STRATEGIC ASSESSMENT AND DISCOVERY DOCUMENT (SADI) 
COMMUNITY FACILITIES  

 
SECTION I – STRATEGIC ASSESSMENT 
 
  
The purpose of this the strategic assessment is to provide a high-level outline of the proposed initiative, describing 
the need for change, related benefits and how this fits with Auckland Council’s strategic outcomes. If the budget 
holder agrees with the strategic assessment, s/he should sign off approval to move the proposed initiative into the 
work programme for consideration by the decision making body.  
 
INVESTMENT PROPOSAL INFORMATION 
Initiative Name: 
Albany Pools - install solar 
Decision making body: 
Upper Harbour 
 
panels 
Business unit/ 
department/CCO, local 
board, etc. 
Park/Reserve/Facility:   
Objectives: 
To increase energy 
efficiency in a more 
sustainable way for the 
environment 
To save money long-term 
on electricity. 
 
Initiative Lead:  
Melissa Johnston 
Is this a planned initiative  New 
or new? 
 
 
Sentient ID# 
36482 
Date:  
27 May 2022 
 
 
 
 
STRATEGIC CASE 
Introduction 

What does this proposed initiative involve?  
Scope: To install a Solar Photovoltaic (PV) array on the roof of Albany Stadium Pool. The proposed solution from 
Reid Technology Limited is a 242 kilowatt peak (kWp) system made up of 440 solar modules. It is expected the 
system will generate approximately 335,900 kWh of electricity per year. 
Activity Description (proposed): Install solar panels on the roof of the pool complex as part of Project Gigawatt. 
FY21/22 - investigation and design  
FY22/23 - physical works 
 
Risk Adjusted Programme (RAP) project. 
 
Out of Scope:  
Anything unrelated to the solar panels 
 
What is the targeted delivery date / estimated time to deliver this initiative?   
30 June 2023 
 
If possible, provide a ballpark figure of delivering this proposed project. 
Capex:  
Funding Sources 
Financial Year 
Financial Year Two 
Financial Year 
Total 
One 
Three + 
ABS: Capex - 
$22,070 
$369,500 
$0 
$391,570 
Development 
Project Total 
$22,070 
$369,500 
$0 
$391,570 
 
Is funding sought to build the business case? No 
 
 
Page 1 of 8 
 
 

Strategic assessment – Outlining the need for investment 
Auckland Council has declared a climate emergency and has committed to reducing carbon emissions by half by 
2030, and net zero emissions by 2050.  
All carbon reduction strategies rely on increased use of electricity in both transport and stationary heating. This will 
increase demand for electricity and Project Gigawatt is aiming to install enough distributed generation to offset this 
increase in electricity use by Auckland Council. 
Solar PV technology has been steadily decreasing in price over the last 20 years. Although Auckland Council pays 
a small amount per kilowatt hour (kWh) of electricity purchased, the cost of solar PV technology has decreased to 
the point that it is now a commercially viable solution on Council facilities. 
 
The following benefits are being derived from the project: 
•  Increased electricity generation in the Auckland Region giving improved energy resilience in dry 
years. 
•  335,900 kWh of electricity generation annually. 
•  Auckland Council’s Greenhouse Gas (GHG) emissions will reduce by 42 tonnes of carbon dioxide 
equivalent (CO2e) per year.1 
•  Approximately $38,000 in reduced electricity charges per year (10.5% Internal Rate of Return). 
What are the measurable benefits of implementing this change? 
Increased electricity generation in the Auckland Region giving improved energy resilience in dry years. 
 
 
Options Analysis: 
Consider the options below to determine the best outcome. Describe the sought outcome and how this decision 
was made. 
 
1.  Do nothing 
2.  Remove asset and reinstate site 
3.  Renew asset to todays’ standards 
4.  Renew and upgrade the level of service 
5.  Upgrade park or facilities level of service 
6.  Other 
5.Upgrade park or facilities level of service 
 
What would happen if we didn’t continue with this proposed initiative?  
The electricity supply for the Albany Pools would continue to be delivered via the national grid and the costs would 
continue to increase over time. This would also neglect to fulfil Auckland Council’s commitment to reducing carbon 
emissions where possible across the region.  
 
What are the risks / Issues / Constraints / Assumptions relating to the project? 
Constraints: In planning and delivering the work, there are some general environmental and/or site-specific 
constraints that require due considerations.  
Some examples are:  
- Building occupants/tenants  
- Weather conditions 
- Current operation of the premises - make sure you liaise and communicate with building occupier/tenants. You 
may require them to shut their operations during their peak business. 
- There is a risk that the pool roof cannot take the weight of the solar panels. This risk is considered to be low as 
the building was intended to have solar panels, but these were cut from the build project due to budget constraints. 
A structural assessment will be undertaken as part of the project. 
-If the grid is congested with generation Vector may require grid strengthening in the area before agreeing to have 
distributed generation connected to their electricity network. The risk of this is low as there is a large electrical 
supply to the building. A distributed generation (DG) application will be lodged with Vector before the design is 
finalised. 
-The equipment will need to be shipped to New Zealand. Supply chain constraints may cause delays. 
Further requirements should be discussed with the relevant Design principal. Refer to Practice notes for further 
detail on constraints and how to manage them. 
 
