CHRISTCHURCH TRANSPORT OPERATIONS CENTRE  
A partnership of Christchurch City Council, New Zealand Transport Agency and Environment Canterbury 
Keeping Christchurch Moving 
www.tfc.govt.nz 
TMP Cover Notes 
 
Attached is an accepted Traffic Management Plan (TMP) from a  CTOC, Traffic Management 
Coordinator.  Acceptance is conditional on the  requirements below, and to any notes added to the 
TMP. 
Failure to  comply with any of  these requirements may cause the TMP acceptance to be revoked. 
 
Collaboration Expected 
The  Client and Contractor must collaborate with any other  Clients / Contractors that submit future TMP 
requests for the same area.  CTOC expects  all parties  to work  together to  advance their projects, and notes that 
compromises and changes to the TMP configuration may be required at times.  Should collaboration not occur this  
TMP acceptance may be  revoked . 
 
Network Impact 
Activities on any road must be planned so as to cause as little disruption, delay or inconvenience to 
road users as  practicable without compromising safety. The length, width and duration of any 
TTM must be restricted to the minimum required for the safe operation of the activity. 
 
TTM Principles 
TMPs must be deployed in accordance with the principles contained in COPTTM, CTOC Local 
Operating Procedures (LOP), and the CCC Construction Standard Specification (CSS). 
 
Real Time Operations Contact 
The  Real Time Operations team must be contacted prior to and during any work within 
50 metres of a set of traffic lights.  Refer to CTOC LOP for further details. 
Real Time Operations contact number (03)941-8620 
 
Permission to affect CCC Assets 
It is the responsibility of the Client to arrange and pay for any  permits required for works that affect CCC road assets. 
Permits include Corridor Access Request (CAR), Temporary Use of a Legal Road,  and 
Construction Zones. Contact the CCC Asset Protection Team  for further details. 
Placement of any containers, skips, hoardings and scaffolding on legal road will require Temporary 
Use of a Legal Road  approval. A copy of the approved form  must be attached to the onsite TMP at all 
times,  and be available on request to any CCC Council Officer. 
 
Parking Meters 
Where metered car parks cannot be used because of work  being undertaken, the Client must pay 
the associated costs  for loss of revenue by contacting the  CCC Parking  Operations 
Team.  Payments  must be arranged before the accepted TMP can be installed. 
Note if a Time Limit car park or loading zone is required to be used as part of the worksite, you may   
be required to provide a Time Limit car park or Loading Zone in an alternative location for public use.
 
 
Public Notifications 
Notifications  must be carried out a minimum of 5 working days prior to the installation of the 
accepted TMP. A record must be kept of who, when, and how the notifications 
were  made. Notifications  must be tailored to communicate the impacts of the work to affected 
stakeholders. Where impacted, the stakeholders receiving notifications must include: 
bus operators, businesses, private residences, schools ,  hospitals , and emergency service 
providers. 
 
V3 
Page 1 of 2    
 
 
 
5/9/2014 


 
CHRISTCHURCH TRANSPORT OPERATIONS CENTRE  
A partnership of Christchurch City Council, New Zealand Transport Agency and Environment Canterbury 
Keeping Christchurch Moving 
www.tfc.govt.nz 
Pedestrian Access 
When there is a need to detour pedestrians from the footpath into the carriageway and there are no 
dropped kerbs or driveways available,  a solution must be implemented to safely 
transition wheelchairs, mobility scooters, prams etc  down the level difference. Options include ramps, 
and (for long term sites)  installing a  dropped kerb in compliance with CCC Construction 
Standard Specification. Storm water flows must be maintained. The onsite STMS/TC  must 
monitor and ensure that facilities are maintained so that the health & safety  of members  of the public  are 
protected. 
 
Footpath Closures 
Footpath closures  are permitted on roads with traffic  volume of 5,000 vehicles per day or less,  
provided that the following conditions are met: 
 
There is an alternative suitable footpath on the other side of the road. 
 
