This is an HTML version of an attachment to the Official Information request 'Sustainability initiatives'.

Business Case – Medium complexity V18 
 
 
Project information 
 
Project name 
Albany Pools - install solar panels 
Sentient ID# 
36482 
Programme name 
PRG Energy Ef iciency and Sustainability 
Programme Sentient 
27039 
ID # 
Project complexity 
 
rating (PCAT) 
Author and date 
Deena Benjamin 
Project budget 
$376570.00 
requested and funding 
source(s) 
Estimated start and 
29/Apr/2022 
finish date 
03/Mar/2023 
 
Document control 
<Text in grey boxes or <> provides commentary and guidance for drafting purposes only and should 
be deleted when no longer required.> 
 
Document history 

Version 
Date 
Updated by 
Update details 
 
 
 
 
 
 
 
 
 
Strategic case (Case for change) 
Introduction  
Background 
This is the first project being undertaken using Project Gigawatt funding. 
Project Gigawatt developed out of a desire from within Council to explore 
how solar and battery technology could be used to minimise energy 
usage within Community Facilities and demonstrate Council’s 
commitment to sustainability and its low carbon action plan. • 

closed Request for Proposal was issued to three known suppliers of solar 
photovoltaic (PV) arrays, all of whom responded to the RFP. After 
evaluation and discussions, we recommended awarding the contract to 
Reid Technology Limited for a contract value of $362,263.65, plus a 10% 
contingency. James Brown from Stellar is the PM looking after this 
project. 
 
Opportunity/problem 
Give evidence-based facts (where possible) for the problem/opportunity 
to demonstrate current state, what problem is to be addressed and what 
would happen if we were to continue status quo.  
Please consider: 
- Consider user feedback by consulting with service providers 
- Park Services may undertake a service assessment if necessary. 
Typically for buildings this has been conducted as part of a wider 
assessment on service levels and the growth areas throughout the city 
have been considered. PSR should be consulted with to determine if any 
strategic or service assessments have been done. 
- To cater for growth. 
- Most local boards have networks plans which have an initial review of 
1 | P a g e  
Business Case  – Medium complexity   
 
 
 


Business Case – Medium complexity V18 
 
 
Introduction  
the provision in the area and proposed high level options for the identified 
gaps. This is essentially a strategic review. 
- To maintain the service level through renewal. 
 
Objectives 
To increase energy efficiency in a more sustainable way for the 
environment 
To save money long-term on electricity 
 
 
 
- Use of safe methodologies. Ensure work is accomplished keeping into 
account safe methodologies this could include removal of asbestos, 
seismic improvements, etc., health and safety of public/staff/workers is 
important to consider, ensure methodologies are robust and safe in 
design. 
 
- Improved whole of life costing. This means considering how many years 
is it going to last, including maintenance costs, i.e., building wash, etc.  
 
- Ensure sustainability. Consider using sustainable products of ering 
higher lifetime, carbon free specs, environmental friendly, better UV 
protection, bet er degradation, etc.] 
 
High level benefits 
Increased electricity generation in the Auckland Region giving improved 
energy resilience. 
Carbon Footprint reduction 
Alignment to strategy: 
Auckland Plan Outcomes 
Our Strategy Goals 
 
 
Climate Priorities 
Māori Outcomes 
Built environment 
No specific outcome focus areas 
Describe the strategic linkage in more detail here: 
 
 
 
 
Climate change 
Project management and decision-making to consider the reduction of 
(adaptation and 
GHG emissions through sourcing of low-carbon material options and use 
mitigation): 
of products with environmental declarations for embodied carbon 
 
reductions. Consideration should be given to minimise waste from existing 
components through recycling and aiming for maximum diversion from 
landfill. 
 
Māori outcomes and   
engagement  
Alignment to existing  <Describe any alignment or link to an existing programme/s of work> 
programmes:  
Constraints 
Constraints: In planning and delivering the work, there are some general 
environmental and/or site-specific constraints that require due 
considerations.  
Some examples are:  
- Building occupants/tenants  
- Weather conditions 
2 | P a g e  
Business Case  – Medium complexity   
 
 
 


Business Case – Medium complexity V18 
 
 
- Current operation of the premises - make sure you liaise and 
communicate with building occupier/tenants. You may require them to shut 
their operations during their peak business. 
- There is a risk that the pool roof cannot take the weight of the solar 
panels. This risk is considered to be low as the building was intended to 
have solar panels, but these were cut from the build project due to budget 
constraints. A structural assessment wil  be undertaken as part of the 
project. 
-If the grid is congested with generation Vector may require grid 
strengthening in the area before agreeing to have distributed generation 
connected to their electricity network. The risk of this is low as there is a 
large electrical supply to the building. A distributed generation (DG) 
application wil  be lodged with Vector before the design is finalised. 
-The equipment wil  need to be shipped to New Zealand. Supply chain 
constraints may cause delays. 
 
