Attachment C
THE ACT
UNDER
INFORMATION
RELEASED
NZ Transport Agency and Auckland
Transport
OFFICIAL East West Connections Project
Construction Erosion and Sediment Management
Assessment to Support Option Selection
November 2014
This document is in draft form. The contents, including any opinions, conclusions or recommendations contained in, or which may be implied from,
this draft document must not be relied upon. GHD reserves the right, at any time, without notice, to modify or retract any part or all of the draft
document. To the maximum extent permitted by law, GHD disclaims any responsibility or liability arising from or in connection with this draft
document.
Table of contents
1.
Introduction..................................................................................................................................... 1
1.1
Shortlist Option Summary .................................................................................................... 1
1.2
Purpose of this report........................................................................................................... 4
1.3
Assessment brief ................................................................................................................. 5
1.4
Scope and Limitations.......................................................................................................... 5
2.
Methodology of the Assessment .................................................................................................... 6
3.
Key Design Assumptions ............................................................................................................... 7
3.1
ESC Assessment Assumptions ........................................................................................... 7
3.2
Construction in Landfill Sites ............................................................................................... 7
4.
Erosion and Sediment Control Principles and Design Criteria ...................................................... 9
4.1
Erosion Control versus Sediment Control............................................................................ 9
THE ACT
5.
Recommended mitigation required .............................................................................................. 14
5.1
Anticipated Erosion Protection Measures .......................................................................... 14
5.2
Anticipated Sediment Protection Measures ....................................................................... 15
5.3
Other Measures ................................................................................................................. 17
5.4
Non-sediment contaminants .............................................................................................. 18
UNDER
6.
Assessment of Options ................................................................................................................ 21
6.1
Assessment of Option A (1) ............................................................................................... 21
6.2
Assessment of Option B (2) ............................................................................................... 21
6.3
Assessment of Option C (5) ............................................................................................... 22
6.4
Assessment of Option D (8) ............................................................................................... 23
INFORMATION
6.5
Assessment of Option E (13) ............................................................................................. 23
6.6
Assessment of Option F (14) ............................................................................................. 23
7.
Conclusion and Recommendation ............................................................................................... 25
RELEASED
7.1
Conclusions ....................................................................................................................... 25
7.2
Recommendations ............................................................................................................. 25
7.3
Summary ............................................................................................................................ 26
8.
References ................................................................................................................................... 27
OFFICIAL
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | i
1.
Introduction
The East West Connections project is responding to the immediate and growing freight access
issues at either end of the Neilson Street/Church Street corridor caused by inefficient transport
connections and a lack of response to changes in the industry’s supply chain strategies. The
project is also addressing the inadequate quality of transport choices between Māngere,
Ōtāhuhu and Sylvia Park.
The long list of options was developed in a 2-stage process. The option identification process
began with identifying changes at a component level (e.g. lane widening; interchange
improvements) across the geographical area.
To ensure a full spectrum of components was considered, the study area was separated into
segments. All components were then assessed through a multi-criteria analysis. Where broadly
equivalent components (in terms of either transport performance or social, environmental or
cultural outcomes) were identified, the best alternative proceeded to the development of the
long list options. If no broadly equivalent alternative component existed, the component was
progressed to the development of long list options.
THE ACT
All options were assessed through a multi-criteria analysis, which considered a full range of
impacts and performance against the project’s objectives and the East West Connections
outcomes. Six options were identified to progress to the short list for the Onehunga-Penrose
connection. These options range from low investment to high investment.
These 6 options are the subject of this assessment and a detailed description of each are held
in the Detail Business Case. The following summarised descriptions have been used as the
UNDER
basis of the following assessment.
1.1
Shortlist Option Summary
1.1.1 Option A (Long List Option 1): Existing route upgrade
This option looks to upgrade the existing roads. This includes improving capacity on
INFORMATION
SH20, Neilson Street and Church Streets. It also provides freight lanes.
Auxiliary lanes / capacity improvements on SH20 (Queenstown Road to Gloucester Park)
Some widening of Onehunga Harbour Road at Gloucester Park (e.g. around the
RELEASED
Onehunga Port area, beneath SH20 and potential to increase this from 2 to 3 lanes up to
Neilson Street / Onehunga Mall intersection).
Upgrading of the intersection at Onehunga Mall / Neilson Street intersection (potentially
including widening of bridge over the rail line) to provide for dedicated movements
OFFICIAL
between Onehunga Mall / Neilson Street.
Capacity improvements on Neilson St, for example extending the 4-laning from Alford St
to Church St (potential impact on some road frontages, but looking to minimise)
New signalised intersection to provide access to Metroport (for example, providing for
dedicated turning median).
Cycleway uses Hugo Johnston Road (within the road corridor), may impact on tree
planting etc. in existing road reserve, will then connect to Church Street East and Great
South Road (level crossing) to connect to existing cycle path to Sylvia Park.
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 1
Freight lane priority at Mt Wellington Interchange where this can fit beneath existing
bridge constraints.
1.1.2 Option B (Long List Option 2): Upgrade with South Eastern Highway
Ramp
This option proposes an upgrade of existing roads with new ramp connections from Church
Street to SH1 and South Eastern Highway.
Auxiliary lanes / capacity improvements on SH20 (Queenstown Road to Gloucester
Park).
Some widening of Onehunga Harbour Road at Gloucester Park is likely (e.g. around the
Onehunga Port area, beneath SH20 and potential to increase this from 2 to 3 lanes up to
Neilson Street / Onehunga Mall intersection.
At Onehunga Mall / Neilson Street intersection, upgrading of intersection is required
(potentially including widening of bridge over the rail line) to provide for dedicated
movements between Onehunga Mall / Neilson Street.
Looking at capacity improvements on Neilson St, for example extending the 4-laning from
THE ACT
Alford St to Church St (potential impact on some road frontages, but looking to minimise).
New signalised intersections and upgrades to intersections at Metroport (for example:
providing for a dedicated turning median), Church St, Hugo Johnston Drive and Great
South Road (grade separation at Hugo Johnston Drive and Great South Road may be
considered).
Cycleway using Hugo Johnston Road (within the road corridor), may impact on tree
UNDER
planting etc. in existing road reserve, will then connect to Church Street East and Great
South Road (level crossing) to connect to existing cycle path to Sylvia Park.
New connections for ‘southern’ traffic on SH1, with ramps from the South Eastern Arterial
(looking at ramps of 2-lanes in each direction to connect from interchange to tie in with
SH1 at Mt Wellington). This requires an auxiliary lane extension on SH1 down to Princes
Street interchange.
INFORMATION
1.1.3 Option C (Long List Option 5): Upgrade with new Galway Street and
inland connections
This option proposes a new connection from Onehunga Harbour Road to Galway Street, and
RELEASED
upgrade of Neilson and Angle Streets and Sylvia Park Road, and a new connection for Angle
Street to Sylvia Park Road and to SH1.
Auxiliary lanes / capacity improvements on SH20 (Queenstown Road to Gloucester Park)
OFFICIAL
Some widening of Onehunga Harbour Road at Gloucester Park is likely (e.g. around the
Onehunga Port area, beneath SH20.
New connection from Onehunga Harbour Road onto Galway Street (may impact on traffic
movements / access to SH20 from Onehunga Mall / Onehunga Harbour Road)
4-lanes on Galway Street with upgraded intersection to Neilson Street, upgrading of
intersection required (potentially including widening of bridge over the rail line) and to
address increased traffic from Onehunga Mall to Galway Street.
Looking at capacity improvements on Neilson St, for example extending the 4-laning from
Alford St to Angle St and upgrading of Angle Street (e.g. up to 4-lane, which may require
some additional land).
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 2
New connection from Angle Street to Great South Road for between 2 and 4 lanes, and
where practicable on land between Transpower towers and foreshore (not reclamation).
