe environment within which UC can continue to operate has been a prime
consideration for the newly formed Campus Construction Safety group.
Our remediation experience to date has shown that contractor carparking has been an issue for
both the campus and the surrounding neighbour hoods .This has come in the form of increased
pressure on all of the Ilam campus parking which has necessitated the allocation of 100 free
Contractor specific parks most of which are located around the Creyke Rd Hawkins house and the
purchase of 25 UC parking permits . During the construction peaks within the summer breaks the
Fine Arts and Law carparks have been available free for contractor use. UC’s neighbours have also
experienced an expanded pressure and scale of non‐residents parking on the surrounding streets.
under
UC’s ability to continue to comply with the CCC parking requirements has also been affected by the
large number of construction hoardings and traffic management plans required directly removing
463 carparks from service by the start of 2015.
The culmination of these pressures have required there to be a rethink of the contractor carparking
provision for the next 3 yrs at least.
Car parking options
The options considered for the provision of temporary contractor carparking included
Temporary construction –this involves the temporary establishment of carparks at various green
space locations on campus . These would be made from recycled concrete chip or a gravel base with
a temporary edge detail they would however still need a temporary resource consent and
stormwater treatment .Unfortunately they would not be the most aesthetically pleasing solution so
are best suited to edge of campus locations away from main entrances or frontages. They would be
available to contractors at the current daily cost of $7.50/day.
Construction hoardings – This is where the site construction hoardings are expanded to
Released
accommodate some construction car parking. This obviously is the contractors preferred option but
the scale and location of the current constructions zones and their impact on campus requires them
to be minimised not expanded so this was not considered further.
Construction of a car parking building – The capital cost ,design and consent time for this
permanent solution makes this option unachievable within the short timeframe available so was not
considered further.
Reallocation of existing UC parks – This involves the temporary reallocation of established UC staff
or student asphalted car parks for specific contractor use which are either charged or made available
free . This is currently in place around the Hawkins Creyke road house providing 70 parks.
The reallocation areas being considered are a section of the Dove dale Campus Carpark No 2 where
initially 80 will be provided free on a trial basis .This will encourage the early morning car poolers to
drop off their occupants to site and then park with a no cost option. Contractor vehicles will need
specific identification as the remaining Staff student Dovedale car parks will continue to be charged.
OIA
Another area currently being considered is a section of the western side of the Student union
carpark to encourage the potential use of the Student event centre as a Contractor lunch location
should this proposal be successful. This would be available at a daily charge. This proposal attempts
to provide a centralised contractor lunch location for all contractors complete with an approved
smoking area with morning teas delivered to site so as to reduce the contractor pressure on UC
student site amenities at key times.
Temporary car park options
A wide variety of locations were considered and preliminary construction costs were established
with allowances made for reinstatement as these options are clearly temporary as they use crushed
under
concrete or gravel chip as a base. Locations that have been priced with a financial assessment
include are shown on the site map ( see appendix). The financial options assessment (see appendix)
is conservative and based on a 75% occupancy during the parking year ( Feb –Nov).
1 Alice Candy West ‐ 95 parks Cost $201K Income $96K pa . This option is preferred as it placed
away from site frontage bit still at the edge of campus and is no available with the loss of the
Archives project.
2 McMillan Brown South ‐ 47 parks Cost $117K Income $48K pa . This is close to option 1 but
displaces specific functions and events held within this zone
3 Music south ‐ 82 parks Cost $197K Income $83K pa . This requires the removal of a number of
significant trees and effects an area adjacent to the Music amphitheatre which is being encouraged
as an outdoor option for performances with the loss of use of the Jack Mann theatre.
4 Between Uni drive and Science road ‐ 97 parks Cost 237K Income $97k This significant Ilam road
frontage site would also require the bringing forward of the time frame for the removal of the pines
at the south end.
Released
5 Science road North – 35 parks Cost $81K Income $35K This small extension of the Sciences carpark
requires the removal of a significant group of cedars for relatively little return.
6 Ilam fields East – 443 Parks Cost $985K Income $449K – This high profile community site
adjacent to Ilam road provides the the greatest number of parks .It also provides the greatest
impact on the student experience in terms of green fields availability for sport and clubs , large
student event location and general green space all of which is a unique aspect of UC.
7 Research and industry zone – 115 parks Cost $281K Income $109K – This Creyke road frontage
site utilises the north undeveloped section of the proposed R&I development . This area also
includes the Hawkins Creyke road office and it is not proposed to shift this . It does however require
the R&I development to be under way and the Creyke road houses be demolished prior to the
carpark being established .Should this not occur then the current default provision of the existing 70
parks in this area would remain available at no cost.
8 Fine Arts Carpark East ‐ 176 parks Cost $380K Income $178K – This high profile site along the
Clyde road frontage requires the removal of a large number of prominent trees earth mounds and
OIA
borders the much photographed large concrete entrance sign by University drive.
CCC Parking Plan
These have been confirmed as being linked to the UC staff and student numbers with the carpark
count only related to those available on campus for that purpose so this precludes those used at UC
accommodation facilities. By December of 2015 UC will have lost some 463 carparks with approx.
160 of these being permanent with the rest being returned to service when the respective
construction hoardings are removed. This will of course be a moving feast as the cycle of
remediation works progresses .So although at December 2015 UC will officially be 138 carparks short
of the 3106 required within the CCC City Plan at that time it can readily confirm that some 283 parks
are only unavailable on a temporary basis.
under
Recommendation
Of the options considered it is proposed to establish the details and progress the detailed planning
for the following
Alice Candy East built option 1 with a daily charge
95
Research and Industry built option 7 with a daily charge
108 or 70
Undertake the Dovedale Carpark 2 allocation at no cost on a trial basis
80
Proposed provision of contractor specific car parking in 2015
283 or 245
This approach will also ensure we are only providing 138 car parks less than the current CCC Cityplan
requirements of 3106 while a further 283 are temporarily unavailable.
Released

s9(2)(b)
under OIA
s9(2)(b)(ii)
(ii)
s9(2)(b)
(ii)
Released
s9(2)(b)(ii)

OIA
under
Released
Document Outline