There is suitable clear sight distance available for pedestrians to make a safe crossing. 
 
Transitions from kerb to road level (eg ramps) have been put in place where required. 
 
Crossing points are clearly defined  using appropriate signage. 
 
STMS has carried out a risk assessment  on site to ensure that the location is appropriate.  This 
assessment must consider the likely users of the crossing point e.g. if near a primary school, then 
particular care is needed to determine a safe location and additional mitigation may be necessary. 
 
A Site Specific TMP is required for any footpath closure that affects a Zebra crossing or dedicated 
school crossing point. 
 
Where any of the above requirements cannot be met or traffic volumes are above 5,000 vehicles per day, a 
Site Specific TMP is required. 
 
Recycling & Waste Collections 
Where the TTM prevents normal collections from occurring, the contractor must either enable collection vehicle 
access through their worksite, or pre-arrange alternative collection points. 
 
 
 
Programme and Nature of Worksite Changes 
 
When work is completed early, the STMS must update TMPforCHCH (close the TMP). 
 
Where a date extension is required for an existing  worksite, the STMS must submit an Extension form to 
TMPforCHCH prior to the End  Date of the original TMP. 
 
The TMP details contained in TMPforCHCH must reflect the current site conditions. If the 
nature    of    the    worksite  or    TTM    impact changes    significantly    after    TMP 
acceptance, then a Revision to the TMP must be submitted. 
 
Water Discharge 
All discharges of de-watering or drilling liquids onto  legal roads or into the drainage system requires a 
discharge permit. The discharged water/drilling liquid is only allowed to be 
discharged to the environment via a silt trap. 
 
 
 
Further information can be found at:   www.tmpforchch.co.nz 
V3 
Page 2 of 2    
 
 
 
5/9/2014 






TRAFFIC MANAGEMENT PLAN 
TMP Proforma 
Version 1.1 
TMP4CHCH # 
25838 
SCIRT # 
10969 
Project Reference:  PRJ#10969 – TMP#0273 – Fendalton Bridge 
Contractor: 
Principal: 
RCA: CTOC 
Organisations 
 
 
 
 
Permanent  
Peak Volumes 
Road Names 
Road Level 
AADT 
Speed 
AM 
PM 
Fendalton Rd 
LV ☐ L1 ☐ L2 ☒ 
50kph 
21870 
7.00am to  4.00pm to 
Dean Ave 
LV ☐ L1 ☐ L2 ☒ 
50kph 
36500 
9.00am 
6.00pm 
Harper Ave 
LV ☐ L1 ☐ L2 ☒ 
29700 
 
 
Summary of Construction Work 
Repairs to Fendalton Bridge – removal & fixing hand rail, reinstatement of concrete capping and sealing of two separate cracks 
Work Programme 
START DATE: 
Monday, 12 January 2015 
END DATE: 
Friday, 27 February 2015 
TTM Onsite 
Stages or specifics of use (e.g. establishment/disestablishment time, continuous setup, time etc.) 
Inter Peak 
☒  establishment/disestablishment of TTM, concrete deliveries 
Daytime (7am - 6pm) 
☒  Construction  
Night-time (6pm – 7am)  ☐   
All Day (24hrs) 
☐   
Program Sequence 
Repairs to Fendalton Bridge – require the footpath to be closed to pedestrians. TTM to manage pedestrians is to have a lane closure with 
a footpath diversion around the site. 
 
 
 
No lane closures during 
critical world cup period.Feb 
9th to 23rd Feb 
(inclusive).Must maintain 2 
lanes 2 way during this 
period.
 