At Sylvia Park Road, increasing capacity of some of Sylvia Park Road (e.g. additional
lanes) and may require land take and relocation of Transpower towers.
Ramps over Mt Wellington Highway to connect onto SH1, serving the south, with
increased capacity (e.g. auxiliary lanes) on SH1 down to Princes St.
Waikaraka Cycleway maintained and extended alongside new road sections to connect
to Sylvia Park.
1.1.4 Option D (Long List Option 8): Upgrade with Gloucester Park
interchange and new Galway St and inland connections.
This option proposes an upgrade at Gloucester Park Interchange and a new connection from
Onehunga Harbour Road to Galway Street. It also proposes an upgrade of Neilson and Angle
Streets and Sylvia Park Road, and a new connection for Angle Street to Sylvia Park Road and
to SH1.
Auxiliary lanes / capacity improvements on SH20 (Queenstown Road to Gloucester
THE ACT
Park).
New interchange at SH20 at Gloucester Park, to restrict access to Neilson Street and
divert all traffic onto Onehunga Harbour Road (widening requirements for Onehunga
Harbour Road, e.g. 3+ lanes).
New connection from Onehunga Harbour Road onto Galway Street (may impact on traffic
movements / access to SH20 from Onehunga Mall / Onehunga Harbour Road).
UNDER
4-lanes on Galway Street with upgraded intersection to Neilson Street, upgrading of
intersection required (potentially including widening of bridge over the rail line) and to
address increased traffic from Onehunga Mall to Galway Street.
Looking at capacity improvements on Neilson St, for example extending the 4-laning from
Alford St to Angle St and upgrading of Angle Street (e.g. up to 4-lane, which may require
INFORMATION
some additional land).
New connection from Angle Street to Great South Road for between 2 and 4 lanes, and
where practicable on land between Transpower towers and foreshore (not reclamation).
At Sylvia Park Road, increasing capacity of some of Sylvia Park Road (e.g. additional
RELEASED
lanes) and may require land take and relocation of Transpower towers.
Ramps over Mt Wellington Highway to connect onto SH1, serving the south, with
increased capacity (e.g. auxiliary lanes) on SH1 down to Princes St.
OFFICIAL
Waikaraka Cycleway maintained and extended alongside new road sections to connect
to Sylvia Park.
1.1.5 Option E (Long List Option 13): New foreshore Connection
This option proposes a new connection from SH20 to SH1 along the foreshore.
Auxiliary lanes / capacity improvements on SH20 (Queenstown Road to Gloucester
Park).
New interchange at SH20 at Gloucester Park, with access to Neilson Street and onto
Onehunga Harbour Road (may require some changes to traffic movements from
Onehunga Harbour Road onto SH20).
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 3
New connection from Gloucester Park along foreshore to Great South Road, with local
connections at Captain Springs Road, Southdown (Metroport) and Great South Road to
connect (via intersection) onto Vesty Drive.
New bridge from Vesty Road to provide new ramp connection to SH1 at Panama Road
(between businesses and residential areas).
New ramp connections at Panama Road (potentially requiring replacement of Panama
Road Bridge) with increased capacity (e.g. auxiliary lanes) on SH1 down to Princes St.
Waikaraka Cycleway maintained and extended alongside new road sections to Great
South Road and then onto alignment around Hamlin’s Hill.
1.1.6 Option F (Long List Option 14): New foreshore and inland connection
This option proposes a new connection form SH20 to SH1 (partly along the foreshore and partly
inland).
Auxiliary lanes / capacity improvements on SH20 (Queenstown Road to Gloucester
Park).
New interchange at SH20 at Gloucester Park, with access to Neilson Street and onto
THE ACT
Onehunga Harbour Road (may require some changes to traffic movements from
Onehunga Harbour Road onto SH20).
New connection from Gloucester Park along foreshore to Captain Springs Road and then
inland to Great South Road.
New intersections at Captain Springs Road, Southdown (Metroport) and Great South
Road (may require relocation of Transpower towers).
UNDER
At Sylvia Park Road, increasing capacity of some of Sylvia Park Road (e.g. additional
lanes) and may require land take and relocation of Transpower towers.
Ramps over Mt Wellington Highway to connect onto SH1, serving the south, with
increased capacity (e.g. auxiliary lanes) on SH1 down to Princes St.
Waikaraka Cycleway maintained and extended alongside new road sections to connect
INFORMATION
to Sylvia Park.
1.2
Purpose of this report
RELEASED
A high level geometric design of the 6 short-listed road corridor options (A – F) has been
undertaken. This design work was for the purposes of costing each option, and identifying
potential areas of risk with regards to consentability, constructability and cost.
In conjunction with the high level design, this Construction Erosion and Sediment Management
OFFICIAL
Assessment (CESMA) provides an overview assessment of the potential residual effects of
construction related erosion and sedimentation and provides an assessment of each option
against key relevant regulatory criteria including the Proposed Auckland Unitary Plan (PAUP).
This CESMA is to be used solely for the purpose of informing the selection selecting a preferred
option. Rather than focusing on particular details which have not yet been designed or
confirmed its purpose is to highlight the main issues with regards to erosion and sedimentation
for each option. This CESMA identifies the potential risks and mitigation measures that could be
adopted to manage and minimise these risks of construction related erosion and sedimentation.
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 4
There are a range of interrelated issues and effects between ecology (freshwater, terrestrial,
marine) and hydrology and stormwater management and treatment which are described in the
ecology and stormwater assessment reports.
The development of a quantitative assessment of the magnitude of the potential erosion and
sedimentation effects for each of the 6 options has not been carried out and it is anticipated that
the identification of any subsequent mitigation measures required will be the subject of further
detailed analysis to be carried out in subsequent work packages.
1.3
Assessment brief
The East West Connection environmental team requested this assessment report be provided
for use as a separate Appendix to the Detailed Business Case in the selection of a preferred
option which is the subject of this CESMA
The brief also includes the preparation of a Recommendation Letter that identifies the nature of
further technical investigations that are considered necessary to evaluate the preferred option.
This letter will identify opportunities to note going forward for the project, considering mitigation
and design considerations that may cross over into other disciplines.
THE ACT
1.4
Scope and Limitations
This CESMA has been prepared by GHD for the East West Connections Project and may only
be used and relied on by the NZ Transport Agency and Auckland Transport (AT) for the
purpose agreed between GHD and the East West Connections Project Team as set out above.
GHD otherwise disclaims responsibility to any person other than NZ Transport Agency and
Auckland Transport (AT) arising in connection with this assessment. GHD also excludes implied
UNDER
warranties and conditions, to the extent legally permissible.
If the NZ Transport Agency and Auckland Transport (AT) wish to provide this assessment to a
third party recipient to use and rely upon, then GHD’s prior written consent will be required.
Before this assessment is released to the third party recipient, the third party recipient will be
required to execute a GHD prepared deed poll under which the recipient agrees:
INFORMATION
to acknowledge that the basis on which this assessment may be relied upon is consistent
with the principles set out above; and
to the maximum extent permitted by law, GHD shall not have, and the recipient forever
releases GHD from, any liability to the recipient for loss or damage howsoever in
RELEASED
connection with, arising from or in respect of this assessment whether such liability arises
in contract, or tort (including negligence).
The services undertaken by GHD in connection with preparing this assessment were limited to
those specifically detailed above and are subject to the scope limitations stated.
OFFICIAL
The opinions, conclusions and any recommendations in this assessment are based on
conditions encountered and information reviewed at the date of preparation of the
CESMA. GHD has no responsibility or obligation to update this assessment to account for
events or changes occurring subsequent to the date that this document was prepared.
The opinions, conclusions and any recommendations in this CESMA are based on assumptions
described in this report. GHD disclaims liability arising from any of the assumptions being
incorrect.