Further requirements should be discussed with the relevant Design 
principal. Refer to Practice notes for further detail on constraints and how 
to manage them. 
Dependencies 
- Adequate budget 
- Structural surveys 
Assumptions 
-The roof is checked to ensure it can take the weight of the solar panel 
prior to installation. 
- Budget is adequate 
- Consents are non-notified and approved 
- Stakeholders and Governing body are informed 
- Programme of works for the project is manageable  
 
Health, safety and 
 
wellbeing 
[Edit as required: 
At Auckland Council, we put the health and safety of our people and the 
people of Auckland first. We empower everyone working across the 
council family to stop work and speak out if they see unsafe work 
practices. 
As part of the due diligence process, it is important to regularly monitor 
and audit the work site(s) using iAuditor, to ensure that all the safety 
controls that are discussed and agreed to in meetings or written into 
documentations are put in place and checked to operate effectively. 
 
- Ensure contractor provides Site-Specific Safety Plan (SSSP) and it is 
reviewed and approved by project manager. Al  projects must have a 
Safety in Design report and register. It is recommended this be attached to 
the front page of the design/professional services document 
- Council has an obligation to provide accessible and inclusive assets 
- Accessible and inclusive considerations include: 
- Providing accessible or mobility impaired access 
- Ensure fire egress and emergency evacuation processes  
- Removing uneven surfaces and trip hazards (e.g. signage etc) 
- Ensure methodology and oversee impact on staff/public.  
- Working on heights, working on edges, working on roof or confined space 
etc.  
- Ask for SSSP and site audit plan. 
- Some of the H&S related risks to people and users wil  only be possible 
to mitigate by scheduling the work i.e. doing the work after hours or closing 
the facility which wil  all have budget implications and critical to consider at 
3 | P a g e  
Business Case  – Medium complexity   
 
 
 


Business Case – Medium complexity V18 
 
 
the time of setting the budget] 
High level risks and 
Unsuitable ground conditions, unidentified closed landfil s or other below 
issues 
ground issues not allowed for in project planning 
Closed landfills and arboricultural works require asset owner approvals 
(AOAs). They often required significant timeframes to be reviewed and 
granted. 
Damage during construction to works and equipment. Damage after 
construction to the asset. Includes high winds, tornadoes, heavy rain, slips 
and king tides etc. 
Stakeholders not consulted on proposed design or informed of project 
progression, including physical works timeframes 
Issues with neighbours complaining about the park, works or operations. 
Errors, mistakes, broken plant, lack of resource etc. 
Always a risk on major construction projects. Common injuries and deaths 
are falling from height, impact with vehicles and heavy lifting. 
Clubs, users and leaseholders are required to meet the consent conditions 
once operating 
Example: Covid 19 has resulted in work stoppages, increased costs, lack 
of resources, il ness and material shipment delays 
Differing political opinions and expectations can lead to major delays and 
cost increases i.e. for additional security due to protestors 
Usergroups and park bookings teams need to be kept up to date with the 
programme of work. 
Possible scope creep pressure from future users, stakeholders and 
politicians 
Heavy vehicles moving on and off site, general public vehicles. 
Common to many construction projects trenching is prone to collapse 
without warning 
Children may be out of the immediate reach of their parents and are prone 
to irrational and dangerous behaviour. Both design and construction 
methodology need to consider this risk. 
Consequence: Potential injury or death. 
Cause: Inadequate design or errors during the design process. Design 
does not consider all elements of safety in design for the given site, 
situation, user group or environment. 
Consequence: Injury 
 
Economic case (Determing value for money) 
In Scope 
To install a Solar Photovoltaic (PV) array on the roof of Albany Stadium Pool. The proposed solution 
from Reid Technology Limited is a 206.8 kilowatt peak (kWp) system made up of 440 solar modules. 
It is expected the system wil  generate approximately 335,900 kWh of electricity per year. 
 
Out of scope 
Anything unrelated to the solar panels 
 
Service change assessment 
  Service / process description  Proposed change & impact 
Will this initiative cause a 
 
change to a service or process 
e.g. adding an additional 
service, changing or removing 
4 | P a g e  
Business Case  – Medium complexity   
 
 
 


Business Case – Medium complexity V18 
 
 
an existing service? 
 