 
 
Page 2 of 8 
 
 

 
Assumptions:  
-The roof is checked to ensure it can take the weight of the solar panel prior to installation 
- Budget is adequate 
- Consents are non-notified and approved 
- Stakeholders and Governing body are informed 
- Programme of works for the project is manageable  
 
What other works are planned or are on the go that may impact this project? 
Timing of the delivery of the following projects will need to be considered: 
19839 Albany Pool - install disability amenities 
27837 Albany Stadium Pool - renew components 
 
What other similar projects / initiatives / programmes are currently on the go?  
TBC - 36270 Albany Pool - Phase Out Boiler 
 
Auckland Plan Outcomes 
Our Strategy Goals 
 

Possible Choices 
Aligns To 
Possible Choices 
Aligns To 
Belonging and 
Environment and cultural 
Focus on communities 
Change how we serve our 
participation 
heritage 
that need us most 
customers 
Māori identity and well-
Change how we serve our 
being 
customers 
Homes and places 
Be a smaller and more 
adaptable organisation 
Transport and access 
Deliver within our means 
Environment and cultural 
 
heritage 
Opportunity and 
 
prosperity 
Describe the strategic linkage in more detail here: 
Focus area 6: Use green infrastructure to deliver greater resilience, long-term cost savings and quality environmental 
outcomes 
 
You can read more about the Auckland Plan here: https://www.aucklandcouncil.govt.nz/plans-projects-policies-
reports-bylaws/our-plans-strategies/auckland-plan/homes-places/Pages/default.aspx 
 
Local Board Plan outcomes and/or key initiatives 
 
LB Plan Outcome:
 2020UH5 - A resilient local economy 
LB Plan Objective: Our local businesses and industry are resilient and sustainable. 
 
Relevant documents adopted by the local board 
 
Auckland’s Climate Plan 2020 
https://www.aucklandcouncil.govt.nz/plans-projects-policies-reports-bylaws/our-plans-strategies/topic-based-plans-
strategies/environmental-plans-strategies/aucklands-climate-plan/Documents/auckland-climate-plan.pdf 
 
 
 
CLIMATE CONSIDERATIONS - “CLIMATE IMPACT” 
Climate Change (Adaptation and Mitigation):
 Project management and decision-making to consider the 
reduction of GHG emissions through sourcing of low-carbon material options and use of products with 
environmental declarations for embodied carbon reductions. Consideration should be given to minimise waste from 
existing components through recycling and aiming for maximum diversion from landfill. 
 
Climate Priorities: Built environment 
Impact on Climate Goals: Positive impact on our climate change resilience 
 
 
Page 3 of 8 
 
 



 
MĀORI OUTCOMES AND ENGAGEMENT 
Māori Outcomes:
 No specific outcome focus areas 
Degree of Māori Outcomes: Low or indirect outcomes 
Māori Outcomes and Engagement: Inform Mana Whenua 
 

 
KEY STAKEHOLDERS  
Community Engagement Required:
 Inform 
Community Engagement Approach: Via the Communication Advisor 
Community Engagement Details: Local Board Members would like the Communications Advisor to inform the 
public. 
 
Stakeholders:  
Sarah Clarke - Centre Manager 
- Santosh Puthran – Senior Aquatics Facilities Specialist  
- Kris Bird – Area Operations Manager 
- Customers of Albany Pools 
- Members of the public 
 
 
 
STRATEGIC ASSESSMENT APPROVALS 
Author: 
Work Programme Lead 
Melissa Johnston 
 
Prepared in Consultation With: 
Area Manager  
Kris Bird 
Service / Benefit Owner/s 
Chris Mc Arthur – Energy, Efficiency and Sustainability Manager 
Gwyn De-Arth - Regional Aquatic Facilities Manager 
Matthew Burden - Senior Centre Manager 
 
Approval and Acceptance: 
This initiative is worthy of inclusion in the work programme and further development into the initiate phase. I agree 
that the potential benefits identified are realistic, and the required budget appropriate to support movement into the 
work programme for approval by the decision makers.  
Approver / Sponsor 
Kris Bird 
Signature: 
 
 
 
 
 
Appendices 
36482 Albany Pool 
Solar Array - Memo - May 2022.pdf
 
 
 