GHD has prepared this CESMA based on the information provided by the NZ Transport Agency
and Auckland Transport (AT) and others who provided information to GHD (including
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 5
Government authorities), which GHD has not independently verified or checked beyond the
agreed scope of work. GHD does not accept liability in connection with such unverified
information, including errors and omissions in this CESMA report which were caused by errors
or omissions in that information.
2.
Methodology of the Assessment
This section outlines the general methodology followed in order to provide an indication of the
effects of erosion and sedimentation resulting from the construction of the 6 short-listed options
and sets out the context for our assessment.
The process undertaken for the current high level / conceptual design was as follows:
1.
Review the conceptual geometric design of each option and assess the erosion and
sediment control (ESC) measures required during the construction of the various
elements of each option.
2.
Determine the high level potential effects of erosion and sedimentation for the
construction of each option.
THE ACT
3.
Assess the effects of the construction of the project in relation to erosion and
sedimentation; and
4.
Identify the range of erosion and sediment control measures that could be used to reduce
the effects of erosion and sedimentation from the construction of the works.
Assessment of Route Options
UNDER
Drawings for the alignments of the 6 short-listed route options discussed in Sections 1.1.1 to
1.1.6 were reviewed.
Review of Technical Guidance documents
There are two main guidance documents applicable to this project as follows:
INFORMATION
1.
Auckland Regional Council, 1999 (updated 2007) ‘
Technical Publication 90 – Erosion and
Sediment Control: Guidelines for Land Disturbing Activities in the Auckland Region’
(TP90); and
2.
NZ Transport Agency, 2014, “Erosion and Sediment Control Guidelines for State
RELEASED
Highway Infrastructure”,
TP90 provides information on the appropriate use, design and construction of ESC devices and
practices for the Auckland region.
The Transport Agency guidelines are “ …
intended to provide the minimum requirement for
OFFICIAL
erosion and sediment control that state highway construction projects shall comply with.
Construction includes new construction and state highway maintenance projects. This guideline
has been prepared with the intention that it will meet or exceed current local erosion and
sediment control guidelines so that compliance with it will minimise consenting related issues. If
a local standard is amended and becomes more stringent than this Standard, the more stringent
requirements shall be met if required by resource consent”
Both TP90 and the Transport Agency’s guidelines are sufficient to develop appropriate erosion
and sediment control practices to mitigate against the potential effects of sedimentation
resulting from the construction of the final project. However, for the purposes of this assessment
we refer to TP90.
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 6
3.
Key Design Assumptions
The high level geometric design has been carried out for each option and this ESC assessment
is based on the following drawing sets.
3818683-1, 2, 5, 8, 13 and 14 – all Revision B Preliminary
This CESMA has adopted the alignments articulated in the Indicative Business Case EWC Long
List Summary, with the following key design amendments that have been adopted since then:
The alignments that follow the northen foreshore of the Mangere Inlet (Options E and F)
may be constructed on a new embankment separate from the foreshore and wick drains
could be used to dewater sediments
in situ beneath the embankment.
Option F has an inland alignment through the current MetroPort area.
We have assumed that the alignments that follow existing roads (including widening of
the road carriageway and intersection improvements) require only shallow (unsaturated
soil/rock) excavations.
The construction works for all Options only require temporary dewatering, not permanent
THE ACT
groundwater dewatering and the groundwater effects are assessed in the Groundwater
Assessment Report.
3.1
ESC Assessment Assumptions
1.
It should be noted that there are areas of risk that are not included in this assessment.
This is a consequence of the high level nature of the review and design work carried out
UNDER
to date.
2.
Calculations have not been carried out on the erosion potential and subsequent sediment
yields for each option as part of this assessment and hence the location and size of ESC
measures have not been assessed. It is anticipated that these will be carried out for the
preferred option at subsequent design phases of the project, including the work required
to support a full Assessment of Environmental Effects and lodgement of Resource
INFORMATION
Consent applications for the project.
3.
The ESC measures described in TP90, in its current form, are considered to be
appropriate for the management of erosion and sedimentation during construction works.
RELEASED
(It is noted that Auckland Council is currently in the process of updating a number of their
technical standards and design guidelines. The various ESC measures and design
standards associated with ESC may be change in any subsequent update or replacement
of TP90).
OFFICIAL
4.
The ESC measures discussed in this assessment are a combination of physical control
measures and good site / project management processes.
5.
The ESC assessment described in this assessment does not provide sufficient detail to
be used to establish a permanent or temporary construction designation for the preferred
option and additional design and assessment works will be required in subsequent
phases of the project.
3.2
Construction in Landfill Sites
It is anticipated that Construction across the landfills could comprise one of the following
methods, as stated in the Contaminated Land Assessment. However, from an ESC perspective
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 7
the effects can be managed through the implementation of appropriately design and
constructed ESC measures and through site management practices:
1.
Excavation of the refuse beneath the alignment prior to construction - Based on likely
depths to original harbour sediments, excavation may need to extend to 8 metres below
grade, although depths will be variable.
2.
Development at-grade or on-embankment – This would rely on ground improvement by
dynamic compaction or pre-loading. The primary effect of these techniques is upon
groundwater, because the compaction will cause transient discharges of contaminants
and a long-term reduction in the shallow aquifer (landfill) permeability that could cause
leachate breakouts upgradient from the alignment. Modelling these effects reliably would
be problematic. Similarly, the compaction would disturb the landfill gas equilibrium and
create unintentional gas migration.
3.
Construction on piles that extend to bedrock (either Waitemata series or basalt) - This
would require the removal of contaminated soil and groundwater from within the pile
caissons for off-site disposal, thereby benefiting the environment in relation to those
materials. Depending upon the spacing of the piles, effects on groundwater flow may be
ACT
limited because flow between the piles will be uninterrupted. Therefore, effects on
THE
groundwater quality could be managed to avoid leachate breakouts. Most of the refuse
volume in the landfill would remain undisturbed, which would also limit the effects on
landfill gas.
UNDER
INFORMATION
RELEASED
OFFICIAL
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 8
4.
Erosion and Sediment Control
Principles and Design Criteria
Erosion is a natural process and occurs when the surface of the land is worn away (eroded) by
the action of water, wind, ice or geological processes. Through the erosion process, soil
particles are dislodged, generally by rainfall and surface water flow. As rain falls, water droplets
concentrate and form small flows. As this flow moves down a slope, the combined energy of the
rain droplets and the concentration of flows has the potential to dislodge soil particles from the
surface of the land.
Sedimentation occurs when these soil particles are deposited. The amount of sediment
generated depends on the erodibility of the soil, the energy created by the intensity of the rain
event, the site conditions (for example the slope and the slope length) and the area of bare
earth or unstabilised ground open to rainfall.
During development works, that exposes areas of land, the erosion and sediment process is
accelerated and it is essential that effective erosion and sediment control measures are
THE ACT
provided during construction works to ensure minimal effect on the receiving environment.
4.1
Erosion Control versus Sediment Control
Erosion control is based on the practical prevention of sediment generation in the first instance.
If erosion control measures and practices are effective then sediment generation will be
minimised and the primary reliance on the sediment control measures is reduced.
Sediment control refers to management of the sediment after it has been generated (eroded). It
UNDER
is inevitable that some sediment will be generated through land disturbance activities even with
best practice erosion control measures in place. Sediment control measures are designed to
capture this sediment to minimise any resultant sediment-laden discharges to waterways.
Rather than primarily relying on sediment control measures, reducing erosion will have the
direct effect of reducing sediment generation and therefore less sediment laden runoff will need
INFORMATION
to be intercepted, treated and discharged from the sediment control measures.