Outline options analysis  
<To make an informed decision, what options have been researched to demonstrate we are getting 
value for money for the investment? How do the options stack up against each other?> 
  Option 
Description 
<Option 1> 
 
<Option 2> 
 
<Option 3-5 etc.> 
 
 
Description     (click here for CBA 
Option 1: Do 
Option 2: 
Option 3: 
Option 4: 
worksheet) 
nothing 
Appraisal period (years) 
 
 
 
 
Implementation cost ($000) 
 
 
 
 
Whole of life cost ($000) (ongoing 
 
 
 
 
consequential opex, disposal cost, plus 
implementation cost) 
Cost Benefit analysis: 
Financial benefits and costs (excluding depreciation) 
Net present value of benefits ($000) 
 
 
 
 
Net present value of costs (whole of life) 
 
 
 
 
($000) 
Net present value ($000) 
 
 
 
 
Non-financial benefits 
Benefit 1 
 
 
 
 
Benefit 2 
 
 
 
 
Benefit 3 
 
 
 
 
  Preferred option 
<Highlight the rationale or compelling reasons for preferring one option over others. Along with the 
above analysis there may be other considerations that have resulted in the preferred option such as 
time to deliver, risk, climate impact etc> 
 
 
 
Benefits tables 
<The Benefits Library is a guide which can be used to assist with completing the financial benefits 
and non-financial benefits tables below. Please contact the EPMO if you require additional 
assistance> 
 Benefits and dis-benefits  
 
Category  Sub-
Type 
Metric 
Benefit statement  Benefit 
Benefit 
Source of  Baseline 
Expecte
category 
Description 
Measure and  data or 
d benefit 
Method 
cost 
and 
centre/GL 
date(s) 
code 
 
Non-
 
 
 
Increased electricity 
Increased 
Electricity 
 
 
TOTAL 
financial 
generation in the 
electricity 
Invoices as well   
 
 
Auckland Region 
generation in 
as the ESP 
 
 
giving improved 
the Auckland 
monitoring 
 
energy resilience. 
Region giving 
 
 
improved 
energy 
resilience. 
 
5 | P a g e  
Business Case  – Medium complexity   
 
 
 


Business Case – Medium complexity V18 
 
 
Benefit owner & Role 
Santosh Puthran 
Benefit Reporter 
Sentient Admin 
 
*Note: If there are additional benefits, add extra rows, with a Benefit owner signature line after each 
benefit. 
  Non-quantifiable Benefits and additional information 
 
 
 
Commercial case (Procurement of preferred option) 
Detailing the procurement strategy 
 
[Edit as required: 
- Design services wil  be procured via the professional service Master Service Agreement (MSA) 
procurement panel unless alternative procurement can be justified and approved by the panel 
manager. 
- Physical works procurement process in CF currently stipulates the Full Facilities Maintenance 
(FFM) supplier for the area associated with should be included within the supplier selection 
depending on the value. The remaining suppliers should be selected upon consultation with 
experienced the Design Principal and procurement staff. 
- Bulk tenders and amalgamation should be considered when timing and efficiency warrants. 
However depending on the number of projects single tenders may also be let. PMs should consult 
with the Design principals and/or Area Managers. 
- Weighted attributes should be considered or contractors asked to submit resource list, current 
projects, and programme if a non-conforming tender is chosen. 
- Health and Safety should be given a high priority, and at tender stage worker competency 
assessed, including for example current Heavy Transport (HT) licensing for drivers, other relevent 
tickets and plant experience. 
- Site works and equipment installation can be tendered separately or under a main contractor. Either 
contract must have the equipment supplier responsible for the equipment installation to keep the 
compliance liability with the manufacturer. 
- Build and equipment suppliers should be selected upon consultation with experienced The Design 
principal and procurement staff. 
- Defects period: recommended to be 12 months  
- For sensitive sites and high value projects, weighted attributes are useful for ensuring the contractor 
has relevant previous experience., product warranty generally 5 years, feel free to discuss with 
Design Team] 
 
 
6 | P a g e  
Business Case  – Medium complexity   
 
 
 


