HEALTH AND SAFETY    
PROCEDURE 
 
Asbestos Management 
 
Objective: 
 
To  provide  a  healthy  and  safe  environment  for  South  Canterbury  District  Health  Board  (SCDHB) 
employees, contractors, patients, volunteers and visitors. 
Frequency: 
SCDHB must review and (if necessary) revise the asbestos management  plan every five years, or 
when: 
  asbestos controls are reviewed 
  asbestos is removed, disturbed, sealed or enclosed 
  the plan is no longer adequate for managing the asbestos risks. For example, if new asbestos is 
identified, or if a previously inaccessible area is now accessible. 
This  procedure  applies  to  all  staff,  contractors,  patients,  volunteers  and  visitors  who  may  come  in 
contact with asbestos on SCDHB premises. 
Alert: 
Asbestos or Asbestos Containing Material (ACM) must be considered present within all DHB buildings 
and  as  such  the  Facilities  /  Maintenance  Manager  must  be  contacted  if  concerned.  Known  and 
presumed locations will be listed within the Asbestos management plan & site management surveys 
[register]: iHub Knowledge base / Health & Safety / Asbestos. 
Definitions: 
Asbestos 
A generic name given to a group of fibrous silicate materials that occur 
naturally in the environment: 
Chrysotile (white asbestos)
Crocidolite (blue asbestos) – known to cause the most harm due to the 
fibres  being  relatively  long  and  thin,  therefore  more  likely  to  reach  the 
lungs than the curlier fibres of chrysolite. 
Amosite (brown asbestos)
ACM 
Asbestos Containing Material can be found in a wide variety of products 
e.g. floor tiles, wallboard, roofing. 
Asbestos management 
A guiding document that outlines practices associated with the location 
plan & site management  of all asbestos / ACM within SCDHB buildings.  
surveys [register]  
Compiled by an asbestos specialist. 
PPE 
 
Personal Protective Equipment 
 
Responsibility: 
 
 
Employees 
  Will  ensure  the  Asbestos  management  plan  &  site  management  surveys  [register]  has  been 
reviewed for clarification of asbestos in-situ locations in areas of intended work 
  If unidentified asbestos / ACM is suspected in the workplace, advise the Maintenance Manager 
immediately 
  Asbestos incidents are to be recorded in Safety1st [Employee or Contractor and Facilities, Building 
& Property forms] 
 
AUTHOR:  
P. Moore 
FILE NUMBER:         H&S 04.10 
 
AUTHORISED:  
Sep 2019 
REVIEW DUE:           Sep 2021 
  
 
This is a controlled document. The electronic version is the most up-to-date. Printed versions are valid on the day of printing only. 
Page 1 of 4 


HEALTH AND SAFETY    
PROCEDURE 
 
  Seek  advice  from  the  Health,  Safety  &  Wellbeing  Manager  should  you  have  any  concerns 
regarding asbestos / ACM +/- exposure. 
 
Contractors 
  Will ensure the Asbestos management plan & site management surveys [register] has has been 
reviewed for the location of proposed works 
  If unidentified asbestos / ACM is suspected in the workplace, advise the Maintenance Manager 
immediately 
  All  contractors  will  be  required  to  outline  their  own  asbestos  management  practices  when 
submitting a ‘request for information’ (RFI). 
 
Facilities / Maintenance Manager: 
  Will adhere to the Controlling building and maintenance works flow chart contained within section 
3.4 of the Asbestos management plan & site management surveys before initiating any building 
works or maintenance tasks   
  Will  ensure  the  Emergency  Procedures  [section  3.8,  Asbestos  management  plan  &  site 
management surveys] are communicated and followed  
  Will ensure a register of asbestos locations is maintained and updated with details of how the 
asbestos risks are managed  
  Will ensure signage is posted in all locations where asbestos / ACM remains in-situ 
  Will ensure all contractors are advised of known asbestos / ACM in-situ locations and the safe 
operating procedures required  
  Will supervise all work associated with asbestos and undertake appropriate notifications 
  Will advise the Senior Leadership Team and the Health, Safety & Wellbeing Manager of asbestos 
issues 
 
Building and Refurbishment Committees: 
  Ensure asbestos free products are used in the construction / renovations within SCDHB  
Procedure:  
SCDHB will: 
  Ensure asbestos material is not used by SCDHB  
  Leave existing asbestos material in-situ where it is safe to do so, and have safety precautions 
implemented in meeting legislative requirements 
  Ensure no employee, patient or visitor is placed at risk of exposure to asbestos fibres 
  Take  all  practicable  steps  to  confirm  the  identity  of  suspected  asbestos  products  in  SCDHB 
properties. A register of confirmed asbestos locations will be held by the Facilities / Maintenance 
Manager in accordance with the Health and Safety at Work (Asbestos) Regulations 2016 
  Communicate newly identified asbestos to relevant staff, patients and others without delay and in 
a planned manner 
  Ensure contractors are informed of the presence of known or suspected asbestos in areas in which 
they are working 
 
Asbestos Related 
Exposure  to  asbestos  fibre  may  occur  when  materials  containing  asbestos 
Health 
are sanded, sawn, drilled or handled during maintenance or removal tasks.   
Considerations 
All employees / contractors  working with asbestos are fully informed of the 
hazards of exposure and advised of responsibilities associated with wearing 
PPE, not entering restricted areas and reporting procedures.   
 
