This is an HTML version of an attachment to the Official Information request 'Request for Background Calculations used for LGWM MRT and Mt Vic Tunnel Options'.


 
 
 
 
 
 
 
 
 
SHI and MRT IBC Integration and Scope 
 
Agenda Item: 

Item for: 
Approval  
Addressee: 
Partnership Board 
Owner: 
David Dunlop  
Date: 
28 April 2021 
Version: 
Final  
Doc no: 
0070/21 
 
Purpose 
This paper outlines the change in scope for the Mass Rapid Transit (MRT) and Strategic Highway 
Improvements (SHI) IBCs, the next steps for their delivery, and requests Board approval of the updated 
scope. 
 
Executive Summary  
To successfully deliver the MRT and SHI IBC’s the programme team has considered the technical work 
completed, taken lessons learned from the work completed in 2020 and the 2020/2021 sprint phase and 
recommend that a Programme Report and a single Combined MRT & SHI IBC be delivered.  The key 
reasons for this are: 
1.  The Programme Report will provide funders, partners, stakeholders, and the public a clear 
understanding of the integrated programme.  This will include all elements of the programme, the 
dependencies and how they fit together, and delivery staging.   
2.  The practicalities of delivering two separate packages that are significantly connected and impact 
on the single complex transport system has been challenging.  The programme is now at a stage 
that the individual packages have developed separate options in previous work, it is now the right 
under the Official Information Act 1982
time to combine these pieces of work and deliver the remainder of the work through a single 
system based assessment.  The Combined MRT & SHI IBC will provide a stronger one transport 
system assessment and business case, and provide time and cost efficiencies in its delivery. 
 
To successfully deliver the two documents in a short timeframe the team require the Board’s clear 
strategic direction regarding the scope and objectives to ensure that the team can focus on delivery of the 
work to avoid time consuming changes.  
 
Background  
Released 
The MRT and SHI packages delivered separate Draft Interim IBCs in October 2020.  These were reviewed 
by the partners technical advisors with strong feedback requesting clarification of how the two packages 
integrated with the wider programme and with each other.  To enable partners to make good system wide 
 


 
 
 
 
 
 
decisions the partners will require a clear understanding of the benefits of the whole of programme 
preferred solution, how the different components are integrated, how it will be implemented, and the 
overall cost implications.  The remainder of this paper outlines how this will be achieved, the scope 
assumptions that require Board approval, risks, and timeframes for the business case delivery. 
 
Scope changes 
The previous technical assessments identified that the current scope constrains the programmes ability to 
deliver on the objectives of the programme.  A few key scope changes require Board approval to enable 
the programme assessments to be completed.  The proposed scope changes are outlined in Attachment 
1 Proposed Scope changes
 
Next steps 
The next steps are illustrated in Attachment 2, MRT and SHI next steps.  The key points to note include: 
1.  The “Programme Report” and “Combined MRT/SHI IBC” will be issued together for the review and 
approval of the MRT and SHI components. 
2.  The “Programme Report” will provide a clear understanding of the whole of programme in regards 
to the Scope, Problems, Objectives, Options assessment, and delivery (Management Case) of the 
programme.  It will set out how the different packages fit together to achieve the programme 
objectives and the role of each package. 
3.  The Combined MRT/SHI IBC will provide the additional detail of the separate project components 
required to meet the Programme Report requirements.  It will also provide any additional details 
required for the business case process at a package and project level. 
4.  The schedule for delivery is very compressed.  The next steps are robust and scheduled as 
efficiently as possible to achieve an early as possible delivery.  The driver for timeframes are the 
requirements to reflect the updated objective weightings in previous work, meet RMA and 
business case requirements, and enable a successful public engagement process to be delivered. 
5.  Attachment 3 outlines the key risks and mitigations proposed to deliver the next steps within the 
proposed schedule. 
 
Key Issues 
Risk Analysis  

The proposed schedule for delivery of the Programme Report and Combined MRT and SHI IBC is very 
compressed.  Approval processes within the programme and partners is streamlined and cannot absorb 
delays or changes in scope.  To mitigate this, it will be necessary for the Board to confirm the scope in 
Attachment 1 and support the programme by messaging that additional scope cannot be accommodated 
and help prioritise resources to achieve reviews and approvals as necessary.  The Technical Assessment 
sprint phase teamwork approach with partners technical advisors forming part of the team will be 
under the Official Information Act 1982
enhanced during the next steps. 
 