Business Case – Medium complexity V18 
 
 
Risk Description 
Mitigation 
Date 
Owner 
Idenfitied 
Unsuitable ground conditions, 
Ensure design follows NZ 
24/08/2022   
unidentified closed landfil s or 
ground investigation 
other below ground issues not  specification at a minimum. 
allowed for in project planning 
Closed landfills and 
Ideally have AOAs approved 
24/08/2022   
arboricultural works require 
the year before physical works 
asset owner approvals (AOAs).  is scheduled to begin consider 
They often required significant  processing times of 6 months 
timeframes to be reviewed and  or more. 
granted. 
Damage during construction to  Careful planning of work and 
24/08/2022   
works and equipment. Damage  consideration of weather 
after construction to the asset.  impacts 
Includes high winds, 
tornadoes, heavy rain, slips 
and king tides etc. 
Stakeholders not consulted on  Share and seek feedback from  24/08/2022   
proposed design or informed of  key stakeholders to ensure the 
project progression, including 
design is fit for purpose and 
physical works timeframes 
meets users expectations] 
Issues with neighbours 
Adhere to resource consent 
24/08/2022   
complaining about the park, 
conditions - keep neighbours 
works or operations. 
informed 
Errors, mistakes, broken plant,  Adhere to best practice at all 
24/08/2022   
lack of resource etc. 
times. Competitive 
procurement process, 
selecting only the best value 
contractors contract. Strict 
adherence to programme and 
quality plans 
Always a risk on major 
Ensure Health and safety is 
24/08/2022   
construction projects. Common  the number 1 priority - adhere 
injuries and deaths are falling 
to best practice on site - follow 
from height, impact with 
all Council Process - regular 
vehicles and heavy lifting. 
audits. 
Clubs, users and leaseholders  Community Services to 
24/08/2022   
are required to meet the 
monitor and control 
consent conditions once 
operating 
Example: Covid 19 has 
Sufficent planning, 
24/08/2022   
resulted in work stoppages, 
contingency, contract 
increased costs, lack of 
managment and safety 
resources, il ness and material  planning. 
shipment delays 
Differing political opinions and  Allow sufficient contingency for  24/08/2022   
expectations can lead to major  politically sensitive projects 
delays and cost increases i.e. 
for additional security due to 
protestors 
7 | P a g e  
Business Case  – Medium complexity   
 
 
 


Business Case – Medium complexity V18 
 
 
Usergroups and park bookings  Ensure assets are booked out  24/08/2022   
teams need to be kept up to 
or otherwise allocated for the 
date with the programme of 
duration of the works. 
work. 
Possible scope creep pressure  Limit scope to that specified in  24/08/2022   
from future users, stakeholders  this business case 
and politicians 
Heavy vehicles moving on and  TMPs and safety audits. 
24/08/2022   
off site, general public 
vehicles. 
Common to many construction  Follow Worksafe best practice  24/08/2022   
projects trenching is prone to 
including benching and shoring 
collapse without warning 
of works 
Children may be out of the 
Isolate. Engineering Control 
24/08/2022   
immediate reach of their 
parents and are prone to 
irrational and dangerous 
behaviour. Both design and 
construction methodology 
need to consider this risk. 
Consequence: Potential injury 
or death. 
Cause: Inadequate design or 
Follow Master Service 
24/08/2022   
errors during the design 
Agreement (MSA) panel and/or 
process. Design does not 
approved procurement 
consider all elements of safety  processes for professional 
in design for the given site, 
services. Ensure Safety in 
situation, user group or 
Design is included within the 
environment. 
scope of work. Ensure all 
Consequence: Injury 
adequate indemnity insurances 
are in place. 
 
 
 
 
Issue Description 
Resolution  
Resolution  Owner 
Date 
 
 
 
 
 
Financial case (Affordability & funding) 
Financial analysis 
Please complete the financial 
FY 2022 
FY 2023 
FY 2024 
FY 2025 
FY 2026-28 
Total 
analysis spreadsheet and use the 
output to complete this table 
Capital expenditure 
 
 
 
 
 
 
Operating expenditure 
 
 
 
 
 
 
Total expenditure 
 
 
 
 
 
 
Consequential operating expenditure 
 
 
 
 
 
 
Financial benefits (revenue/cost 
 
 
 
 
 
 
reduction) 
Net ongoing cost 
 
 
 
 
 
 
<Please attach the financial analysis spreadsheet as an appendice.> 
 
Financial sources 
<Specifically, how is this initiative being funded i.e. is part of it from existing BAU? New or additional funding 
request or LTP allocated funds? Is there any other external party funding involved? Are other departments 
within council also contributing a portion from their own BAU budget? 