Typically, land with steep slopes and long slope lengths generate a greater amount of energy
for rainfall and hence increase erosion. Any reduction of this energy through the use of erosion
control measures will reduce erosion and hence any subsequent sedimentation.
RELEASED
4.1.1 General principles and management techniques
During construction of the preferred option, ESC should be undertaken and implemented with a
hierarchy and priority order as follows:
OFFICIAL
1.
Prevention: Excluding clean water runoff from entering the active work areas, therefore
preventing clean water runoff from combining with excavated spoil and/or construction
material and can be achieved through the use of clean water diversion (CWD) channels
and/or bunds to divert runoff from the upstream side of the work area.
2.
Capture: Any sediment laden runoff generated within the working area can be captured
through the use of dirty water diversion (DWD) channels and/or bunds on the
downstream side of the construction site which are used to direct silt laden runoff from
the site to an appropriate sediment control device. Sediment capture could be
implemented through the use of one or more sediment control measures.
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 9
3.
Minimisation: Limiting the length of time and the area of disturbed soil is exposed to
wind and rainfall can reduce the erosion potential to generate erosion. Timely stabilisation
of exposed areas and the construction of impermeable areas can also reduce the
potential for erosion to occur.
4.
Staging and Sequencing of Works: Construction activity could be carried out in stages
and works within those stages could be sequenced not only to enable the permanent
works to be constructed efficiently but to also manage erosion and sedimentation. It is
anticipated that working areas will be progressively stabilised to prevent erosion as
appropriate as the works progress.
4.1.2 Streamworks general principles
Construction works within or adjacent to existing streams are generally considered to be a
higher risk than earthwork activities due to the close vicinity of the receiving environment and
the associated increased potential for sediment yield. Construction within streams should be
undertaken in a manner that recognises this risk and the sensitivity of the receiving
environment.
Where practical, streamworks activities and any associated works within these environments
THE ACT
should be undertaken in an ‘offline’ environment and allow for the temporary diversion of flows
around the area of works or working immediately next to the stream with no formal stream
diversion required.
It is anticipated that streamworks are to be restricted or controlled to avoid the fish spawning
and migration periods (September to February) or where this cannot occur then fish relocation
methodologies will be developed and implemented.
UNDER
Where such work needs to be undertaken during the main migration period, the section of
stream in which the work is to be carried out is to be isolated (stop-nets at each end of the
works section) and any resident fish caught and relocated within the stream. The lower stop-net
should be retained to prevent any fish entering the works area.
4.1.3 ESC Measures and Design Criteria
INFORMATION
Table 1 summarises the main ESC principles and design criteria which would be anticipated to
apply to this project. :
Table 1 - ESC Measures and Design Criteria
RELEASED
Device /
Criteria
Methodology
Erosion Control Measures
OFFICIAL
Clean Water Diversions
Clean water diversion channels and bunds are to be designed and
(CWD)
implemented in accordance with TP90.
Construction Staging
Staging and sequencing are both important management measures
and Sequencing
and will be implemented as necessary to reduce the amount of
exposed earth during construction and should be considered at
design stages of the project.
Contour Drains
Where required, Contour drains are to designed and implemented in
accordance with TP90.
Device Location
All ESC devices should be located outside the 20 year ARI flood
level unless no other viable alternative exists.
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 10
Device /
Criteria
Methodology
Dirty Water Diversions
Dirty water runoff diversion channels and bunds are to be designed
(DWD)
and implemented in accordance with TP90.
Pipe Drop Structures /
Flumes will be used in accordance with the TP 90 to safely transfer
Flumes
runoff from the top of batters to the bottom of the batter slopes to
prevent erosion of the batter surface during rainfall events.
Rock Check Dams
Where required, rock check dams be placed in all CWDs and DWDs
and will be designed and implemented in accordance with TP90.
Stabilisation for Erosion
Progressive and rapid stabilisation of disturbed areas utilising top soil
and Dust Management
(where necessary) and seed, mulch and geotextiles will be ongoing
Purposes
throughout the Project. Stabilisation will be undertaken to:
Minimise any open areas or disturbed earth which may be
specified within future consent conditions for the project; and
Reduce the open area locations to assist with a reduction in
sediment generation.
THE ACT
Stabilised Entrance
Stabilised entrance ways are to be established at all ingress and
Ways
egress points of the site.
Sediment Control Measures
Construction Stage
CESCPs or similar are to be submitted prior to commencement of
Erosion and Sediment
work.
Control Plans
CESCPs will likely include:
UNDER
(CESCPs)
Contour information;
A list of proposed ESCs;
Chemical treatment design and details;
Catchment boundaries;
Location of the Work;
INFORMATION
Details of construction methods;
Contingency measures;
Design details;
RELEASED
A programme for managing non-stabilised areas;
The identification staff who will manage ESCs – Including
inspection, operation and maintenance during construction
and any close down times outside of the normal “earthworks”
season;
OFFICIAL The identification of staff who monitor compliance with
conditions;
A chain of responsibility for managing environmental issues;
Methods and procedures for decommissioning measures;
and
Reporting and reactive procedures for the management and
clean up in the event of the accidental discharge of sediment
or other contaminants.
Container Impoundment Container Impoundment Systems will be used where necessary and
Systems
will be sized based on the catchment size and as such will generally
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 11
Device /
Criteria
Methodology
apply to smaller catchment areas. Their primary use would be during
the initial earthworks in steep or “difficult” locations prior to the
formation of a SRP or DEB structure.
Decanting Earth Bunds
Where required, DEBs and decant systems are to be designed and
(DEBs) and Decant
implemented in accordance with TP90
Systems
Decommissioning of
Removal of devices will be in accordance with the CESCP.
Devices
Flocculation
Where considered appropriate, based on local soils conditions and
the sensitivity of the receiving environment to sediment deposition,
flocculation may be applied to SRPs and DEBs to assist in the
reduction of sediment discharged to the receiving environment.
Non-Structural
These elements could include:
Measures
Manually raised decant devices on SRPs and DEBs;
ACT
Batch dosing of SRPs and DEBs with chemical flocculant
THE
where required;
Proactive monitoring and reporting programme
Risk identification and management accordingly;
Progressive stabilisation as works progress; and
Weather
response.
Pumping Activities
Pumping of sediment laden runoff and groundwater during
UNDER
construction should be to SRPs, DEBs to grass buffer zones or to
temporary sediment retention devices such as Container
Impoundment Systems.
Sediment Retention
Where required, SRPs are to be designed and implemented in
Ponds
accordance with TP90..
Streamworks
At all practical times these activities, and any associated works within
INFORMATION
these environments will be undertaken in an offline ‘dry’ environment.
Construction during fish spawning and migration periods will be
assessed and managed accordingly.
Super Silt Fences and
All super silt fences and silt fences are to be designed and
RELEASED
Silt Fences
implemented in accordance with TP90.
Through the design and construction phases of the Project, it is recognised that there will be
scope for innovation and alternative means of achieving the same environmental outcome as
may be specified in any future consent conditions.
OFFICIAL
It is recommended that ESC measures are planned during the detailed design phase of the
Project and constructed and maintained during construction.
These principles and practices will also be further detailed and designed within site specific
Construction Stage Erosion and Sediment Control Plans (CESCPs).
4.1.4 Construction Stage Erosion and Sediment Control Plans
The implementation of CESCPs will allow for further innovation, flexibility and practicality of
approach to erosion and sediment control and in doing so will allow the construction of the
Project to continually adapt to changing construction and climatic conditions.
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 12
CESCPs shall be submitted prior to commencement of work and will likely include a range of
data and other information such as:
Contour
information;
A list of proposed ESCs;
Chemical treatment design and details;
Catchment
boundaries;
Location
of
the
Work;
Details of construction methods;
Contingency
measures;
Design
details;
A programme for managing non-stabilised areas;
The identification staff who will manage ESCs;
The identification of staff who monitor compliance with conditions;
THE ACT
A chain of responsibility for managing environmental issues;
Methods and procedures for decommissioning measures; and
Reporting and reactive procedures for the management and clean up in the event of the
accidental discharge of sediment or other contaminants.