 
AE/CTOC_STAMP 
 
By Kevin Westeneng L2-3NP #956 at 11:41 am, Dec 01, 2014
 
SCIRT # 10969 
TMP Page 1 of 4 
 



Site Specific Layout Diagrams                                                                                                        Number of Diagrams Attached: 
 
Stage # 
Page # 
Description 
 
TMP 1 
West side of footpath Closed – one lane closure for concrete deliveries 
 
TMP 2 
East side of footpath Closed – one lane closure for concrete deliveries 
 
TMP 3 
West side of footpath Closed – Four lane contra flow 
 
TMP 3a  West side of footpath Closed – Four lane contra flow 
 
TMP 4 
East side of footpath Closed – Four lane contra flow 
 
TMP 4a  East side of footpath Closed – Four lane contra flow 
 
TMP 5 
VMS Strategy 
SCIRT Universal plans to be used:  
Proposed TSL 
Approval of Temporary Speed Limits (TSL) are in terms of section 5 of 
Land Transport Rule: Setting of Speed Limits 2003, Rule 54001 
Attended 
Day 
30kph ☒     40kph ☐     50kph ☐     60kph ☐     70kph ☐     80kph ☐ 
 
Location 
Time and Dates 
A temporary maximum speed limit is hereby fixed for motor vehicles travelling between: Dean Ave, 
7.00am 12/01/2015 to 6.00pm 
Harper Ave and Fendalton Rd. 
27/02/2015 
Unattended 
Day/Night 
30kph ☒     40kph ☐     50kph ☐     60kph ☐     70kph ☐     80kph ☐ 
Location 
 
Time and Dates 
A temporary maximum speed limit is hereby fixed for motor vehicles travelling between: Dean Ave, 
6.00pm 12/01/2015 to 7.00am 
Harper Ave and Fendalton Rd. 
27/02/2015 
TSLs MUST BE REMOVED WHEN NOT REQUIRED 
Contact Details (for STMS contact details for this site, refer to company personal list) 
 
Name 
Contact # 
Email or STMS Qualifications. 
Project 
Derek McDermott 
021 420 795 
[email address] 
Manager 
151 
L2/3 STMS NP 
10/11/2014 
TMP Designer 
Gwynmarie Tomlin 
343 9725 
ID # 
Qualification  
TMP Design Date 
 
 
 
 
AE/CTOC_STAMP 
 
By Kevin Westeneng L2-3NP #956 at 11:41 am, Dec 01, 2014
 
SCIRT # 10969 
TMP Page 2 of 4 
 



Site Specific Details 
General TTM Concept and Principles Used: 
Repairs to Fendalton Bridge – require the footpath to be closed to pedestrians. TTM to manage pedestrians with a footpath diversion around the site. 
Discussion of Critical Areas: 
Level 2 road with double lanes not providing an alternative crossing point for pedestrians. 
Traffic Impact Assessment: 
Maintain lanes with a pushed contra flow. Dropping the traffic to one lane for concrete deliveries (Inter peak) will cause
will not   traffic dela
cause 
ys. 
traffic 
VMS Strategy to warn road users of delays. 
delays greater than 
Site Accessing Methodology: 
permitted by 
Traffic should follow the direction of traffic as per the TMP and follow the instructions given by the STMS
COPTTOM(<5min)
 
On-Site Monitoring Plan 
Attended 
2 hourly checks 
Required: Yes ☒  No ☐ 
Unattended   
Daily Check 
Impact Mitigation Strategy 
 
No Public Notification Required 
 
Standard Project Notifications (detail below) 
Mitigation Level 
Site Specific Details 
 
Level 1 Mitigation 
Letter drop to residents 
 
Level 2 Mitigation 
 
 
Level 3 Mitigation 
VMS broads warning of traffic delays 
 
Level 4 Mitigation 
 
Contingency Plans  
The incident will be assessed and the required TTM measures installed 
Authorisations  
Real Time Operations notification required: Yes ☒  No ☐ 
 
All work within 50m of a signalized intersection must be notified to CTOC’s RTO team. This includes sign 
deployment, and detouring significant volumes of traffic through signalized intersections. RTO contact details are: 
  (03) 941 8620 (6am – 6pm and for emergencies) or [email address] 
Real Time 
 
Operations 
(RTO) 
RTO notification time frames: 
 
  24-48 hours before work commences (email preferred) 
  At time of day deployment (phone call preferred) For night deployments, provide confirmation of planned 
deployment during the preceding business hours 
  24-48 hours of major site changes or disestablishment (phone call preferred) 
 