The WCC Draft District Plan engagement is currently scheduled for October and November 2021.  The 
proposed engagement periods for LGWM will overlap.  To mitigate this, it will be necessary for the LGWM 
and Planning for Growth teams to continue meeting regularly to align the necessary technical details and 
messaging to ensure consistency.   
 
Financial Implications 
Released 
Additional costs have been incurred during the sprint phase, and additional costs will be incurred by the 
Programme to review previous work to reflect the recent Objective weighting changes, and complete the 
 


 
 
 
 
 
 
remaining programme assessment work.  The additional costs will be absorbed within the existing 
programme budgets.   
 
A successful programme wide public engagement period that covers MRT and SHI is key to the future 
success of the LGWM programme.  A budget has been identified to cover this scope; however, the public 
engagement approach, scope and delivery details are yet to be agreed.  There is a risk that the cost to 
resource and deliver a successful engagement process may increase over the allowed budget once the 
engagement process is developed.  To mitigate this early engagement planning will be undertaken to 
confirm costs early and identify if additional budget is required, or if there is a need to reduce scope. 
 
Legal and Compliance 
The RMA legal advisor and Waka Kotahi IQA team have provided advice that the proposed process meets 
the RMA options assessment process and business case process requirements.  The IQA team support 
the strengthened one system approach of the assessments that will be completed through the Programme 
Report and Combined MRT and SHI IBC. 
 
The existing RACIE is being updated to reflect the structure changes but has not yet been officially 
approved.  To achieve the compressed schedule proposed the streamlined approval processes are 
required.  It is recommended that the Board approve the following approval process: 
1.  Partners (Councillors) Approve Final IBC 
2.  LGWM Board Approve Objective weightings and scope change, Engagement Strategy, 
Technically Preferred Option prior to engagement, Preferred option. Consultation with Partners 
(Councillors) will occur. 
3.  Consult with LGWM Board regarding Engagement material, Interim IBC, Draft IBC, Final IBC-  
4.  Programme Director approves remaining technical and engagement approvals, with consultation 
with PLT. 
 
Strategic Issues 
Understanding affordability of the programme is an important factor for the programme partners.  It is 
recommended that the Programme Report presents a cost range for the programme during the IBC phase. 
The reason for this is, the IBC stage is early in the project life cycle with relatively high cost uncertainty, 
and it is assumed that the ownership and delivery cost agreement principles will not be confirmed by the 
partners during the IBC phase.  It is recommended that the funding agreements occur during the DBC 
phase once improved cost certainty and ownership models are understood. 
 
Future Board engagement 
The Programme team will be back to: 
under the Official Information Act 1982
1.  Obtain staged approvals for the Public engagement Strategy to enable efficient approvals 
2.  Provide updates on the Program Report and Combined MRT and SHI IBC to provide no surprises 
and enable efficient approvals 
3.  Raise any changes in risk to delivery or schedule  
 
Recommendation 
It is recommended that the Board: 
Approves the MRT and Strategic Highways to be delivered as one IBC 
Released 
Approves the scope changes proposed in Attachment 1 to enable the efficient delivery of the Programme 
Report and the Combined MRT and SHI IBC 
 


 
 
 
 
 
 
Approves the streamlined approval processes proposed to be applied to the Programme Report and 
Combined MRT & SHI IBC, prior to the RACIE being updated and approved to reflect the structure 
changes. 
Notes the risks identified in Attachment 3 for the proposed delivery schedule  
Approves the Programme Report provides a cost range at the programme level and not at partner level.  
 
Attachments  
Attachment 1: 
Proposed Scope changes 
Attachment 2: MRT and SHI next steps 
Attachment 3: Key Risk and Mitigations 
under the Official Information Act 1982
Released 
 



 
 
 
 
 
 
 
 
 
 