UNDER
INFORMATION
RELEASED
OFFICIAL
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 13
5.
Recommended mitigation required
Prior to construction commencing it is expected that CESCPs will be prepared by the contractor
appointed to undertake the construction of the works.
The CESCPs will take into account the various environmental and ecological values within the
natural environment in order to determine the most effective and appropriate form of ESC
devices and management practices required to manage erosion and sedimentation during the
construction of the project.
The options considered range from predominantly using existing road corridors to providing new
roads across existing industrial land to new roads on embankment adjacent to the existing
foreshore. The use of existing road corridors would limit the extent of exposed earth, thereby
reducing the erosion potential of the construction works and hence would require a lesser
degree of ESC than a new road across existing green fields for example and this would have
implications for construction costs, which are outside the scope of this assessment.
5.1
Anticipated Erosion Protection Measures
THE ACT
ESC measures that are anticipated to be applicable to the construction stage of the project are
expected to be a range of physical measures and site management practices as described
below.
5.1.1 Construction Staging and Sequencing
The extent of exposed soil and length of time that area is exposed has a direct influence on the
sediment yield leaving a particular area of the site. Bulk earthworks and construction activities
UNDER
should be staged and sequenced in order to limit the area of exposed soil required to complete
an element of the work. Open earthworks areas need to progressively stabilised to reduce the
potential for erosion to occur. It is possible that an open area limit may be adopted during
construction as a control measure in this regard.
5.1.2 Clean and Dirty Water Diversions (CWD and DWD)
INFORMATION
CWDs provide for the controlled conveyance of stormwater runoff and could be used on the
Project to prevent run on water from the undisturbed catchment areas above the works from
entering the construction area.
RELEASED
Where required, CWDs need to be designed in accordance with TP90 to ensure that the works
are sufficiently protected from flows from the natural catchment outside of the works.
DWDs transfer sediment laden water to sediment retention devices for treatment within the
construction areas. They are effectively a conveyance device and as with the CWDs need to be
OFFICIAL
designed in accordance with TP90.
CWDs need to be fully stabilised with either vegetation or geotextile cloth. DWDs could also be
stabilised but this would be dependent upon soil type for the specific area of works.
A maintenance programme should be implemented during construction activity to remove the
sediment deposited within the DWDs. During construction, excavated pits or sumps could also
be used and could be positioned at regular intervals.
5.1.3 Contour Drains
Contour drains are temporary ridges or excavated channels or a combination of the two that are
constructed to convey water across a slope at a minimum gradient. They reduce the slope
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 14
length and therefore the velocity of water flowing down disturbed slopes and hence reduce the
erosive power of construction runoff.
5.1.4 Rock Check Dams
Check dams are small dams made of rock or other non-erodible material constructed across a
swale or channel to act as a control structure. The purpose of a check dam is to reduce the
velocity of flow within the channel and prevent scour of the channel surface. Check dams also
allow for some settlement of suspended solids within the channel.
5.1.5 Stabilisation for Erosion and Dust Management Purposes
Stabilisation of exposed earth is a key element of erosion protection and could include a
combination of the placement of mulching, geotextile and the use of hard fill material.
Progressive and rapid stabilisation of disturbed areas should be ongoing throughout the
construction of the project. Stabilisation will particularly apply at stockpile areas and batter
establishment to reduce both erosion and dust generation.
Mulch is typically applied to slopes of less than 15 degrees, above which alternatives such as
geotextile should be considered. The development of the CESCPs will need to determine the
THE ACT
specifics of this stabilisation technique and timing.
Stabilisation will be undertaken with three key purposes:
To achieve any open area limitations that may be specified within consent conditions for
the project;
To reduce the open areas of disturbed earth in higher risk locations to assist with a
UNDER
reduction in sediment generation; and
In response to the adaptive monitoring programme to address any potential effects or
undesirable monitoring trends.
5.1.6 Pipe Drop Structure / Flume
Temporary pipe drop structures or flumes are constructed to convey construction runoff down a
INFORMATION
slope face without causing erosion of the slope and are generally used to prevent scour of the
batters.
5.1.7 Stabilised Construction Entrance Way
RELEASED
Stabilised Construction Entrance Ways are a stabilised pad of aggregate placed on a filter base
and are located where construction traffic enters or exits a construction site. They help to
prevent site entry and exit points from becoming a source of sediment and also help to reduce
dust generation and disturbance along public roads.
OFFICIAL
Alternatively wheel washes could be placed to ensure, that no vehicles leave a construction site
and enter public spaces unless tyres are clean and vehicles do not contribute to sediment
deposition on public road surfaces.
5.2
Anticipated Sediment Protection Measures
Sediment control during construction involves the interception and treatment of sediment-laden
runoff from the various construction areas along the Project and should be carried out in
accordance with the guidelines contained in TP90.
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 15
Sediment control will be established through the use of recognised sediment control measures
and site management practices. Sediment control devices will need to be located outside the 20
year ARI flood level, unless no other viable alternative exists. If sediment control devices are
required within the 20 year ARI flood level, they should be designed to capture the minimum
catchment area and should be subjected to an increased inspection and maintenance regime.
The general sediment control measures and principles that may be used on the Project could
be as follows:
5.2.1 Sediment Retention Pond (SRP)
Where required, SRPs should be designed and constructed in accordance with TP90 and are
generally designed to receive the flows from the upstream catchment during a 100 year ARI rain
event. They are designed with a minimum 3% volume criterion applied in relationship to
catchment size (i.e. 300 m3 SRP volume per 10000 m2 or 1 ha of contributing catchment).
SRP spillways are to be designed and constructed to ensure that they safely pass the 100 year
ARI rain event with low velocity, which will reduce the risk of scour on the downstream side of
the spillway.
ACT
Forebays of SRPs need to be established and designed to capture the majority of the sediment
THE
entering the SRP. Any sediment that is not captured within the forebay area will be transferred
into the main body of the SRP and will be captured through the provision of baffles within the
SRP itself.
Prior to the construction of SRPs it will be necessary to:
Check ground conditions through the use of bore holes and undertake a geotechnical
assessment of the proposed SRP site;
UNDER
Determine the need or otherwise for a shear key establishment; and
Remove any unsuitable material and confirm ground conditions as appropriate for SRP
establishment.
5.2.2 Decanting Earth Bund (DEB)
INFORMATION
Decanting earth bunds (DEB) are temporary berms or ridges of compacted soil, which are
constructed to create impoundment areas where ponding of sediment-laden runoff can occur
and which provide time for suspended solids to settle out before the runoff is discharged to the
receiving environment.
RELEASED
DEBs should be designed and constructed in accordance with TP90.
All spillways from the DEBs are to be designed and constructed to safely pass the 100 year ARI
rain event with low velocity and therefore minimal scour potential.
OFFICIAL
5.2.3 Pumping Activities
All SRPs and DEBs should be fitted with floating decants with a mechanism to control outflow
such as a manual decant pulley system to be used during pumping activities to these structures.
Wherever possible, gravity flow will be used rather than pumping. Where decants are manually
plugged, they should only be lowered once an acceptable standard of discharge quality can be
achieved. The pumping rates and volumes to SRPs and DEBs will be designed for the total
pump volume to be fully captured within the SRP or DEB.
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 16
Further pumping will also be required with associated activities such as bridge construction.
Pumping flows to SRPs and DEBs ensures that any sediment laden flows are discharged to a
treatment device prior to entering the receiving environment.