AUTHOR:  
P. Moore 
FILE NUMBER:         H&S 04.10 
 
AUTHORISED:  
Sep 2019 
REVIEW DUE:           Sep 2021 
  
 
This is a controlled document. The electronic version is the most up-to-date. Printed versions are valid on the day of printing only. 
Page 2 of 4 


HEALTH AND SAFETY    
PROCEDURE 
 
Any  employee  who  is  potentially  exposed  to  asbestos  and  who  is  also  a 
smoker will be offered appropriate information on the increased health risk of 
the combined exposures. 
Where SCDHB has previously directed any employee to undertake works that 
involves  asbestos  prior  to  14  January  1999,  or  circumstances  out  of  the 
employee’s control have significantly exposed the employee to asbestos, they 
shall be entitled to “a full asbestos medical”.  This wil  include: 
  A full occupational history 
  Medical examination (referral to their GP) 
  Chest x-ray 
  Lung functions tests 
This medical will be available to any former employee of SCDHB who meets 
the criteria (above) and are not already enrolled in a surveillance programme 
from another employer.  The cost of the medical monitoring will be met by the 
SCDHB.    The  Health,  Safety  &  Wellbeing  Manager  will  arrange  medical 
monitoring.  Staff identified as “significantly exposed” or who have developed 
an asbestos related disease, are encouraged to register on the Department 
of Labour asbestos exposure register. 
Identifying 
Possible sources of asbestos fibre that are of most concern include: 
Asbestos 
  Sprayed on fibre / sound proofing / thermal insulation 
  Acoustic plaster sound proofing 
  Insulation 
  Lagging 
  Asbestos cement materials 
  Brake linings in vehicles and machines 
Where asbestos / ACM is suspected, confirmation of presence will be verified 
by sample analysis, obtained by a suitably licensed person and tested at an 
accredited laboratory. 
Results will be conveyed to the Facilities / Maintenance Manager with a copy 
to the Health, Safety & Wellbeing Manager. 
Work must not start until results of analysis are known. 
Asbestos Register  A record of presence and condition of asbestos [in-situ] in the facility is made 
and  maintained  by  the  Facilities  /  Maintenance  Manager.  The  register 
contains the following details: 
  Location 
  Status 
  Assessment of exposure risk – numbers of people entering location, 
potential  to  release  fibres  into  workplace  air,  monitoring  results  (air 
sampling) 
  Hazard control plans that are regularly updated 
Asbestos Signage  Where asbestos materials are to be left intact, signage is affixed to the area 
and is clearly visible and indicates asbestos present. 
Asbestos Hazard 
The control of asbestos hazard must refer to the most appropriate method for 
Control Plan 
the particular circumstances.  Methods of control may include: 
  Removal 
 
AUTHOR:  
P. Moore 
FILE NUMBER:         H&S 04.10 
 
AUTHORISED:  
Sep 2019 
REVIEW DUE:           Sep 2021 
  
 
This is a controlled document. The electronic version is the most up-to-date. Printed versions are valid on the day of printing only. 
Page 3 of 4 


HEALTH AND SAFETY    
PROCEDURE 
 
  Encapsulation or sealing 
  Enclosure 
  Further assessment for damage or deterioration 
Hazard control advice will be sought from a suitably licensed person. 
Purchasing & 
No  new  product  containing  asbestos  will  be  purchased  by  SCDHB.    No 
Maintenance 
maintenance, repair or new work will use any product that contains asbestos. 
Associated Documents: 
  Hazard Management & Control: (H&S 04) 
  Risk management: (QR1) 
  Personal Protective Equipment (PPE): (QR14) 
Equipment: 
References: 
  Health and Safety at Work (Asbestos) Regulations 2016 
  Health and Safety at Work Act 2015 (HSWA) 
  Health and Safety at Work (General Risk and Workplace Management) Regulations 2016 
  WorkSafe NZ https://worksafe.govt.nz/topic-and-industry/asbestos/ 
 
 
 
AUTHOR:  
P. Moore 
FILE NUMBER:         H&S 04.10 
 
AUTHORISED:  
Sep 2019 
REVIEW DUE:           Sep 2021 
  
 
This is a controlled document. The electronic version is the most up-to-date. Printed versions are valid on the day of printing only. 
Page 4 of 4