This is an HTML version of an attachment to the Official Information request 'LGOIMA Request for Environmental Impact Assessments Related to Lake Rotokākahi'.


Monthly Report 8 
Months Ending: 31st  December 2023 and 31st January 
2024 
Tarawera Sewerage Scheme 
Construction – Stage 1 
Document Set ID: 20240890
Version: 1, Version Date: 04/04/2024














 
Contract No. RLC Contract No. 22/038 
Contract Name: Tarawera Sewerage Scheme:  
Construction – Stage 1 
 
Table of Contents 

 
1.  Executive Summary ........................................................................................... 3 
2.  Health & Safety .................................................................................................. 3 
  General Comments .................................................................................... 3 
  Incident & Near Miss Summary .................................................................. 3 
3.  Environmental .................................................................................................... 4 
  General Comments .................................................................................... 4 
  Interaction with Regional Council ................................................................ 5 
4.  Quality ................................................................................................................ 5 
  General Comments .................................................................................... 5 
  Compliment/Complaints/Progress .............................................................. 5 
  Recent Non-conformances ......................................................................... 5 
5.  Programme and Progress .................................................................................. 5 
  General Comments .................................................................................... 5 
  Achievements ............................................................................................. 5 
6.  Delays ................................................................................................................ 5 
7.  Design Issues..................................................................................................... 6 
8.  Stakeholder Engagement ................................................................................... 6 
  General Comments .................................................................................... 6 
  Cultural Engagement/Accidental Discoveries ............................................. 6 
9.  Financials: .......................................................................................................... 6 
10.  Contract Corrospondence .................................................................................. 6 
11.  Procurement & SUBCONTRACTS ..................................................................... 7 
  Procurement Status .................................................................................... 7 
Appendix A: Programme ............................................................................................ 8 
Appendix B: Progress Claim & Supporting Information .............................................. 9 
Appendix C: Correspondence Register .................................................................... 10 
Appendix D: Project Dashboard ............................................................................... 11 
Appendix E: Site Photos .......................................................................................... 12 
Appendix F: Site Weather Records .......................................................................... 16 
 
 
Document ID: FHLIB-
1677224255-21616 
This is an uncontrolled copy if photocopied or printed from the Intranet. 
Version: 7.0 
Copyright © 2024, Fulton Hogan Ltd. Al  rights reserved. 
Page 2 of 17 
Document Set ID: 20240890
 
Version: 1, Version Date: 04/04/2024




 
Contract No. RLC Contract No. 22/038 
Contract Name: Tarawera Sewerage Scheme:  
Construction – Stage 1 
 
1.  EXECUTIVE SUMMARY 
The required outcome of the implementation of the Tarawera Scheme is the safe collection and conveyance of 
wastewater from properties within the Area of Benefit to the Rotorua Wastewater Treatment Plant, via a connection 
into the existing Rotorua sewerage network. The Tarawera Scheme will comprise of LPGP units instal ed on each 
property within the Area of Benefit, connected to low pressure mains, and a trunk main to the agreed connection 
point of the existing network at the junction of Okareka Loop Road and Tarawera Road. The scope of this contract 
covers Stage 1 of the construction works, being the construction of the reticulation network, trunk main and pump 
stations. The LPGP units and connection of properties to the network wil  be delivered under a separate Stage 2 
contract.  
 
The work to be carried out under Stage 1 comprises the supply, construction, instal ation and commissioning, including 
civil, mechanical and electrical aspects, of: 
•  The low-pressure gravity street mains and property laterals including installation of and connection to each Boundary 
Assembly, and al  associated works, including any required valves, flush points, scour points, chambers, culvert 
crossings, bridge crossings, road crossings, and all associated pipelines and fit ings. 
•  The trunk main connecting the Area of Benefit to the Rotorua wastewater network and all associated works, including 
any required valves, flush points, scour points, chambers, culvert crossings, bridge crossings, road crossings, and all 
associated pipelines and fit ings. 
•  The three new pump stations and all associated works (two transfer stations and one booster station), including but 
not limited to earthworks, wet wel , valve chamber, flow meter chamber, pipework, valves, odour filter (if required), 
concrete works, crash bar ier, fencing and electrical works. 
•  Installation of mains feed cables from Unison-supplied point of connection to each pump station electrical cabinet, 
testing and livening of such.  
2.  HEALTH & SAFETY 
 General Comments 
  Very busy sites with a lot of teams working in the final push prior to Christmas – working long hours on site in hot 
conditions. 
  Regular breaks and hydration needed to assist with fatigue management.  
  Additional crews brought in to help out with the work load prior to Christmas to ensure that excavations where 
closed up and al  TTM could be removed over the Christmas shutdown period 
  Heavy TTM presence with additional traf ic management to assist with the high number of visitors at the Blue Lake 
and pedestrians on the walking track as wel  as the multiple events that are occuring 
  Ongoing commitment to deliver our Leadership Safety Actions which require our leadership staf  to have safety 
related conversations with our staf  throughout the month. Some examples of last months items are: 
  Fatigue 
  Heat Stress and Hydration 
  Working near pedestrians 
  Protest action occurring regarding the works past Lake Rotokakahi started in Late January 
  Additional measures being put in place to protect workers on site 
  Police Involvement following incident on site where worker has been threatened  
  Incidents with vehicles intentional y ignoring traf ic management in place, driving into oncoming traf ic and 
running over traf ic management equipment 
 Incident & Near Miss Summary 
Please see outlined below our incident and near miss summary report for the previous month: 
 