5.2.4 Container Impoundment Systems
In locations where SRPs or DEBs cannot be located due to slope, room constraints or instability
issues, container impoundment systems will be used. These are retrofitted with a decant system
and will also be subject to chemical flocculation.
It is expected that these systems will be used primarily in the early stages of earthworks for
small catchment areas before it is possible to construct SRP structures.
5.2.5 Super Silt Fence (SSF)
Super silt fences are fabric fences reinforced with stakes and netting backing to allow a physical
barrier to flows leaving the area of earthworks without passing through the SSF. Their design
and placement will be based upon the criteria contained within TP90. SSFs will be used in those
areas of work adjacent to, or in the immediate vicinity of watercourses.
As a risk management tool for SSFs the fabric will be installed with a minimum 200mm of fabric
THE ACT
placed upslope at the base of the trench.
5.2.6 Flocculation
Flocculation is a chemical treatment method for increasing the retention of suspended solids
from construction earthworks runoff in SRPs and DEBs where chemical flocculant is added to
the construction runoff flowing into a SRP or DEB via a rainfall activated system (flocculant
UNDER
shed) or via manual batch dosing.
The use of flocculation chemicals increases the efficiency of SRPs and DEBs and reduces the
amount of sediment discharged to the receiving environment (sediment yield).
Where considered appropriate, depending on soil conditions, SRPs and DEBs will be
chemically treated with a flocculant appropriate for the soil type and discharge location.
INFORMATION
5.3
Other Measures
5.3.1 Permanent Stormwater Devices
RELEASED
The Project will also include the installation of a number of permanent stormwater treatment
wetlands and swales for permanent stormwater treatment from impervious surfaces.
Where practical, permanent stormwater treatment and detention devices should be installed
early in the Project.
OFFICIAL
Where the location of a SRP coincides with a permanent stormwater treatment wetland, the
wetland will be used on a temporary basis as a SRP. These will be converted to long term
stormwater wetland features at the completion of the earthworks activity within that sub-
catchment.
No existing natural wetlands will be used for primary treatment of sediment-laden runoff from
the construction phase.
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 17
5.3.2 CESCPs
CESCPs are detailed erosion and sediment control plans which will be submitted for specific
work areas or activities within the site. They will provide the detailed design, specific ESC
measure location, staging and sequencing of works for that location.
The CESCPs will be developed prior to construction works commencing and will determine
specific measures to be employed in particular areas.
5.3.3 Contaminated Land
The Contaminated Land Assessment for the project identifies the presence of a number of
landfill sites through the project study area. Any future erosion and sediment control measures
proposed will need to take cognisance and reference the recommendations and requirements of
any future Contaminated Land Management Plan (CLMP). The provisions of a CLMP .can be
incorporated into the CESCPs for the relevant areas of the project.
5.3.4 Decommissioning of Devices
All ESC measures will remain in place until such a time as the catchment contributing to that
device is stabilised. Once the contributing catchment is considered stabilised the particular ESC
THE ACT
measure can be decommissioned. The decision process and procedure for this will be outlined
within the CESCPs.
5.4
Non-sediment contaminants
There are a range of non-sediment contaminants typically used during construction activity and
these generally consist of materials that may directly or indirectly discharge into the receiving
UNDER
environment from site activity.
Non-sediment contaminants that are typically used in construction activity are listed in Table
Table 2:
Table 2 – Typical Non-Sediment Contaminants
Potential
Indicator
Non-Visible Potential
INFORMATION
Product /
Contaminants
Contaminants
Work
Activity
Adhesives
Adhesives
Oily sheen or
Phenols
RELEASED
Glues
discoloration
Formaldehydes
from some
Resins
Asbestos
products
Epoxy
Volatile Solvents and
PVC
Cement
Naphthalene
OFFICIAL
Asphalt Paving
Hot and Cold Mix
Oil Sheen
Oil, petroleum distillates,
Asphalt
Poly aromatic
hydrocarbons
Cleaning Products
Cleaners, ammonia, lye,
Discolouration
Acidity / alkalinity
caustic sodas, bleaching
agents, chromate salts
Concrete
Cement
Discolouration
Alkalinity (High pH)
Flocculants
Specific to Flocculant
Clarity
Aluminium
toxicity
used but can include pH
pH
and aluminium
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 18
Potential
Indicator
Non-Visible Potential
Product /
Contaminants
Contaminants
Work
Activity
Sanitary Waste
Portable Toilets,
Discolouration, Bacteria, Biological
disturbance of sewer
sanitary waste
Oxygen Demand,
lines
Pathogens
Vehicle and
Equipment operation,
Oil sheen,
Hydrocarbons and
Equipment Use
maintenance, washing,
sediment
coolants
refuelling
5.4.1 Storage and Management of Non-Sediment Contaminants
The management of these non-sediment contaminants will be subject to specific best
management practice and industry guidelines.
It is currently unclear as to the specific nature of these non-sediment contaminants and the
associated volumes however Table 3 provides some generic guidance as to the expected
management approach.
THE ACT
Table 3 – Non-Sediment Contaminant Management Approach
Product / Work Activity
Management Approach
Adhesives
Store materials in an area that is not subject to rainfall
contact
UNDER
Use adhesives carefully and clean up any spilled
material
Properly dispose of containers once they are empty
Asphalt Paving
Water runoff should discharge to a treatment system
designed to capture hydrocarbons
INFORMATION
Cleaning Products
Store materials in an area that is not subject to rainfall
contact
Use adhesives carefully and clean up any spilled
material
Properly dispose of containers once they are empty
RELEASED
Concrete
Concrete truck chutes, pumps and internals should only
be washed out into the formed areas awaiting
installation of concrete
Unused concrete remaining in trucks shall be returned to
OFFICIAL the concrete batching plant
Hand tools should only be washed out into the formed
areas awaiting installation of concrete
Flocculants
Ensure the use of flocculants follows an approved
flocculant management plan and industry best practice.
Regularly measure pH of the discharge from sediment
retention devices.
Sanitary Waste
Avoid knocking over portable toilets
Place portable toilets away from site vehicle movement
areas
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 19
Product / Work Activity
Management Approach
Service portable toilets regularly
Empty portable toilets before they are moved.
Avoid breaking sanitary sewer lines that may exist on
site
Vehicle and Equipment Use
Fuel storage tanks shall be bunded to store a minimum
of 100% of the tank’s capacity. Note that for this project
no bulk fuel storage is expected and mobile refuelling
will occur.
Procedures and practices shall be put in place to
minimise or eliminate the discharge of lubricants,
coolants or hydraulic fluids to the receiving environment
Have spill prevention and control measures and
procedures in place
THE ACT
UNDER
INFORMATION
RELEASED
OFFICIAL
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 20
6.
Assessment of Options
There are 6 options currently being assessed in the current phase of the project. The options
share similarities, particularly from an erosion and sediment control perspective. The proposed
alignments traverse the same catchment areas and runoff generated by both existing and
proposed surfaces generally discharge to the same receiving environments – ultimately the
Manukau Harbour, Mangere Inlet, or Otahuhu Creek.
6.1
Assessment of Option A
The effects of Option A on the environment are relatively minor with regard to erosion and
sediment control as the majority of this option utilises the existing road corridors. There will be
limited soil disturbance.
As discussed in the Contaminated Land Assessment there is the potential that shallow soil
within the road corridor could be contaminated from adjacent HAIL sites and as a result it is
anticipated that excavated soil would be removed from site in sealed truck and trailer units, to
be disposed of at a licensed tip facility.
THE ACT
The construction constraints, whilst working within an existing road corridor results in the extent
of exposed earth, that has the potential to become eroded during rainfall events, being
minimised and with implementation of appropriate construction staging and site management
practices during construction, it is not expected that significant sediment would be generated.