Attachment 1: Proposed Scope changes 
Existing scope 
Proposed scope 
Reason for change 
Two separate IBCs for MRT and SHI 
One combined MRT and SHI IBC 
To provide a single system assessment of the significant 
investments and provide efficiencies in the IBC delivery. 
Note: This approach is supported by RMA legal and 
Waka Kotahi IQA experts. 
MRT route “from the railway station to 
MRT route “from the railway station to the eastern 
The current scope prescribes the route solution, rather 
Newtown, and Newtown to the airport” 
and southern suburbs” 
than an outcome and allowing the evidence to confirm 
the best route to achieve the objectives.  Current 
evidence indicates that other MRT routes may better 
deliver on the urban development and mode shift 
objectives at a reduced cost compared to the current 
scope requirements. 
Congestion charging is not included in the 
Include congestion charging as a tool that can be 
Congestion charging was a key component of the 
current Indicative Package provided to the 
investigated by the LGWM Programme to provide 
Recommended Programme of Investment from the PBC 
LGWM programme for consideration in the 
recommendations on the benefits and potential 
which was removed for consideration within the IBCs.  
IBCs. 
implementation of congestion charging.  Due to 
Congestion charging can provide considerable benefits 
insufficient time high level assumptions and 
to the programme including contributing to mode shift, 
sensitivity testing will be included in the 
carbon and financial outcomes for the programme.  It is 
Programme Report and IBCs to identify what 
also a realistic option that should be considered during 
impact congestion charging could have.   
option assessment processes to minimise RMA legal 
The programme will return to the LGWM Board to 
challenges for not considering a reasonable and minimal 
request approval for the scope and additional 
environmental effects option. 
funding required to proceed with a Business Case 
under the Official Information Act 1982
for congestion charging. 
 
 
 
Released 


 
 
 
 
 
 
Attachment 2: MRT and SHI next steps 
 
 
 
under the Official Information Act 1982
 
Released 

 
 
 
 
 
 
Attachment 3: Key Risk and Mitigations 
Assumption 
Risk Description 
Proposed mitigation 
To achieve the proposed schedule the programme 
There is a risk that if the objectives and 
If there are changes to the objectives, they will need 
cannot wait until the Councillor meetings to confirm 
weightings require changes following Partner  to be treated as a sensitivity test.  
the Objectives and Weightings for the assessment 
approvals that rework of the assessment 
work to commence.  It is assumed that the 
work would be required resulting in delays to 
Objectives and weightings that are agreed by the 
delivery of the Interim IBC and public 
LGWM Board at 28 April meeting (today) will be 
engagement period 
used to commence assessment work immediately 
Approval processes require just one step approval 
There is a risk that approval requests are not 
Undertake a staged approach to inform approvers 
for each required approval 
granted at the first attendance of LGWM 
early to provide the best chance of obtaining 
Board or Councillor meetings resulting in 
approvals at the required time.  This is particularly 
delays 
relevant to the Technically Preferred option and the 
Engagement Strategy approvals 
To achieve the engagement period proposed the 
There is a risk that Councillor approval 
Recommend that special out of cycle council 
detailed engagement material will start following the 
requires changes to the Technically 
meetings be held to Consult and obtain feedback on 
Board approval of the Technically Preferred option 
Preferred option resulting in delays to 
the Technically Preferred option as early as possible 
but developed at risk prior to Partner (Councillors) 
completing engagement material and the 
after the LGWM Board meeting to minimise the risk 
approval. Awaiting the regular September 
engagement period. 
to delaying the engagement period.  
Councillor meetings will delay public engagement 
 
until November/December.  
The Draft IBC reporting will start development 
There is a risk that the delivery of the Draft 
Provide a robust and evidenced based public 
following Public engagement but in parallel to 
IBC will be delayed if the Partners confirm 
engagement process that provides clarity on the 
Partner Approval processes.  It is assumed that the 
that the Preferred Option is required to be 
benefits of the Technically Preferred option to obtain 
programme will understand the key changes likely 
reasonably different to the Technically 
strong support from the Partners and the public 
to be required by the Partners as a result of the 
Preferred option following public 
during the public engagement period. 
Public Engagement feedback and commence the 
engagement.  
In addition, the programme team take a risk-based 
Draft IBC. 
approach and if substantial public feedback and 
under the Official Information Act 1982
early post engagement feedback from the Board and 
Partners indicates substantial changes to the 
Preferred option may be likely then the programme 
should delay progressing the Draft IBC until clarity is 
obtained. 
 
Released 

 
 
 
 
 
 
Due to the limited time available a collaborative 
There is a risk that stakeholders consider the  Provide a robust engagement process to outline the 
option development and assessment process is 
option selection process excludes suitable 
range of options considered and ensure the 
unable to be undertaken with Stakeholders to 
input from various different stakeholder 
engagement clearly outlines the partners genuine 
identify a Technically Preferred option 
groups 
desire to obtain feedback and openness to changing 
the technically preferred option should better options 
be identified that achieve the programmes objectives 
 
under the Official Information Act 1982
 
Released 

Document Outline