Document ID: FHLIB-
1677224255-21616 
This is an uncontrolled copy if photocopied or printed from the Intranet. 
Published:8/05/2023 
Version: 7.0 
Copyright © 2024, Fulton Hogan Ltd. Al  rights reserved. 
Page 3 of 17 
Document Set ID: 20240890
 
Version: 1, Version Date: 04/04/2024


Document Set ID: 20240890
Version: 1, Version Date: 04/04/2024


Document Set ID: 20240890
Version: 1, Version Date: 04/04/2024




Contract No. RLC Contract No. 22/038 
Contract Name: Tarawera Sewerage Scheme: 
Construction – Stage 1 
 Initial establishment, service location and preliminary works at Cliff Rd delayed due to neighbouring resident blocking
access to the site
 Protest action at Lake Rotokakahi – second dril ing crew disestablished until an agreement has been made for our
workers safety.  Drilling crews having to remove all equipment from site each day which is reducing the daily
productivity. Additional testing having to be completed to check that pipe work has not been sabotaged
7. DESIGN ISSUES
 Working drawings for both the Fire Station and Transfer Station pumping stations currently underway
8. STAKEHOLDER ENGAGEMENT
 General Comments 
 Interactions continuing with residents as works occur outside of their property should access be af ected.
 Road Closure instal ed on Cliff Rd – resident access maintained
 Very high number of wide loads coming through the site over the summer months. The narrow road environment
is creating chal enges with being able to get these loads through with us having to in some cases completely shut
down the site and remove all our equipment for them to fit through.
 Protest action occurring at Lake Rotokakahi
 Cultural Engagement/Accidental Discoveries 
 No interaction with cultural team over the previous month
 Accidental discovery process in place
 Works stopped and process followed for a possible discovery which was investigated and identified as
bovine
 FH Site inductions continuing to provide information around the accidental discovery protocols and what to look
for
9. FINANCIALS:
Please find attached with this report the progress claim for the period ending 31st January ‘23 – Appendix B 
10. CONTRACT CORROSPONDENCE
Please refer to NTE/NTC attached with this report - Appendix C. 
Document ID: FHLIB-
1677224255-21616 
This is an uncontrolled copy if photocopied or printed from the Intranet. 
Published:8/05/2023 
Version: 7.0 
Copyright © 2024, Fulton Hogan Ltd. Al  rights reserved. 
Page 6 of 17 
Document Set ID: 20240890
Version: 1, Version Date: 04/04/2024


Document Set ID: 20240890
Version: 1, Version Date: 04/04/2024


 
Contract No. RLC Contract No. 22/038 
Contract Name: Tarawera Sewerage Scheme:  
Construction – Stage 1 
 
Appendix A: Programme 
 
 
Document ID: FHLIB-
1677224255-21616 
This is an uncontrolled copy if photocopied or printed from the Intranet. 
Published:8/05/2023 
Version: 7.0 
Copyright © 2024, Fulton Hogan Ltd. Al  rights reserved. 
Page 8 of 17 
Document Set ID: 20240890
 
Version: 1, Version Date: 04/04/2024


Document Set ID: 20240890
Version: 1, Version Date: 04/04/2024


 
Contract No. RLC Contract No. 22/038 
Contract Name: Tarawera Sewerage Scheme:  
Construction – Stage 1 
 
Appendix B: Progress Claim & Supporting Information 
 
 
Document ID: FHLIB-
1677224255-21616 
This is an uncontrolled copy if photocopied or printed from the Intranet. 
Published:8/05/2023 
Version: 7.0 
Copyright © 2024, Fulton Hogan Ltd. Al  rights reserved. 
Page 9 of 17 
Document Set ID: 20240890
 
Version: 1, Version Date: 04/04/2024


 
Contract No. RLC Contract No. 22/038 
Contract Name: Tarawera Sewerage Scheme:  
Construction – Stage 1 
 