Whilst considered to be a secondary form of ESC, the placement of catchpit protection, such as
filter cloths and filter socks would also assist in the capture of sediment laden runoff from the
site prior to its discharge to the existing, and proposed stormwater reticulation system and
UNDER
subsequently the receiving environment.
There are works proposed to provide auxiliary traffic lanes on State Highway 20 which are
within the existing road designation near to the Coastal Marine Area (CMA). From an erosion
and sediment control perspective effective robust ESC measures would need to be provided,
such as staging of the works to reduce the erosion potential of any exposed earth along with
INFORMATION
appropriately designed and constructed sediment retention ponds capture any generated
sediment, dosing the SRP with chemical flocculant may be required to increase the efficiency of
the SRP and reduce sediment yields discharged to the marine environment.
Specific management measures should be developed as part of the CESCP production to
RELEASED
include the handling or treatment of any contaminated soil areas. This would also be included in
a Contaminated Land Management Plan (CLMP).
6.2
Assessment of Option B
OFFICIAL
As with Option A above, the effects of Option B on the environment are considered to be
relatively minor with regard to erosion and sediment control as the majority of this option utilises
the existing road corridors and as with option A there will be limited soil disturbance.
As with options A, there is also the potential that shallow soil within the road corridor could be
contaminated from adjacent HAIL sites, and the ESC measures required would be similar to
option A.
As with Option A , there are works proposed to provide auxiliary traffic lanes on State Highway
20 which are near to the Coastal Marine Area (CMA). From an erosion and sediment control
perspective effective robust ESC measures would need to be provided, such as staging of the
works to reduce the erosion potential of any exposed earth along with appropriately designed
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 21
and constructed sediment controls to capture any generated sediment, dosing the sediment
controls in the case of SRPS and DEBs with chemical flocculant may be required to increase
the efficiency of the SRP and reduce sediment yields discharged to the marine environment.
Specific management measures should be developed as part of the CESCP production to
include the handling or treatment of any contaminated soils areas. This would also be included
in a Contaminated Land Management Plan (CLMP).
6.3
Assessment of Option C
The effects of Option C on the environment in relation to erosion and sediment control are
relatively minor, but will depend on the construction method adopted for the sections of
carriageway that cross the existing closed landfills of Pikes Point East and the NZ Rail Fill Site
and the new connection from Onehunga Harbour Road onto Galway Street where the alignment
adopts a route through the Galway Street landfill. These are discussed in more detail in the
Contaminated Land Assessment.
At the Gloucester interchange the alignment utilises roads that skirt the periphery of the
Gloucester Reserve, and along Nielsen Street the alignment skirts the Pikes Point West landfill.
THE ACT
Further east the alignment also crosses areas around the former Southdown freezing works
including Southdown reserve and industrial sites where asbestos is prevalent in soil.
At 36 and 38 Miami Parade, the alignment skirts to the south of the former Dominion Oil
Refinery which has a discharge to ground and groundwater.
Specific ESC measures would need to be developed and any recommendations provided in the
CLMP would need to be incorporated and considered in any CESCP prior to construction
commencing.
UNDER
The management of stormwater runoff would need to be considered carefully so as to prevent
any exposed refuse, and potentially leachate, from the landfills from becoming mobilised during
rainfall events.
Depending on the volume of stormwater runoff generated during, it may be possible to construct
SRPs in the vicinity to collect stormwater runoff from the landfill areas to allow any sediment to
INFORMATION
settle out and then pump collected stormwater to the nearest wastewater manhole.
If leachate contaminated stormwater is generated and pumped to the wastewater system,
approval would be needed from Watercare and the downstream wastewater system would need
RELEASED
to be analysed to ensure it has sufficient capacity to receive pumped stormwater flows without
impacting on the downstream system. Alternatively, on site treatment will be required or sucker
trucks will need to be utilised to collect contaminated stormwater for off-site treatment and
disposal.
SRPs would need to be isolated from the landfill material through the use of an impermeable
OFFICIAL
layer (such as a clay liner or impermeable synthetic membrane).
Ongoing and consistent weather monitoring would be required so that effective planning of
construction activities could be carried out along with any required stabilisation of exposed earth
along the route.
There are works proposed to provide auxiliary traffic lanes on State Highway 20 which are near
to the Coastal Marine Area (CMA). From an erosion and sediment control perspective effective
robust ESC measures would need to be provided, such as staging of the works to reduce the
erosion potential of any exposed earth along with appropriately designed and constructed
sediment retention ponds capture any generated sediment, dosing the SRP with chemical
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 22
flocculant may be required to increase the efficiency of the SRP and reduce sediment yields
discharged to the marine environment.
6.4
Assessment of Option D
This Option is the same as for Option C, with additional works in the Gloucester Reserve to
provide the upgrade at Gloucester Park Interchange. The alignment across Gloucester Reserve
introduces an increased risk of encountering landfill material in this area. Otherwise, the
assessment of contaminated land effects for Option D is the same as for Option C (including the
considerations regarding construction techniques through the landfills).
6.5
Assessment of Option E
The alignment of Option E was influenced by the geotechnical, hydrogeological and
contaminated land considerations and the design response was to provide for a new
embankment separate from the existing foreshore, so that this option does not impinge upon
the landfills and the existing leachate interception trench and as such works are proposed within
the Coastal Marine Area (CMA).
THE ACT
From an erosion and sediment control perspective, effective robust ESC measures would need
to be provided, such as staging of the works to reduce the erosion potential of any exposed
earth and to minimise the disturbance of the marine muds along the proposed embankment.
For the landside works appropriately designed and constructed sediment retention ponds to
capture any generated sediment and dosing the SRP with chemical flocculant may be required
to increase the efficiency of the SRP and reduce sediment yields discharged to the marine
environment.
UNDER
Access would be required within the CMA to facilitate the construction of the proposed bridge
piers between the eastern end of the proposed embankment and Ann’s Creek.
The construction of the bridge foundations and piers could potentially mobilise marine sediment
at each location and a detailed construction methodology would need to be developed and
incorporated within the CESCPs for the works.
INFORMATION
This option also includes the Gloucester Reserve considerations, and also extends across
industrial land to the east of Ann’s Creek. Most of the eastern industrial zone is relatively recent
(post 1990’s) with the exception of the Westfield Freezing Works and Westfield Chemical
Fertiliser Works.
RELEASED
Works within the contaminated land areas of this option would be subject to the provisions and
requirements set out in a future CLMP.
Overall, the potential effects of this Option on the environment with respect to erosion and
OFFICIAL
sediment control are considered to be minor and further mitigation and ESC measures may be
required.
6.6
Assessment of Option F
As with Option E, the alignment of Option F was influenced by the geotechnical,
hydrogeological and contaminated land considerations and a new embankment within the
separate from the existing foreshore is proposed along the western part of the Mangere Inlet.
On the eastern side of the Mangere Inlet the alignment crosses Pikes Point landfill and the NZ
Rail fill sites.
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 23
From an erosion and sediment control perspective effective robust ESC measures would need
to be provided, such as staging of the works to reduce the erosion potential of any exposed
earth and to minimise the disturbance of the marine muds along the proposed embankment.
For the landside works appropriately designed and constructed sediment retention ponds to
capture any generated sediment and dosing the SRP with chemical flocculant may be required
to increase the efficiency of the SRP and reduce sediment yields discharged to the marine
environment. SRPs would need to be isolated from the landfill material through the use of an
impermeable layer (such as a clay liner or impermeable synthetic membrane).
The construction of the bridge foundations and piers could potentially mobilise marine sediment
at each location and a detailed construction methodology would need to be developed and
incorporated within the CESCPs for the works.
The eastern sector crosses the Pikes point East landfill and NZ Railways fill area. The
alignment also encompasses Miami Parade and according to the contamination assessment
runs adjacent to the HAIL sites in that area and within the contaminated land areas of this
option would be subject to the provisions and requirements set out in a future CLMP.
