This is an HTML version of an attachment to the Official Information request 'Delays to roll-out of "AT HOP Day Pass"'.
Project Status Report  
 
 
 
 
Project Name: 
AT HOP Daily Pass 
Project Manager:  /////////////////////////// 
Reported date 
6 May 2014 
Period covered 
17 April – 6 May 
Status Summary 
Still awaiting completion of AIFS testing to confirm go-live date 
 
Project Indicators 
 
2 back 
1 back 
Current 
Status / Comment 

AMBER – due to risk around scope and schedule.  Can change to green 
OVERALL 
 
 
 
once go-live date for B/R/F pass is known 

Until testing has been completed and product specs and limitations are 
Scope 
 
 
 
confirmed this will remain amber 
Progress / Schedule 
 
 
 

Still uncertainty re. launch date as testing has not been completed 

No significant expenditure anticipated (assuming AIFS component can be 
Budget 
 
 
 
managed as part of existing project budget) 
People / Resources 
 
 
 

Sufficient staffing and resources are in place 

Technical risk – if problems arise during AIFS testing, and limited AIFS 
resource should problems arise during bus roll-out.   

Customer risk – ability to clearly communicate complex usability rules re. 
Risks 
 
 
 
no. passes per card  

Commercial risk – that operators relitigate agreed apportionment process – 
will draft letter/agreement to confirm (previous verbal agreement has been 
minuted). 

Some uncertainty re. ability to produce usage-based reports (i.e. number of 
Issues 
 
 
 
stages travelled by operator per pass type) hence change from green to 
amber.  Required for pass reconciliation process. 
 
Progress This Period 
Activities Planned for Next Period 
Testing update 
 
Website content and day pass map to be finalised. 
 
Testing has identified a number of critical issues – refer 
 
Complete marketing collateral internal review process (to be 
Attachment 1 for detailed description. 
submitted to lawyers once launch date is confirmed). 
 
Result is it’s highly unlikely to make the target 14th May EOD 
 
Liaise with BI/AIFS to ensure reporting requirements are 
deployment date. 
achievable (linked to Monthly Pass settlement report 
 
Awaiting advice from AIFS team re. next available launch date 
development). 
(assuming technical issues are resolved).  Current estimate mid-
 
Letters of agreement sent to operators to formalise reconciliation 
June. 
process (once reporting specs confirmed).   
Other 
 
Operator update to be circulated 
 
Finalisation of marketing content awaiting results of AIFS testing. 
 
Agreement from key stakeholders to further extend Discovery 
 
Decision to withdraw Discovery Day Pass on 31 May, even if 
Day Pass 
further delays to AT HOP Day pass has been revisited – now 
 
Track return of letters of agreement 
plan to keep it in-market until Day Pass is available (subject to 
 
Ongoing AIFS testing 
agreement from key stakeholders/retailers). 
 
 
Specific Requests of Steering Group / Escalations 
 
Confirmation required from AIFS team re. implementation dates for B/R/F pass (post testing) 
 
 
Upcoming Milestones 
 
No. 

Date 
Milestone 
Comment 

10 Feb 2014 
Phase 1 AIFS testing completed (Bus/Rail-only pass) 
Done  

Mid May 2014 
Phase 2 AIFS testing completed (Bus/Rail/Ferry pass) 
Assuming no further issues arise 

16 May  2014 
Marketing comms drafted 
Web content and maps still to be finalised  

1 June  2014 
Marketing comms approved 
Internal approval will progress in parallel with AIFS testing 

Mid June  2014 
Go-live  B/R/F pass (indicative) 
Estimate o be confirmed with AIFS team  
 
 

 

Project Status Report  
 
 
 
ATTACHMENT 1 – AT HOP DAY PASS TESTING UPDATE – 1/5/14 
 
EOD 16.1.x Implementation update: 
 
Key deliverable – Implementation of a set of  day pass products to replace the Discovery Pass  
 
Products include: 
 
Bus/Rail  
Zone A 
Zone B 
Zone C 
Zone BC 
 
Bus/Rail/Inner Harbour Ferry 
Zone AB 
Zone ABC 
 
Target EOD Release and date: 16.1.x 14/5/2014 22:00 
 
Key release drivers – Day Pass, Murphy Buses to support go live 19/4/2014, and a number of BAU 
changes (some route/timetable changes go live 16/5) 
 
Testing Update: 
 
Testing has identified a number of critical issues, including 
 
1.  Critical - Performance issue on TOT devices – sub second to around 10 seconds to read a card – 
this issue is under investigation with Thales France 
2.  Critical - Fixed apportionment percentages not been treated correctly – //////////////////////////////////////// 
///////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////
////////////////////////////////////////////////////////////////////////////////////////////////////////////// – this issue is with OSL for 
review, investigation has indicated it is not a database issue – further review will be undertaken 
next week in HK 
3.  Incorrect contract types – IVU export issue – to be resolved with an additional export and EOD – 
this will compress testing time 
4.  Major – Inconsistent treatment of day pass purchase across sales channels (VRD, TOT, SRD, 
and Web) – Jira raised and passed to Thales for investigation 
5.  Minor - Use of Frontier stop points has meant purchase of adjacent zones is not possible, while 
the system is working as designed – it would extensively mean customers using the other period 
monthly pass product would not be able to use their existing card for Day Pass. 
 
 
Potential mitigation options: 
 
1.  Delay Day Pass implementation (already done at least twice – potential reputational to AT) 
2.  For the TOT performance issue – it may be mitigated by reducing the available day pass 
products from the proposed 6 to less products (potentially just he ABC and AB Ferry products – a 
small test has indicated this may be viable) 
3.  For the appointment issue – potentially adjusting percentages and undertake an out of system 
wash up at an agreed interval (weekly/monthly perhaps) 
 
Further update expected re. Issue 1 from Thales 6th May (who subsequently confirmed the issue sits 
within their Ticket Processing engine which means a software patch will be required).