 
 
 
 
 
 
 
 

 
 
AE/CTOC_STAMP 
 
By Kevin Westeneng L2-3NP #956 at 11:42 am, Dec 01, 2014
 
SCIRT # 10969 
TMP Page 3 of 4 
 



 
Engineer/TMC to complete following section when approval or acceptance required 
 
SCIRT Traffic Manager  
Approved  
as Approving Engineer
by Engineer  
By Kevin Westeneng L2-3NP #956 at 11:42 am, Dec 01, 2014
Name, Date, Signature, Qualification and ID no. Required 
 
Accepted by 
TMC 
By Craig Halkett #22437 For CTOC From Date And Time Of Stamp at 9:09 am, Dec 05, 2014
Name, Date, Signature, Qualification and ID no. Required 
Qualifier for Engineer or TMC Approval 
This TMP is approved on the following basis: 
1.  To the best of the Approving Engineer’s/TMC’s judgment this TMP conforms to the requirements of CoPTTM and/or CTOC LOPs 
2.  This plan is approved on the basis that the activity, the location and the road environment have been correctly represented by the applicant. Any inaccuracy in the 
portrayal of this information is the responsibility of the applicant. 
3.  The STMS is reminded that it is the STMS's duty to postpone, cancel or modify operations due to adverse traf ic, weather or other conditions that af ect the safety of 
this site. 
4.  If this TMP interacts / overlaps with another TMP, contact between STMSs must occur, to ensure agreement on: (i) what work activities can viably occur concurrently 
(ii) what the TTM configuration will be (iii) who is responsible for each Working Space (iv) who is responsible for maintaining / managing each TTM component. The 
objective is for all parties to work collaboratively together, without compromising safety or traf ic ef iciency. Agreements must be documented, and updated as 
necessary as work progresses. If agreement cannot be reached, then CTOC must be contacted to resolve the issue. 
5.  The Site Specific details in this TMP are supplemented by information contained in the SCIRT supplementary TMP document. This supplementary document must be 
treated as part of the TMP and be onsite/presentable at all times. 
 
 
 

 
 
SCIRT # 10969 
TMP Page 4 of 4 
 


No lane closures during 
critical world cup period.Feb 
9th to 23rd Feb (inclusive) . 
By Kevin Westeneng L2-3NP #956 at 11:50 am, Dec 01, 2014


By Kevin Westeneng L2-3NP #956 at 11:51 am, Dec 01, 2014
No lane closures during 
critical world cup 
period.Feb 9th to 23rd Feb 
(inclusive) 


By Kevin Westeneng L2-3NP #956 at 11:51 am, Dec 01, 2014
Barriers to be 
tweaked to allow 
the left turn bay to 
remain open.
This lane should 
No lane closures 
remain open if 
possible. STMS to 
during critical world 
assess if large 
cup period.Feb 9th to 
vehicles can make 
23rd Feb (inclusive) 
the turn. Adjust 
footpath and 
barriers


By Kevin Westeneng L2-3NP #956 at 11:55 am, Dec 01, 2014


By Kevin Westeneng L2-3NP #956 at 11:55 am, Dec 01, 2014


By Kevin Westeneng L2-3NP #956 at 11:55 am, Dec 01, 2014


Not required as all 
lanes remain open 
and should be little 
disruption 
  FENDALTON RD 
  BRIDGE REPAIRS 
  12 JAN -  *
This would be 
      LEFT TURN  
required on the 
        TRAFFIC  
assumption that the 
POSSIBLE DELAYS
left turn lane is 
closed onto 
* Delivery team to 
Fendalton Road. 
supply end date of 
If it can remain 
left turn lane 
open then remove 
closure.Refer note 
VMS after 
about CWC 
deployment
restriction period 
By Kevin Westeneng L2-3NP #956 at 11:55 am, Dec 01, 2014
on page 1 of 4 of 
this TMP