As with Option E, the potential effects of Option F on the environment with respect to erosion
THE ACT
and sediment control are considered to be minor and further mitigation and ESC measures may
be required.
UNDER
INFORMATION
RELEASED
OFFICIAL
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 24
7.
Conclusion and Recommendation
7.1
Conclusions
1.
We have carried out a high level assessment of environmental effects that relate to
erosion and sediment control based on a high level geometric design of the 6 short-listed
options. We have identified ESC measures that can potentially be implemented to avoid,
remedy and mitigate possible environmental effects that are a consequence of the project
options and the results of this assessment are summarised below:
i)
Options A and B appear to have the least potential to cause adverse residual effects in
relation to erosion and sedimentation and would be the preferred options from an ESC
perspective;
ii) Options C and D require works within existing known landfill sites and careful
consideration of the construction methodology will be required. However from an ESC
perspective, with appropriate ESC measures and following the requirements of any CLMP
the effects on the receiving environment would be considered minor; and
THE ACT
iii) Options E and F appear to have the most potential for adverse effects on the Marine
Environment requiring engineered fill to be placed to form the proposed embankment
along the foreshore within contaminated marine sediments. Depending on the final design
these options may also require bridge supports and foundations to be constructed with the
marine environment.
2.
We note that this is a high level assessment with detailed analysis of earthworks volumes
and the locations of construction accesses and haul roads not yet being developed it is
UNDER
not possible at this stage to determine the sediment yields that would be discharged to
the receiving environment. However, it is considered that with the implementation of a
range of ESC measures in place, as described in Section 5; then the overall residual
environmental effects that relate to the project’s management of erosion and
sedimentation are likely to be less than minor for Options A and B) and minor for Options
C, D E and F.
INFORMATION
3.
The sensitivity of the receiving environment is assessed in the Ecology Assessment and
to a large extent the existing environment is degraded and modified.
4.
The potential water quality effects can largely be mitigated by the placement of
RELEASED
appropriate ESCs and through the implementation of robust site management practices
and construction methodologies.
7.2
Recommendations
OFFICIAL
Undertake a comprehensive quantitative assessment of the magnitude of the environmental
effects that relating to erosion and sedimentation and confirm the subsequent required
measures needed to minimise these effects. To do this the project requires further detailed
analysis as follows:
1.
Confirm the design proposals and construction methods for the various elements of the
preferred option;
2.
Develop a conceptual construction sequence on the preferred option and include as a
minimum:
i)
A conceptual programme of works
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 25
ii) A mass haul diagram to identify where fill material will be cut from and will be placed along
the route alignment
iii) A construction methodology for each element of the works, including excavations,
construction of structure including culverts, bridges and viaducts
iv) The location of haul roads, construction yards and compounds.
3.
Undertake a hydrological assessment to determine and confirm the extent of the
stormwater catchments and flows;
4.
Assess and quantify the key areas of risk not be included in this assessment;
5.
Determine discharge locations for the construction related stormwater runoff, in order to
determine the most appropriate form of ESC to be provided prior to discharging to the
receiving environment.
6.
Assess existing ecological and environmental values along the route to determine the
most appropriate method of ESC, which may also include limiting the extent of open
earthworks;
7.
Undertake a more detailed level of design to determine the alignment’s designation
THE ACT
requirements for the construction and operational phases of the project;
8.
Determine the overland flowpath locations so as to determine the size, extent and
discharge location of any clean water diversions required to prevent run-on water from
entering active work areas.
9.
Develop Erosion and Sediment Control Plans (ESCPs) as part of the design process and
are expected to be required as part of any required resource consent application process
UNDER
and appropriately detailed ESCP will be needed to inform the Assessment of
Environmental Effects and determine any temporary construction related designations
that may be required.
7.3
Summary
The following key points are noted for the management of erosion and sediment for the
INFORMATION
preferred option.
A range of ESC measures would be required for all options, however the scale and
complexity of the required ESC measures depends on a range of factors such as the
extent of exposed earth; the staging of the construction works; the movement of imported
RELEASED
and excavated fill material; the time of year the works are carried out etc.
Where possible permanent stormwater quality devices should be used during
construction for the capture of sediment, such as siting SRPs in the same locations as
permanent constructed wetlands, placing CWD and DWDs in the same locations as
OFFICIAL
permanent swales etc.
ESC measures not only rely on the appropriate design and placement of physical controls
but also require rigorous site management practices to be implemented during
construction.
ESCPs shall be prepared during the detailed design stage. The ESCP will rely on the
preparation of the construction stage ESCPs (CESCP) which will allow for contractor
input into the preparation and management of the site from an ESC perspective.
The options range in scale in terms of complexity of construction and as such a range of erosion
and sedimentation effects are to be expected.
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 26
Both TP90 and the Transport Agency guideline documents place emphasis on a number of
principles that apply to the prevention of erosion and interception of sediment generated and
thereby reducing any sediment discharging to the receiving environment.
There will be constraints on construction working room to facilitate the construction of sections
for some of the proposed options; and particularly for the options involving works within the
existing road network. This can been seen as both a positive and negative scenario in relation
to erosion and sedimentation, as firstly it would place a limit on the exposed areas of earth and
hence reduce the erosion potential of the works, but conversely space is limited for the ESC
measures. However, with the implementation of appropriately designed, constructed and
maintained ESC measures in place, in combination with effective site management processes it
is considered the effects of erosion and sedimentation would be minor.
As noted in the Contaminated Land Assessment the presence of a number of landfill sites could
represent a major constraint for construction and they also pose the greatest environmental
risks. From an erosion and sediment control perspective, the adoption of a piled construction
through the landfill areas would be preferred as this reduces the extent of any excavation
required and subsequent potential for erosion to occur during rainfall events.
On the basis of existing information provided to undertake this assessment, from an ESC
THE ACT
perspective Options A and B would be preferred.
However, the preferred Option should be selected on the basis of network performance and
overall objectives of the project, provided that the alignment either avoids known landfills or
adopts a construction method that minimises effects on the environment.
8.
References
UNDER
1.
Auckland Regional Council, 1999 (updated 2007) ‘
Technical Publication 90 – Erosion and
Sediment Control: Guidelines for Land Disturbing Activities in the Auckland Region’
(TP90); and
2.
NZ Transport Agency, 2014, “Erosion and Sediment Control Guidelines for State
INFORMATION
Highway Infrastructure”,
3.
Auckland Council GIS
4.
East West Connections Project - 6 Shortlisted Conceptual Design Drawings
RELEASED
OFFICIAL
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 27
THE ACT
UNDER
GHD
Level 3, 27 Napier Street
INFORMATION
Freemans Bay
T: 64 9 370 8000 F: 64 9 370 8001 E: [email address]
© GHD Limited 2014
RELEASED
This document is and shall remain the property of GHD. The document may only be used for the
purpose for which it was commissioned and in accordance with the Terms of Engagement for the
commission. Unauthorised use of this document in any form whatsoever is prohibited.
C:\Users\ACain2\AppData\Local\Microsoft\Windows\Temporary Internet
Files\Content.Outlook\HNY12ICS\GHD - Erosion and Sediment Control Phase III Assessment
OFFICIAL
EWC_draft 2 Oct 2014.docx
Document Status
Rev Author Reviewer
Approved
for
Issue
No.
Name Signature
Name Signature
Date
3 Tony Murray
Murray
04/11/2014
Cain
Wallis
Wallis
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 28
THE ACT
UNDER
www.ghd.com
INFORMATION
RELEASED
OFFICIAL
GHD | Report for NZ Transport Agency and Auckland Transport - East West Connections Project, 51/32651/ | 29