This is an HTML version of an attachment to the Official Information request 'Newmarket Traffic Signal Review'.

 
Date: 26 July 2021 
From:
 s7(2)(a) Privacy  
To: Auckland Transport 
Re: Broadway / Teed Street Signalised Crossing Review 
 
Introduction 
Auckland Transport have completed a review of the proposed signalised pedestrian  crossing on 
Broadway south of Teed Street following feedback from the Newmarket Business Association.  The 
review considered two new options: combining the proposed signalised crossing with the existing 
signalised intersection at Broadway/Remuera Road  to  create a single intersection  and the ful  
signalisation of the Broadway/Teed Street intersection.   
Options 
Do nothing: Existing layout with signalised intersection at Remuera Road/Broadway combined with 
pedestrian refuge island/solid median at Teed Street. 
Option 1: New midblock pedestrian crossing with pedestrian phase linked to the pedestrian phase at 
the existing Remuera Road/Broadway signalised intersection.   
Option 2:  Combination of the proposed pedestrian crossing with  the existing Remuera 
Road/Broadway intersection  to form a single intersection with dedicated pedestrian phase.  The 
operation would involve: 
•  No change in cycle time 
•  Additional inter-green times required for vehicles to clear the intersection between signal phases 
taken from the Broadway through movements.   
•  Pedestrian crossing green time remaining  the same as the existing Remuera Road/Broadway 
intersection.  This arrangement would not operate as a Barnes Dance as the green time required 
to allow for crossing diagonally would be excessive. 
Option 3: Signalising the Broadway/Teed Street Intersection and linking it to the Remuera 
Road/Broadway signalised intersection.   
Model ing 
An Aimsun microsimulation model was used to compare the existing layout with options 1 and 2 
over the 2 hour PM peak between 4-6pm which was considered the critical period. It is considered 
option 3 would operate similar to option 1.   





 
 
Figure 1. Microsimulation models for option analysis 
Analysis  
Travel time: 
The base model and Option 1 resulted in similar total travel time for vehicles over the 2-hour model ed 
period (4-6pm) indicating no significant change to existing operation.  
Option 2 resulted in an increase in the total travel time of around 24 vehicle-hours (12 seconds / 
vehicle).  This is as a result of the increased inter-green time between phases A and C and then B and 
A which is required due to the increased distance vehicles need to travel to clear the intersection. 
 
Figure 2. Broadway/Remuera Road signal phase diagram 
 
 




 
Operation: 
Analysis of the model showed the pedestrian crossing operating wel  for Option 1. Vehicles would be 
held between the new signalised crossing and the  Broadway/Remuera Road  intersection  on the 
pedestrian crossing phase (phase C) which is illustrated in figure 3 below. 
The model of Option 2 showed vehicles being regularly ‘trapped’ in the intersection area resulting 
from queuing back from the Remuera Road/Nuffield Street intersection which can be seen in figure 4 
below.  Drivers will be unable to determine if they can clear the intersection due to the lack of visibility 
of queues between Broadway (north) and Remuera Road. 
Broadway  
Teed Street 
New 
Signalised 
Vehicles trapped in 
Crossing 
intersection on 
phase change 
Remuera Road 
 
 
Figure 3: Option 1 during pedestrian phase 
Figure 4: Option 2 during pedestrian phase 
(5:00pm) 
(5:00pm) 
 
 
Safety: 
Option 1 would result in a significant improvement for pedestrian safety and amenity by providing a 
dedicated pedestrian phase across Broadway which is a busy 4 lane road. 
Option 2 will benefit pedestrians by providing a dedicated pedestrian crossing phase, however it will 
likely cause some conflicts between pedestrians and vehicles as drivers trapped within the intersection 
are likely to attempt to find gaps in pedestrians crossing to clear the intersection.    The size of the 
intersection may also promote red light running as drivers consider they can make up time due to the 
significant inter-green period. 
Option 3 would result in a significant improvement for pedestrians crossing Broadway however would 
reduce pedestrian amenity for through pedestrians on the western Broadway footpath.  The current 


 
zebra crossing at Teed Street  allows pedestrian priority  and  the  raised  table  ensures left turning 
vehicles turn at very low speeds.  Signalising Teed Street would introduce delays for pedestrians and 
due to the one-way operation and narrow width of Teed Street pedestrians are likely to cross at any 
time resulting in potential conflicts.  
Conclusions 
It is considered that Option 1 consisting of a new signalised mid-block crossing is the preferred option 
as it provides a high level of pedestrian amenity, increases pedestrian safety and minimises impact on 
the operation of the surrounding network.   
Design Considerations   
As a result of recent changes in best practice regarding pedestrian safety, consideration has also been 
given to including a raised speed table at the proposed mid-block signals. Speed survey data taken in 
May 2018 on Broadway between Khyber Pass Road and Teed Street showed:  7  day average 85th 
percentile speed of 38.3km/hr southbound and 41.6km/hr northbound.  Several one hour intervals 
during the early morning were recorded with 85th percentile speeds of approximately 50km/hr and in 
one hour period reached 56km/hr. 
Due to the crossing being located in the town centre with high numbers of pedestrian movements and 
operating speeds significantly above 30km/hr it is considered that installation of a raised table should 
also be provided in conjunction with the new crossing. 
It should be noted that Broadway is a level 2 Lifeline route indicating its importance to emergency 
services which would require construction of a table with shal ow ramps of between 1:15 to 1:20. 
Raising the crossing with shallow  ramps should reduce the high-end  traffic speeds while also 
minimising disruption for emergency services.   
Broadway is also being considered for tranche 3 of the speed limit review with the assessment due for 
completion by the end of September 2021. To reduce the speed limit to the likely target of 30km/hr 
it is likely a route treatment will be required consisting of a series of speed devices.  Installation of 
traffic calming at the proposed Teed Street Crossing would likely be an optimal location for the route 
treatment combined with a raised crossing at the mid-block crossing to the north, resulting in 90m 
separation. 
Programme of works  
The below details the preliminary programme of works to progress the crossing: 
•  August 2021: Finalise project details 
•  September – October 2021: Update detailed design 
•  November – December 2021: Consultation 
•  January – March 2022: Construction 
 

Document Outline