Appendix C: Correspondence Register 
 
 
Document ID: FHLIB-
1677224255-21616 
This is an uncontrolled copy if photocopied or printed from the Intranet. 
Published:8/05/2023 
Version: 7.0 
Copyright © 2024, Fulton Hogan Ltd. Al  rights reserved. 
Page 10 of 17 
Document Set ID: 20240890
 
Version: 1, Version Date: 04/04/2024


 
Contract No. RLC Contract No. 22/038 
Contract Name: Tarawera Sewerage Scheme:  
Construction – Stage 1 
 
Appendix D: Project Dashboard 
 
 
Document ID: FHLIB-
1677224255-21616 
This is an uncontrolled copy if photocopied or printed from the Intranet. 
Published:8/05/2023 
Version: 7.0 
Copyright © 2024, Fulton Hogan Ltd. Al  rights reserved. 
Page 11 of 17 
Document Set ID: 20240890
 
Version: 1, Version Date: 04/04/2024


Document Set ID: 20240890
Version: 1, Version Date: 04/04/2024


Document Set ID: 20240890
Version: 1, Version Date: 04/04/2024



 
Contract No. RLC Contract No. 22/038 
Contract Name: Tarawera Sewerage Scheme:  
Construction – Stage 1 
 
Appendix E: Site Photos 
 
 
Valve Assembley  
 
Document ID: FHLIB-
1677224255-21616 
This is an uncontrolled copy if photocopied or printed from the Intranet. 
Published:8/05/2023 
Version: 7.0 
Copyright © 2024, Fulton Hogan Ltd. Al  rights reserved. 
Page 12 of 17 
Document Set ID: 20240890
 
Version: 1, Version Date: 04/04/2024



 
Contract No. RLC Contract No. 22/038 
Contract Name: Tarawera Sewerage Scheme:  
Construction – Stage 1 
 
 
 
Wet Well Excavation in Progress 
 
Document ID: FHLIB-
1677224255-21616 
This is an uncontrolled copy if photocopied or printed from the Intranet. 
Published:8/05/2023 
Version: 7.0 
Copyright © 2024, Fulton Hogan Ltd. Al  rights reserved. 
Page 13 of 17 
Document Set ID: 20240890
 
Version: 1, Version Date: 04/04/2024



 
Contract No. RLC Contract No. 22/038 
Contract Name: Tarawera Sewerage Scheme:  
Construction – Stage 1 
 
 
 
Unknown Chorus discovered whilst removing earth bund for pumpstation 
 
 
 
 
 
 
Document ID: FHLIB-
1677224255-21616 
This is an uncontrolled copy if photocopied or printed from the Intranet. 
Published:8/05/2023 
Version: 7.0 
Copyright © 2024, Fulton Hogan Ltd. Al  rights reserved. 
Page 14 of 17 
Document Set ID: 20240890
 
Version: 1, Version Date: 04/04/2024



 
Contract No. RLC Contract No. 22/038 
Contract Name: Tarawera Sewerage Scheme:  
Construction – Stage 1 
 
 
 
 
Valves being bolted together 
 
 
 
 
Document ID: FHLIB-
1677224255-21616 
This is an uncontrolled copy if photocopied or printed from the Intranet. 
Published:8/05/2023 
Version: 7.0 
Copyright © 2024, Fulton Hogan Ltd. Al  rights reserved. 
Page 15 of 17 
Document Set ID: 20240890
 
Version: 1, Version Date: 04/04/2024



 
Contract No. RLC Contract No. 22/038 
Contract Name: Tarawera Sewerage Scheme:  
Construction – Stage 1 
 
Appendix F: Site Weather Records 
 
 
 
 
Document ID: FHLIB-
1677224255-21616 
This is an uncontrolled copy if photocopied or printed from the Intranet. 
Published:8/05/2023 
Version: 7.0 
Copyright © 2024, Fulton Hogan Ltd. Al  rights reserved. 
Page 16 of 17 
Document Set ID: 20240890
 
Version: 1, Version Date: 04/04/2024



 
Contract No. RLC Contract No. 22/038 
Contract Name: Tarawera Sewerage Scheme:  
Construction – Stage 1 
 
 
 
 
 
 
 
 
 
Document ID: FHLIB-
1677224255-21616 
This is an uncontrolled copy if photocopied or printed from the Intranet. 
Published:8/05/2023 
Version: 7.0 
Copyright © 2024, Fulton Hogan Ltd. Al  rights reserved. 
Page 17 of 17 
Document Set ID: 20240890
 
Version: 1, Version Date: 04/04/2024