8 | P a g e  
Business Case  – Medium complexity   
 
 
 




Business Case – Medium complexity V18 
 
 
 
Contingency 
<What contingency is included in the above costs. This is calculated by individual projects and is based on 
risk.> 
 
Management case 
Change Impact Assessment 
For scoring assessment guideline, please refer to “Change impact assessment matrix” in Kotahi 
<If you scored 1 extreme or 2 High or 3 Medium, you’d need to engage a “Change Manager”> 
Impact Assessment 
Impact 
(Low, Moderate, Medium, High, Extreme) 
Size of the change 
 
Complexity of the change 
 
People increase/reduction change 
 
People – skil s, training, new ways of working   
System change 
 
Process change 
 
Organisation structure change 
 
Culture change 
 
 
Change management 
The <name of programme/project/nitiative> wil  follow Auckland Councils Change Management 
Framework.  
 
 
 
The change management plan wil  need to be completed in the plan phase, if applicable. 
 
Stakeholder engagement 
  Key stakeholders 
The following stakeholder groups wil  be impacted by this change in the following ways: 
Stakeholder name / group / 
Evidence of collaboration / 
Agreed outcome 
contact 
impact assessment 
- Sarah Clarke - Centre 
 
 
Manager 
- Santosh Puthran – Senior 
Aquatics Facilities Specialist  
- Kris Bird – Area Operations 
Manager 
- Customers of Albany Pools 
- Members of the public 
 
 
 
 
 
 
 
 
The stakeholder engagement plan wil  need to be completed in the plan phase, if applicable. 
9 | P a g e  
Business Case  – Medium complexity   
 
 
 


Business Case – Medium complexity V18 
 
 
 
Outline project plan 

  Outline project plan 
How wil  this project be delivered, by who and when?  
Deliverable(s) 
Delivered by 
Date due 
 
 
 
[Edit as required: 
A deliverable is an element of 
output within the scope of the 
project. Refer to the Auckland 
Design Manual, practice notes & 
specifications for more detailed 
information. 
 
The deliverable should consider: 
- Aesthetics 
- Protection of structure 
- Continued use  
- Extension of life 
- Replacement with new due to new 
standards or changes to building 
code  
- Outlook of an asset 
- Futureproofing of an asset 
 
Ultimately, the asset should be fit 
for purpose and aligned to the 
scope and objectives (consider the 
whole of life considerations, 
including maintenance and end of 
life). For example, safe, functional 
space could be the deliverable, 
whereas HVAC would form part of 
the scope.] 
 
 
 
 
 
 
 
Health and safety 
This project is expected to < include / not include > design or modification of an existing asset, as 
such the requirements of Safety in Design wil  apply/not apply to this project.  
There is legal responsibility on Auckland Council (as the ‘Person Conducting a Business or 
Undertaking’) to ensure, so far as is reasonably practicable, the health and safety of workers and 
other persons over the life of the asset.  
 
The following health and safety related risks were identified in the option assessment relating to this 
project which wil  need to be considered for elimination or where not able to be eliminated to be 
minimised. 
  Option  Health and Safety Risk 
Project Phase 
 
<e.g. Striking live power cables> 
 
 
<e.g. Stormwater network surcharge, dislodging manhole lid exposing   
risk of falling> 
 
<e.g. Work in confined space to clean device> 
 
10 | P a g e  
Business Case  – Medium complexity   
 
 
 


Business Case – Medium complexity V18 
 
 
 
 
Approval and acceptance 
Handover activities 
The following activities and documents wil  be handed over once acceptance criteria have been met: 
<Designs, procedures, registers, maintenance manuals, templates, as built materials, post-project 
benefits monitoring and realisation activities, post project evaluation etc. (attach any relevant 
documentation to appendices)> 
  Governance sign of   Name 
Signature to endorse  Date 
Comment 
I agree that the potential costs/benefits identified are realistic, and the low complexity delivery path 
reflects PCAT findings and approve and or endorse the project to continue for funding. 
Financial Manager /   
 
 
 
Commercial 
Manager 
Project sponsor 
Grant Jennings 
 
 
 
Business owner 
Julie Pickering 
 
 
 
 
Benefit Owner 
Santosh Puthran   
 
 
  SME endorsement If  Name 
Signature to endorse  Date 
Comment 
applicable 
Eg.Change, legal, 
 
 
 
 
financial 
transactions, 
governance, 
communications etc 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
  Advisor/stakeholder  Name 
Signature to endorse  Date 
Comment 
endorsement 
 
 
 
 
 
 
 
 
 
 
Appendices 
Appendices 
<Attach PCAT report and all related supporting documents/information to this section> 
 
 
11 | P a g e  
Business Case  – Medium complexity   
 
 
 

Document Outline